Professional Documents
Culture Documents
PROJECT:
TITLE:
APPROVED
P a g e 1 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
CONTROL OF MODIFICATIONS
Revision Modifications Date
1 Client’s Comments as per E-mail dated February 10th 18/2/2018
As per ENGINEER (TE) comments sheet No. 17-020-MS-
2 21/3/2018
002_COMMENTS SHEET Dated
DISTRIBUTION
External Internal No. of copies
APC Engineer 1
ELAF Head Office 1
MEIL Site Office 1
P a g e 2 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
TABLE OF CONTENT
PURPOSE ............................................................................................................................ 6
SCOPE ................................................................................................................................. 6
GENERAL ...................................................................................................................... 6
2.2.1 Above ground pipes installations. Comprise, aboveground portions of fuel natural
gas pipeline. ....................................................................................................................... 6
REFERENCES ....................................................................................................................... 7
DEFENITIONS ...................................................................................................................... 8
RESOURCES ........................................................................................................................ 8
First Aid........................................................................................................................ 9
P a g e 3 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
A qualified and experienced TPI NDE personnel shall be designated to examine the welding
and fabrication activities including inspection and testing. ............................................ 21
House Keeping........................................................................................................... 21
Responsibilities .......................................................................................................... 21
APPENDIX A .............................................................................................................................. 22
APPENDIX B .............................................................................................................................. 23
APPENDIX C .............................................................................................................................. 24
APPENDIX D .............................................................................................................................. 25
APPENDIX E .............................................................................................................................. 26
APPENDIX F .............................................................................................................................. 27
P a g e 4 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
APPENDIX G.............................................................................................................................. 28
P a g e 5 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
PURPOSE
This document describes the methodology and procedure of Fuel Gas Pipeline erection and
welding for the Arab Potash Company New Gas turbine power plant, and to ensure that all
concerned persons are familiar with the sequence of activities, utilization of resources, and
execution of the works in compliance with applicable Safety and Quality Procedures and in
accordance with Client’s Reference Documents.
SCOPE
GENERAL
The CONTRACTOR shall be responsible for the preparation of all required equipment and
measurement devices needed to accomplish the satisfactory piping system erection in
accordance with Client’s Reference Documents.
This method statement is intended to outline the welding and erection activities of the
followings,
2.2.1 Above ground pipes installations. Comprise, aboveground portions of fuel natural gas
pipeline.
All activities will be carried out in accordance with the contract details and in full compliance to
the Normative references. All work within the rights-of-way of the standards and specifications
will be done in compliance with Client’s Reference Documents.
P a g e 6 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
REFERENCES
EXTEND OF APPLICATION
The present method statement is all carbon steel grades intended to be used for this project
(i.e. API 5L X52 or ASTM A 333 Gr. 6)
P a g e 7 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
DEFENITIONS
• Client: ARAB POTASH COMPANY (APC)
• Contractor: MEIL (Megha Engineering & Infrastructure Ltd.)
• Sub-Contractor: ELAF Contracting Company
RESOURCES
See Appendix A
Safety Equipment
Necessary measures will be taken for the safety of the equipment and any other works affected
by the works subject of this document. Relevant entities which might require protection include
any such works in the vicinity of the area of work or on the service access or discharge path.
The construction team will ensure that any such requirements are documented.
While welding activities taking place all fabricators, welders, helpers and any personnel may
attend shall be equipped with proper PPE See Appendix C
Fire extinguishers of ABC type shall be located within workspace and workshop for emergency.
Extinguisher shall be maintained all the time
P a g e 8 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
Construction Hazard.
See Appendix B
See Appendix C
Before commencing any works, all employees will attend a site safety induction training to
ensure all safety measures are understood and implemented and to cover specific procedures
in case of emergency. If necessary, practical training exercises will be conducted on escape
routes and assembly points.
First Aid.
Prior to the commencement of work, arrangements will be done for medical facilities and
first aid box to be available from prompt attention to the injured person. The sub-contractor’s
vehicle assigned to the job site will be used for transporting the injured person to the first aid
station and to the nearest hospital when required.
Procurement of materials
P a g e 9 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
Mainly materials for the Fuel Gas Pipeline have been provided by the OWNER. Materials of types
not available in APC warehouses have been provided by the CONTRACTOR as per the
requirements and specifications of the project.
• Material quality and conformity check shall be carried out by QC engineer to ensure all
material are in good conditions in coordination with OWNER/ENGINEER
• In the event of any non-conformity of the material at the time of delivery, the
CONTRACTOR must immediately inform the OWNER/ENGINEER before accepting the
delivery. If this condition is not observed, the CONTRACTOR will be the only responsible
for all the consequences resulting therefore.
• Pipes should indicate the diameter, length, standards and heat Nos. which shall be
matching with the MTC (Mill Test Certificate), pipes shall be inspected to insure its
availability and compliance to the specifications
• All fittings (threaded, grooved, butt or socket welded), couplings, flanges, shall be
checked in coordination with OWNER/ENGINEER
• Welding electrodes and shall be inspected prior to each welding activity, to insure proper
storage, pre-heat and validity if applicable
• Inert shielding gas (Argon) purity certificate shall be submitted to the CONTRACTOR for
each patch of gas delivered to site for review and approval
• Insure coated pipes and shop coated pipes and fittings are inspected and confirmed by
the CONTRACTOR prior to fabrication
P a g e 10 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
• The pipes must show no evidence of dents. The damaged part shall be cut out and the
undamaged parts will be beveled again and bear an identification number, etc.
• CONTRACTOR should repair the defects of external coating if any.
• Pipes may be stored outdoor with a special care to prevent corrosion due to moisture,
rainfalls or dust. For coated pipes and fittings, it shall be handled with care to avoid
scratching and coating damage, over stacking for more than 8 layers is not allowed.
• All pipes ends should be capped and protected, for beveled ends a proper protection of
mechanical loadings and impacts should be arranged
• Pipes should be stored horizontally leveled, supported by soft surface sections.
• Pipes should be supported on a flat grade to prevent rolling.
• Loading and unloading of pipes should be carried out with care and using proper hoists
or mobile high-up if needed
• Fitting should be stored in wooden boxes (shipping sea worthy boxes are favorable) in a
locked storage place and should be handled properly with care
• Welding electrodes shall be kept packed in its original packing until needed and should
be stored in dry place.
Pre-erection check
• Issue the work permit in coordination with CONTRACTOR engineer and HSE department
including work duration, count of human resources, tools and equipment
• Make sure all materials to be installed are approved by CONTRACTOR engineer
• Make sure all openings, sleeves, supports, concrete sleepers along the pipe run are
permitted and inspected
Pipes fabrication
P a g e 11 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
9.5.1 Cutting
Pipe fabricator shall measure and mark the pipes intended to be cut using proper marking tool
(paint marker pen). A line all around the circumference of the pipe shall be marked to insure
straight cut. Pipe should be fixed properly in horizontal position to avoid movement while
cutting using vices and supports.
Grinders shall be inspected prior to use and insure performance; valid cutting disk of the proper
thickness and application shall be used. Grinder guard shall not be removed in any case
Cutting speed should be slow and careful to insure no departure of marked line, pipe cutting
starts from the top of the surface then moving down slowly and insure the disk penetrates
completely, pipe shall be rolled over to face the uncut surface of the pipe and so on until the
pipe is completely teared. The two pipe pieces supposed to be heated due to friction. Cooling
with water or any other medium is not permitted.
9.5.2 Beveling
Proper beveling shall be applied to the pipe butt, forming the required type V shaped groove to
achieve the required weld profile. Power 5 inches grinder should be used to bevel the pipe butt
to the desired V angle specified in the approved WPS.
For either shop or field welding, pipes shall be fitted properly in accordance to approved
drawings measurements, alignment and gap between the two edges shall be minded carefully.
P a g e 12 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
For underground fuel gas pipe, pipes shall be supported on temporary supports for fit up, every
two pipes (24m) will be fitted up on aboveground supports, while the fit up of the 24 m parts
will be done underground with enough workspace hole to be excavated.
Tack welds shall be applied with sufficient quantity to insure pipe fit up is kept firm and robust,
tack weld shall be applied to pipe surface not to the groove, however, it should be shaped to
match with groove angle. Joints with tack welds should not be hoisted or subjected to direct
mechanical loading may cause tack weld defects
Fit up shall be inspected prior to welding by QC personnel. Joints information shall be written
maximum 10 cm next on the pipe surface. Heat No, Welder No, Date and pipe size shall be
written
9.5.4 Welding
After fit up inspected and approved, welders may directly start with welding activity of the pipe
joints
9.5.4.1 WPS
9.5.5
The qualified WPS for each material intended to be used for the piping systems. Pipe materials
intended to be used are
Procedure Qualification Record (PQR) is implemented for each of the above materials.
PQR and WPS may be merged for more than one material if WPS and PQR requirement were
similar.
P a g e 13 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
WPS containing more than one process shall be approved as a combination of the two processes.
WPS includes the following basic parameters mentioned below and the complete process for
implementation,
9.5.5.1 Welders
Welders intended to applicate the WPS for the above pipe materials shall be qualified and
tested, test shall be witnessed by the Approved Third-Party Inspector and other concerned
persons.
Welders pass the test should be certified and provided with an ID card showing Name, date of
test, material and projects assigned to.
At least one sample of each material test sample shall pass the following tests to consider
qualified WPS,
9.5.5.3 Process
P a g e 14 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
Welding processes shall be implemented in compliance to the WPS and applicable codes and
standards mentioned in chapter 3. See Appendix E for PWPS
4 passes of welds are required for each joint for all material the PWPS took into account pipes
material and joints strength and flexibility in order to produce a successful weld, the four passes
are Root, Hot, Fill and Cover. Root pass basically intended to penetrate the original 2 plates
(pipes) materials and form the first bead. Root pass filler material usually differs than other
passes filler materials. In the scope of this method statements all root passes shall be done with
E70s filler material which is with the same characteristics for all passes, using Gas Tungsten Arc
Welding (GTAW).
After accomplishment of root pass, grinding may be applied to the root pass bead to remove
unwanted particulates, such as shields, coolants, dusts, and in order to smoothen the bead
surface for the next pass.
After grinding is accomplished and visually accepted, welder starts with the hot pass with E70s
GTAW process continuously all around the joint, grinding after hot pass may be required.
Summary for the welding processes to be implemented is explained in Table 9-1 and Figure 9-1
P a g e 15 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
For the fill and cover passes same procedure shall be implemented by SMAW Process using
E7018-1 electrodes. When using SMAW process grinding shall be done carefully between passes
to insure successful welds.
Figure 9-1 and Table 9-1 summarize the processes for each piping system.
Tests to be implemented for the welding joints are in accordance with ASME B 31.3, Visual
Testing (VT) shall be implemented for all piping welding joints for all systems.
Radiography Examination (RT) should be implemented for welded joints to examine welding
quality. RT should be done for 100% o in accordance to the Client Reference Documents.
Welding book should be prepared and submitted to show the joints information and testing
record. Welding book format is shown in Appendix G
Visual examination procedures shall be in accordance with ASME Section V Article 9, and this
specification.
Visual Examination shall be implemented and reported for all welds by the TPI
Acceptance criteria for Visual Inspection shall be in accordance with ASME VIII, division 2
P a g e 16 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
Penetrant materials shall meet the requirements of ASME Section V, Article 6 for Sulphur and
halogen content regardless of the type of material to be examined.
Liquid penetrant of welds shall include a band of base metal at least 25 mm wide on each side
of the weld.
The evaluation of indications and the acceptance criteria shall be in accordance with ASME
Section VIII, Division 1 or 2, whichever is applicable.
PT examination and evaluation shall be in accordance with ASME Code Section VIII Division 1
Appendix 8.
Magnetic particle examination procedures shall be in accordance with the requirements and
methods specified in ASME Section V, Article 7.
Magnetic particle examination of welds shall include a band of base metal at least 25 mm wide
on each side of the weld.
MT examination and evaluation shall be in accordance with ASME code Section VIII Division 1,
Appendix 6.
P a g e 17 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
Radiographic examination will be carried out by the approved TPI and their personnel
Industrial radiographic film selection shall be based on the type of radiation source and thickness
of material to be radio-graphed.
Intensifying screens such as lead foil, lead oxide, or fluorescent may be used.
Each radiograph must be identified uniquely, the identification on the film shall include:
• Project Designation;
• Location/Line/Weld number;
• Date;
• Datum and Location Marker (metric tape);
• Welder’s identification (or operator).
Interpretation and acceptance criteria of radiographs shall be in accordance with ASME Section
VIII, (division 1 or 2) and in accordance with ASME B31.3.
Ultrasonic examination procedures shall be in accordance with the requirements and methods
specified in ASME Section V, Article 4, 5.
UT examination and evaluation shall be in accordance with the ASME Code Section VIII,
Appendix 12.
P a g e 18 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
Golden Welds are those welds to which no hydrostatic test can be implemented on, due to
connection with existing installations or to an equipment may not be hydrostatically tested.
Any welds may be considered “Golden” as per the above definition shall be subjected to
additional NDE.
• 100% VT and
• 100% RT and
• 100% UT and
• 100% PT or MT
Testing of Golden Welds shall be implemented in the presence of OWNER/ENGINEER and TPI
report shall be submitted for approval.
P a g e 19 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
9.5.9 Quality
Inspection reports for VT, RT will be submitted for approval on stages enclosed with welding
book and welding maps
CWI will witness the welding activities to provide advisory and inspection for the production
Welders will be provided with all equipment and machines to insure the best quality of work
All welding activities (Shop and Field Welds) shall be carried out within a weather protected
areas (Enclosures). Those enclosure shall be capable to prevent any effect of wind, draught,
drizzle, rain.
TPI and OWNER/ENGINEER acceptance shall be taken in consideration for the weather
protected welding areas and shall be immediately stopped if any nonconformity or welding been
affected by weather.
A welding barrier constructed of fire retardant material may be provided to protect against
wind, drizzle and dust.
Inspection for filler metals (Electrodes), welding machines, grinders and tools maybe
implemented to insure the best quality.
P a g e 20 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
A qualified and experienced TPI NDE personnel shall be designated to examine the welding and
fabrication activities including inspection and testing.
CONSTRUCTION PROGRAM
House Keeping
The work area shall be maintained neat and tidy as reasonable practical at all times.
Executed works in areas were other works are still being carried out shall be
pr ote c te d as per the contract requirements.
Responsibilities
See Appendix D.
P a g e 21 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
APPENDIX A
NO. DESCRIPTION
2 Grooving machine
3 Threading machine
4 Welding machine
9 Angle tool
10 Caliper
12 Wrenches set
P a g e 22 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
APPENDIX B
CONSTRUCTION HAZARD
Highly Extremely
Corrosives Oxidizing Toxic Highly Toxic Irritating Harmful
flammable flammable
☐ ☒ ☒ ☐ ☒ ☐ ☒ ☒
Danger for the Confined Slippery Danger of Falling from
Explosive Other
Environment Space Surface Electrocution Height
☐
☐
☐ ☒ ☒ ☒ ☒ ☒ ☐
P a g e 23 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
APPENDIX C
Safety
Safety Hi-Vest Eye Face Mask Respirator Ear
Helmet
Precaution Required Protection Protection Required Required Protection
Helmet
✓ ✓ ✓ ✓ ✓ ✓
Gloves Safety Protective Safety Equipment Life Jacket
Required Shoes Clothing Harness Guards Lifejacket Other
Required
P a g e 24 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
APPENDIX D
RESPONSIBILITIES
Overall
Position Supervise Perform Short Description
Resp.
Project Manager ✓
Site Manager ✓ ✓
Safety Manager ✓
QA/QC Engineer ✓ ✓
Foreman ✓ ✓
Charge hand ✓
Laborer ✓
Helper ✓
P a g e 25 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
APPENDIX E
• Welding Procedure Specification for API 5L X52 – 12 Inch size
18-033/GETE/WPS/01
• Welding Procedure Specifications for ASTM A333 SCH80 – 4 Inch Size
18-033/GETE/WPS/02
P a g e 26 OF 28
ARAB POTASH COMPANY
NEW GAS TURBINE POWER PLANT
APPENDIX F
Test Pack for Fuel Gas pipeline
P a g e 27 OF 28
DESCRIPTION OF TEST PACKS RELATED TO WELDING - Fuel Gas System (FG)
FW SW NDE(RT) REPAIR
Test Pack Document No. Joint History Dia Extent of NDT
S. No Welder ID
(System Description) (Isometric) Joint No. From HT NO. To HT NO. (Inches) VT RT
1 Fuel Gas System APC - N - GP - ISO - 001 1 FLANGE REDUCER 6 100% 100%
2 Fuel Gas System APC - N - GP - ISO - 001 2 REDUCER PIPE 12 100% 100%
3 Fuel Gas System APC - N - GP - ISO - 001 3 PIPE ELBOW 12 100% 100%
4 Fuel Gas System APC - N - GP - ISO - 001 4 ELBOW PIPE 12 100% 100%
5 Fuel Gas System APC - N - GP - ISO - 001 5 PIPE ELBOW 12 100% 100%
6 Fuel Gas System APC - N - GP - ISO - 001 6 ELBOW PIPE 12 100% 100%
7 Fuel Gas System APC - N - GP - ISO - 001 7 PIPE PIPE 12 100% 100%
8 Fuel Gas System APC - N - GP - ISO - 001 8 PIPE ELBOW 12 100% 100%
9 Fuel Gas System APC - N - GP - ISO - 001 9 ELBOW PIPE 12 100% 100%
10 Fuel Gas System APC - N - GP - ISO - 001 10 PIPE ELBOW 12 100% 100%
11 Fuel Gas System APC - N - GP - ISO - 001 11 ELBOW PIPE 12 100% 100%
12 Fuel Gas System APC - N - GP - ISO - 001 12 PIPE PIPE 12 100% 100%
13 Fuel Gas System APC - N - GP - ISO - 001 13 PIPE PIPE 12 100% 100%
14 Fuel Gas System APC - N - GP - ISO - 001 14 PIPE PIPE 12 100% 100%
15 Fuel Gas System APC - N - GP - ISO - 001 15 PIPE PIPE 12 100% 100%
16 Fuel Gas System APC - N - GP - ISO - 001 16 PIPE PIPE 12 100% 100%
17 Fuel Gas System APC - N - GP - ISO - 001 17 PIPE ELBOW 12 100% 100%
18 Fuel Gas System APC - N - GP - ISO - 001 18 ELBOW PIPE 12 100% 100%
19 Fuel Gas System APC - N - GP - ISO - 001 19 PIPE ELBOW 12 100% 100%
20 Fuel Gas System APC - N - GP - ISO - 001 20 ELBOW PIPE 12 100% 100%
21 Fuel Gas System APC - N - GP - ISO - 001 21 PIPE PIPE 12 100% 100%
22 Fuel Gas System APC - N - GP - ISO - 001 22 PIPE PIPE 12 100% 100%
23 Fuel Gas System APC - N - GP - ISO - 001 23 PIPE PIPE 12 100% 100%
24 Fuel Gas System APC - N - GP - ISO - 001 24 PIPE PIPE 12 100% 100%
25 Fuel Gas System APC - N - GP - ISO - 001 25 PIPE PIPE 12 100% 100%
26 Fuel Gas System APC - N - GP - ISO - 001 26 PIPE PIPE 12 100% 100%
27 Fuel Gas System APC - N - GP - ISO - 001 27 PIPE PIPE 12 100% 100%
28 Fuel Gas System APC - N - GP - ISO - 001 28 PIPE ELBOW 12 100% 100%
29 Fuel Gas System APC - N - GP - ISO - 001 29 ELBOW PIPE 12 100% 100%
30 Fuel Gas System APC - N - GP - ISO - 001 30 PIPE ELBOW 12 100% 100%
31 Fuel Gas System APC - N - GP - ISO - 001 31 ELBOW ELBOW 12 100% 100%
32 Fuel Gas System APC - N - GP - ISO - 001 32 ELBOW PIPE 12 100% 100%
33 Fuel Gas System APC - N - GP - ISO - 001 33 PIPE ELBOW 12 100% 100%
34 Fuel Gas System APC - N - GP - ISO - 001 34 ELBOW PIPE 12 100% 100%
35 Fuel Gas System APC - N - GP - ISO - 001 35 PIPE PIPE 12 100% 100%
DESCRIPTION OF TEST PACKS RELATED TO WELDING - Fuel Gas System (FG)
FW SW NDE(RT) REPAIR
Test Pack Document No. Joint History Dia Extent of NDT
S. No Welder ID
(System Description) (Isometric) Joint No. From HT NO. To HT NO. (Inches) VT RT
36 Fuel Gas System APC - N - GP - ISO - 001 36 PIPE FLANGE 12 100% 100%
37 Fuel Gas System APC - N - GP - ISO - 001 37 PIPE PIPE (Stub - In) 4 100% 100%
38 Fuel Gas System APC - N - GP - ISO - 001 38 PIPE ELBOW 4 100% 100%
39 Fuel Gas System APC - N - GP - ISO - 001 39 ELBOW PIPE 4 100% 100%
40 Fuel Gas System APC - N - GP - ISO - 001 40 PIPE FLANGE 4 100% 100%
41 Fuel Gas System APC - N - GP - ISO - 001 41 FLANGE PIPE 4 100% 100%
42 Fuel Gas System APC - N - GP - ISO - 001 42 PIPE ELBOW 4 100% 100%
43 Fuel Gas System APC - N - GP - ISO - 001 43 ELBOW PIPE 4 100% 100%
44 Fuel Gas System APC - N - GP - ISO - 001 44 PIPE ELBOW 4 100% 100%
45 Fuel Gas System APC - N - GP - ISO - 001 45 ELBOW PIPE 4 100% 100%
46 Fuel Gas System APC - N - GP - ISO - 001 46 PIPE FLANGE 4 100% 100%
47 Fuel Gas System APC - N - GP - ISO - 001 47 PIPE PIPE (Stub - In) 4 100% 100%
48 Fuel Gas System APC - N - GP - ISO - 001 48 PIPE ELBOW 4 100% 100%
49 Fuel Gas System APC - N - GP - ISO - 001 49 ELBOW PIPE 4 100% 100%
50 Fuel Gas System APC - N - GP - ISO - 001 50 PIPE FLANGE 4 100% 100%
WELD SUMMARY - Fuel Gas System (FG)
No. of Joints
Test Pack Field Weld Joints DIA (inches) Total No.
S.No for NDT
(System Description) 4 6 12 of Joints 100%
Total 0 0 0 0
APPENDIX G
Sample welding book format
P a g e 28 OF 28
EMPLOYER CONTRACTOR POWER GENERATION AND ENERGY SOLUTION SUB-CONTRACTOR
WELDING DATA BASE ELAF Contracting Company
FUEL GAS PIPE LINE
PIPE 1 PIPE 2 Pipe Pipe RT Report RT Report REPAIR 1 UT Report UT Report REPAIR 2 UT Report UT Report Coated Date of
JOINT # Welder # System DATE PIPE 1 # PIPE 2 # Status Status Status
HEAT # HEAT # Support # Support # # Date DATE # Date DATE # Date (Yes/ No) Coating
1 OF 2
EMPLOYER CONTRACTOR POWER GENERATION AND ENERGY SOLUTION SUB-CONTRACTOR
WELDING DATA BASE ELAF Contracting Company
FUEL GAS PIPE LINE
PIPE 1 PIPE 2 Pipe Pipe RT Report RT Report REPAIR 1 UT Report UT Report REPAIR 2 UT Report UT Report Coated Date of
JOINT # Welder # System DATE PIPE 1 # PIPE 2 # Status Status Status
HEAT # HEAT # Support # Support # # Date DATE # Date DATE # Date (Yes/ No) Coating
2 OF 2