Ericsson PO Express Rollout_Q3, Y2016_GF_Outdoor_Mahini Bazar _CMNKT50_34m 3 leg Ang

Bill Summary

GF_Outdoor_Mahini Bazar _CMNKT50_34m 3 leg Ang


Q3, Y2016 Ericsson PO Express RollouComilla
As per Existing_Bill
Sl No Item of particulars
Amount (Tk.)
A Construction of OD cabinet base / Equipment building 437,590.68
Civil work cost (Fixed) 420,369.18
Civil work cost (Changable) 17,221.50
B 3 legged Tower Foundation 560,048.88
B.1 - Earth Work in excavation and back filling with sand filling 37,676.19
B.2 - Structural design and Necessry test 13,500.00
B.3 - RCC, CC work, NCF and Plaster 266,844.84
B.4 - Reinforcement 237,977.85
B.5 - Premium for Piling and Templete caring 4,050.00
B.5 - Boring (18" dia) charge for pile + Palasiding works -
C Elecrical Work 9,270.00
D Grounding work 53,654.24
Ramp work -
Access road / Access road with Guide wall 6,120.00
7% Mobilization Charge 74,667.87
Total Civil work 1,141,351.67
Details Summary BoQ
Vendor: 382855149.xlsx
Page 2 of 48

Power Connection
GRAND Total = 1,141,351.67
As per Design
Civil Team 1.00 110,000.00 110,000.00 Total Value
Stone 595.86 220.00 131,089.20 Vat Tax 11.5%
Steel 4,359.07 65.00 283,339.72 Civil Cost
Sylhet Sand 600.00 60.00 36,000.00 Overhead 3%
Loacl Sand 400.00 25.00 10,000.00 So profit
Brick 600.00 12.00 7,200.00
Brick Chips 385.75 100.00 38,575.09
Cement 307.25 450.00 138,264.04
Pacakge Grill 1.00 95,000.00 95,000.00
Electrical 1.00 15,000.00 15,000.00
Technician 1.00 10,000.00 10,000.00
Engineer Salary 1.00 30,000.00 30,000.00
-
-
-
-
-
-
-
904,468.04
As per work
1,141,351.67 Civil Team 1 110,000.00 110,000.00
131,255.44 Stone 550 220.00 121,000.00
904,468.04 Steel 4500 62.00 279,000.00
34,240.55 Sylhet Sand 350 60.00 21,000.00
71,387.64 Loacl Sand 400 18.00 7,200.00
Brick 600 10.00 6,000.00
Brick Chips 350 95.00 33,250.00
Cement 160 450.00 72,000.00
Pacakge Grill 1 95,000.00 95,000.00
Electrical 1 15,000.00 15,000.00
Technician 1 10,000.00 10,000.00
Engineer Salary 1 30,000.00 30,000.00
-
-
-
-
-
-
-
799,450.00
Total Value 1,141,351.67
Vat Tax 11.5% 131,255.44
Civil Cost 799,450.00
Overhead 3% 34,240.55
So profit 176,405.68
Estimate Breakdown
Description
CC_Brick Chips
Item L B H Nos of Item Volume/m3
Mat 5.8 5.8 0.1 1 3.364
BTS Column base 1.5 1.5 0.1 2 0.45
RCC_Stone
Item L B H Nos of Item Volume/m3
Mat 5.8 5.8 0.5 1 16.82
Padestal 2.4 0.65 0.65 3 3.042
RCC_Brick chips
Item L B H Nos of Item Volume/m3
Bts base 1.5 1.5 0.3 2 1.35
Bts column long 3.9 0.3 0.3 2 0.702
Bts column short 2.8 0.3 0.3 2 0.504
GB 1 2.4 0.3 0.4 2 0.576
GB2 3.7 0.3 0.4 2 0.888
FB 1 2.8 0.3 0.3 2 0.504
FB 2 3.7 0.3 0.3 2 0.666
Slab 4.3 4 0.15 1 2.58
Stair 4 1 0.25 1 1
Barbet Base 1 1 0.3 4 1.2
Barbet Column 2 0.25 0.25 4 0.5
0
0
te Breakdown
Stone Sylhet Sand Local Sand Cement Brick Chips Steel
573.81318 438.14574 60.602553 249.838409 423.683406 0
Stone Sylhet Sand Local Sand Cement Brick Chips Steel
- - 53.452278 14.2539408 106.904556 -
- - 7.150275 1.90674 14.30055 -
- - - - - -
- - - - - -
485.9298 242.9649 - 129.58128 - -
87.88338 43.94169 - 23.435568 - -
- - - - - -
- - - - - -
- 19.50075 - 10.4004 39.0015 -
- 10.14039 - 5.408208 20.28078 -
- 7.28028 - 3.882816 14.56056 -
- 8.32032 - 4.437504 16.64064 -
- 12.82716 - 6.841152 25.65432 -
- 7.28028 - 3.882816 14.56056 -
- 9.62037 - 5.130864 19.24074 -
- 37.2681 - 19.87632 74.5362 -
- 14.445 - 7.704 28.89 -
- 17.334 - 9.2448 34.668 -
- 7.2225 - 3.852 14.445 -
- - - - - -
- - - - - -
Civil_T.F BOQ of
Vendor Name: 382855149.xlsx
Page 8 of 48

Ericsson PO Express Rollout_Q3, Y2016_GF_Outdoor_Mahini Bazar _CMNKT50_34m 3 leg Ang

Fixed Item
Measurement
Sl No Material Code Item of particulars Unit Quantity
Type
1 IN19009-CIVT Tension Test of deformed M.S. bars including elongation,bend etc Fixed L.S.
2 IN00005-DDCC Design fee for Green Field Service building with tower foundation Fixed Each 1.00
3 IN00074-MCCC Mass concrete /CC work with bricks chips (1:2:4) (CC Below Pilecap) Fixed m3 3.38
4 IN00036-EARC Earth work in excavation Fixed m3 103.13
5 IN00039-EARC Earth / Sand Back filling Fixed m3 85.61
6 IN00067-RCCC RCC work (1:1.5:3) with stone chips (Pile) Fixed m3 19.86
7 IN00095-PILC Boring (18" dia) charge in cast in situ pile Fixed m -
8 IN00078-RODC Reinforcement (MS Bar) 60 grade (Sub Structure) Fixed kg 3,043.20
Rig/Pilling Machine/driving machine carrying charge in all over
IN00092-PILC Fixed LS -
Bangladesh
9 IN00093-PILC Rig/Pilling Machine/drivig machine carrying charge in island site Fixed LS
Rig/Pilling Machine/drivig machine carrying charge in Hill/Haore/critical
IN00094-PILC Fixed LS
site as per
Carrying EIC
and justification
Setting of Template and Anchor bolt
CIV52.1 (a) Dhakaand
Carrying district(12m,
Setting of 15m, 20m,and
Template 23m, 25m &
Anchor 32m SST)
bolt Fixed Set
CIV52.2 (b) Outside Dhaka district (12m, 15m, 20m, 23m, 25m & 32m SST) Fixed Set 1.00
10
CIV52.3 Carrying and Setting of Template and Anchor bolt Fixed Set
(c) Critical sites (12m, 15m, 20m, 23m, 25m & 32m SST)
11 IN00081-PLSC 12 mm Plastering (1:4) with cement sand F.M 1.2 Fixed m2 6.53
12 IN00083-PLSC NCF Work only Fixed m2 6.53
TOTAL (CIVIL WORKS)

Changable Item

Measurement
Sl No Material Code Item of particulars Unit Quantity
Type
10 IN00040-EARC Sand Filling Changeble m3 -

Signature of Robi EIC Signature of Robi


Civil_T.F BOQ of
Vendor Name: 382855149.xlsx
Page 9 of 48

IN00049-PALC Palasiding works -(b) Palasiding work by bamboo post only ( c/c to 10'' ) Changeble RM -

TOTAL (CIVIL WORKS)

Signature of Robi EIC Signature of Robi


Civil_T.F BOQ of
Vendor Name: 382855149.xlsx
Page 10 of 48

Y2016_GF_Outdoor_Mahini Bazar _CMNKT50_34m 3 leg Ang

Fixed Item
Existing RAx
Amount (Taka)
rate (Taka)
5,850.00 -
13,500.00 13,500.00
7,425.00 25,074.23
193.50 19,955.12
207.00 17,721.06
12,100.00 240,330.20
720.00 -
78.20 237,977.85
37,800.00 -

47,700.00 -
45,000.00
-
2,500.00 -
4,050.00 4,050.00

5,400.00 -

153.00 999.47
67.50 440.94
TOTAL (CIVIL WORKS) 560,048.88

Changable Item

Existing RAx
Amount (Taka)
rate (Taka)

612 -

Signature of Robi EIC Signature of Robi


Civil_T.F BOQ of
Vendor Name: 382855149.xlsx
Page 11 of 48

675 -

TOTAL (CIVIL WORKS) -

Signature of Robi EIC Signature of Robi


Page 12 of 48 382855149.xlsx

CXCKR74
Footing/Pile Pile EGL to Cut off level Below EGL 2.500
Number of Pile Cut off length CC 0.100
Pile Length Pile cap 5.800m 5.8 m .5 m Above EGL 0.500
Width Depth Width Depth Width Depth
FB1 0.300 0.450 FB3 GB1 0.300 0.400
FB2 0.300 0.450 FB4 GB2 0.300 0.400
Column Size 0.300 0.300 SB1
Col. Main Bar 20 mm 32.000 16 mm 8.000
Pedestal 2.40 m .65 m .65 m

1 Reinforcement (MS Bar-60 Grade) (IN00078-RODC) Sub Structure)


No of Total
Bar Size Weight Length Nos of Bar weight
Location/ Description Item length
mm kg/m m m kg
Pile
Straight bar Full length 16 mm 1.579 0 - 0.000 7.000 -
Straight bar Short Length 16 mm 1.579 0 0.000 -
Lapping 16 mm 1.579 0 0.960 0.000 7 -
Stirrup 10 mm 0.617 0 1.206 0.000 0 -
Close ring 10 mm 0.617 0 1.005 0.000 1 -
Pile Cap
Top bar long (Upper) 16 mm 1.579 1 6.220 6.220 47 461.605
Top bar short (Upper) 16 mm 1.579 1 6.220 6.220 47 461.605
Bottom Bar long (Lower) 16 mm 1.579 1 6.220 6.220 47 461.605
Bottom Bar short (Lower) 16 mm 1.579 1 6.220 6.220 47 461.605
Extra side binder 10 mm 0.617 3 22.720 68.160 2 84.109
Chair 10 mm 0.617 1 1.300 1.300 14 11.229
Pedestal Column
Main Bar upto EGL 20 mm 2.467 3 3.364 10.092 32.000 796.703
Main Bar upto EGL 16 mm 1.579 3 3.364 10.092 8.000 127.482
Stirrup 10 mm 0.617 3 2.380 7.140 12 52.865
10 mm 0.617 3 2.050 6.150 12 45.535
10 mm 0.617 3 2.050 6.150 12 45.535
U Bar 10 mm 0.617 3 2.250 6.750 8 33.318
Kg Total 3,043.195
Say = Kg Total 3,043.195

Sl No Description of Material Unit Quantity


2 Design fee for Green Field Service building with tower foundation ( IN00005-DDCC)
Width/ Vol./area
Description of work Length (m) Breadth (m) Unit Total No (B) Total Qty
depth (m) length (A)
Structure Each 1 1.000
Each Total 1.000
Say = Each Total 1.000

Sl No Description of Material Unit Quantity


3 Earth work in excavation ( IN00036-EARC )
Width/ Vol./area
Description of work Length (m) Breadth (m) Unit Total No (B) Total Qty
depth (m) length (A)
Pile Cap 6.300 6.300 2.500 99.225 m3 1 99.225
Gate Column Footing 1.600 1.600 1.200 3.072 m3 0 -
Boundary Column Footing 1.100 1.100 1.075 1.301 m3 3 3.902
m3 Total 103.127
Say = m 3
Total 103.127
Page 13 of 48 382855149.xlsx

4 Earth / Sand Back filling (IN00039-EARC)


Width/ Vol./area
Description of work Length (m) Breadth (m) Unit Total No (B) Total Qty
depth (m) length (A)
Pile Cap 6.300 6.300 2.500 99.225 m3 1 99.225
Gate Column Footing 1.600 1.600 1.200 3.072 m3 0 -
Boundary Column Footing 1.100 1.100 1.075 1.301 m3 3 3.902
Deduction
Concrete of Pile Cap 5.800 5.800 0.500 16.820 m3 1 (16.820)
Concrete of column 0.350 0.350 1.900 0.233 m3 3 (0.698)
Boundary Column Footing 0.600 0.600 0.250 0.090 m3 0 -
Boundary Column 0.200 0.200 0.750 0.030 m3 0 -
Gate Column Footing 1.000 1.000 0.250 0.250 m3 0 -
m3 Total 85.609
Say = m3 Total 85.609
5 Sand Filling ( IN00040-EARC )
Width/ Vol./area
Description of work Length (m) Breadth (m) Unit Total No (B) Total Qty
depth (m) length (A)
Access Road 12.000 4.000 1.000 48.000 m 3
0 -
Land Development 12.000 9.000 0.300 32.400 m3 0 -
m 3
Total -
Say = m3 Total -

6 RCC work (1:1.5:3) (IN00067-RCCC (A)) with stone chips (Pile - without shuttering Work)
Width/ Vol./area
Description of work Length (m) Breadth (m) Unit Total No (B) Total Qty
depth (m) length (A)
Pile - 0.159 - m3 0 -
Pedestal 2.400 0.650 0.650 1.014 m3 3 3.042
Pile Cap 5.800 5.800 0.500 16.820 m3 1 16.820
m3 Total 19.862
Say = m3 Total 19.862

7 Mass concrete /CC work with bricks chips (1:2:4) (IN00074-MCCC) with brick chips ( Sub Structure )
Width/ Vol./area
Description of work Length (m) Breadth (m) Unit Total No (B) Total Qty
depth (m) length (A)
CC Below Pilecap / footing 5.800 5.800 0.100 3.364 m3 1 3.364
Ladder base 0.500 0.250 0.100 0.013 m3 1 0.013
m3 Total 3.377
Say = m3 Total 3.377

8 12 mm Plastering (1:4) with cement sand F.M 1.2 (IN00081-PLSC)

Width/ Vol./area
Description of work Length (m) Breadth (m)
depth (m) length (A)
Unit Total No (B) Total Qty

Pedestal 2.6 .68 mm 1.755 m^2 3 5.265


Pedestal Top .65 mm .65 mm 0.4225 m^2 3 1.268
Total 6.533
9 NCF Work only

Width/ Vol./area
Description of work Length (m) Breadth (m)
depth (m) length (A)
Unit Total No (B) Total Qty

Pedestal 2.6 0 0.675 1.755 m^2 3 5.265


Pedestal Top .65 mm .65 mm 0.4225 m^2 3 1.268
Total 6.533

10 Boring (18" dia) charge in cast in situ pile (IN00095-PILC)


Width/ Vol./area
Description of work Length (m) Breadth (m) Unit Total No (B) Total Qty
depth (m) length (A)
Pile 0.300 m 0 -
Say = m2 Total -

11 Palasiding works - Supplying,fitting,placing,driving etc. complete as per EIC direction


Width/ Vol./area
Description of work Length (m) Breadth (m) Unit Total No (B) Total Qty
depth (m) length (A)
Page 14 of 48 382855149.xlsx

(b) Palasiding work by bamboo post only


IN00049-PALC
( c/c to 10'' ) 23.200 23.200 m 0

Say = m2 Total -
Civil BoQ
Vendor: 382855149.xlsx
Page 15 of 48

Fixed Item
Measurement Existing RAx
Sl No Material Code Item of particulars Unit Quantity
Type rate (Taka)
1 IN00036-EARC Earth work in excavation Fixed m3 7.776 193.50
2 IN00039-EARC Earth / Sand Back filling Fixed m3 6.10 207.00
3 IN00059-PAWC 5" Brick work (1:4) Fixed m2 11.100 760.00
4 IN00060-PAWC 10" Brick work (1:4) Fixed m3 0.188 5,040.00
5 IN00065-RCCC RCC work (1:1.5:3) with brick chips Fixed m3 12.73 9,700.00
6 IN00068-MCCC 38mm Artificial patent stone work with NCF (1:1.5:3) with brick chips Fixed m2 23.320 432.00
7 IN00074-MCCC CC work (1:2:4) with brick chips Fixed m3 0.450 7,425.00
SS door with polysterin for BTS with a SS lock protector, hatch bolt, door
CIV47.67 handle, tower bolt etc ( 1.5" thick shutter with 16 BWG,double sheet for Fixed m2 - 7,000.00
making box)
8 IN00156-TILC Colour glazed wall tiles any size (local Best quality as per EIC) Fixed m2 - 1,600.00
Colour glazed homogenous floor tiles any size (local Best quality as per
IN00157-TILC
EIC)
Fixed m2 - 1,700.00
9
10 IN00081-PLSC 12 mm Plastering (1:4) with cement sand F.M 1.2 Fixed m2 48.880 157.50
11 IN00161-AMXC Admixture for concreting Fixed Ltr 5.000 198.00
12 IN00105-PNTC plastic paint Fixed m2 - 135.00
IN00091-ROFC Flexible roofing compound & Painting Fixed m2 - 180.00
13 IN00106-PNTC Weather coat Fixed m2 43.380 144.00
14 IN00078-RODC Reinforcement (MS Bar) 60 grade (Super Structure) Fixed kg 1,315.878 78.20
17 IN00141-STLC Grill works as 4" c/c Changeble m2 32.490 2,655.00
18 IN00150-CGIC Colored CI sheet works Changeble m2 25.485 1,206.00
19 IN00129-STLC MS Angle work Changeble kg 225.200 78.20
20 IN00308-GIPC 100mm GI Pipe Changeble RM 6.000 1,450.00
21 IN00434-MISC Best quality door lock (Best quality foreign/kiko As per EIC) Changeble Nos 2.000 765.00
Supplying, fitting and fixing of GI Barbed Wire (3ply, 12BWG) in
22 IN00133-STLC
Boundary wall 6" c/c both horizontally and vertically
Fixed m2 12.00 720.00
TOTAL (CIVIL WORKS)
Signature Of Vendor Representative Signature Of Robi EIC Signature Of Robi Design Team
Civil BoQ
Vendor: 382855149.xlsx
Page 16 of 48

Changble Item

Measurement Existing RAx


Sl No Material Code Item of particulars Unit Quantity
Type rate (Taka)

23 IN00040-EARC Sand Filling Changeble m3 - 612


24 IN00060-PAWC 10" Brick work (1:4) Changeble m3 - 5040
24 IN00170-LDRC Ms steel ladder with railing (6" step). Changeble Sqm - 6750
Ms steel ladder for roof access 450mm wide, making with angle
IN00171-LDRC 50mmx50mmx5mm two nos vertical post and 20mm dia deformed rod Changeble Sqm -
26 @300 c/c with safety case as per EIC 6300
Supplying,fitting,fixing of galvanized steel horizontal outdoor cable
27 IN00125-STLC ladder with necessary hole (angle: 38mmx38mmx4mm, step @ Changable Sqm 4.30 4,005.00
300mm, 300~400mm width)
28 IN00169-LDRC Aluminum Folding ladder ( Wide 14") Changable Sqm - 1485
TOTAL (CIVIL WORKS)

Signature Of Vendor Representative Signature Of Robi EIC Signature Of Robi Design Team
Civil BoQ
Vendor: 382855149.xlsx
Page 17 of 48

Amount (Taka)

1,504.66
1,263.11
8,436.00
947.52
123,488.71
10,074.24
3,341.25

7,698.60
990.00
-
-
6,246.72
102,901.63
86,260.95
30,735.15
17,610.64
8,700.00
1,530.00
8,640.00

420,369.18 100%
Signature Of Vendor Representative Signature Of Robi EIC Signature Of Robi Design Team
Civil BoQ
Vendor: 382855149.xlsx
Page 18 of 48

Amount (Taka)

-
-
-

17,221.50

-
17,221.50 100%

Signature Of Vendor Representative Signature Of Robi EIC Signature Of Robi Design Team
Vendor: Page 19 of 48 382855149.xlsx

As Standard drawing
Length (m) Breth (m) EGL to PL Below egl Floor slab Roof slab Floor height
BTS space (o/o) 4.00 4.30 2.00 1.200 0.150 1.500
Gen Space (o/o) Width Depth
Length witdth depth No GB
Footing 1.50 1.50 0.300 2.000 FB1 0.30 0.450
Column 0.300 0.300 4.000 FB2 0.30 0.45
Equipment Base RB1
CC (Below Footing) 1.50 1.50 0.100 RB2

Fill only colour

Sl No Description of Material Unit Quantity


1 Earth work in excavation ( IN00036-EARC )
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Footing 1.800 1.800 1.200 3.888 m3 2 7.776
m3 Total 7.776
Say = m3 Total 7.776
2 Earth / Sand Back filling (IN00039-EARC)
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Footing 1.800 1.800 1.200 3.888 m3 2 7.776
Deduction
Base 1.500 1.500 0.300 0.675 m3 2 1.350
Concrete of column 0.900 0.300 0.300 0.081 m3 4 0.324
m3 Total 6.102
Say = m3 Total 6.102
3 Sand Filling ( IN00040-EARC )
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Access Road 15.000 2.500 1.000 37.500 m3
0 -
Land Development 15.000 12.000 0.500 90.000 m3 0 -
m 3
Total -
Say = m3 Total -
Vendor: Page 20 of 48 382855149.xlsx

4 5" Brick work (1:4) (IN00059-PAWC)


Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
BTS wall - Long 3.401 1.500 5.102 m2 0 -
BTS wall - Short 3.700 3.000 11.100 m2 1 11.100
Parapet 16.602 0.150 2.490 m2 0 -
Generator wall _Long - 1.050 - m2 2 -
Generator wall _Short - 1.050 - m2 2 -
Deduction
Door 2.100 1.100 2.310 m2 0 -
10" Brick column for Door 0.250 1.500 0.375 m2 -
` (0.600) 0.420 (0.252) m2 0 -
Grill 3.401 0.500 1.701 m2 -
m2 Total 11.100
m2 Total 11.100
Say = m2 Total 11.100
5 10" Brick work (1:4) (IN00060-PAWC)
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Equipment wall/Door Wall Co 0.250 0.250 3.000 0.188 m3 1 0.188
BTS wall - Long (Inlet wall) 3.401 0.250 1.500 1.275 m2 - -
Inlet 0.620 0.620 0.384 m2 0 -
Brick Column 2.600 0.25 0.250 0.650 m3 0 -
m3 Total 0.188
m3 Total 0.188
Say = m3 Total 0.188
6 10" Brick work (1:4) (IN00060-PAWC)
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Access road - Guide wall 5.000 0.250 1.500 1.875 m3 0 -
m3 Total -
m3 Total -
Say = m3 Total -

7 RCC work (1:1.5:3) (IN00067-RCCC) with brick chips (Sub Structure)


Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Footing 1.500 1.500 0.300 0.675 m3 2 1.350
Colume up to PL 2.350 0.350 0.350 0.288 m3 4 1.152
GB 1 - Long 3.700 0.300 0.400 0.444 m3 2 0.888
GB 2 - Short 2.400 0.300 0.400 0.288 m3 2 0.576
Floor beam (FB1) - Long 3.700 0.300 0.450 0.500 m3 2 0.999
Floor beam (FB2) - Short 2.400 0.300 0.450 0.324 m3 2 0.648
Roof beam (RB1) - Long 3.700 - - - m3 0 -
Roof beam (RB2) - Short 2.400 - - - m3 0 -
Floor Slab 4.001 4.300 0.150 2.581 m3 1 2.581
Roof Slab 4.600 5.200 - - m3 1 -
Extra slab for stair 4.001 1.000 0.150 0.600 m3 1 0.600
Column (Barbed wire) 2.000 0.250 0.250 0.125 m3 4 0.500
Column Base (Barbed wire) 1.600 1.600 0.250 0.640 m3 4 2.560
RCC Stair West Slab 4.000 0.900 0.150 0.540 m3 1 0.540
Step 0.900 0.250 0.150 0.034 m3 10 0.338
m3 Total 12.731
Say = m3 Total 12.731
Vendor: Page 21 of 48 382855149.xlsx

8 Artificcial patent stone work with NCF (1:1.5:3) (IN00072-MCCC) with brick chips
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
BTS Floor 4.000 4.300 17.200 m2 1 17.200
BTS roof 4.901 5.200 25.485 m2 -
Step top 0.900 0.250 0.225 m2 10 2.250
Veranda 4.300 0.900 3.870 m2 1 3.870
m2 Total 23.320
Say = m2 Total 23.320
9 CC work (1:2:4) with brick chips
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Footing Bottom 1.500 1.500 0.100 0.225 m3 2 0.450
Ladder Base 0.450 0.450 0.075 0.015 m3 0 -
Door Front 1.400 0.600 0.075 0.063 m3 0 -
Generator floor - - 0.075 - m3 1 -
Total 0.450
Say = m3 Total 0.450

9 12 mm Plastering (1:4) with cement sand F.M 1.2 (IN00081-PLSC)


Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
BTS wall - Long 3.700 3.000 11.100 m2 2 22.200
Beam 4.300 0.900 3.870 m2 4 15.480
Column 1.500 1.200 1.800 m2 4 7.200
Parapet 19.600 0.450 8.820 m2 0 -
Generator wall _Long 0 2 1.05 - m2 0 -
Generator wall _Short 0 0 1.05 - m2 0 -
Column (Barbed wire) 0.500 2.000 1.000 m2 4 4.000
Deduction
Beam at celing portion 16.602 0.00 m2 0 -
Door 2.100 1.100 2.310 m2 0 -
Inlet 0.600 0.600 0.360 m2 0 -
Outlet 0.520 0.420 0.218 m2 0 -
Generator door 2.100 1.500 3.150 m2 0 -
m2 Sub Total 48.880
Say = m2 Total 48.880
Vendor: Page 22 of 48 382855149.xlsx

10 Weather coat (IN00106-PNTC)


Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
BTS wall - Long 3.700 3.000 11.100 m2 2 22.200
BTS wall - Short 4.300 0.900 3.870 m2 4 15.480
Carnish with edge 1.500 0.450 0.675 m2 4 2.700
Parapet 19.600 0.450 8.820 m2 0 -
Generator wall _Long 0 1.05 - m2 0 -
Generator wall _Short 0 1.05 - m2 0 -
Column (Barbed wire) 0.5 2 1.000 m2 3 3.000
Deduction
Door 2.100 1.100 2.310 m2 0 -
Inlet 0.600 0.600 0.360 m2 0 -
Outlet 0.520 0.420 0.218 m2 0 -
Generator door 2.100 1.500 3.150 m2 0 -
Say = m2 Total 43.380
11 Plastic paint
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Celing 4.001 4.30 - 17.204 m2 0 -
Say = m2 Total -
12 Flexible roofing compound & Painting
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Celing 4.850 5.45 - 26.433 m2 0 -
Say = m2 Total -
13 Grill works as 4" c/c (IN00141-STLC)
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Equipment area Long wall 3.700 2.850 10.545 m2 2 21.090
Short wall 4.000 2.850 11.400 m2 1 11.400
m2 Total 32.490
Say = m2 Total 32.490
13 CI Sheet work
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Total Area (Gen. Room) 4.901 5.200 25.485 m2 1.000 25.485
m2 Total 25.485
Say = m2 Total 25.485
14 Ms Angle & Box
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Parlin (38mm x 38mm x
5mm) 4.901 0.071 13.66 kg 8 109.280
Parlin
Rafter C/C-0.7m
(38mm x 38mm x 0.005
5mm) 5.2 0.071 14.49 kg 8 115.920
Rafter C/C-0.7m 0.005
Peripheral Angle Box 0.0 0.071 0 kg 0 -
(38mm x 38mm x 5mm-Box) 0.005
MS Plate for pipe 0.3 0.300 0.005 3.53 kg 0 -
m2 Total 225.200
Say = m2 Total 225.200
15 100 mm MS Pipe
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
MS pipe 100mm 3 Rm 2 6.000
Say = m2 Total 6.000
Ms steel ladder for roof access 450mm wide, making with angle 50mmx50mmx5mm two nos vertical post
16
and 20mm dia deformed rod @300 c/c with safety case as per EIC
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Vendor: Page 23 of 48 382855149.xlsx

Ladder (EGL to PL) 3.075561 0.500 1.537781 m2 0 -


Total -

17 Ms steel ladder with railing (6" step).


Ladder (PL to roof) 3.075561 0.500 1.537781 m2 0 -
Say = m2 Total -
18 Colour glazed wall tiles any size (local Best quality as per EIC)
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
BTS Room Long wall Inside 3.401 1.500 5.102 m2 0 -
BTS Room Short wall Inside 3.700 1.500 5.550 m2 0 -
Beam Bottom 14.202 0.125 1.775 m2 2 3.551
Column cubla 1.500 0.350 0.525 m2 #REF! #REF!
Sub Total -
Deduction
BTS Door 1.05 2.100 2.205 1 2.205
Inlet 0.45 0.500 0.225 1 0.225
Outdoor 0.40 0.420 0.168 1 0.168
m2 Sub Total 2.60
Say = m2 Total -

18 Colour glazed homogenous floor tiles any size (local Best quality as per EIC)
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
BTS Floor 4.001 4.300 17.204 m2 1 17.204
Say = m2 Total -
SS door with polysterin for BTS with a SS lock protector, hatch bolt, door handle, tower bolt etc ( 1.5" thick
19
shutter with 16 BWG,double sheet for making box)
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
BTS Door 2.100 1.050 2.205 m2 0 -
Generator Door 2.100 1.500 3.150 m2 0 -
Say = m2 Total -
Vendor: Page 24 of 48 382855149.xlsx

20 Reinforcement (MS Bar) (Super Structure)


No of Total
Bar Size Weight Length Nos of Bar weight
Location/ Description Item length
mm kg/m m m kg
Footing
Main Bar Long 16 mm 1.58 2 1.500 3.000 8 37.872
Main Bar Short 16 mm 1.58 2 1.500 3.000 8 37.872
Column
Main bar up to EGL 16 mm 1.58 2 3.328 6.656 8 84.025
Stirrup 10 mm 0.62 2 0.980 1.960 19 22.977
Main bar EGL to Roof 16 mm 1.58 0 2.140 0.000 6.000 -
Stirrup 10 mm 0.62 0 0.980 0.000 11.000 -
Grade Beam (GB2)- Long -
Main bar (St) 16 mm 1.58 2 4.400 8.800 6 83.318
Stirrup 10 mm 0.62 2 0.950 1.900 22 25.791
Grade Beam (GB1)- Short -
Main bar (St) 16 mm 1.58 2 3.400 6.800 6 64.382
Stirrup 10 mm 0.62 2 0.950 1.900 14 16.412
Floor Beam
Floor Beam (FB1)
Main bar (St) 20 mm 2.47 2 3.600 7.200 6 106.531
Stirrup 10 mm 0.62 2 1.280 2.560 14 22.113
Floor Beam (FB2)
Main bar (St) 20 mm 2.47 2 4.500 9.000 6 133.164
Main bar (ckd) 20 mm 2.47 2 1.500 3.000 2 14.796
Stirrup 10 mm 0.62 2 1.255 2.510 22 34.071
Slab (Floor)
St Bar at Long section (1) 10 mm 0.62 1 4.220 4.220 20.42857143 53.191
Ckr Bar at Long section (1) 10 mm 0.62 1 4.520 4.520 29.66666667 82.736
Extra top Long section 10 mm 0.62 1 1.550 4.220 77 200.488
St Bar at Short section(2) 10 mm 0.62 1 3.921 3.921 50.33333333 121.769
Stair Slab 10 mm 0.62 2 4.000 8.000 8 39.488
10 mm 0.62 2 0.900 1.800 20 22.212
Slab (Roof)
St Bar at Long section (1) 10 mm 0.62 0 4.741
0.000 19 -
Ckr Bar at Long section (1) 10 mm 0.62 0 4.741
0.000 18 -
Extra top Long section 10 mm 0.62 0 1.450
0.000 19 -
St Bar at Short section(2) 10 mm 0.62 0 5.040
0.000 18 -
Ckr Bar at Short section 10 mm 0.62 0 5.040
0.000 17 -
Extra top (3) 10 mm 0.62 0 1.700
0.000 18 -
Column (Barbed wire) 12 mm 0.89 4 1.700
6.800 4 24.154
Column (Barbed wire) Base 12 mm 0.89 4 2.200
8.800 4 31.258
RCC Stair Main bar 10 mm 0.62 2 4.400
8.800 6.000 32.578
10 mm 0.62 2 1.000
2.000 20 24.680
Kg Total 1,315.878
Say = Kg Total 1,315.878
Supplying, fitting and fixing of GI Barbed Wire (3ply, 12BWG) in Boundary wall 6" c/c both horizontally
13
and vertically (IN00133-STLC)
Breadth Width/ Vol./area
Description of work Length (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Equipment area Long wall 6.000 2.000 12.000 m2 1 12.000
Short wall 0.600 0.500 0.300 m2 0 -
m2 Total 12.000
Say = m2 Total 12.000
Vendor: Page 25 of 48 382855149.xlsx

2.000
2.00
Vendor: Page 26 of 48 382855149.xlsx
Fixed Item
Measurement
Sl No Material Code Item of particulars
Type
1 4 x 25 rm NYY Aluminium Cable (Meter to BTS) Fixed
2 IN10037-CBLE 1 x 2.5 rm BYA CABLE Fixed
3 IN10038-CBLE 1 x 1.5 rm BYA CABLE Fixed
4 IN10044-SWTE 15 amp 2 pin Combined socket Fixed
5 IN10045-SWTE 15 amp 3 pin Combined flat socket Fixed
6 IN10046-SWTE 15 amp 3 pin Combined round socket Fixed
7 IN10049-SWTE 2 gang 1 way Fixed
8 IN10048-SWTE 1 gang 1 way (For security light) Fixed
9 IN10153-LGHE Energy saving light (23 w) Fixed
10 IN10205-PFPE 1.5 dia plastic flexible pipe Fixed
11 IN10212-PLCE 1" Plastic channel Fixed
12 IN15051-CNIG 1.5 " dia copper clamp Fixed
13 IN10219-CSOE 16 rm Cable socket Fixed
14 IN10216-CSOE 2.5 rm Cable socket Fixed
15 IN10215-CSOE 1.5 rm Cable socket Fixed
16 IN10262-MISE Battel holder Fixed
17 IN10266-MISE Plastic board MK fitting Fixed
18 IN10065-CBRE 10 AMP SP Circuit Breaker Fixed
19 IN10102-CBRE 63 AMP TP Circuit Breaker (16KA) (for Genset DB) Fixed
20 IN10185-MDBE DB for Genset room (half rate due to Small size) Fixed
Transportation and Installation of Main Distribution
21 No code Fixed
Box(MDB)

Transportation of cable ladders with accessories from


No Code Changable
Tongi Warehouse to the site (a). Inside Dhaka district

21 Transportation of cable ladders with accessories from


No Code Changable
Tongi Warehouse to the site (b). Except Dhaka district

Transportation of cable ladders with accessories from


No Code Changable
Tongi Warehouse to the site (c). Critical site
TOTA

Changable Item
Measurement
Sl No Material Code Item of particulars
Type
22 IN10148-LGHE Security light shade (As per EIC) Fixed
23 No Code Fire Extinguisher Changeble
Supplying,fitting,fixing of painted steel horizontal cable
24 IN00125-STLC Changable
tray as per the instruction of EIC(as per drawing)

Supplying,fitting,fixing of painted steel vertical cable


25 IN00126-STLC Changable
tray as per the instruction of EIC(as per drawing)

4'' Long Rowel Bolt - (If not available at Robi Ware


26 IN00431-MISC Changble
house for Equipment ladder)
Outdoor Cable Ladder (Supplied by Robi) Modification
27 No Code Changable
and Installation
TOTA
m
RAx rate
Unit Quantity Amount (Taka)
(Taka)
m - 401.870375 -
m 20.00 32.4 648.00
m 12.4797 -
m 473 -
each 1.00 473 473.00
each 1.00 473 473.00
each 2.00 315 630.00
each 113 -
each 1.00 396 396.00
m 10.00 54 540.00
m 62.5 -
each 45 -
each 19.6666666667 -
each 7.4166666667 -
each 4.5833333333 -
each 1.00 50 50.00
each 5.00 62 310.00
each 325 -
each 2250 -
each 9000 -
each 1.00 2250 2,250.00

each -
3600

each -
4500
each -
6300
TOTAL (ELECTRICAL WORKS) 5,770.00

tem
RAx rate
Unit Quantity Amount (Taka)
(Taka)
each 996.666666667 -
each 1.00 3,500.00 3,500.00
Sqm -
2700 -

Sqm -
2700 -

Nos 0.00
90 -

m - 450.00
-
TOTAL (ELECTRICAL WORKS) 3,500.00
100%
Fixed Item

Measuremen
Sl No Material Code Item of particulars Unit Quantity
t Type
50 rm GREEN cable interconnect
1 IN15001-GRCG Fixed m 3
with pit bio metric connector
3 IN15059-MISG Concrete Chamber (1'-0" x 1'-0" x1'-6") Fixed Each 2
5 IN15056-MISG Copper planger Fixed each 6
6 IN15057-MISG Aluminium MGB Fixed each 2
7 IN15009-GRAG 75 rm GREEN / BLACK Aluminium ca Fixed m 30
No code Bi-Metalic Conductor (Al-Cu) - CME it Fixed Each 3
TOTAL (GROUNDING)

Changable Item

Measuremen
Sl No Material Code Item of particulars Unit Quantity
t Type
50 rm naked copper cable with 20 '
8 IN15032-BORG Changeble m 30
long 1.5 GI pipe (Grounding Boring)
9 IN15035-SOCG 50 rm cable socket Changeble Each 10
10 IN15049-CNIG .5 " dia copper clamp Changeble Each 20
TOTAL (GROUNDING)
RAx rate
Amount (Taka)
(Taka)
945.00 2835.00
1,460.62 2921.24
338.00 2028.00
540.00 1080.00
180.00 5400.00
180.00 540.00
TOTAL (GROUNDING) 14804.24 100%

RAx rate
Amount (Taka)
(Taka)
33750.00
1,125.00
68.00 680.00
27.00 540.00
TOTAL (GROUNDING) 38850.00 100%
Civil_Ramp BOQ of
Vendor Name: 382855149.xlsx
Page 34 of 48

RAMP
RAMP Required ? No
Fixed Item

Sl
Material Code Item of particulars Measurement Type Unit Quantity RAx rate (Taka)
No
1 IN00067-RCCC RCC work (1:1.5:3) with stone chips (Above Pile Cap and Fixed m3 4.30 12,100.00
footing)
2 IN00068-MCCC 38mm Artificial patent stone with NCF (1:2:4) Fixed m2 4.80 432.00
Mass concrete /CC work with bricks chips (1:2:4) (CC Below
3 IN00074-MCCC Fixed m3 0.32 7,425.00
Pilecap)
4 IN00081-PLSC 12 mm Plastering (1:4) with cement sand F.M 1.2 Fixed m2 42.03 157.50
5 IN00083-PLSC NCF Work only Fixed m2 4.80 67.50
6 IN00106-PNTC Weather coat Fixed m2 37.23 144.00
7 IN00128-STLC Stair Railing consistts of 1.5 dia handle (MS pipe) Fixed m2 - 1,467.00
8 IN00161-AMXC Admixture for concreting Fixed Ltr 8.00 198.00
9 IN00078-RODC Reinforcement (MS Bar) 60 grade (Super Structure) Fixed kg 546.15 75.76
10 IN00036-EARC Earth work in excavation Fixed m3 9.72 193.50
11 IN00039-EARC Earth / Sand Back filling Fixed m3 8.50 207.00
12 IN00074-MCCC Mass concrete /CC work with bricks chips (1:2:4 )(Genset Fixed m3 0.32 7,425.00
floor)
13 IN00052-BFSC One layer brick flat soling (IN00052-BFSC) Fixed m2 315.00
TOTAL (CIVIL WORKS)

Signature of Robi EIC Signature of Robi


Civil_Ramp BOQ of
Vendor Name: 382855149.xlsx
Page 35 of 48

AMP

ed Item

Amount (Taka)

52,017.90
2,073.60
2,405.70
6,620.36
324.00
5,361.70
-
1,584.00
41,376.45
1,880.82
1,759.29

2,405.70
-
117,809.51 100%
-

Signature of Robi EIC Signature of Robi


Page 36 of 48 382855149.xlsx

As per DWG of RAMP


CC 0.075 Below EGL 1.000
Footing 1.2 1.200 0.250 3.000 Ramp Length 4.000 0.125
Number Length Size Size Ramp Bredth 1.200
Column
3.00 0.250 0.250 Ramp Height (cc to top) 3.000
Width Depth No Width Depth No
Top Beam 0.400 0.400 1.000 Short Beam 0.400 0.400 2.000
Central Column 4.70 0.400 0.40
Sl No Description of Material Unit Quantity
1 Earth work in excavation ( IN00036-EARC )
Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Footing 1.800 1.800 1.000 3.240 m3 3 9.720
Start point of Ramp 1.200 1.200 0.500 0.720 m3 0 -
m3 Total 9.720
Say = m3 Total 9.720
Page 37 of 48 382855149.xlsx

2 Earth / Sand Back filling (IN00039-EARC)


Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Footing 1.800 1.800 1.000 3.240 m 3
3 9.720
Start point of Ramp 1.200 1.200 0.500 0.720 m3 0 -
Deduction
Concrete of footing 1.200 1.200 0.250 0.360 m3 3 (1.080)
Concrete of column 0.750 0.250 0.250 0.047 m3 3 (0.141)
m3 Total 8.499
Say = m3 Total 8.499
3 One layer brick flat soling (IN00052-BFSC)
Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Boundary Column Footing 1.200 1.200 1.440 m2 0 -
m2 Total -
Say = m2 Total -
Page 38 of 48 382855149.xlsx

5 RCC work (1:1.5:3) (IN00067-RCCC (B)) with stone chips (With Shuttering Work)
Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Footing 1.200 1.200 0.250 0.360 m3 3 1.080
Column 2.275 0.250 0.250 0.142 m3 3 0.427
Ramp Slab 4.000 1.200 0.125 0.600 m3 1 0.600
Mid Beam _Long 4.000 0.275 0.275 0.303 m3 1 0.303
Top Beam _Short 1.200 0.275 0.275 0.091 m3 2 0.182
RAMP Access Column (Center) 4.7 0.400 0.40 0.752 m3 1 0.752
RAMP Access Slab 3.25 0.900 0.13 0.366 m3 1 0.366
RAMP Access Slab 2.54 0.600 0.13 0.191 m3 1 0.191
Tie Beam (Room to central column) 2.5 0.400 0.40 0.400 m3 1 0.400
m2 Total 4.299
Say = m2 Total 4.299
6 Mass concrete /CC work with bricks chips (1:2:4) (IN00074-MCCC) with brick chips ( Sub Structure )
Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
CC Below footing 1.200 1.200 0.075 0.108 m3 3 0.324
m3 Total 0.324
Say = m3 Total 0.324

7 12 mm Plastering (1:4) with cement sand F.M 1.2 (IN00081-PLSC)


Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Column 2.275 1.000 2.275 m2 3 6.83
Ramp Slab 4.000 1.200 4.800 m2 2 9.60
Mid Beam _Long 1.200 1.200 1.440 m2 3 4.32
Top Beam _Short 1.200 1.200 1.440 m2 3 4.32
Side 4.000 0.125 0.500 m2 2 1.00
RAMP Access Column (Center) 4.70 1.600 7.520 m2 1 7.52
RAMP Access Slab 3.25 0.90 2.925 m2 1 2.93
RAMP Access Slab 2.54 0.600 1.524 m2 1 1.52
Tie Beam (Room to central column) 2.50 1.600 4.000 m2 1 4.00
Say = m2 Total 42.034
Page 39 of 48 382855149.xlsx

8 38mm Artificial patent stone with NCF (1:2:4)


Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
On Ramp top 4.000 1.200 1.00 4.800
Say = m2 Total 4.800
9 NCF work Only
Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Equeal To plaster 4.800
Say = m2 Total 4.800

10 Weather coat (IN00106-PNTC)


Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Column 2.28 0.00 1.00 2.28 m2 3.00 6.83
Ramp Slab 4.00 0.00 1.20 4.80 m2 1.00 4.80
Mid Beam _Long 1.20 0.00 1.20 1.44 m2 3.00 4.32
Top Beam _Short 1.20 0.00 1.20 1.44 m2 3.00 4.32
Side 4.00 0.00 0.13 0.50 m2 2.00 1.00
RAMP Access Column (Center) 4.70 0.00 1.60 7.52 m2 1.00 7.52
RAMP Access Slab 3.25 0.00 0.90 2.93 m2 1.00 2.93
RAMP Access Slab 2.54 0.00 0.60 1.52 m2 1.00 1.52
Tie Beam (Room to central column) 2.50 0.00 1.60 4.00 m2 1.00 4.00
Say = m2 Total 37.23
11 Stair Railing consistts of 1.5 dia handle (MS pipe) (IN00128-STLC)
Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Railing 4.000 0.900 3.600 m2 0 -
m2 Total -
Say = m2 Total -

12 Admixture for concreting (IN00161-AMXC)


Length Width/ Vol./area
Description of work Breadth (m) Unit Total No (B) Total Qty
(m) depth (m) length (A)
Reobuilt -1000 8.000 Ltr 1 8.000
Total 8.000
Say = Total 8.000
Page 40 of 48 382855149.xlsx

13 Reinforcement (Super Structure) - (MS Bar-60 Grade) (IN00078-RODC)


No of
Bar Size Weight Length Total length Nos of Bar weight
Location/ Description Item
mm kg/m m m kg
Column
Main Bar 16 mm 1.579 3 3.209 9.627 6 91.206
Main Bar 12 mm 0.888 3 3.209 9.627 0 -
Stirrup 10 mm 0.617 3 0.780 2.340 12.00 17.325
Footing
Main Bar - Bottom Layer 16 mm 1.579 3 1.183 3.548 6.000 33.609
Tie Bar - Bottom Layer 10 mm 0.617 3 1.183 3.548 6.000 13.133
Main Bar - Top Layer 12 mm 0.888 0 1.183 0.000 6.000 -
Tie Bar - Top Layer 10 mm 0.617 0 1.183 0.000 6.000 -
Binder 10 mm 0.617 0 4.800 0.000 3.000 -
Top Beam _Long
Main Bar 16 mm 1.579 1 4.120 4.120 5 32.527
16 mm 1.579 1 4.120 4.120 0 -
Extra top 20 mm 2.467 1 1.400 1.400 -
Stirrup 10 mm 0.617 1 1.380 1.380 18 15.326
Beam _Short
Extra top 16 mm 1.579 2 1.320 2.640 5 20.843
Stirrup 10 mm 0.617 2 1.380 2.760 4 6.812
RAMP Slab
Long Bar - Bottom 10 mm 0.617 1 4.000 4.000 6.000 14.808
Long Bar - Top 12 mm 0.888 1 4.000 4.000 11 39.072
Short Bar - Bottom 10 mm 0.617 1 1.200 1.200 27 19.991
Short Bar - Top 10 mm 0.617 1 1.200 1.200 54 39.982
RAMP Access Column (Center)
Main Bar 16 mm 1.579 1 3.209 3.209 6.000 30.402
Stirrup 16 mm 1.579 1 1.380 1.380 14 30.506
Tie Beam (Room to central column) -
Main Bar 16 mm 1.579 1.000 2.400 2.400 6 22.738
Stirrup 10 mm 0.617 1.000 1.380 1.380 10 8.515
RAMP Access Slab 10 mm 0.617 2.000 5.790 11.580 8 57.159
RAMP Access Slab 10 mm 0.617 2.000 0.900 1.800 47 52.198
Total 546.152
Civil_Access BOQ of
Vendor Name: 382855149.xlsx
Page 41 of 48

Access Road

Fixed Item

Measurement RAx rate


Sl No Material Code Item of particulars Unit Quantity
Type (Taka)
1 IN00060-PAWC 10" Brick work (1:4) Fixed m2 - 5,040.00
2 IN00081-PLSC 12 mm Plastering (1:4) with cement sand F.M 1.2 Fixed m2 - 153.00
3 IN00083-PLSC NCF Work only Fixed m2 - 67.50
4 IN00036-EARC Earth work in excavation Fixed m3 - 193.50
(e) Sand filling(carrying from others) with fine local sand minimum F.M.
5 IN00040-EARC 0.80 in 150 mm layers leveling, watering and consolidating each layer up Fixed m3 10.00 612.00
to finished level
TOTAL (CIVIL WORKS)

Signature of Robi EIC Signature of Robi


Civil_Access BOQ of
Vendor Name: 382855149.xlsx
Page 42 of 48

oad

Amount (Taka)
-
-
-
-

6,120.00

6,120.00

Signature of Robi EIC Signature of Robi


Page 43 of 48 382855149.xlsx

Access road / Access road with Guide wall _ As per DWG (Top width 1500mm)
Access Road 1.000 Access road with Guide wall
Length Width Depth Length Width Depth
Access Road 10 m 2m .50 m 5m 2m 1.5 m
Brick Layer-1 .500 m .500 m
Brick Layer-2 .375 m .300 m
Brick Layer-3 .25 m .70 m

Sl No Description of Material Unit Quantity


1 Earth work in excavation ( IN00036-EARC )
Vol./area
Description of work Length (m) Breadth (m) Width/ depth (m) Unit Total No (B) Total Qty
length (A)
Brick Foundation 5.000 0.700 0.500 1.750 m3 2 -
m3 Total -
Say = m3 Total -
Page 44 of 48 382855149.xlsx

2 Earth / Sand Back filling (IN00039-EARC)


Vol./area
Description of work Length (m) Breadth (m) Width/ depth (m) Unit Total No (B) Total Qty
length (A)
Brick Foundation 5.000 0.700 0.500 1.750 m 3
2 -
Deduction
Brick wall 5.000 0.500 0.500 1.250 m3 2 -

m3 Total -
Say = m3 Total -
(e) Sand filling(carrying from others) with fine local sand minimum F.M. 0.80 in 150 mm layers leveling, watering and consolidating
3
each layer up to finished level
Vol./area
Description of work Length (m) Breadth (m) Width/ depth (m) Unit Total No (B) Total Qty
length (A)
Earth filling 10.000 1.500 0.500 7.500 m2 1 7.500
Earth filling_Guide wall 5.000 1.500 1.000 7.500 m2 1 -
Earth filling (Slope) 10.000 0.250 0.500 1.250 m2 2 2.500
m2 Total 10.000
Say = m2 Total 10.000
Page 45 of 48 382855149.xlsx

4 10" Brick work (1:4) (IN00060-PAWC)


Vol./area
Description of work Length (m) Breadth (m) Width/ depth (m) Unit Total No (B) Total Qty
length (A)
Brick Layer-1 5.500 0.500 0.500 1.375 m3 2 -
Brick Layer-2 5.750 0.375 0.300 0.647 m3 2 -
Brick Layer-3 6.000 0.25 0.700 1.050 m3 2 -
End of Access road_ without wall
Brick Layer-1 1.500 0.50 0.500 0.750 m3 0 -
Brick Layer-2 1.500 0.38 0.300 0.450 m3 0 -
Brick Layer-3 1.500 0.25 0.700 1.050 m3 0 -
- m3
m3 Total -
m3 Total -
Say = m3 Total -
5 12 mm Plastering (1:4) with cement sand F.M 1.2 (IN00081-PLSC)
Vol./area
Description of work Length (m) Breadth (m) Width/ depth (m) Unit Total No (B) Total Qty
length (A)
Brick Layer-3 6.000 0.700 4.200 m2 2 -
Say = m2 Total -
Page 46 of 48 382855149.xlsx

6 NCF work Only


Vol./area
Description of work Length (m) Breadth (m) Width/ depth (m) Unit Total No (B) Total Qty
length (A)
Equeal To plaster -
Say = m2 Total -
Sheet Sl No Item Code
Civil_T.F 8 IN00078-RODC
Measurement_T.F. 11 IN00049-PALC
Civil 19 IN00129-STLC

Civil 27 IN00125-STLC

Measurement 3
Item Details Change Option
Reinforcement (MS Bar) 60 grade (Sub Structure) Rate Can Change (As per PO)
Palasiding works Length can chage as per site condition
MS Angle work Rate Can Change (As per PO)
Supplying,fitting,fixing of galvanized steel horizontal outdoor cable ladder with
Quantity can Change as per site actual
necessary hole (angle: 38mmx38mmx4mm, step @ 300mm, 300~400mm width)

(e) Sand filling(carrying from others) with fine local sand minimum F.M. 0.80 in Quantity can Change as per site actual
150 mm layers leveling, watering and consolidating each layer up to finished level