Professional Documents
Culture Documents
Definition of Dams
Advantages and Disadvantages of Dams
Classification of Dams
Types of Dams
What is a Dam?
Spillway
Freeboard
Sluiceway
Gallery
Heel
Toe
Definitions
Sluice Gates
Three Gorges Dam
Shipping Locks
Shipping Locks
Hoover Dam
Hoover Dam
Location: Arizona and Nevada, USA
Completion Date: 1936
Cost: $165 million
Reservoir Capacity: 1.24 trillion cubic feet
Type: Arch/ Gravity
Purpose: Hydroelectric power/flood control
Reservoir: Lake Mead
Materials: Concrete
Engineers: Bureau of Reclamation
Storage Dam
Detention Dam
Diversion Dam
Coffer Dam
Debris Dam
Classification of Dams
Detention Dam:
1. Water is stored during floods and release
gradually @ safe rate
2. Ist type: water is stored & then released
3. 2nd type: water is not released,
water seeps in pervious banks
Water level in well rises
Lift irrigation is possible
4. Seeping may be sufficient that surface water
Classification of Dams
Diversion Dam:
1. Raise water level in river & thus provides head
for carrying or diverting water into canals e.g.
weir or barriage
Classification of Dams
Coffer Dam
Classification of Dams
Debris Dam:
1.detention dams are constructed across
tributary carrying large silt and sediments
2. Debris dams traps the sediments and thus to
exclude the sediments to flow to the main
reservoir formed on main river.
Classification of Dams
Rigid Dam
Non Rigid Dam
Classification of Dams
Gravity Dam
Arch Dam
Buttress Dam
Embankment Dam
Gravity Dam
Material of Construction:
Concrete, Rubber Masonry
Gravity Dam
ADVANTAGES
• External forces are resisted by weight of dam
• More strong and stable
• Can be used as overflow dams also with spillway feature
• Highest dams can be made as gravity dams cuz of its high
stability
• Specially suited for heavy downpour; slopes of earthen dams
might get washed away
• Less maintenance required
• Gravity dam does not fail suddenly but earthen dams
Gravity Dam
DISADVANTAGES
• Can be made only on sound rock foundation
• Initial cost is high
• Takes more time to construct if materials are not available
• Requires skilled labour
Arch Dam
Material of Construction:
Concrete
Arch Dam
Curved in plan
Carried load horizontally to its by arch action
Balance of water load is transferred to the foundation by cantilever
action
Advantages
adapted in gorges where length is small in proportion to
height
dam require less material
can be made in moderate foundation cuz of load
distribution as compared to gravity dams
Arch Dam
Curved in plan
Carried load horizontally to its by arch action
Balance of water load is transferred to the foundation by cantilever
action
Disadvantages
require skilled labor
speed of construction is slow
require strong abutments of solid rock of resisting arch
thrust
Buttress Dam
Material of Construction:
Concrete, Timber, Steel
Buttress Dam
• Retain water between buttress
• Less massive than gravity Dams
• Ice pressure: ice tends to slide over the inclined U/S
so this factor is unimportant
• when future increase in reservoir; Future extension is
possible by extending buttress and slab
• Power house can be made B/W buttress; thus
reducing cost
• Can be designed to accommodate moderate
movement of foundation without any serious damage
Buttress Dam
Disadvantages
skilled labor requirements
deterioration of u/s as very thin concrete face
Embankment Dam
Material of Construction:
Earth, Rock
Earth and rockfill Dam
• Made of locally available soil & gravels
• Can be made on any type of available foundation
• Can be constructed rapidly
• Cheaper
• Future consideration can be made (raising height)
Disadvantages
• Vulnerable to damage by floods
• Cannot be used as overflow dams
not suitable where heavy downpour is more common
• High maintenance cost
Types of Dam
Factors governing selection of types of dam
Topography-Valley Shape
Climate conditions
Availability of construction materials
Environmental considerations
Overall cost
General considerations
Communication road link, rail roads
Locality: free from mosquitoes as labor
and staff colonies are constructed
Gravity Dam
Gravity Dam
W
Water Pressure
• Water pressure on the upstream face is the main
• destabilizing (or overturning) force acting on a gravity dam.
Water Pressure
Gravity Dam
Forces on Gravity Dam
Water Pressure
Gravity Dam
Forces on Gravity Dam
Water Pressure
Uplift Pressure
Uplift Pressure
A portion of the weight of the dam will be supported on the upward pressure of
water; hence net foundation reaction due to vertical force will reduce.
The area over which the uplift pressure acts has been a question of investigation
from the early part of this century.
The second school of thought, recommend that the effective area may be taken
approximately equal to the total area.
Gravity Dam
Forces on Gravity Dam
uplift Pressure
Gravity Dam
Forces on Gravity Dam
uplift Pressure
in case of
drainage
gallery
Gravity Dam
Forces on Gravity Dam
Silt Pressure
IS code recommends that
a) Horizontal silt and water pressure is assumed to be equivalent to that of a fluid with a mass of 1360
kg/m3, and
b) b) Vertical silt and water pressure is determined as if silt and water together have a density of 1925
kg/m3.
The gradual accumulation of significant deposits of fine sediment, notably silt, against the face of the dam
generates a resultant horizontal force, Ps.
a) Submerged unit weight of silt
b) Angle of internal friction
c) Height to which silt is deposit
Gravity Dam
Forces on Gravity Dam
Ice Pressure
Ice is subjected to expansion and contraction due to temperature variations
magnitude of forces varies b/w 250 kN/m2- 1500kn/m2 applied to the face of dam
over the anticipated area of contact of ice with the face of dam.
The problem of ice pressure in the design of dam is not encountered in India except,
perhaps, in a few localities.
Gravity Dam
Forces on Gravity Dam
Wind Pressure
Measures for temperature control of concrete in solid gravity dams are adopted during
construction.
The force and dimensions of waves depend mainly on the extent and configuration of
the water surface, the velocity of wind and the depth of reservoir water.
The height of wave is generally more important in the determination of the free board
requirements of dams to prevent overtopping by wave splash.
80 km/h over water in case of maximum reservoir condition should generally be assumed for
calculation of wave height if meteorological data is not available.
Sometimes the following Molitor’s empirical formulae are used to estimate wave height
A earth-fill dam in
Australia.
Embankment Dam
Rock-Fill Embankment Dam
Embankment Dam
Earth Dams:
• most simple and economic (oldest dams)
• built of natural materials.
• constructed with low-permeability soils to a nominally homogeneous
profile (single material)
• The section featured neither internal drainage nor a cutoff to restrict
seepage flow through the foundation. Dams of this type proved vulnerable
associated with uncontrolled seepage, but there was little progress in
design prior to the nineteenth century. It was then increasingly recognized
that, in principle, larger embankment dams required two component
elements.
• 1. An impervious water-retaining element or core of very low
permeability of soil, for example, soft clay or a heavily remoulded ‘puddle’
clay, and
• 2. Supporting shoulders of coarser earthfill(or of rockfill), to provide
structural stability
Embankment Dam
Homogeneous Embankment Dam
Embankment Dam
simple zoning
finer more cohesive soils placed adjacent to the impervious core
element
coarser fill material towards either face.
Central core checks the seepage
Transition zone prevent piping through cracks (that may develop
in the core)
Outer zone gives stability to the central impervious fill
Clay with fine sand as material of impervious core
Coarse sand gravel as outer shell
Transition filters are provided in between these 2 zones when
there is abrupt change in zones
Embankment Dam
Zone-Based Embankment Dam
Embankment Dam
Diaphragm Earth Dam
Thin impervious core(diaphragm) surrounded by earth or rockfill
Types:
1.Homogeneous embankment type
2.Zoned embankment type
3.Diaphragm type
Embankment Dam
Seepage calculations in embankment dams
Above the phreatic line, there will be a capillary zone in which the
hydrostatic pressure is negative
Since the flow through the capillary zone is insignificant, it is usually neglected and
hence the seepage line is taken as the deciding line between the saturated soil below
and dry or moist soil above in a dam section.
Embankment Dam
Seepage calculations in embankment dams
The flow of the seepage water below the phreatic line can be approximated by the
Laplace Equation
∂2 φ/ ∂x 2 + ∂ 2 φ/ ∂y 2 = 0
where φ=k*h is the velocity potential, k= permeability of soil; h= head causing flow
Embankment Dam
Homogeneous dam with horizontal drainage filter
Embankment Dam
It is assumed that the phreatic line which emanates at P, meets the horizontal
drainage blanket at B and is, for most of its downstream part, a parabola (first
proposed by A. Casagrande).
This curve is termed as the Base Parabola and is assumed to have its focus at
A, the upstream edge of the horizontal drainage blanket.
The Base Parabola, on its upstream part is assumed to meet the reservoir
water surface at a point P0 that is 0.3L upstream of P, as shown in Figure 49.
In order to obtain the Base Parabola, one has to consider P0 as the centre, and
draw an arc A-R, with the radius equal to P0-A. The point R is on a horizontal
line at the same elevation of the reservoir surface. From point R, a
perpendicular is dropped on to the top surface of the horizontal drainage
blanket to meet it at a point C.
Knowing the focus, the directrix and the point P0, a parabola can be drawn,
which gives the Base Parabola shape. It may be recalled that point B is mid
way of points A and C. At its upstream point, however, the parabola has to be
modified such that it takes a curve upwards and meets the point P with the
gradient of the phreatic line being perpendicular to the dams upstream face.
components
• Core
• Casing or shell
• Cutoff
• Slope protection measure
• Internal drainage system
• Surface drainage
components
Drainage system
• The conventional types of seepage control and drainage
features generally adopted for the embankment dam are:
• a) Impervious core,
• b) Inclined/vertical filter with horizontal filter,
• c) Network of inner longitudinal drain and cross drains,
• d) Horizontal filter,
• e) Transition zones/transition filters,
• f) Intermediate filters,
• g) Rock toe, and
• h) Toe drain.
Inclined/Vertical Filter
• Inclined or vertical filter abutting
downstream face of either impervious core
or downstream transition zone is provided
to collect seepage emerging out of
core/transition zone and thereby keeping
the downstream shell relatively dry. In the
eventuality of hydraulic fracturing of the
impervious core, it prevents the failure of
dam by piping.
Horizontal Filter
• It collects the seepage from the inclined/vertical
filter or from the body of the dam, in the absence
of inclined/vertical filter, and carries it to toe
drain. It also collects seepage from the
foundation and minimizes possibility of piping
along the dam seat.
Inner Longitudinal and Inner
Cross Drains
• When the filter material is not available in the
required quantity at reasonable cost, a network
of inner longitudinal and inner cross drains is
preferred to inclined/vertical filters and horizontal
filters. This type of drainage feature is
generally adopted for small dams, where the
quantity of seepage to be drained away is
comparatively small.
Rock Toe and toe drain
• The principal function of the rock toe is to provide
drainage.
• It also protects the lower part of the downstream slope
of an earth dam from tail water erosion.
• Rock available from compulsory excavation may be
used in construction of the rock toe.
• Where this is not possible and transportation of rock is
prohibitively costly, conventional pitching should be used
for protecting the downstream toe of the dam.
• The top level of the rock toe/pitching should be kept
above the maximum tail water level (TWL).
Concrete Diaphragm
• A single diaphragm or a double diaphragm
may also be used for seepage control
(Figure 46). Concrete cutoff walls placed
in slurry trench are not subject to visual
inspection during construction, therefore
require special knowledge, equipment and
skilled workmen to achieve a satisfactory
construction.
Relief Wells
• Relief wells are an important adjunct to most of the preceding basic
schemes for seepage control.
• Prevent excess hydrostatic pressures in the downstream
portion of the dam, which could lead to piping.
• They also reduce the quantity of uncontrolled seepage flowing
downstream of the dam
• . Relief wells should be extended deep enough into the foundation
so that the effects of minor geological details on performance are
minimized.
failure
• The various modes of failures of earth
dams may be grouped under three
categories:
• 1. Hydraulic failures
• 2. Seepage failures, and
• 3. Structural failures
• This type of failure occurs by the surface
erosion of the dam by water. This may
happen due to the following reasons:
Hydraulic failures
Buttress Dam
: is a gravity dam reinforced by structural supports.
Buttress
:a support that transmits a force from a roof or wall to another
supporting structure.
Typical Sections of
Buttress Dams
Buttress Dam
Multiple-Arch Dam
(Buttress Dam)
Types of Dam
Rockfill 3%
Earthfill 58%
Other 16%
Timber Crib 2%
Dam Failure
June 5, 1976: the failure in the Teton Dam led to flooding in the
cities of Sugar City and Reburg in Idaho. The dam failure killed 14
people and caused over $1 billion in property damages.
The dam failed because the bedrock was not strong enough to
support the structure. Currently the dam is once again used for
hydroelectric power.
Dam Failure