Professional Documents
Culture Documents
Murli Iyengar, Geotechnical Consultant (Formerly Exe. Director, Engineers India Ltd.)
miyengar.in@gmail.com
ABSTRACT: Instances of leakage from the joints between the panels of a Diaphragm wall, during
construction, are not uncommon and several cases have been reported in literature, along with measures
taken for repair & rectification. This paper deals with one such case wherein, following repairs to stop the
leakage, a parametric study was carried out using PLAXIS, considering various scenerios of subsoil
disturbance, both the decrease in the subsoil strength as well as likely extent of zone of disturbance. The
back-analysis was based on the data from the inclinometers, installed in the Diaphragm wall panels and cone
penetration tests carried out to establish the subsoil condition, pre and post leakage.This enabled to establish
the most probable combination for assessment of the BM developed in the wall for ascertaining its structural
adequacy. Based on the study it was concluded that the disturbed zone is limited to about 5m beyond the face
of the D’Wall, defined by Case A. The computed deformation for the lower Es values (Cases B &C) and 10m
disturbed zone (Case D), is much in excess of the observed deformation, hence not applicable.
Keywords: Diaphragm Wall, Water Leakage, Deep Excavation
1
Analysis of a Diaphragm Wall Panel after Leakage during Deep Excavation
to the ground level in the joint from the outside.. 4 ASSESSMENT OF THE SUBSOIL
This was followed by PU grouting
routing from inside, till CONDITIONS AFTER THE EVENT
the water flow was completely arrested.
Thereafter, TAM grouting was carried out from the 4.1 DCPT Tests
outer side to increase the water tightness of the
joint. It was apprehended that subsoil in the vicinity of
the leaking joint could have been affected. In
order to assess the disturbance to the subsoil,
Ground Elev (+) 3
DCPT (Dynamic Cone Penetration Tests), were
Silty Sand : SPT N =7
conducted using “Geotools”. To facilitate
(Phi=35, E'=11 MPa) ROOF SLAB Elev (-) 0.4
comparison with a “base reading”, tests were also
GWT = (-) 2
DIAPHRAGM WALLS
Toe Elev (-) 21.7
carried out in the unaffected area, nearest to the
Silty Sand : SPT N =30
(Phi= 37.5, E' = 25 MPa) CONCOURSE SLAB Elev (-) 6.4
site, where the subsoil was relatively undisturbed
by the event.
2
Indian Geotechnical Conference IGC2016
15-17 December 2016, IIT Madras, Chennai, India
4 A,B &C @
Disturbed Actual
Case A Case D Case C
locations
6
Depth (m)
D&E @
8 Undisturbed
Locations
10
Original
12
Soil
14
16
Case B
18
20
A B C D E
3
Analysis of a Diaphragm Wall Panel after Leakage during Deep Excavation
value of 27 mm at el. -8.0 m. Above this level also It appears that the “Water Bars” provided in the
the same trend is noted upto El. -2, although the panel joints may have got disturbed during
increase in deflection is smaller. At the time of construction, leading to water leakage. Therefore,
leakage, the Roof slab was already in position. as an additional measure, it was decided to carry
out “Jet grouting” behind the joints for all
In Fig. 4, the actual deflection of the Inclinometer,
remaining panel joints, prior to proceeding with
installed in the wall panel, is also shown. It is
excavation. No such leakage issues were
seen that the recorded Inclinometer readings
reported thereafter. The Station box is now fully
immediately after leakage, match the plot Case A
completed and ready to be put into service.
representing the projected values for reduced Es
value of 3000 kPa and disturbance zone of 5m. 7 CONCLUSIONS
For Cases B & C representing lower Es values i.e. The observed values for the D’Wall
higher soil disturbance conditions, it is seen that inclinometer matches well with thecomputed
computed deflection values of the Inclinometer, deformation for Case A.
exceed the actually recorded values. So is the
case for Case D, which considers a 10 disturbed As per Case A the BM in D’Wall has
zone. Based on this, it is concluded that the soil increased from 858 to 952 kN.m/m on account
disturbance has not spread beyond 5m from of leakage but remains well within its capacity.
D’Wall face.
The disturbed zone is limited to about 5m
beyond the face of the D’Wall.
Table 1: Summary of Plaxis Analysis Results
Cases Es*(kP Max BM Remark The computed deformation for the lower Es
a) D’Wa (kN.m/ s values (Cases B & C) and 10m disturbed
ll Def m) zone (Case D), is in excess of the observed
(mm) deformation, hence not considered applicable.
Original 11000 20.5 858 Case A
Soil is The reduction in Subsoil strength has a more
A –Es=3000 3000 28.9 922 closest
pronounced effect on deformation values of
Disturbance to the
actual the D’Wall compared to the effect of the
upto 5m
Inclino extent of zone of disturbance.
B-Es =2000 2000 36.7 1020
meter
Disturbance
readings
upto5m
References
C- Es=1000 1000 46 900
Disturbance RJJ Mair (1998), ‘Recent experiences of tunneling and
upto 5 m Deep Excavations in London SOA’, Proceeding
D- Es=2000 2000 40 1040 Fourth International Conference on Case histories in
Disturbance Geotechnical Engineering. Paper 9.- March 1998
upto 10 m
Horodeckiet. al. (2004), ‘Deep Excavations Braced by
Actually 27 Diaphragm Walls’ , ’Proceedings Fifth International
measured Conference on Case Histories in Geotechnical
values Engineering, New York, April 13 – 17, 2004
Mohammad et. al.(2013) ‘Characteristics of diaphragm
*Es – Mod. Of Elasticity of soil
wall lateral deformations and ground surface
Since Case A matches closest to the actual settlements’Case study in Iran-Ahwaz metro -
inclinometer readings, it is considered most Tunnelling and Underground Space Technology 35
representative to reflect BM & SF values (2013) 109–121’
developed in D’Wall after leakage. As per Table 1, Suched Likitlersuanget. al.(2013)- ‘Finite Element
the BM in D’Wall has increased from 858 to 952 Analysis of a Deep Excavation : A case study from
kN.m/m. However, it is still well within its design Bankok MRT ‘– Soils & Foundations-Vol 53, Issue 5,
capacity. Hence no additional structural October 2013, Pages 756 – 773
modifications were necessary, other than
improvement of surrounding subsoil by grouting.