You are on page 1of 140

Interim Payment Certificate No.

01 New
Payable Summary
Construction of Upper Parajuli Khola Hydropower Project

A. Original Contract Amount (NRs.): 156,751,288.12


B. Original Contract Amount with VAT (NRs.) : 177,128,955.58
Claim Till 30th falgun 2074

Previous Current Total Remakrs


S.N. Description
(NRs.) (NRs.) (NRs.)
C Value of work executed excluding VAT 5,796,391.88 11,808,355.64 17,604,747.52
D VAT 753,530.94 1,535,086.23 2,288,617.17
E Value of work including VAT 6,549,922.82 13,343,441.87 19,893,364.69
F Deductions
i Retention money @ 5% of C 289,819.59 590,417.78 880,237.37
ii (iii) TDS @ 1.5% of C 86,945.88 177,125.33 264,071.21
iii (ii) Advance Deduction @ 30% of C 1,738,917.56 3,542,506.69 5,281,424.25
iv Performance Guarantee@ 5% of C 289,819.59 590,417.78 880,237.37
H Total Deductions (i)+(ii)+(iii) 2,405,502.62 4,900,467.58 7,305,970.20
I Amount Payable from work completed 4,144,420.20 8,442,974.29 12,587,394.49

Net Payable Amount of Current IPC in words in NRs.: Rupees Eighty four lakh forty two thousand nine hundred seventy
four rupees and paisa forty nine only.

Submitted by: Approved by: Verified by:

Contractor Chairman Robin Lal Chitrakar


Interim Payment Certificate No. 01 New
Summary of Bill of Quantities
Civil Construction of Upper Parajuli Khola Hydropower Project

Claim Till 30th Falgun 2074

Item
Description BOQ Amount Previous Current Total Remarks
No.
A Civil Works
A1 Weir, Intake and Floodwall for weir 25036373.75 1101140.29 4269533.57 5370673.86
A2 Gravel Trap & Spillway 2651444.30 1095890.17 1095890.17
A3 Approach Canal 553532.29 0.00
A4 Desilting Basin 4903194.62 1594407.77 831751.27 2426159.04
A5 Headrace Canal 45450087.76 2225111.25 211299.39 2436410.64
A6 Kholsi Crossing 1015569.80 0.00
A7 Forebay Basin / Spillway 13855850.09 754232.57 4537831.22 5292063.79
A8 Penstock, Anchor Block & Support Piers 6405970.99 0.00

A9 Powerhouse and Tailrace 16414722.42 799550.02 799550.02


A10 Switchyard (Civil Works) all complete 3839947.50 0.00
B Hydro-Mechanical Works 0.00
B3 Other local procurement contract 16601838.29 0.00
C ELECTRO-MECHANICAL 1178187.35 0.00
D TRANSMISSION LINE 18844568.97 0.00
Additonal Works 121500.00 62500.00 184000.00
Total 156751288.12 5796391.88 11808355.64 17604747.52
VAT @ 13 % 20377667.46 753530.94 1535086.23 2288617.18
Grand Total 177128955.58 6549922.82 13343441.87 19893364.70

Submitted by: Approved by: Verified by:

Contractor Chairman Robin Lall Chitrakar


Rara Hydropower Development Company Pvt. Ltd.

SN Description of work Designed As per contract Quantity Amount

UnitQty dis rate amt previous present hold total previou present hold total
A CIVIL
A1 Weir, Intake and Floodwall for
1 weir 25m Excavation in Boulder
Earthwork m3 ### 612.66 1,835,909.21 - - -
2 Mix Soil
Backfilling by Earthmaterials m3 906.60 195.11 176,886.73 - - -
3 Stone Soling in Foundation m3 51.66 3,323.88 171,711.64 - - -
4 M10 Concrete Soling m3 32.19 9,425.50 303,444.55 - - -
5 M25 Concrete PCC m3 487.94 17,437.17 8,508,292.73 52.06 17.83 34.23 907,810.98 310,936.65 596,874.33
6 M40 Concrete PCC m3 62.63 18,851.00 1,180,638.13 - - -
7 M60 Concrete PCC m3 41.07 25,448.85 1,045,184.27 - - -
8 Admixture kg 637.77 278.05 177,331.95 - - -
9 Boulder Rip Rap m3 209.75 1,873.79 393,027.45 - - -
10 Gabion Protection Structures m3 378.47 4,241.47 1,605,269.15 - - -
11 M20 40% Plum Concrete m3 101.64 11,781.87 1,197,556.39 - - -
12 Reinforcement kg ### 111.22 5,259,855.17 6,802.20 6,802.20 - 756,540.26 756,540.26 -
13 River Bed Maerial Packing+ m3 114.92 3,323.88 381,967.49 46.55 46.55 154,733.26 154,733.26
sediment filling for compaction
14 Formworks m2 ### 659.78 914,474.21 87.65 14.47 87.65 57,829.85 9,547.15 48,282.70
20 Protection Works - use of excavator hr 56.00 923.70 51,727.20 - - -
for boulder protection
21 River diversion works (earth m3 522.73 2,827.65 1,478,097.48 522.73 522.73 - 1,478,106.91 1,478,106.91 -
excavation in boulder mix soil)
22 Dewatering hr 250.00 250.00 62,500.00 35.00 35.00 8,750.00 8,750.00
23 Debris clearing ( due to flood) hr 45.00 6,500.00 292,500.00 45.00 45.00 292,500.00 292,500.00
24 Admixture ( Quick set) kg - -
25 Admixture (Super plasticizer kg - -
@1.5%)
Subtotal A1 ### - - ### ### ###
-
A2 Gravel Trap & Spillway
1 Site Clearance m2 190.00 28.28 5,373.20 - - -
2 Earthwork Excavation in Soft Soil m3 874.36 612.66 535,685.40 - - -
3 Stone Soling in Foundation m3 25.53 3,323.88 84,858.66 - - -
4 PCC 1:3:6, (M10) m3 17.16 9,425.50 161,741.58 - - -
5 PCC 1:1.5:3, (M20) m3 81.43 13,195.70 1,074,525.85 - - -
6 Formworks m2 235.39 659.78 155,305.61 - - -
7 Reinforcement kg ### 111.22 633,954.00 - - -
Subtotal A2 ### - - -
-
A3 Approach Canal
1 Earthwork in Excavation in soft soil m3 260.66 612.66 159,695.96 - - -

Page 3 of 140
Rara Hydropower Development Company Pvt. Ltd.

2 Earthmaterial Back filling m3 36.97 195.11 7,213.22 - - -


3 Stone Soling in foundation m3 5.77 3,323.88 19,178.79 - - -
4 PCC 1:3:6 (M10) m3 3.91 9,425.50 36,853.71 - - -
5 PCC 1:1.5:3 (M20) m3 13.02 13,195.70 171,808.01 - - -
6 Reinforcement bar kg 770.00 111.22 85,639.40 - - -
7 Form works m2 110.86 659.78 73,143.21 - - -
Subtotal A3 553,532.29 - -

A4 Desilting Basin
1 Site Clearance m2 - - - -
2 Earthwork Excavation in BMS m3 - 612.66 - - -
3 Stone Soling in Foundation m3 - 3,323.88 - - -
4 PCC 1:3:6, (M10) m3 - 9,425.50 - - -
5 PCC 1:1.5:3, (M20) m3 166.07 13,195.70 2,191,400.66 95.35 40.11 55.23 1,258,168.61 529,343.71 728,824.90
6 Stone Masonry Works m3 62.36 7,482.27 466,594.36 - - -
7 Formworks m3 902.48 659.78 595,438.25 632.40 222.17 410.23 417,242.76 146,583.19 270,659.57
8 Reinforcement kg ### 111.22 711,630.05 5,624.74 5,624.74 - 625,583.63 625,583.63 -
9 Admixture kg 800.00 282.76 226,208.00 - - -
10 Canal Crossing (for irrigation Kulo) ### 1.00 - - -
11 debris removal manually Md 691.00 776.30 536,423.30 691.00 691.00 536,423.30 536,423.30
12 backfilling Hr 27.00 6,500.00 175,500.00 9.00 9.00 58,500.00 58,500.00
Subtotal A4 ### - - ### ### ###

Page 4 of 140
Rara Hydropower Development Company Pvt. Ltd.

A5 Headrace Canal
1 Site clearance m2 755.25 28.28 21,358.47 - - -
2 Earthwork Excavation in Canal m3 ### 282.76 2,262,080.00 7,869.26 7,869.26 2,225,111.25 2,225,111.25
3 Access roadExcavation in Boulder
Earthwork m3 ### 612.66 2,441,676.78 - - -
4 Mix Soil
Earthwork Excavation in Medium m3 140.75 1,131.06 159,196.70 - - -
Rock Soil
5 Eathwork in back filling m3 ### 195.11 606,856.49 - - -
6 0.15m Stone Soling in foundation m3 444.91 3,323.88 1,478,827.45 - - -
7 PCC 1:1.5:3, M20 m3 ### 13,195.70 ### - - -
8 Reinforcement kg ### 111.22 ### - - -
9 FormWork m2 ### 659.78 6,412,925.69 - - -
10 PCC 1:3:6, M10 (0.1m Conrete m3
11 Soling)
River Training Works
a Concrete (1:2:4) with 30% plum m3 -
b FormWork m2 -
c Gabion Protection Structure m3 -
d Earthwork in backfilling m3 -
e Earthwork Excavation m3 -

Subtotal A5 ### - - ### ###

A6Kholsi Crossing
1Budhi kholsi crossing
aSite clearance m2 30.00 28.28 848.40 - - -
bEarthwork Excavation in Boulder m3 30.00 612.66 18,379.80 - - -
cMix Soil
Earthwork Excavation in Medium m3 3.00 1,131.06 3,393.18 - - -
Rock Soil
d Eathwork in back filling m3 6.00 195.11 1,170.66 - - -
e 0.15m Stone Soling in foundation m3 5.47 3,323.88 18,181.62 - - -
f PCC 1:2:4, M15 (0.1m Conrete m3 2.74 9,425.50 25,825.87 - - -
g Soling)
PCC 1:1:2, M25 m3 34.37 17,437.17 599,315.53 - - -
h Reinforcement kg ### 111.22 307,601.15 - - -
i FormWork m2 61.92 659.78 40,853.58 - - -
2 Other kholsi crossing
a Earth work in excavation in soft m3 -
b soil
gabion protection structure m3 -
c boulder riprap m3 -
d stone masonry m3 -

Subtotal A6 ### - - -
-
A7 Forebay Basin / Spillway -
1 Site Clearance m2 540.00 28.28 15,271.20 250.00 250.00 7,070.00 7,070.00

Page 5 of 140
Rara Hydropower Development Company Pvt. Ltd.

2 Earthwork in Excavation m3 ### 612.66 952,043.01 1,035.74 1,035.74 634,556.31 634,556.31


3 Stone soling in foundation m3 97.22 3,323.88 323,147.61 28.46 0.14 28.32 94,605.85 473.57 94,132.28
4 PCC (1:3:6) M10 m3 58.82 9,425.50 554,407.91 18.84 16.88 1.96 177,576.42 159,102.44 18,473.98
5 PCC (1:1.5:3) M20 m3 319.95 13,195.70 4,221,964.22 - - -
6 Reinforcement Bars kg ### 111.22 3,558,493.91 - - -
7 Formwork for PCC/RCC m2 ### 659.78 1,110,343.76 - - -
8 Trashrack for Forebay Set 1.00 - - - -
9 Penstock inlet gate Set - - - -
10 Bitumin filler pad 12mm thick m2 4.76 - - - -
11 Water stopper m - - - - -
12 Sealant Rm - - - - -
15 Retaining Wall - - - -
a Gabion Protection Strucutre m3 550.00 4,241.47 2,332,808.50 - - -
13 Excavation for slope stabilization m3 ### 300.00 787,369.97 2,624.57 2,624.57 - 787,369.97 787,369.97 -
Subtotal A7 ### - - ### 946,945.98 754,232.57

A8 Penstock, Anchor Block & -


1 Support
Forbay toPiers
PH access road
i Access Road km -
2 Excavation Soil (BMS) m3 ### 612.66 877,696.72
3 Filling soil m3 ### 195.11 249,949.45 - - -
4 Gravel soling m3 7.44 1,583.48 11,773.17 - - -
5 Penstock crossing Kholsi crossing - - - -
6 M15 Plum concrete (30% plum) m3 25.67 11,310.60 290,331.79 - - -
7 Hume Pipe Dia. 1.50 m m 20.00 10,368.05 207,361.00 - - -
8 M20 PCC Anchor block & Sadal m3 121.19 13,195.70 1,599,155.90 - - -
9 Support
Reinforcement steel kg ### 111.22 539,417.00 - - -
10 Gravel base for penstock for 100% m3 331.16 1,873.79 620,524.30 - - -
11 length
stone masonry for Sadal Support m3 268.60 7,482.27 2,009,761.67 - - -
(1:6 C/S ratio)
Subtotal A8 ### - -

A9 Powerhouse and Tailrace


1 Earthworks Excavation in Soft Soil m3 ### 612.66 621,255.62
2 Backfilling m3 948.80 195.11 185,120.37
3 100 mm gravel filling m3 72.57 3,323.88 241,213.97 - - -
4 M10 Concrete Soling m3 59.19 9,425.50 557,895.35 - - -
5 M20 Concrete for RCC m3 174.18 13,195.70 2,298,427.03 - - -
6 M20 Concrete for RCC m3 215.69 13,195.70 2,846,180.53 - - -
7 M25 Structural Concrete m3 6.48 17,437.17 112,992.86 - - -
8 Formwork m2 ### 659.78 960,224.02 - - -
9 Reinforcement steel for RCC works kg ### 111.22 2,580,304.00 - - -
10 Stone Masonry works m3 137.57 7,482.27 1,029,335.88 - - -
11 Fixing Aluminium Windows m2 106.60 9,161.58 976,624.43 - - -

Page 6 of 140
Rara Hydropower Development Company Pvt. Ltd.

12 Fixing Doors Nos. 17.25 9,425.50 162,589.88 - - -


13 Rolling shutters m2 48.00 2,733.39 131,202.72 - - -
14 Steel works Ton 1.23 14,138.25 17,390.05 - - -
15 Iron work in Truss of 4"Dia pipe m 774.48 2,780.52 2,153,457.13 - - -
16 Iron work in Truss of 2.5"Dia pipe m 228.90 1,329.00 304,208.10 - - -
17 CGI Sheet roofing m2 688.84 1,131.06 779,119.37 - - -
18 Gabion Protection Structures m3 96.00 4,241.47 407,181.12 - - -
19 Dewatering hr 200.00 250.00 50,000.00
Subtotal A9 ### - -

A10 Switchyard (Civil Works) all


1 complete
Civil works for switchyard, fencing m2 375.00 10,239.86 3,839,947.50
with GI pipes and 11SWG GI wire
mesh; 15m x 15m ground area with
10cm crushed rock soling,
electricall hardware supports all
complete
Subtotal A10 ###
A11 Access / construction road - - -

- - -
A12 Day works

A13 General Item


TOTAL (CIVIL) A1 - A13 ###

B3 Other local procurement


1 contract
Penstock pipe cutting & processing T 274.80 1,800.72 494,837.86
Final processing / preparation at T 394.09 23,711.68 9,344,535.97
2
site & Installation
3 C clamp, Bel-mouth, base plates, T 0.90 22,619.12 20,357.21 - - -
installation
Branch pipes after bifurcation T 4.24 ### 659,784.90 - - -
4
supply and delivery
5 Branch pipes after bifurcation T 4.24 22,619.12 95,900.77 - - -
6 installation
Transportation and handling to site T 275.70 6,597.85 1,819,055.22 - - -
7 Pipe coating outside- material m ### 1,371.41 2,009,115.65 - - -
8 Pipe coating outside- transport, LS 1.00 82,284.61 82,284.61 - - -
labor
9 Welding rods, consumption per m 1.00 ### 1,281,867.84 - - -
meter run
10 Penstock pipe Weld Quality test No 1.00 ### 754,039.91 - - -
11 Air Vent pipe m 5.00 3,298.92 16,494.60 - - -
12 Flushing Valve Set 1.00 23,563.75 23,563.75 - - -

Page 7 of 140
Rara Hydropower Development Company Pvt. Ltd.

Total B3 ### - - -
-
TOTAL (HYDRO-MECH) - ### - - -
-
C ELECTRO-MECHANICAL -
5 Earthing works final design, supply Lot 1.00 ### 706,912.41 - - -
of materials and installation,
Manpower for Installation (Local
technical expert, skilled and
unskilled labour) under the
supervision of HVGCL experts
7 Local travel, lodging, fooding of Lot 1.00 ### 471,274.94 - - -
HVGCL experts
TOTAL C ### - - -

D TRANSMISSION LINE
D1 33 KV Line Complete Works
I Supply materials ex-works
1 11m Steel Telescopic poles nos 155.00 32,046.70 4,967,238.50 - - -
2 33 KV Disc Insulator with tension set 756.00 2,639.14 1,995,189.84 - - -
set(3 bolted type)
3 33kv Pin Insulator with insulator set 630.00 822.85 518,395.50 - - -
4 spindle
HT Stay Insulator nos 140.00 502.85 70,399.00 - - -
5 HTstay set nos 140.00 3,291.38 460,793.20 - - -
7 Stay wire 7/8swg m ### 68.57 115,197.60 - - -
8 Crossarm channel 125x nos 147.00 754.04 110,843.88 - - -
9 65x6x300mm
Crossarm channel 125x65x nos 147.00 3,770.20 554,219.40 - - -
10 6x1900mm
Crossarm channel 125x65x nos 84.00 6,315.08 530,466.72 - - -
11 6x3300mm
Flat Bracing (40x760x6mm) nos 336.00 329.89 110,843.04 - - -
12 Bracing Angle ( 50x50x5x2416 nos 42.00 2,827.65 118,761.30 - - -
14 mm)
Brack Strap(60*6*410) nos. 252.00 377.02 95,009.04 - - -
15 Pole Clamp for Top 300mm Arm nos 210.00 484.56 101,757.60 - - -
16 Pole Clamp for 1900mm Arm nos 210.00 706.91 148,451.10 - - -
17 Pole Clamp for Bracing Angle Top nos 84.00 565.53 47,504.52 - - -
18 Pole Clamp for Bracing Angle nos 84.00 565.53 47,504.52 - - -
19 Bottom
Stay clamp nos 140.00 377.02 52,782.80 - - -
20 Nut bolts with washer lot 14.00 45,242.39 633,393.46 - - -
21 100 sq mm ACSR conductor Km 44.10 ### 4,838,334.92 - - -

II Transportation ktm to Site Kg


1 11m Steel Telescopic poles nos 80.00 2,356.37 188,509.60 - - -
2 33 KV Disc Insulator with tension set 756.00 182.85 138,234.60 - - -
set(3 bolted type)
3 33kv Pin Insulator with insulator set 630.00 182.85 115,195.50 - - -
4 spindle
HT Stay Insulator nos 140.00 45.71 6,399.40 - - -

Page 8 of 140
Rara Hydropower Development Company Pvt. Ltd.

5 HTstay set nos 140.00 274.28 38,399.20 - - -


7 Stay wire 7/8swg m ### 4.74 7,963.20 - - -
8 Crossarm channel 125x nos 95.00 141.38 13,431.10 - - -
9 65x6x300mm
Crossarm channel 125x65x nos 108.00 282.76 30,538.08 - - -
10 6x1900mm
Crossarm channel 125x65x nos 84.00 282.74 23,750.08 - - -
11 6x3300mm
Flat Bracing (40x760x6mm) nos 336.00 27.43 9,216.48 - - -
12 Bracing Angle ( 50x50x5x2416 nos 159.00 282.76 44,958.84 - - -
14 mm)
Brack Strap(60*6*410) nos. 252.00 9.14 2,303.28 - - -
15 Pole Clamp for Top 300mm Arm nos 210.00 18.29 3,840.90 - - -
16 Pole Clamp for 1900mm Arm nos 210.00 27.43 5,760.30 - - -
17 Pole Clamp for Bracing Angle Top nos 84.00 27.43 2,304.12 - - -
18 Pole Clamp for Bracing Angle nos 84.00 27.43 2,304.12 - - -
19 Bottom
Stay clamp nos 140.00 18.36 2,570.40 - - -
20 Nut bolts with washer lot 14.00 3,657.09 51,199.26 - - -
21 100 sq mm ACSR conductor Km 44.10 1,828.55 80,639.06 - - -
-
III Erection, stringing and other Km 14.00 ### 2,559,965.52 - - -
testing & commissioning charges
Subtotal D1 ### - - -

TOTAL (TRANSMISSION LINE) ### - - -

Additional Works 121,500.00 121,500.00


-
GRAND TOTAL (A+B+C+D) ### - ### ###

Total scope of works


VAT
Chargeable by Vendors /
contractors

Page 9 of 140
Rara Hydropower Development Company Pvt. Ltd.

Quantity Amount

previous present total previous present total

- - - - -
- - - - -
- 10.27 10.27 - 34,151.22 34,151.22
- 7.05 7.05 - 66,412.07 66,412.07
34.23 110.47 144.70 596,874.33 1,926,271.96 2,523,146.29
- - - - -
- - - - -
- - - - -
- 68.34 68.34 - 128,060.99 128,060.99
- 16.00 16.00 - 67,863.52 67,863.52
- - - - -
- ### 17,518.80 - 1,948,441.27 1,948,441.27
46.55 - 46.55 154,733.26 - 154,733.26

87.65 149.04 236.69 48,282.70 98,332.53 146,615.23


- - - - -

- - - - - -

35.00 - 35.00 8,750.00 - 8,750.00


45.00 - 45.00 292,500.00 - 292,500.00
- - -
- - -
- 1,101,140.29 4,269,533.57 5,370,673.86
- -
- -
- 190.00 190.00 - 5,373.20 5,373.20
- 874.86 874.86 - 535,993.20 535,993.20
- 18.30 18.30 - 60,830.49 60,830.49
- 13.27 13.27 - 125,077.33 125,077.33
- - - - -
- - - - -
- 3,314.30 3,314.30 - 368,615.95 368,615.95
- - 1,095,890.17 1,095,890.17
- -
- -
- - - - -

Page 10 of 140
Rara Hydropower Development Company Pvt. Ltd.

- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - -
- -
- -
- - - - -
- 47.29 47.29 - 28,975.39 28,975.39
- 2.12 2.12 - 7,059.92 7,059.92
- 1.42 1.42 - 13,346.51 13,346.51
55.23 19.90 75.14 728,824.90 262,637.73 991,462.63
- - - - -
410.23 38.89 449.11 270,659.57 25,656.34 296,315.91
- 3,565.68 3,565.68 - 396,575.39 396,575.39
- - - - -
- - - - -
691.00 - 691.00 536,423.30 - 536,423.30
9.00 15.00 24.00 58,500.00 97,500.00 156,000.00
- 1,594,407.77 831,751.27 2,426,159.04
- -

Page 11 of 140
Rara Hydropower Development Company Pvt. Ltd.

- -
- 90.00 90.00 - 2,545.20 2,545.20
7,869.26 7,869.26 2,225,111.25 - 2,225,111.25
- 288.00 288.00 - 176,446.08 176,446.08
- - - - -

- - - - -
- 9.72 9.72 - 32,308.11 32,308.11
- - - - -
- - - - -
- - - - -
- - -
- - -
- - -
- - -
- - -
- - -
- - -
- -
- 2,225,111.25 211,299.39 2,436,410.64
- -
- -
- -
- - - - -
- - - - -
- - - - -

- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- -
- -
- -
- -
- -
- -
- - - -
- - -
- - -
250.00 - 250.00 7,070.00 - 7,070.00

Page 12 of 140
Rara Hydropower Development Company Pvt. Ltd.

1,035.74 - 1,035.74 634,556.31 - 634,556.31


28.32 - 28.32 94,132.28 - 94,132.28
1.96 16.75 18.71 18,473.98 157,877.13 176,351.11
- 111.06 111.06 - 1,465,510.81 1,465,510.81
- ### 17,161.02 - 1,908,649.07 1,908,649.07
- 331.05 331.05 - 218,423.14 218,423.14
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- 2,624.57 2,624.57 - 787,371.07 787,371.07
- 754,232.57 4,537,831.22 5,292,063.79
- -
- -
- -
- -
- -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -

- 1305.047 1,305.05 - 799,550.02


- - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -

Page 13 of 140
Rara Hydropower Development Company Pvt. Ltd.

- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - -
- - - 799,550.02 799,550.02

- -

- -
- - - - -

- - - -
- -
- -
- -
- - 11,745,855.64 17,420,747.52
- -
- -
- -
- -
- -
- -

- - - - -
- - - - -

- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -

Page 14 of 140
Rara Hydropower Development Company Pvt. Ltd.

- - - -
- - -
- - - -
- - -
- - -
- - - - -

- - - - -

- - - -
- -
- -
- -
- -
- - - - -
- - - - -

- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- -
- -
- - - - -
- - - - -

- - - - -
- - - - -

Page 15 of 140
Rara Hydropower Development Company Pvt. Ltd.

- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - - - -
- - -
- - - - -

- - - -
- -
- - - -
- -
- -
- 121,500.00 62,500.00 184,000.00
- - -
5,796,391.88 11,808,355.64 ###

Page 16 of 140
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Item No. A1 Weir Intake and Floodwall


S.No. BOQ No. Descrition of Works Chainage/Detail Unit No
1 A1.3 Stone Soling on Foundation
D/S Apron m3 1
D/S divide wall Right side m3 1
6 Th Cutoff m3 1
Wing Wall m3 1

2 A1.4 M10 PCC


D/S Apron m3
Undersluice m3
6 Th Cutoff m3
Wing Wall m3

3 A1.5 M25 Concrete PCC


D/S Apron m3
Undersluice D/S bed m3
Undersluice D/S bed extension m3
Undersluice D/S Wall extension m3
Flood Wall m3 1
Wing Wall m3
Wing Wall m3
Wing Wall m3
6 Th Cutoff m3
Didide Wall weir side m3 1

4 A1.9 Boulder Rip Rap


Weir Downstream m3
Undersulice Downstream m3

A1.12 Reinforcement
5 Kg

8 Kg

6 A14 Formworks
Flood Wall m2 1
m2 1
WingWall m2 1
WingWall m2 2
WingWall m2 2
WingWall m2 2
Wing Last Part m2 1
Didide Wall weir side m2 2
Undersluice D/S bed extension m2 2
Undersluice D/S Wall extension m2 2
5th Cutoff m2 1
6Th Cutoff m2 2

7 A1.10 Gabine Protection Structure m3


Right Bank With Wing Wall m3 8
Item No. A2 Gravel Trap and Spillway
S.No. BOQ No. Descrition of Works Chainage Unit No
A2.1 Site Clearance m2
1

Earthwork Excavation
A2.2 Boulder mix soil
Gravel Trap m3 1
Spillway m3 1.00
Flushing Arragnement m3 1.00

A2.3 Stone Soling in Foundation


Gravel Trap m3 1
Inlet Zone m3 1.00
Trap Zone m3 1.00
Outlet Zone m3 1.00

Flushing Arrangement m3 1.00


Spillway

A2.4 M10 PCC


Gravel Trap
Inlet Zone m3 1.00
Trap Zone m3 1.00
Outlet Zone m3 1.00
Flushing Arrangement
Outlet Zone m3 1.00
Flushing canal m3 1.00
Spillway m3 1.00

A2.7 Renforcement Gravel Trap kg

Item No. A4 Desilting Basin


S.No. BOQ No. Descrition of Works Chainage/Detail Unit No
A4.1 Earthwork Excavation
Desender Flushing

A4.3 Stone Soling in Foundation


Flushing m3

A4.4 M10 PCC Flushing

A4.5 M20 Concrete


Desander Outlet-I m3
Desander Outlet-II m3
Inlate Column Left Right m3 4
Inlate Column Middle m3
2
Flushing Flshing 1 m3 1
Flushing 2 m3
1

A4.7 Formwork
Inlate Column Left Right m2 4
Inlate Column Middle m2
2
Desander Outlet m2
2
Flushing Bed And Wall 1 out Side m2
2
Bed And Wall 2 out Side m2 2
Bed And Wall 1 InSide m2
2
Bed And Wall 2 inside m2
2
Top Slab 1 m2
1
Top Slab 2 m2
1

A4.8 Reinforcement
Desander Outlet & Flushing Kg

Kg

A4.12 Backfilling Hr 1

Item No. A5 Headrace Power Canal


S.No. BOQ No. Descrition of Works Chainage/Detail Unit No
A5.1 Site Clearance 1+90-1+120 m2 1

Earthwork Excavation in Boulder


A5.3 Mix Soil 1+90-1+120 m3 1
A5.6 Stone Soling 1+90-1+120 m3 1

Item No. A7 Forebay And Spillwal


S.No. BOQ No. Descrition of Works Chainage/Detail Unit No
1 A7.5 M20 Concreting m3
Inlet Section m3 1.00
Inlate Transitions m3 1.00
Silting Zone m3 1.00
Penstock Inlet transition m3 1.00
Flushing chamber m3 1.00
Inlat Section Left And Right Wall m3 2.00
Inlate Transitions Left Wall m3 1.00
Inlate Transitions Right wall m3 1.00
Silting Zone Left Wall m3 1.00
Silting Zone Right Wall m3 1.00

A7.6 Renforcement Bar

A7.8 Formwork
Inlet Section m2 1
Inlate Transitions m2 2
Silting Zone m2 2
Penstock Inlet transition m2 2
Flushing chamber m2 3
Inlat Section Left And Right Wall m2 4
Inlate Transitions Left Wall m2 2
Inlate Transitions Right wall m2 2
Silting Zone Left Wall m2 2
Silting Zone Right Wall m2 2

A7.4 M10 concrete


Flow Section m3 1.00
Base Penstock Inlet m3 1.00

A7.13 Excavation for slope stabilization M3

Item No. A9 Powerhouse And Taiace


S.No. BOQ No. Descrition of Works Chainage/Detail Unit No
Earthwork Excavation in Soft
A9.1 Soil m3 1
Length Breadth Height Area Quantity Remarks
10.27
13.4 2.7 0.15 5.43
13.54 1.855 0.15 3.77
14 0.3 0.15 0.63
3 1 0.15 0.45

7.05
13.4 2.7 0.1 3.62
13.54 2 0.1 2.71
14 0.3 0.1 0.42
3 1 0.1 0.30

110.47
10 4.38 43.83
10 2.112 21.12
3.4 2 0.5 3.40 Slab extension (curved Part)
4.14 0.75 2.577 8.00 Wall extension (curved Part)
5 0.85 4.22 17.94
1 0.85 4.37 3.71 1st Step
1 0.829 3.37 2.79 2nd Step
1 0.7905 2.37 1.87 3rd Step
14 0.3 1 4.20
10 0.3 1.2 3.60

68.34
0.5 100.65 50.33
1 18.02 18.02

17518.80
10750.09 From Sheet HR 1
Previously Uncertified in IPC 1 New
6768.72 From Sheet HR 2

149.04
5 3.92 19.60
4 3.92 15.68
1 4.37 4.37
1 3.92 7.84 1st Step
1 3.37 6.74 2nd Step
1 2.37 4.74 3rd Step
1 2.37 2.37 Last End Side
10 1.2 24
3.4 0.5 3.4
4.34 2.577 22.37
10 0.993 9.93 Above from 1.95 m
14 1 28

16
2 1 1 16
Length Breadth Height Area Quantity Remarks
190 190

874.86
12.6 5 3.9 245.7
22.32 3.16 7.78 547.92
18.00 1.04 4.34 81.24

18.30
8.80
1.93 5.00 0.15 1.45
8.00 5.00 0.15 6.00
2.50 3.60 0.15 1.35

0.15 10 1.5
0.15 53.357 8.00

13.27

1.93 4.80 0.10 0.93


8.00 0.61 4.88
2.60 3.60 0.10 0.94

2.80 0.68 0.10 0.19


0.10 10.00 1.00
0.10 53.36 5.34

3314.296 From Sheet GR

Length Breadth Height Area Quantity Remarks

3.34 14.16 47.2944

0.15 14.16 2.124

0.1 14.16 1.416

19.903
2.025 7.002 0.504 7.146
1.7 6.95 0.656 7.751
0.3 0.3 1.47 0.529
0.6 0.3 1.47 0.5292
4.68 0.56 2.62 1
2.37 0.56 1.33 2

38.8862
1.2 1.47 7.056
1.8 1.47 5.292
2.1316 4.2632
4.13 0.9 7.434 4.13
2.37 0.9 4.266
4.68 0.5 4.68
2.37 0.5 2.37
4.68 0.5 2.34
2.37 0.5 1.185

3565.68
1530.56 From Sheet DR 1
Previously Uncertified in IPC 1 New,
From Sheet DR 2
2035.12

15

Length Breadth Height Area Quantity Remarks


30 3 90

30 3.2 3 288
30 2.16 0.15 9.72

Length Breadth Height Area Quantity Remarks


111.06
0.50 2.40 0.40 0.48
5.10 1.44 7.344
25.35 4.80 0.40 48.67
4.8 2.0554 9.87
1.45 0.4255 0.62
0.5 0.52 0.52
5.10 0.6382 3.25
5.10 0.435 2.22
25.35 0.96305 24.41
30.35 0.45055 13.67

17161.02 From Sheet FR

331.05
3.4 0.4 1.36
5.1 0.4 4.08
25.3 0.4 20.24
5.12 0.4 4.096
3.92 0.25 2.94
0.5 1.3 2.60
5.1 2.075 21.17
5.1 1.3 13.26
30.35 3.105 188.47
30.35 1.2 72.84

16.75 Previously Uncertified in IPC 1 New


25.50 5.00 0.10 12.75
8.00 5.00 0.10 4.00

Previously Uncertified in IPC 1 New,


From Sheet FE
2624.57

Length Breadth Height Area Quantity Remarks

1305.0469 From sheet PE


PRO SOLUTIONS PVT.LTD.
Kathamandu,Nepal
Client: Rara Hydropower Company Pvt.Ltd.
Project :Upper Parajuli Khola Hydropower Project
Contractor:Pro Solutations Pvt.Ltd.
Date 2074/10/22
Item: Renforcement For Weir And Intake
SN Description Ø of bar (mm)Unit Wt.(Kg/m) No. of Bar
1 Undersulice

20 2.47 26
0.165 9.903 1.225
0

2 16 1.58 51
1.792
0.3
0.404
5.767

3 16 1.58 29

0.202

9.842 0.442

4 20 2.47 51

0.363 0.3

4.708

5 16 1.58 48
0.403

1.171 1.514

6 Divide Wall
1 20 2.47 43
left

3.027

0.30
0
2 Verible length
1 2.887 20 2.47 2
2 3.086 20 2.47 2
3 3.285 20 2.47 2
4 3.485 20 2.47 2
5 0.30 3.685 20 2.47 2
6 3.885 20 2.47 2
7 4.085 20 2.47 2
8 4.335 20 2.47 2

1 Divide Wall 20 2.47 65

2.927

0.30

2 Divide Wall Right 20 2.47 43

3.4

0.3

3 Verible Length

3.357 20 2.47 1
3.556 20 2.47 1
3.755 20 2.47 1
3.955 20 2.47 1
4.155 20 2.47 1
4.355 20 2.47 1
4.555 20 2.47 1
4.805 20 2.47 1

1 Divide Wall Right 16 1.58 80

3.44

0.3

2 Variable Length
3.357 16 1.58 1
3.556 16 1.58 1
3.755 16 1.58 1
3.955 16 1.58 1
4.155 16 1.58 1
4.355 16 1.58 1
4.555 16 1.58 1
4.805 16 1.58 1

Distribution Bar on Divide wall Left Si 20 2.47 26


0.1 0.20
10

Distribution on Divide wall Right 20 2.47 16


Distribution on Divide wall Right 16 1.58 15

Undersulice Right Wall Additional Par 16 1.58 17

1.81
0.5
0.4
1.9
Distribution Bar Bottom And Top 16 1.58 16

Flood wall vertical bar 12 0.889 44

4.97

Flood Wall Distribution Bar

0.3
Wing wall
A
First Step 20 2.47 10

4.27

0.3

B Second Step 20 2.47 10


3.27

0.3
B Third Step 20 2.47 12

2.27

0.3
Wing Wall Distribution
A
0.8

1.24
0.58
1 0.938 16 1.58 5
2 1.938 16 1.58 5
3 2.938 16 1.58 5
4 2.938 16 1.58 5
5 3.774 16 1.58 12

B
0.2
0.58
0.82 16 1.58 5
1.82 16 1.58 5
2.82 16 1.58 5
3.82 16 1.58 5
3.656 16 1.58 12
Cap Bar of Flood And Wing Wall
0.6 20 2.47 35

1 1

Flood wall Distribution


Outer Side 16 1.58 27

3.94
0.698
0.2
Inner Side 16 1.58 27
4.582

Intake
Bed Top bar
0.3
0.3
1 6.19 20 2.47 1
2 6.19 20 2.47 1
3 6.19 20 2.47 1
4 5.899 20 2.47 1
5 5.752 20 2.47 1
6 5.551 20 2.47 1
7 5.34 20 2.47 1
8 5.13 20 2.47 1
9 4.935 20 2.47 1
10 4.732 20 2.47 1
11 4.53 20 2.47 1
12 4.327 20 2.47 1
13 4.124 20 2.47 1
14 3.921 20 2.47 1
15 3.718 20 2.47 1
16 3.513 20 2.47 1
17 3.313 20 2.47 1
18 3.11 20 2.47 1
19 2.907 20 2.47 1
20 2.704 20 2.47 1
21 2.502 20 2.47 1
22 2.299 20 2.47 1
23 2.096 20 2.47 1
24 1.893 20 2.47 1
25 1.69 20 2.47 1
26 1.488 20 2.47 1
27 1.285 20 2.47 1
28 1.089 20 2.47 1
29 1.048 20 2.47 1
Distribution Bar
0.75 1.09
0.5
5.873 20 2.47 1
5.67 20 2.47 1
5.48 20 2.47 1
5.28 20 2.47 1
5.08 20 2.47 1
4.88 20 2.47 1
4.69 20 2.47 1
4.49 20 2.47 1
4.29 20 2.47 1
4.1 20 2.47 1
3.9 20 2.47 1
3.7 20 2.47 1
3.507 20 2.47 1
3.31 20 2.47 1
3.11 20 2.47 1
2.91 20 2.47 1
2.71 20 2.47 1
2.52 20 2.47 1
2.32 20 2.47 1
2.12 20 2.47 1
1.93 20 2.47 1
1.73 20 2.47 1
1.53 20 2.47 1
1.33 20 2.47 1
1.21 20 2.47 1
0.82 20 2.47 1
0.488 20 2.47 1

Intake Get
Bottom Bar

1 0.834 16 1.58 30
0.5
4.433

2 0.3 16 1.58 18
0.3
5.88

3 0.3
0.3 20 2.47 9
5.848

4 20 2.47 18
0.3
0.3
5.848
5
0.8 20 2.47 30
0.5
0.5

6 Distribution Bar 20 2.47 30

6 Th Cuttof
Type -14 16 1.58 73
0.9

0.2
Type -13 16 1.58 73
0.24

0.7

Distribuon Bar 16 1.58 10


Total Length (m) Quantity (Kg) Drg Remark

11.293 725.24 Undersulice type- 8 Sction 3-3

8.263 665.83 Undersulice type- 8 section 4-4

10.486 480.47 Undersulice type- 9 Section 3-3

5.371 676.585 Undersulice type- 4 section 4-4

3.088 234.194 Weir Type -13 Section 2-2

Sub -Total 2782.32

3.327 353.361 Undersulice type- 2 section 4-4


3.187 15.74 Undersulice type- 2 section 4-4
3.386 16.73
3.585 17.71
3.785 18.70
3.985 19.69
4.185 20.67
4.385 21.66
4.635 22.90

3.227 518.095 Undersulice type- 3 section 4-4 With Churve Part

3.7 392.977 Undersulice type- 5 section 4-4

3.657 9.03 Undersulice type- 5 section 4-4


3.856 9.52
4.055 10.02
4.255 10.51
4.455 11.00
4.655 11.50
4.855 11.99
5.105 12.61

3.74 472.736 Undersulice type- 7 section 4-4 With Curve Part

Undersulice type- 7 section 4-4


3.657 5.78
3.856 6.09
4.055 6.41
4.255 6.72
4.455 7.04
4.655 7.35
4.855 7.67
5.105 8.07

10.3 661.466 Undersulice Section 4-4 With Rebar Type 2 And 3

15.344 606.39 Undersulice Section 4-4 With Rebar Type 5


15.805 374.58 Undersulice Section 4-5 With Rebar Type 7

4.61 123.82
.

3.34 84.435

Sub -Total 3882.981


5.27 206.141 Flood wall for Equivalent

4.57 112.88

3.57 88.179
2.57 76.17

3.558 28.11
4.558 36.01
5.558 43.91
5.558 43.91
6.394 121.23

1.6 12.64
2.6 20.54
3.6 28.44
4.6 36.34
4.436 84.107

2.6 224.77

5.638 240.517

4.582 195.468
Sub -Total 1599.359

6.79 16.77
6.79 16.77
6.79 16.77
6.499 16.05
6.352 15.69
6.151 15.19
5.94 14.67
5.73 14.15
5.535 13.67
5.332 13.17
5.13 12.67
4.927 12.17
4.724 11.67
4.521 11.17
4.318 10.67
4.113 10.16
3.913 9.67
3.71 9.16
3.507 8.66
3.304 8.16
3.102 7.66
2.899 7.16
2.696 6.66
2.493 6.16
2.29 5.66
2.088 5.16
1.885 4.66
1.689 4.17
1.648 4.07

8.213 20.29
8.01 19.78
7.82 19.32
7.62 18.82
7.42 18.33
7.22 17.83
7.03 17.36
6.83 16.87
6.63 16.38
6.44 15.91
6.24 15.41
6.04 14.92
5.847 14.44
5.65 13.96
5.45 13.46
5.25 12.97
5.05 12.47
4.86 12.00
4.66 11.51
4.46 11.02
4.27 10.55
4.07 10.05
3.87 9.56
3.67 9.06
3.55 8.77
3.16 7.81
2.828 6.99

Sub -Total 684.25

5.767 273.356 Section L -L

6.48 184.29 Intake Section 5-5

6.448 143.34 Intake Get bed Section 5-5

6.448 286.678

Intake type 4 Section L-L


1.8 133.38

1.6 118.56
sub -Total 1139.60

2 230.68
1.64 189.16

15.3 241.74

Sub -Total 661.5776

Total 10750.09
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Item: Renforcement For Weir And Intake

SN Description Ø of bar (mm) Unit Wt.(Kg/m) No. of Bar Total Length (m) Quantity (Kg)
D/S Apron Weir Part
1 Top Bar Type 6 16 1.58 46 15.793 1147.84

2 Top Distributon Bar 16 1.58 69 11.42 1245.01

3 Bottom Main bar Type 11 16 1.58 48 11.315 858.13

0.5
10.315
0.5

4 Bottom Distribution 16 1.58 48 11.46 869.13

5 5thCutoff Weir Type 12 16 1.58 48 5.021 380.79

2.785
2.031
0.205
6 5thCutoff Undersulice Type 10 16 1.58 20 5.421 171.30

0.7
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Item: Renforcement For Weir And Intake

SN Description Ø of bar (mm) Unit Wt.(Kg/m) No. of Bar Total Length (m) Quantity (Kg)
2.49
2.031

0.2

7 Distribution Bar on 5th Cutof 16 1.58 26 14.46 594.02


total D/S Apron weir 5266.21

a intake bed bottom


intake Triangle Bottom Main Bar
1 16 1.58 1 8.664 13.69
2 16 1.58 1 8.498 13.43
3 1.4 1.4 16 1.58 1 8.295 13.11
4 16 1.58 1 8.093 12.79
5 5.864 16 1.58 1 7.89 12.47
6 16 1.58 1 7.687 12.15
7 16 1.58 1 7.485 11.83
8 16 1.58 1 7.282 11.51
9 16 1.58 1 7.079 11.19
10 16 1.58 1 6.876 10.87
11 16 1.58 1 6.674 10.55
12 16 1.58 1 6.471 10.23
13 16 1.58 1 6.268 9.90
14 16 1.58 1 6.046 9.55
15 16 1.58 1 5.863 9.26
16 16 1.58 1 5.66 8.94
17 16 1.58 1 5.457 8.62
18 16 1.58 1 5.255 8.30
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Item: Renforcement For Weir And Intake

SN Description Ø of bar (mm) Unit Wt.(Kg/m) No. of Bar Total Length (m) Quantity (Kg)
19 16 1.58 1 5.052 7.98
20 16 1.58 1 4.849 7.66
21 16 1.58 1 4.646 7.34
22 16 1.58 1 4.444 7.02
23 16 1.58 1 4.241 6.70
24 16 1.58 1 4.101 6.48
25 16 1.58 1 3.963 6.26
26 16 1.58 1 3.854 6.09
27 16 1.58 1 3.722 5.88
259.82
Bottom Distribution at Intake
1 16 1.58 1 0.931 1.47
2 16 1.58 1 1.129 1.78
3 16 1.58 1 1.326 2.10
4 16 1.58 1 1.523 2.41
5 16 1.58 1 1.72 2.72
6 16 1.58 1 1.918 3.03
7 16 1.58 1 2.115 3.34
8 16 1.58 1 2.312 3.65
9 16 1.58 1 2.509 3.96
10 16 1.58 1 2.707 4.28
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Item: Renforcement For Weir And Intake

SN Description Ø of bar (mm) Unit Wt.(Kg/m) No. of Bar Total Length (m) Quantity (Kg)
11 16 1.58 1 2.904 4.59
12 16 1.58 1 3.101 4.90
13 16 1.58 1 3.298 5.21
14 16 1.58 1 3.496 5.52
15 16 1.58 1 3.693 5.84
16 16 1.58 1 3.89 6.15
17 16 1.58 1 4.08 6.45
18 16 1.58 1 4.284 6.77
19 16 1.58 1 4.482 7.08
20 16 1.58 1 4.679 7.39
21 16 1.58 1 4.876 7.71
22 16 1.58 1 5.073 8.02
23 16 1.58 1 5.271 8.33
24 16 1.58 1 5.475 8.65
25 16 1.58 1 5.634 8.90
26 16 1.58 1 5.748 9.08
27 16 1.58 1 5.628 8.89
28 16 1.58 1 5.508 8.70
156.93
total intake bed bottom 416.75
D Flood Wall
1 Out Side MainBar 16 1.58 27 5.581 238.12

3.881
1.4
0.3
1 In Side Main Bar 16 1.58 27 5.535 236.16
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Item: Renforcement For Weir And Intake

SN Description Ø of bar (mm) Unit Wt.(Kg/m) No. of Bar Total Length (m) Quantity (Kg)

5.235

0.3

Total flood wall 474.28


1 Headwork Distributation 16 1.58 40 3.1 195.92

0.7

0.8
0.8
0.4
0.4

2 Divide Wall on weir Dtion bar


0.95 20 2.47 20 3.536 174.68
1
0.35
0.8
0.436

3 Undersulice type -5 16 1.58 17 3.25 87.30


2.15+0.80 lap
0.3
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Item: Renforcement For Weir And Intake

SN Description Ø of bar (mm) Unit Wt.(Kg/m) No. of Bar Total Length (m) Quantity (Kg)
3 Distribution Bar 16 1.58 20 4.86 153.58

611.47
Grand total 6768.72
Remarks
Remarks

5.864
5.698
5.495
5.293
5.09
4.887
4.685
4.482
4.279
4.076
3.874
3.671
3.468
3.246
3.063
2.86
2.657
2.455
Remarks
2.252
2.049
1.846
1.644
1.441
1.301
1.163
1.054
0.922
Remarks
Remarks

Undersluice intake And Weir Side


Remarks
PRO SOLUTIONS PVT.LTD.
Kathamandu,Nepal
Client: Rara Hydropower Company Pvt.Ltd.
Project :Upper Parajuli Khola Hydropower Project
Contractor:Pro Solutations Pvt.Ltd.
Date 2074/10/22
Item: Renforcement For Gavel trap and spillway
SN Description Ø of bar ( Unit Wt.(K No. of Bar Total Len
Inlet Slope Section
1 16 1.58 16 1.878
0.2

0.839 0.839

1.522 16 1.58 8 2.122

0.6

2.303 16 1.58 8 2.814

0.511

2.465
16 1.58 8 3.1546

0.690

5
0.3 0.30
0.3 0.30 16 1.58 1 5.133
0.712 0.712
3.109

6
0.3 0.3
16 1.58 1 4.928
0.485 0.69
3.153
7 0.3
0.3
16 1.58 1 5.133

0.940 0.940
2.646
8
0.3 0.3
16 1.58 1 4.921
0.691 0.866
2.764

0.3 0.3
16 1.58 1 5.121

1.163 1.163
2.194

0.3 0.3 16 1.58 1 4.916

0.937 1.141
2.238
0.3
0.3 16 1.58 1 5.117

1.386 1.387
1.743

0.3
0.3
16 1.58 1 4.913
1.365
1.161
1.787

0.3 0.3
16 1.58 1 5.1148
1.612 1.612
1.612 1.612
1.291

0.3
0.3
16 1.58 1 4.911
1.590
1.386
1.335

0.3 0.3
16 1.58 1 5.113

1.836 1.836
0.840

0.3 0.3
16 1.58 1 4.91

1.611 1.814
0.884

0.3 0.3
16 1.58 2 5.1
4.5

0.3 0.3 16 1.58 2 4.9

4.3

Mid Section
0.2

0.839 0.839 16 1.58 82 1.878


1.522 16 1.58 41 2.1224

0.6

0.5

2.01
16 1.58 20 3.5223

0.71

0.3

0.8

1.54

16 1.58 20 3.0981
0.55

0.2

0.81 0.81

16 1.58 10 2.8254
0.3 0.3
0.6

0.8 0.8

16 1.58 10 4.1187

0.76 0.76

2.3
16 1.58 41 2.5084

0.21

2.46 16 1.58 41 3.2592

0.8
0.5

2.011
16 1.58 12 3.47

0.658

0.3

0.8

1.543

16 1.58 12 3.039

0.496

0.2

0.806 0.806
16 1.58 12 2.707

0.248 0.248

0.6

0.797 0.797

16 1.58 12 4.012
0.709 0.709

1
0.5

2.01
16 1.58 20 3.37

0.528

0.3

0.8

1.538

0.395 16 1.58 20 2.939

0.2

0.806 0.806
16 1.58 10 2.707

0.147 0.147

0.6

0.794 0.794

16 1.58 10 4.012
0.617 0.619
1

0.5

16 1.58 20 3.264
2.01

0.452

0.3

0.8

1.54

0.296 16 1.58 20 2.8414

0.3

0.806 0.806

16 1.58 10 2.3074
0.048 0.048

0.6

0.793 0.793
16 1.58 10 3.63
0.53 0.53

1.002

0.5

2.01
16 1.58 12 3.1969

0.395

0.301

0.8

1.535

0.235
16 1.58 12 2.77

0.2

16 1.58 6 2.19
0.81 0.81

0.6

0.791 0.791
0.791 0.791

16 1.58 6 3.46
0.441 0.441

Distribution bars

1.540 16 1.58 23 10.654


0.20 0.852
6

8.056

0.206 1.052
16 1.58 23 10.958
1.51
4 8.186

1.495

0.20 0.159 16 1.58 5 1.86


6

0.15
9 16 1.58 5 8.302
8.143

0.20
6
16 1.58 5 2.442
2.236

0.73
9 16 1.58 5 8.826
8.087

Total
Quantity ( Drg Remark

47.47584

26.82208

35.56896

39.87414
8.11014

7.78624

8.11014

7.77518

8.09118

7.76728

8.08486

7.76254

8.081384
7.75938

8.07854

7.7578

16.116

15.484

243.3137
137.4891

111.3047

97.89996

44.64132
65.07546

162.4942

211.131
65.7912

57.61944

51.32472

76.06752
106.492

92.8724

42.7706

63.3896
103.1424

89.78824

36.45692
57.354

60.61322

52.5192

20.7612
32.8008

387.1664

398.2137

14.694

65.5858

19.2918

69.7254
3314.296
PRO SOLUTIONS PVT.LTD.
Kathamandu,Nepal
Client: Rara Hydropower Company Pvt.Ltd.
Project :Upper Parajuli Khola Hydropower Project
Contractor:Pro Solutations Pvt.Ltd.
Date 2074/11/15
Item: Renforcement For Desander
SN Description Ø of bar (mmUnit Wt.(Kg/No. of Bar Total Length (m)

1 Desender Flushing

1 0.30 0.30 16 1.58 38 2.8

0.7
0.7

0.8

2 16 1.58 38 2.2
0.8
0.8

0.6
3 16 1.58 38 1.6
0.4
0.4
0.8
4 16 1.58 38 1

0.1
0.1
0.8
5 Distribution Bar
Wall Bed And Topn Slab 12 0.889 29 5.73
12 0.889 29 3.67

Sub -Total
Desender Flushing Get
1
0.73 12 0.889 12 2.46
0.34
0.34
0.32
2 12 0.889 12 2.4
0.40 0.4

0.33
0.33
0.94

3 Distribution Bar 12 0.889 11 2.4

Sub -Total
Flushing Get Vertical Bar
1 Type -1 16 1.58 6 3.638

0.7
0.7
2.238
Type 2
0.3
0.3 16 1.58 12 1.69
1.09

Type 3 12 0.889 12 5.639

0.32

4.619

0.7
Type 4 12 0.889 18 5.166

0.32

4.646

0.2

Type 5 12 0.889 18 5.366


0.52

4.646

0.2

Distribution bar 10 0.616 44 3.08


1

0.94
0.28
0.215
0.255
0.32

2 10 0.616 88 1.029
0.08

0.869

0.08

3 0.255 10 0.616 44 1.55

0.52
0.52
0.255

Sub -Total

Desender D/S Reguleter Get

1 0.343 12 0.889 9 5.053

4.71

2 0.343 12 0.889 9 3.773

3.33

0.1
Distribution Bar
Left And Right Bar
0.774 10 0.616 26 6.124

0.478
0.3
0.7
1.62
0.7
0.3

0.401
0.774
Middle Bar 10 0.616 26 4.476

1.52
0.478
0.3

0.7
Left ,Right And Middle 10 0.616 52 1.24
0.25

0.74

0.25
Sub -Total
Quantity (Kg) Drg Remark

Flushing Type -1
168.112

132.088 Flushing Type -2

96.064 Flushing Type - 4

60.04 Flushing Type - 3

147.73
94.62

698.65

26.24 Section U-U

25.60 Section U-U

23.47 Section U-U

75.32

34.49 Flushing Get Type -1 Section S-S


32.04

60.157

82.67

85.867

83.48

55.78

42.01
476.49

40.43 Type 3 Section Q-Q

30.188 Type 4

98.082

71.69

39.72

280.11

1530.56
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.
Uncertified from IPC 1
Desender Rebar installed
SN Description Ø of bar (mm)Unit Wt.(Kg/ No. of Bar Total Length (m) Quantity (Kg) Remarks
Desender Left and Right Wall
1 Cap U -Type 12 0.889 376 1.35 451.26 Left and Right

A Inlet Zone 313.29


1 Distribution bar Left & Right Wall
10 0.616 14 1.65 14.23

10 0.616 14 4.796 41.36


2 Distribution bar Middle Wall
10 0.616 28 1.65 28.46
10 0.616 7 2.296 9.90

3 Colum
12 0.89 52 3.115 143.98

4 Stirrup Left And Right


8 0.40 60 1.08 25.6
8 0.40 60 0.824 19.53
5 Middle Wall Colum 8 0.40 30 1.68 19.91
8 0.40 30 0.87 10.31

B Outlet get 1029.91


Flushing Chanal
1 Distribution Bar 10 0.616 26 2.1 33.63
2 Main Bar
16 1.58 30 9.24 437.98

3 Distribution Bar 16 1.58 32 6.8 343.81

4 Main bar Type 6 12 0.89 18 4.197 67.15 Section Q-Q


0.497
0.497
3.203

5 Middle Wall Bar Type -5 12 0.89 40 4.144 147.34


0.714

3.33

0.1

Desender Rebar installed


SN Description Ø of bar (mm)Unit Wt.(Kg/ No. of Bar Total Length (m) Quantity (Kg) Remarks
Desender Left and Right Wall

5 Cap U -Type 12 0.889 188 1.44 240.67 Middle Shear wall

Total 2035.12
PRO SOLUTIONS PVT.LTD.
Kathamandu,Nepal
Client: Rara Hydropower Company Pvt.Ltd.
Project :Upper Parajuli Khola Hydropower Project
Contractor:Pro Solutations Pvt.Ltd.
Date 2074/10/22
Forebay Bar bending schedule
SN Description Ø of bar (mmUnit Wt.(Kg/m)No. of Bar
1
Inlet
Main Bars
1 0.1 0.1

16 1.58 4
1.55 1.55

1.72

0.1
2
0.1

1.2 1.2 16 1.58 4

2.28
3 0.1 0.1

1.31 16 1.58 4
1.31

2.28

Distribution bars
1 Bed 16 1.58 26
2 Wall 16 1.58 20

u/s transition section bed bars

1.27 1.27

1 4.09 16 1.58 1
2 3.99 16 1.58 1
3 3.89 16 1.58 1
4 3.79 16 1.58 1
5 3.69 16 1.58 1
6 3.59 16 1.58 1
7 3.49 16 1.58 1
8 3.39 16 1.58 1
9 3.29 16 1.58 1
10 3.19 16 1.58 1
11 3.09 16 1.58 1
12 2.99 16 1.58 1
13 2.88 16 1.58 1
14 2.78 16 1.58 1
15 2.68 16 1.58 1
16 2.58 16 1.58 1
17 2.48 16 1.58 1
18 2.38 16 1.58 1
19 2.28 16 1.58 1
20 2.18 16 1.58 1
21 2.08 16 1.58 1
22 1.98 16 1.58 1
23 1.88 16 1.58 1
24 1.78 16 1.58 1
25 1.68 16 1.58 1

u/s transition section bed bars

0.45 0.45
4.69 16 1.58 1
4.59 16 1.58 1
4.49 16 1.58 1
4.39 16 1.58 1
4.29 16 1.58 1
4.19 16 1.58 1
4.09 16 1.58 1
3.99 16 1.58 1
3.89 16 1.58 1
3.79 16 1.58 1
3.69 16 1.58 1
3.58 16 1.58 1
3.48 16 1.58 1
3.38 16 1.58 1
3.28 16 1.58 1
3.18 16 1.58 1
3.08 16 1.58 1
2.98 16 1.58 1
2.88 16 1.58 1
2.78 16 1.58 1
2.68 16 1.58 1
2.58 16 1.58 1
2.48 16 1.58 1
2.38 16 1.58 1
2.28 16 1.58 1

u/s transition vertical bar

1 16 1.58 50

1.33

1.21

2 0.1

veriable length

1 3.15 16 1.58 4
2 3.09 16 1.58 4
3 3.02 16 1.58 4
4 2.96 16 1.58 4
5 2.89 16 1.58 4
6 2.83 16 1.58 4
7 2.76 16 1.58 4
8 2.7 16 1.58 4
9 2.63 16 1.58 4
10 2.57 16 1.58 4
11 2.5 16 1.58 4
12 2.44 16 1.58 4
13 2.37 16 1.58 4
14 2.31 16 1.58 4
15 2.24 16 1.58 4
16 2.18 16 1.58 4
17 2.11 16 1.58 4
18 2.05 16 1.58 4
19 1.97 16 1.58 4
20 1.92 16 1.58 4
21 1.86 16 1.58 4
22 1.79 16 1.58 4
23 1.73 16 1.58 4
24 1.66 16 1.58 4
25 1.6 16 1.58 4

Inlet Transition Distribution Bars


Bed
16 1.58 24
16 1.58 16
Wall 16 1.58 38

silting chamber
3 16 1.58 73
0.45 0.45

4.7

4 16 1.58 73
1.33 1.33

4.1
silting chamber vertical bar
5

0.1

Veriable length

1 2.55 16 1.58 40
2 2.59 16 1.58 40
3 2.63 16 1.58 40
4 2.67 16 1.58 40
5 2.71 16 1.58 40
6 2.75 16 1.58 40
7 2.79 16 1.58 40
8 2.826 16 1.58 20
300
Silting chamber
6

0.75 0.75

4.7
16 1.58 55

1.33 1.33

16 1.58 55
4.1
1.33
16 1.58 110
1.21

silting chamber vertical bar


7 0.1

Veriable length

1 16 1.58 54
1 16 1.58 54
2 16 1.58 40
3 16 1.58 40
4 16 1.58 32

Silting Zone Distribution


Bed 16 1.58 50
Wall 16 1.58 60
220
Forebay slope sections
Hump Bar 16 1.58 22
0.2

1.31
1.31

0.3

1.27 1.27

16 1.58 16
4.1

0.87 0.87
16 1.58 16
4.7
1.33
16 1.58 32
1.21
0.1
`
1 16 1.58 4
2 16 1.58 4
3 Variable Length 16 1.58 4
4 16 1.58 4
5 16 1.58 4
6 16 1.58 4
7 0.65 16 1.58 4
8 16 1.58 4
9 16 1.58 4
10 16 1.58 4
11 16 1.58 4
12 16 1.58 4
13 16 1.58 4
14 16 1.58 4
15 16 1.58 4
16 16 1.58 4
0.01

16 1.58 26
6.1

Forebay slope sections Distribution Bars


Bed 16 1.58 50
Wall
16 1.58 64
16 1.58 24

Forebay Submerged Section

16 1.58 13
1.27 1.28

4.1

0.1
.
1.28 16 1.58 39

0.1
1.28

0.01

5.45
16 1.58 26

0.54

0.26 0.26

16 1.58 13
0.61
0.61

4.7

0.1

16 1.58 13
3.8

0.2
1.86
0.1

2.9
16 1.58 13

0.79
0.1
0.1

2.09
Submerged Section
Bed 16 1.58 50
Wall 16 1.58 103

Manhole
0.1

2.87

16 1.58 22

0.76

0.76
0.76

1.01 16 1.58 11
1.01

1.58

0.1

16 1.58 22
3.81
1 1 16 1.58 11

1.1

0.1

16 1.58 20

1.13

0.1
1.13

0.1

1.3
12 0.89 23

0.1

0.1

0.4
0.4 1.10
12 0.89 23

1.59

1.25

12 0.89 23
1.47

0.40

0.1

0.1

1.1
12 0.89 23

0.10
0.1

12 0.89 23
0.7

0.1
0.7

0.3 16 1.58 14
0.3 0.3 0.3

0.6 0.3
Penstock Chamber

4.7
16 1.58 32

0.1

Penstock Chamber Distribution Bars


Bed 16 1.58 50
Total Length (m) Quantity (Kg) Drg Remark

5.02 31.7264

4.88 30.8416

5.1 32.232

94.8

0.5 20.54
0.5 15.8
36.34

6.63 10.48 Inlate Slop Type 1 Section A'-A'


6.53 10.32
6.43 10.16
6.33 10.00
6.23 9.84
6.13 9.69
6.03 9.53
5.93 9.37
5.83 9.21
5.73 9.05
5.63 8.90
5.53 8.74
5.42 8.56
5.32 8.41
5.22 8.25
5.12 8.09
5.02 7.93
4.92 7.77
4.82 7.62
4.72 7.46
4.62 7.30
4.52 7.14
4.42 6.98
4.32 6.83
4.22 6.67
214.28

Inlate Slop Type 1 Section A'-A'

5.59 8.83
5.49 8.67
5.39 8.52
5.29 8.36
5.19 8.20
5.09 8.04
4.99 7.88
4.89 7.73
4.79 7.57
4.69 7.41
4.59 7.25
4.48 7.08
4.38 6.92
4.28 6.76
4.18 6.60
4.08 6.45
3.98 6.29
3.88 6.13
3.78 5.97
3.68 5.81
3.58 5.66
3.48 5.50
3.38 5.34
3.28 5.18
3.18 5.02
173.18

2.54 200.66 u/s transition type-3 sections A'-A'

u/s transition type-1 Sections A'-A'

3.25 20.54
3.19 20.1608
3.12 19.7184
3.06 19.3392
2.99 18.8968
2.93 18.5176
2.86 18.0752
2.8 17.696
2.73 17.2536
2.67 16.8744
2.6 16.432
2.54 16.0528
2.47 15.6104
2.41 15.2312
2.34 14.7888
2.28 14.4096
2.21 13.9672
2.15 13.588
2.07 13.0824
2.02 12.7664
1.96 12.3872
1.89 11.9448
1.83 11.5656
1.76 11.1232
1.7 10.744
591.4256

5.1 193.392
5.1 128.928
4.8 288.192
610.512
5.6 645.904 silting chamber type-2 Sections A'-A'

6.76 779.6984 silting chamber type-1 Sections A'-A'


1425.6024

3.3 208.56 silting chamber type-2 Sections A'-A'


3.34 211.088
3.38 213.616
3.42 216.144
3.46 218.672
3.5 221.2
3.54 223.728
3.576 113.0016
1626.0096

6.2 538.78 silting chamber type-2 Sections B-B

6.76 587.444 silting chamber type-1 Sections B-B


2.54 441.452 Silting Chamber type-3 sections B-B
1567.676

silting chamber vertical bar type-2 sections-B-B

3.65 311.418
3.35 285.822
3.725 235.42
3.775 238.58
3.82 193.1392
1264.3792

28.27 2233.488 .8 m splice length considered


28.272 2680.1856 .8 m splice length considered
4913.6736

3.42 118.8792

6.64 167.8592

6.44 162.8032
2.54 128.4224

6.2 39.184
6.029 38.10328
5.824 36.80768
5.62 35.5184
5.415 34.2228
5.21 32.9272
5.06 31.9792
4.802 30.34864
4.597 29.05304
4.392 27.75744
4.188 26.46816
3.848 24.31936
3.807 24.06024
3.803 24.03496
3.799 24.00968
3.799 24.00968

6.11 250.9988

1311.76656

3.5 276.5

2.8 283.136
2.8 106.176
665.812

6.64 136.3856
3.36 207.0432

6 246.48

6.44 132.2776

5.96 122.4184

5.98 122.8292
967.434

1.87 147.73
1.87 304.3238
452.0538

3.73 129.6548

5.12 88.99

3.91 135.91
3.1 53.88

2.46 77.736

1.5 30.705
3.19 65.2993

3.12 63.8664

1.3 26.611

1.6 32.752

2.1 46.452
Sub -Total 751.85

4.9 247.744

3.12 246.48

Grand Total 17161.02


296
0
Excavation details for the Slope Stabilization
CHAINAGE LENGTH AREA VOLUME
0+000 120.3377 0
0+005 5 138.4874 647.06275
0+010 5 134.846 683.3335
0+015 5 135.0235 674.67375
0+020 5 88.3226 558.36525
0+025 5 130.3177 546.60075
0+030 5 76.5502 517.16975
0+035 5 93.3995 424.87425
0+039.15 4.15 60.8724 126.31023
Total Excavation 4178.39023
forebay Strcture Part Excavation 1035.74
Total Slope cutting 3142.65
previosly carried out 518.08
Slope Stabilization 2624.57
Excavation quantity calculation of powerhouse
Data
Grid Point Previous R.ExcavationCut Type sum
1 851.25 845.5 5.75 a 5.75
2 851.45 845.5 5.95 b 11.9
3 851.67 845.5 6.17 b 12.34
A 4 851.83 845.5 6.33 b 12.66
5 851.97 851.5 0.47 b 0.94
6 852.75 851.5 1.25 b 2.5
7 853.27 851.5 1.77 a 1.77
1 851.18 845.5 5.68 b 11.36
2 851.38 845.5 5.88 d 23.52
3 851.74 845.5 6.24 d 24.96
B 4 851.81 845.5 6.31 d 25.24
5 852.04 851.5 0.54 d 2.16
6 852.55 851.5 1.05 d 4.2
7 852.75 851.5 1.25 b 2.5
1 851.47 845.5 5.97 b 11.94
2 851.59 845.5 6.09 d 24.36
3 851.71 845.5 6.21 d 24.84
C 4 851.85 845.5 6.35 d 25.4
5 852.1 851.5 0.6 d 2.4
6 852.45 851.5 0.95 d 3.8
7 852.79 851.5 1.29 b 2.58
1 851.25 845.5 5.75 b 11.5
2 851.39 845.5 5.89 d 23.56
3 851.76 845.5 6.26 d 25.04
D 4 851.85 845.5 6.35 d 25.4
5 852.1 851.5 0.6 d 2.4
6 852.4 851.5 0.9 d 3.6
7 852.63 851.5 1.13 b 2.26
1 851.18 845.5 5.68 b 11.36
2 851.32 845.5 5.82 d 23.28
3 851.69 845.5 6.19 d 24.76
E 4 851.78 845.5 6.28 d 25.12
5 852 851.5 0.5 d 2
6 852.21 851.5 0.71 d 2.84
7 852.43 851.5 0.93 b 1.86
1 851.32 845.5 5.82 b 11.64
2 851.47 845.5 5.97 d 23.88
3 851.56 845.5 6.06 d 24.24
F 4 851.75 845.5 6.25 d 25
5 851.97 851.5 0.47 d 1.88
6 852.13 851.5 0.63 d 2.52
F

7 852.41 851.5 0.91 b 1.82


1 851.39 845.5 5.89 b 11.78
2 851.54 845.5 6.04 d 24.16
3 851.63 845.5 6.13 d 24.52
G 4 851.82 845.5 6.32 d 25.28
5 852.04 851.5 0.54 d 2.16
6 852.06 851.5 0.56 d 2.24
7 852.48 851.5 0.98 b 1.96
1 851.46 845.5 5.96 b 11.92
2 851.61 845.5 6.11 d 24.44
3 851.7 845.5 6.2 d 24.8
H 4 851.89 845.5 6.39 d 25.56
5 852.11 851.5 0.61 d 2.44
6 852.13 851.5 0.63 d 2.52
7 852.55 851.5 1.05 b 2.1
1 851.51 845.5 6.01 b 12.02
2 851.66 845.5 6.16 d 24.64
3 851.75 845.5 6.25 d 25
I 4 851.94 845.5 6.44 d 25.76
5 852.16 851.5 0.66 c 1.98
6 852.18 851.5 0.68 b 1.36
7 852.6 851.5 1.1 a 1.1
1 851.56 849.5 2.06 b 4.12
2 851.71 849.5 2.21 d 8.84
J 3 851.8 849.5 2.3 d 9.2
4 851.99 849.5 2.49 d 9.96
5 852.21 849.5 2.71 b 5.42
1 851.61 851 0.61 a 0.61
2 851.76 851 0.76 b 1.52
K 3 851.85 851 0.85 b 1.7
4 851.94 851 0.94 b 1.88
5 852.16 851 1.16 a 1.16
835.23

Area of a rectangle 6.25


(a+2b+3c+4d) 835.23

Total Volume of excavation = 1305.047 m3


Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Additional Works:
S.No. Descrition of Works Unit Quantity Rate Amount
Powerhouse Road mantananceby
2 Excavator Hr 4 6500 26000
Charakhola Kulo making And Land Clear
3 of Man B B C By Back Hoe Hr 10 2400 24000
Powerhouse Road mantanance by Back
4 hoe Hr 5 2500 12500

Total 62500
Remarks

Approved By Mangal Bishwakarma


Rara Hydropower Development Company Pvt. Ltd.

SN Description of work Designed Previous Contractor As per contract Quantity Amount

Unit Qty Qty rate Amt Qty dis rate amt previouspresent total previou present
A CIVIL
A1 Weir, Intake and Floodwall for
1 weir 25m Excavation in Boulder
Earthwork m3 3,565.33 568.71 516.96 294,000.32 2,996.62 612.66 1,835,909.21 - -
2 Mix Soil
Backfilling by Earthmaterials m3 987.34 80.74 207.29 16,736.59 906.60 195.11 176,886.73 - -
3 Stone Soling in Foundation m3 99.44 47.78 3,526.48 168,495.21 51.66 3,323.88 171,711.64 - -
4 M10 Concrete Soling m3 64.05 31.86 9,413.63 299,918.25 32.19 9,425.50 303,444.55 - -
5 M25 Concrete PCC m3 582.96 95.02 10,329.91 981,548.05 487.94 17,437.17 8,508,292.73 52.06 52.06 907,810.98
6 M40 Concrete PCC m3 62.63 - 18,000.00 - 62.63 18,851.00 1,180,638.13 - -
7 M60 Concrete PCC m3 41.07 - 24,000.00 - 41.07 25,448.85 1,045,184.27 - -
8 Admixture kg 637.77 - 90.00 - 637.77 278.05 177,331.95 - -
9 Boulder Rip Rap m3 209.75 - 90.00 - 209.75 1,873.79 393,027.45 - -
10 Gabion Protection Structures m3 537.47 159.00 3,190.67 507,316.53 378.47 4,241.47 1,605,269.15 - -
11 M20 40% Plum Concrete m3 124.39 22.75 6,500.00 147,849.00 101.64 11,781.87 1,197,556.39 - -
12 Reinforcement kg ### ### 114.32 ### 47,292.35 111.22 5,259,855.17 6,802.20 6,802.20 756,540.26
13 River Bed Maerial Packing+ m3 172.96 58.04 3,526.48 204,676.90 114.92 3,323.88 381,967.49 46.55 46.55 154,733.26
sediment filling for compaction
14 Formworks m2 1,713.49 327.46 403.19 132,029.00 1,386.03 659.78 914,474.21 87.65 87.65 57,829.85
20 Protection Works - use of excavator hr 56.00 - 56.00 923.70 51,727.20 - -
for boulder protection
21 River diversion works (earth m3 198.00 - 522.73 2,827.65 1,478,097.48 522.73 522.73 1,478,106.91
excavation in boulder mix soil)
22 Dewatering hr 250.00 - 250.00 250.00 62,500.00 35.00 35.00 8,750.00
23 Debris clearing ( due to flood) hr 45.00 - 45.00 6,500.00 292,500.00 45.00 45.00 292,500.00
24 Admixture ( Quick set) kg 150.00 150.00 90.00 13,500.00 -
25 Admixture (Super plasticizer kg 50.00 50.00 120.00 6,000.00 -
@1.5%)
Subtotal A1 ### ### - - ###
-
A2 Gravel Trap & Spillway
1 Site Clearance m2 190.00 - - - 190.00 28.28 5,373.20 - -
2 Earthwork Excavation in Soft Soil m3 874.36 - - - 874.36 612.66 535,685.40 - -
3 Stone Soling in Foundation m3 25.53 - - - 25.53 3,323.88 84,858.66 - -
4 PCC 1:3:6, (M10) m3 17.16 - - - 17.16 9,425.50 161,741.58 - -
5 PCC 1:1.5:3, (M20) m3 81.43 - - - 81.43 13,195.70 1,074,525.85 - -
6 Formworks m2 235.39 - - - 235.39 659.78 155,305.61 - -
7 Reinforcement kg 5,700.00 - - - 5,700.00 111.22 633,954.00 - -
Subtotal A2 - ### - -
-
A3 Approach Canal
1 Earthwork in Excavation in soft soil m3 260.66 - - - 260.66 612.66 159,695.96 - -

Page 110 of 140


Rara Hydropower Development Company Pvt. Ltd.

2 Earthmaterial Back filling m3 36.97 - - - 36.97 195.11 7,213.22 - -


3 Stone Soling in foundation m3 5.77 - - - 5.77 3,323.88 19,178.79 - -
4 PCC 1:3:6 (M10) m3 3.91 - - - 3.91 9,425.50 36,853.71 - -
5 PCC 1:1.5:3 (M20) m3 13.02 - - - 13.02 13,195.70 171,808.01 - -
6 Reinforcement bar kg 770.00 - - - 770.00 111.22 85,639.40 - -
7 Form works m2 110.86 - - - 110.86 659.78 73,143.21 - -
Subtotal A3 - 553,532.29 -

A4 Desilting Basin
1 Site Clearance m2 528.00 528.00 24.87 13,131.36 - - -
2 Earthwork Excavation in BMS m 3
1,859.12 ### 516.96 961,092.74 - - -
3 Stone Soling in Foundation m3 67.92 67.92 3,526.48 239,507.94 - - -
4 PCC 1:3:6, (M10) m 3
44.76 44.76 9,413.63 421,335.25 - - -
5 PCC 1:1.5:3, (M20) m3 397.39 231.32 12,187.40 ### 166.07 13,195.70 2,191,400.66 95.35 95.35 1,258,168.61
6 Stone Masonry Works m 3
62.36 - 7,938.33 - 62.36 7,482.27 466,594.36 - -
7 Formworks m3 1,540.35 637.87 403.19 257,182.81 902.48 659.78 595,438.25 632.40 632.40 417,242.76
8 Reinforcement kg ### ### 114.32 ### 6,398.40 111.22 711,630.05 5,624.74 5,624.74 625,583.63
9 Admixture kg 800.00 - 800.00 282.76 226,208.00 - -
10 Canal Crossing (for irrigation Kulo) ### 1.00 - -
11 debris removal manually Md 691.00 691.00 776.30 536,423.30 691.00 691.00 536,423.30
12 backfilling Hr 27.00 27.00 6,500.00 175,500.00 9.00 9.00 58,500.00
Subtotal A4 ### ### - - ###

Page 111 of 140


Rara Hydropower Development Company Pvt. Ltd.

A5 Headrace Canal
1 Site clearance m2 4,020.00 ### 24.87 81,194.33 755.25 28.28 21,358.47 - -
2 Earthwork Excavation in Canal m3 ### ### 200.00 ### 8,000.00 282.76 2,262,080.00 7,869.26 7,869.26 2,225,111.25
3 Access roadExcavation in Boulder
Earthwork m3 ### ### 516.96 ### 3,985.37 612.66 2,441,676.78 - -
4 Mix Soil
Earthwork Excavation in Medium m3 669.90 529.15 1,865.59 987,176.95 140.75 1,131.06 159,196.70 - -
Rock Soil
5 Eathwork in back filling m3 6,504.63 ### 207.29 703,604.45 3,110.33 195.11 606,856.49 - -
6 0.15m Stone Soling in foundation m3 868.32 423.41 3,526.48 ### 444.91 3,323.88 1,478,827.45 - -
7 PCC 1:1.5:3, M20 m3 2,605.85 ### 12,187.40 ### 1,432.05 13,195.70 ### - -
8 Reinforcement kg ### ### 114.32 ### ### 111.22 ### - -
9 FormWork m2 ### ### 403.19 ### 9,719.79 659.78 6,412,925.69 - -
10 PCC 1:3:6, M10 (0.1m Conrete m3 48.60 48.60 9,413.63 457,502.42
11 Soling)
River Training Works
a Concrete (1:2:4) with 30% plum m3 232.50 232.50 5,818.42 ### -
b FormWork m2 47.00 47.00 403.19 18,949.93 -
c Gabion Protection Structure m3 473.80 473.80 3,190.67 ### -
d Earthwork in backfilling m3 334.60 334.60 207.29 69,359.23 -
e Earthwork Excavation m3 1,070.10 ### 516.96 553,198.90 -

Subtotal A5 ### ### - - ###

A6Kholsi Crossing
1Budhi kholsi crossing
aSite clearance m2 30.00 - 30.00 28.28 848.40 - -
bEarthwork Excavation in Boulder m3 30.00 - 30.00 612.66 18,379.80 - -
cMix Soil
Earthwork Excavation in Medium m3 3.00 - 3.00 1,131.06 3,393.18 - -
Rock Soil
d Eathwork in back filling m3 6.00 - 6.00 195.11 1,170.66 - -
e 0.15m Stone Soling in foundation m3 5.47 - 5.47 3,323.88 18,181.62 - -
f PCC 1:2:4, M15 (0.1m Conrete m3 2.74 - 2.74 9,425.50 25,825.87 - -
g Soling)
PCC 1:1:2, M25 m3 34.37 - 34.37 17,437.17 599,315.53 - -
h Reinforcement kg 2,765.70 - 2,765.70 111.22 307,601.15 - -
i FormWork m2 61.92 - 61.92 659.78 40,853.58 - -
2 Other kholsi crossing
a Earth work in excavation in soft m3 45.60 45.60 356.53 16,257.77 -
b soil
gabion protection structure m3 118.00 118.00 3,190.67 376,499.06 -
c boulder riprap m3 9.13 9.13 1,949.25 17,796.65 -
d stone masonry m3 4.87 4.87 7,938.33 38,659.67 -

Subtotal A6 ### ### - -


-
A7 Forebay Basin / Spillway -
1 Site Clearance m2 540.00 - - - 540.00 28.28 15,271.20 250.00 250.00 7,070.00

Page 112 of 140


Rara Hydropower Development Company Pvt. Ltd.

2 Earthwork in Excavation m3 1,553.95 - - - 1,553.95 612.66 952,043.01 1,035.74 1,035.74 634,556.31


3 Stone soling in foundation m3 97.22 - - - 97.22 3,323.88 323,147.61 28.46 28.46 94,605.85
4 PCC (1:3:6) M10 m3 58.82 - - - 58.82 9,425.50 554,407.91 18.84 18.84 177,576.42
5 PCC (1:1.5:3) M20 m3 319.95 - - - 319.95 13,195.70 4,221,964.22 - -
6 Reinforcement Bars kg ### - - - 31,995.09 111.22 3,558,493.91 - -
7 Formwork for PCC/RCC m2 1,682.90 - - - 1,682.90 659.78 1,110,343.76 - -
8 Trashrack for Forebay Set 1.00 - - - 1.00 - - -
9 Penstock inlet gate Set 1.00 - - - - - -
10 Bitumin filler pad 12mm thick m2 4.76 - - - 4.76 - - -
11 Water stopper m 1.71 - - - - - - -
12 Sealant Rm 4.76 - - - - - - -
15 Retaining Wall - - -
a Gabion Protection Strucutre m3 550.00 - 550.00 4,241.47 2,332,808.50 - -
13 Excavation for slope stabilization m3 2,624.57 2,624.57 300.00 787,369.97 2,624.57 2,624.57 787,369.97
Subtotal A7 - ### - - ###

A8 Penstock, Anchor Block & -


1 Support
Forbay toPiers
PH access road
i Access Road km 2.00 2.00 ### ### -
2 Excavation Soil (BMS) m3 1,432.60 - 1,432.60 612.66 877,696.72
3 Filling soil m3 1,281.07 - 1,281.07 195.11 249,949.45 - -
4 Gravel soling m3 7.44 - 7.44 1,583.48 11,773.17 - -
5 Penstock crossing Kholsi crossing - - - -
6 M15 Plum concrete (30% plum) m3 25.67 - 25.67 11,310.60 290,331.79 - -
7 Hume Pipe Dia. 1.50 m m 20.00 - 20.00 10,368.05 207,361.00 - -
8 M20 PCC Anchor block & Sadal m3 121.19 121.19 13,195.70 1,599,155.90 - -
9 Support
Reinforcement steel kg 4,850.00 - 4,850.00 111.22 539,417.00 - -
10 Gravel base for penstock for 100% m3 - 331.16 1,873.79 620,524.30 - -
11 length
stone masonry for Sadal Support m3 268.60 268.60 7,482.27 2,009,761.67 - -
(1:6 C/S ratio)
Subtotal A8 ### ### - - - - -

A9 Powerhouse and Tailrace - -


1 Earthworks Excavation in Soft Soil m3 1,184.04 170.01 356.53 60,613.67 1,014.03 612.66 621,255.62
2 Backfilling m3 948.80 - - - 948.80 195.11 185,120.37
3 100 mm gravel filling m3 72.57 - - - 72.57 3,323.88 241,213.97 - -
4 M10 Concrete Soling m3 59.19 - - - 59.19 9,425.50 557,895.35 - -
5 M20 Concrete for RCC m3 174.18 - - - 174.18 13,195.70 2,298,427.03 - -
6 M20 Concrete for RCC m3 215.69 - - - 215.69 13,195.70 2,846,180.53 - -
7 M25 Structural Concrete m3 6.48 - - - 6.48 17,437.17 112,992.86 - -
8 Formwork m2 1,455.37 - - - 1,455.37 659.78 960,224.02 - -
9 Reinforcement steel for RCC works kg ### - - - 23,200.00 111.22 2,580,304.00 - -
10 Stone Masonry works m3 137.57 - - - 137.57 7,482.27 1,029,335.88 - -
11 Fixing Aluminium Windows m2 106.60 - - - 106.60 9,161.58 976,624.43 - -

Page 113 of 140


Rara Hydropower Development Company Pvt. Ltd.

12 Fixing Doors Nos. 17.25 - - - 17.25 9,425.50 162,589.88 - -


13 Rolling shutters m2 48.00 - - - 48.00 2,733.39 131,202.72 - -
14 Steel works Ton 1.23 - - - 1.23 14,138.25 17,390.05 - -
15 Iron work in Truss of 4"Dia pipe m 774.48 - - - 774.48 2,780.52 2,153,457.13 - -
16 Iron work in Truss of 2.5"Dia pipe m 228.90 - - - 228.90 1,329.00 304,208.10 - -
17 CGI Sheet roofing m2 688.84 - - - 688.84 1,131.06 779,119.37 - -
18 Gabion Protection Structures m3 250.00 154.00 3,190.67 491,363.18 96.00 4,241.47 407,181.12 - -
19 Dewatering hr 200.00 200.00 250.00 50,000.00
Subtotal A9 ### ### -

A10 Switchyard (Civil Works) all - -


1 complete
Civil works for switchyard, fencing m2 375.00 - 375.00 10,239.86 3,839,947.50
with GI pipes and 11SWG GI wire
mesh; 15m x 15m ground area with
10cm crushed rock soling,
electricall hardware supports all
complete
Subtotal A10 - ###
A11 Access / construction road ### - -

- -
A12 Day works ###

A13 General Item ###


TOTAL (CIVIL) A1 - A13 ### ###

B3 Other local procurement


1 contract
Penstock pipe cutting & processing T 394.09 119.29 2,500.00 298,225.00 274.80 1,800.72 494,837.86
Final processing / preparation at T 394.09 119.29 394.09 23,711.68 9,344,535.97
2
site & Installation
3 C clamp, Bel-mouth, base plates, T 0.90 0.90 ### 189,000.00 0.90 22,619.12 20,357.21 - -
installation
Branch pipes after bifurcation T 4.24 4.24 4.24 ### 659,784.90 - -
4
supply and delivery
5 Branch pipes after bifurcation T 4.24 4.24 4.24 22,619.12 95,900.77 - -
6 installation
Transportation and handling to site T 394.99 119.29 7,000.00 835,030.00 275.70 6,597.85 1,819,055.22 - -
7 Pipe coating outside- material m 1,465.00 ### 1,465.00 1,371.41 2,009,115.65 - -
8 Pipe coating outside- transport, LS 1.00 82,284.61 82,284.61 - -
labor
9 Welding rods, consumption per m 1,465.00 ### 1.00 ### 1,281,867.84 - -
meter run
10 Penstock pipe Weld Quality test No 1.00 - 1.00 ### 754,039.91 - -
11 Air Vent pipe m 5.00 - - - 5.00 3,298.92 16,494.60 - -
12 Flushing Valve Set 1.00 - - - 1.00 23,563.75 23,563.75 - -

Page 114 of 140


Rara Hydropower Development Company Pvt. Ltd.

Total B3 ### ### - -


-
TOTAL (HYDRO-MECH) ### - ### - -
-
C ELECTRO-MECHANICAL -
5 Earthing works final design, supply Lot 1.00 - - - 1.00 ### 706,912.41 - -
of materials and installation,
Manpower for Installation (Local
technical expert, skilled and
unskilled labour) under the
supervision of HVGCL experts
7 Local travel, lodging, fooding of Lot 1.00 - - - 1.00 ### 471,274.94 - -
HVGCL experts
TOTAL C 0.00 ### - -

D TRANSMISSION LINE
D1 33 KV Line Complete Works
I Supply materials ex-works
1 11m Steel Telescopic poles nos 252.00 97.00 9,005.75 873,557.75 155.00 32,046.70 4,967,238.50 - -
2 33 KV Disc Insulator with tension set 756.00 - 756.00 2,639.14 1,995,189.84 - -
set(3 bolted type)
3 33kv Pin Insulator with insulator set 630.00 - 630.00 822.85 518,395.50 - -
4 spindle
HT Stay Insulator nos 140.00 - 140.00 502.85 70,399.00 - -
5 HTstay set nos 140.00 - 140.00 3,291.38 460,793.20 - -
7 Stay wire 7/8swg m 1,680.00 - 1,680.00 68.57 115,197.60 - -
8 Crossarm channel 125x nos 210.00 63.00 850.00 53,550.00 147.00 754.04 110,843.88 - -
9 65x6x300mm
Crossarm channel 125x65x nos 210.00 63.00 3,000.00 189,000.00 147.00 3,770.20 554,219.40 - -
10 6x1900mm
Crossarm channel 125x65x nos 84.00 - 84.00 6,315.08 530,466.72 - -
11 6x3300mm
Flat Bracing (40x760x6mm) nos 336.00 - 336.00 329.89 110,843.04 - -
12 Bracing Angle ( 50x50x5x2416 nos 168.00 126.00 300.00 37,800.00 42.00 2,827.65 118,761.30 - -
14 mm)
Brack Strap(60*6*410) nos. 252.00 - 252.00 377.02 95,009.04 - -
15 Pole Clamp for Top 300mm Arm nos 210.00 - 210.00 484.56 101,757.60 - -
16 Pole Clamp for 1900mm Arm nos 210.00 - 210.00 706.91 148,451.10 - -
17 Pole Clamp for Bracing Angle Top nos 84.00 - 84.00 565.53 47,504.52 - -
18 Pole Clamp for Bracing Angle nos 84.00 - 84.00 565.53 47,504.52 - -
19 Bottom
Stay clamp nos 140.00 - 140.00 377.02 52,782.80 - -
20 Nut bolts with washer lot 14.00 - 14.00 45,242.39 633,393.46 - -
21 100 sq mm ACSR conductor Km 44.10 - 44.10 ### 4,838,334.92 - -

II Transportation ktm to Site Kg


1 11m Steel Telescopic poles nos 252.00 172.00 1,455.00 250,260.00 80.00 2,356.37 188,509.60 - -
2 33 KV Disc Insulator with tension set 756.00 194.00 - 756.00 182.85 138,234.60 - -
set(3 bolted type)
3 33kv Pin Insulator with insulator set 630.00 194.00 - 630.00 182.85 115,195.50 - -
4 spindle
HT Stay Insulator nos 140.00 48.50 - 140.00 45.71 6,399.40 - -

Page 115 of 140


Rara Hydropower Development Company Pvt. Ltd.

5 HTstay set nos 140.00 291.00 - 140.00 274.28 38,399.20 - -


7 Stay wire 7/8swg m 1,680.00 4.85 - 1,680.00 4.74 7,963.20 - -
8 Crossarm channel 125x nos 210.00 115.00 87.30 10,039.50 95.00 141.38 13,431.10 - -
9 65x6x300mm
Crossarm channel 125x65x nos 210.00 102.00 242.50 24,735.00 108.00 282.76 30,538.08 - -
10 6x1900mm
Crossarm channel 125x65x nos 84.00 218.25 - 84.00 282.74 23,750.08 - -
11 6x3300mm
Flat Bracing (40x760x6mm) nos 336.00 29.10 - 336.00 27.43 9,216.48 - -
12 Bracing Angle ( 50x50x5x2416 nos 168.00 9.00 242.50 2,182.50 159.00 282.76 44,958.84 - -
14 mm)
Brack Strap(60*6*410) nos. 252.00 9.70 - 252.00 9.14 2,303.28 - -
15 Pole Clamp for Top 300mm Arm nos 210.00 19.40 - 210.00 18.29 3,840.90 - -
16 Pole Clamp for 1900mm Arm nos 210.00 29.10 - 210.00 27.43 5,760.30 - -
17 Pole Clamp for Bracing Angle Top nos 84.00 29.10 - 84.00 27.43 2,304.12 - -
18 Pole Clamp for Bracing Angle nos 84.00 29.10 - 84.00 27.43 2,304.12 - -
19 Bottom
Stay clamp nos 140.00 19.40 - 140.00 18.36 2,570.40 - -
20 Nut bolts with washer lot 14.00 3,880.00 - 14.00 3,657.09 51,199.26 - -
21 100 sq mm ACSR conductor Km 44.10 1,940.00 - 44.10 1,828.55 80,639.06 - -

III Erection, stringing and other Km 14.00 ### - 14.00 ### 2,559,965.52 - -
testing & commissioning charges
Subtotal D1 ### ### - -

TOTAL (TRANSMISSION LINE) ### ### - -

Additional Works 121,500.00

GRAND TOTAL (A+B+C+D) ### ### - ###

Total scope of works


VAT
Chargeable by Vendors /
contractors

Page 116 of 140


Rara Hydropower Development Company Pvt. Ltd.

Amount

total

-
-
-
-
907,810.98
-
-
-
-
-
-
756,540.26
154,733.26

57,829.85
-

1,478,106.91

8,750.00
292,500.00

###

-
-
-
-
-
-
-
-

Page 117 of 140


Rara Hydropower Development Company Pvt. Ltd.

-
-
-
-
-
-
-

-
-
-
-
1,258,168.61
-
417,242.76
625,583.63
-
-

###

Page 118 of 140


Rara Hydropower Development Company Pvt. Ltd.

-
2,225,111.25
-
-

-
-
-
-
-

###

-
-
-

-
-
-
-
-
-

7,070.00

Page 119 of 140


Rara Hydropower Development Company Pvt. Ltd.

634,556.31
94,605.85
177,576.42
-
-
-
-
-
-
-
-
-
-
787,369.97
###

-
-
-
-
-
-
-
-
-

-
-
-
-
-
-
-
-
-

Page 120 of 140


Rara Hydropower Development Company Pvt. Ltd.

-
-
-
-
-
-
-

-
-

-
-
-
-
-
-
-
-

Page 121 of 140


Rara Hydropower Development Company Pvt. Ltd.

-
-

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

-
-

-
-

Page 122 of 140


Rara Hydropower Development Company Pvt. Ltd.

-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-

121,500.00
-
###

Page 123 of 140


Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Item No. A1 Weir Intake and Floodwall


S.No. BOQ No. Descrition of Works Chainage/Detail Unit No Length
1 A1.5 M25 Concrete
Divide Wall m3 1
Weir Side Wall m3 1
5 th Cutoff m3 1 14
Intake m3 1
D/S Apron Slab m3 1 9.5

2 A1.12 Reinforcement kg

Rever Bed Material Packing +


2 A1.13
Sediment filling For Compaction m3 1 9.2

3 A1.14 Formworks
Divide Wall m2 1 9.71
weir Side Wall Right m2 1
5 Th cutoff m2 2 14
Intake m2 1 7.98

River diversion works (earth


4 A1.21 m3 1
excavation in boulder mix soil)
40
20 m3
1 20
40 m3 1 20

55
60 m3
1 20
80 m3 1 20
95 m3 1 15

5 A1.22 Dewatering Hr
Dewatering at Intake Hr 1
Dewatering at 5th Cutoff Hr 1

6 A1.23 Debris clearing ( due to flood) Hr


Hr 1

Item No. A4 Desilting Basin


S.No. BOQ No. Descrition of Works Chainage/Detail Unit No Length
A4.5 PCC 1:1.5:3, (M20)
Left and Right Shearwall Section P"-P" to Out let m3 2 30
Middle Shearwall Section P"-P" to Out let m3 1 30
Left and Right Shearwall Section Inlet Zone- P"-P" m3 2 12.03
Middle Shearwall Section Inlet Zone- P"-P" m3 1 11.95
Left And Right Wall Inlet Zone m3 2 1.7
Middle Wall Inlate Zone m3 1
Section Q-Q OutLet Zone m3 1 2.03

A4.7 Desender Formworks


Left and Right Shearwall Section P"-P" to Out let m2 4 30
Middle Shearwall Section P"-P" to Out let m2 2 30
Left and Right Shearwall Section Inlet Slop Start- P"-P" m2 4 12.03
Middle Shearwall Section Slop Start- P"-P" m2 2 11.95
Left And Right Wall Inlate Zone m2 4 1.7
Middle Wall Inlate Zone m2 2 1.7
Section Q-Q OutLet Zone m2 2 9.09

A4.8 Reinforcement kg

A4.11 debris removal manually Md

A4.12 backfilling Hr

Item No. A5 Headrace Canal


S.No. BOQ No. Descrition of Works Chainage/Detail Unit No Length
Earthwork Excavation in Canal
A5.2
Road Access
Boulder mix Soil 1+710-1+827 m3 1 117
1 6.5
2 6.5
3 6.5
4 6.5
5 6.5
6 6.5
7 6.5
8 6.5
9 6.5
10 6.5
11 6.5
12 6.5
13 6.5
14 6.5
15 6.5
16 6.5
17 6.5
18 6.5
Earthwork Excavation in Canal
1+710-1+827 1 117
Road Access
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

Item No. A7 Forebay Basin/Spillway


S.No. BOQ No. Descrition of Works Chainage/Detail Unit No Length
A7.1 Site Clarance
Forebay m2 1.00

A7.2 Earthwork Excavation m3


Inlet Zone m3 1.00 4.80
Seltting Zone m3 1.00 25.34
Penstock Chamber m3 1.00 6.99

A7.3 Stone Soling in Foundation


Inlet Zone m3 1.00 5.49
Settling Zone m3 1.00 25.48
Penstock Chamber m3 1.00 8.30

A7.4 PCC (1:3:6) M10


Inlet Section m3 1.00 5.50
Breadth Height Area Quantity Remarks
52.06
1.2 3.39 4.07
0.3 9.48 2.84
0.4 2.05 11.47
1.01 20.65 20.86
4.5 0.3 12.83

6802.20

5.06 46.55

87.65
1.2 11.65
9.48 9.48
2.05 57.34
1.15 9.17

6.72 522.73
4.88 195.30
5.1 1.2 6.12 122.40
4.05 0.9 3.65 72.90

5.95 327.43
5.3 1.55 8.22 164.30
4.5 1.3 5.85 117.00
3.45 1.1 3.80 56.93

35.00
10.50
24.5

45.00
45.00

Breadth Height Area Quantity Remarks


95.35
0.26 2.86 44.79
0.3 2.76 24.84
0.3 1.52 10.97
0.3 1.13 4.06
0.4 1.40 1.91
1.40 1.16 1.63
7.06 0.5 7.15

632.40
2.86 343.2
2.76 165.6
1.52 73.14
1.13 27.05
1.40 9.54
1.40 4.77
0.5 9.09

5624.74

691

Breadth Height Area Quantity Remarks

7869.2575
44.001 5148.13
4.7 7 32.9
5.6 5 28
4.3 5 21.5
5.4 5 27
5.4 7 37.8
12.5 5.5 68.75
7.5 5.5 41.25
5.8 9 52.2
8.6 8 68.8
5.7 8 45.6
6.2 8 49.6
7.9 6 47.4
9 6 54
8.9 7 62.3
6.9 7 48.3
9.3 5 46.5
5.7 5 28.5
6.2 5.1 31.62
23.258 2721.13
4.7 3.46 16.25
5.6 3.48 19.48
4.3 3.48 14.96
5.4 3.36 18.13
5.4 3.03 16.38
12.5 2.72 33.98
7.5 2.76 20.69
5.8 3.99 23.13
8.6 3.58 30.79
5.7 3.75 21.39
6.2 3.77 23.37
7.9 3.36 26.53
9 3.54 31.85
8.9 3.26 29
6.9 3.49 24.05
9.3 2.38 22.14

Breadth Height Area Quantity Remarks

250.00 250.00

1035.74
6.85 2.73 89.66
6.30 3.76 599.85
7.90 6.27 346.23

28.46
3.80 0.15 3.13
5.00 0.15 19.11
5.00 0.15 6.23

18.84
3.80 0.10 2.09
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Item: Renforcement For Weir And Intake

SN Description Ø of bar (mm) Unit Wt.(Kg/m) No. of Bar Total Length (m) Quantity (Kg) Remarks
D/S Apron Weir Part
1 Top Bar Type 6 16 1.58 46 15.793 1147.84

2 Top Distributon Bar 16 1.58 69 11.42 1245.01

3 Bottom Main bar Type 11 16 1.58 48 11.315 858.13

4 Bottom Distribution 16 1.58 24 11.46 434.56


5 5thCutoff Weir Type 12 16 1.58 48 5.021 380.79
6 5thCutoff Undersulice Type 10 16 1.58 20 5.421 171.30
7 Distribution Bar 16 1.58 26 14.46 594.02
total D/S Apron weir 4831.65

a intake bed bottom


intake Triangle Bottom Main Bar
1 16 1.58 1 8.664 13.69 5.864
2 16 1.58 1 8.498 13.43 5.698
3 1.4 1.4 16 1.58 1 8.295 13.11 5.495
4 16 1.58 1 8.093 12.79 5.293
5 5.864 16 1.58 1 7.89 12.47 5.09
6 16 1.58 1 7.687 12.15 4.887
7 16 1.58 1 7.485 11.83 4.685
8 16 1.58 1 7.282 11.51 4.482
9 16 1.58 1 7.079 11.19 4.279
10 16 1.58 1 6.876 10.87 4.076
11 16 1.58 1 6.674 10.55 3.874
12 16 1.58 1 6.471 10.23 3.671
13 16 1.58 1 6.268 9.90 3.468
14 16 1.58 1 6.046 9.55 3.246
15 16 1.58 1 5.863 9.26 3.063
16 16 1.58 1 5.66 8.94 2.86
17 16 1.58 1 5.457 8.62 2.657
18 16 1.58 1 5.255 8.30 2.455
19 16 1.58 1 5.052 7.98 2.252
20 16 1.58 1 4.849 7.66 2.049
21 16 1.58 1 4.646 7.34 1.846
22 16 1.58 1 4.444 7.02 1.644
23 16 1.58 1 4.241 6.70 1.441
24 16 1.58 1 4.101 6.48 1.301
25 16 1.58 1 3.963 6.26 1.163
26 16 1.58 1 3.854 6.09 1.054
27 16 1.58 1 3.722 5.88 0.922
259.82
Bottom Distribution at Intake
1 16 1.58 1 0.931 1.47
2 16 1.58 1 1.129 1.78
3 16 1.58 1 1.326 2.10
4 16 1.58 1 1.523 2.41
5 16 1.58 1 1.72 2.72
6 16 1.58 1 1.918 3.03
7 16 1.58 1 2.115 3.34
8 16 1.58 1 2.312 3.65
9 16 1.58 1 2.509 3.96
10 16 1.58 1 2.707 4.28
11 16 1.58 1 2.904 4.59
12 16 1.58 1 3.101 4.90
13 16 1.58 1 3.298 5.21
14 16 1.58 1 3.496 5.52
15 16 1.58 1 3.693 5.84
16 16 1.58 1 3.89 6.15
17 16 1.58 1 4.08 6.45
18 16 1.58 1 4.284 6.77
19 16 1.58 1 4.482 7.08
20 16 1.58 1 4.679 7.39
21 16 1.58 1 4.876 7.71
22 16 1.58 1 5.073 8.02
23 16 1.58 1 5.271 8.33
24 16 1.58 1 5.475 8.65
25 16 1.58 1 5.634 8.90
26 16 1.58 1 5.748 9.08
27 16 1.58 1 5.628 8.89
28 16 1.58 1 5.508 8.70
156.93
total intake bed bottom 416.75
D Flood Wall
1 Out Side MainBar 16 1.58 27 5.581 238.12

1 In Side Main Bar 16 1.58 27 5.535 236.16


total flood wall 474.28

SN Description Ø of bar (mm) Unit Wt.(Kg/m) No. of Bar Total Length (m) Quantity (Kg) Remarks
1 Headwork Destributatio 16 1.56 40 3.1 193.44 Undersluice intake side
2 Divide Wall on weir Dtion bar
20 2.47 20 3.536 174.68
Total 368.12

3 Undersulice type -5 16 1.58 17 3.25 87.30


3 Distribution Bar 16 1.58 20 4.75 150.10
237.40

Distribution Bar 16 1.58 24 12.5 474

1079.51
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Desender Rebar installed


SN Description Ø of bar (mmUnit Wt.(Kg No. of Bar Total Length Quantity (KgRemarks
Desander reinforcement Grand Total 5624.74
Desender Left and Right Wall
1 Cap U -Type 12 0.889 376 1.94 648.47 Left and Right
2 Distribution Bar p p- p"p" 10 0.616 76 32.5 1521.52 Left and Right
3 Distribution Bar Slop Start- p"p" 10 0.616 68 11.204 469.31 Left and Right
Desender Middle Shear wall
4 Main Bar 12 0.889 240 2.833 604.45 Middle Shear wall
Total 3243.75
A Inlet Zone 313.29
Distribution bar Left &
1 Right Wall
10 0.616 14 1.65 14.23

10 0.616 14 4.796 41.36


Distribution bar Middle
2 Wall
10 0.616 28 1.65 28.46
10 0.616 7 2.296 9.90

3 Colum
12 0.89 52 3.115 143.98

4 Stirrup Left And Right


8 0.40 60 1.08 25.6
8 0.40 60 0.824 19.53
5 Middle Wall Colum 8 0.40 30 1.68 19.91
8 0.40 30 0.87 10.31
B Outlet get 1029.91
Flushing Chanal
1 Distribution Bar 10 0.616 26 2.1 33.63
2 Main Bar
16 1.58 30 9.24 437.98

3 Distribution Bar 16 1.58 32 6.8 343.81


4 Main bar Type 6 12 0.89 18 4.197 67.15
5 Middle Wall Bar Type -5 12 0.89 40 4.144 147.34

Desender Rebar installed


SN Description Ø of bar (mmUnit Wt.(Kg No. of Bar Total Length Quantity (KgRemarks
Desender Left and Right Wall

5 Cap U -Type 12 0.889 188 1.44 240.67 Middle Shear wall


6 Distribution Bar p p- p"p" 10 0.616 34 32.5 680.68 Middle Shear wall
7 Distribution Bar Slop Start- p"p" 10 0.616 17 11.119 116.44 Middle Shear wall
Total 1037.79
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Debris Cleaning at desender

Item No.3
Manually Descrition of Works Chainage Unit Skills
Debris
Cleaning
Date Debris Clean At Weir Headwork Md 4
6/28/2074 Debris Clean At Weir Headwork Md 4
6/29/2074 Debris Clean At Weir Headwork Md 4
6/30/2074 Debris Clean At Weir Headwork Md 4
6/31/2074 16
Total
Descrition of Works Chainage Unit Skills
Date Debris Clean At Weir Headwork Md 4
7/1/2074 Debris Clean At Weir Headwork Md 4
7/2/2074 Debris Clean At Weir Headwork Md 4
7/3/2074 Debris Clean At Weir Headwork Md 4
7/4/2074 Debris Clean At Weir Headwork Md 4
7/5/2074 Debris Clean At Weir Headwork Md 4
7/6/2074 Debris Clean At Weir Headwork Md 4
7/7/2074 Debris Clean At Weir Headwork Md 4
7/8/2074 Debris Clean At Weir Headwork Md 4
7/9/2074
7/10/2074
7/11/2074
7/12/2074 Debris Clean At Weir Headwork Md 4
7/13/2074 Debris Clean At Weir Headwork Md 4
7/14/2074 Debris Clean At Weir Headwork Md 4
7/15/2074 Debris Clean At Weir Headwork Md
7/16/2074 Debris Clean At Weir Headwork Md
7/17/2074 Debris Clean At Weir Headwork Md
7/18/2074 Debris Clean At Weir Headwork Md
7/19/2074 Debris Clean At Weir Headwork Md 4
7/20/2074 Debris Clean At Weir Headwork Md 4
7/21/2074 Debris Clean At Weir Headwork Md 4
7/22/2074
7/23/2074
7/24/2074 Debris Clean At Weir Headwork Md
7/25/2074 Debris Clean At Weir Headwork Md
7/26/2074 Debris Clean At Weir
7/27/2074 Debris Clean At Weir Headwork Md
7/28/2074 Debris Clean At Desender Desender Md
7/28/2074 Debris Clean At Weir Headwork Md
7/29/2074 Debris Clean At Desender Desender Md
7/29/2074 Debris Clean At Weir Headwork Md
7/30/2074 Debris Clean At Desender Desender Md
7/30/2074
60
Total

Descrition of Works Chainage Unit Skills


Date Debris Clean At Desender Desender Md
8/1/2074 Debris Clean At Desender Desender Md
8/2/2074 Debris Clean At Desender Desender Md
8/3/2074 Debris Clean At Desender Desender Md
8/4/2074 Debris Clean At Desender Desender Md
8/5/2074 Debris Clean At Desender Desender Md
8/5/2074 Debris Clean At Desender Desender Md
8/6/2074 Debris Clean At Desender Desender Md
8/7/2074 Debris Clean At Desender Desender Md
8/8/2074 Debris Clean At Desender Desender Md
8/9/2074 Debris Clean At Intake Headwork Md
8/9/2074
Total
Total Labou 691

Unskills Total Labour Remark

19 23
19 23
19 23
19 23
76 92

Unskills Total Labour Remark


19 23
19 23
19 23
19 23
19 23
19 23
19 23
19 23
19 23

19 23
19 23
19 23

19 23
19 23
19 23

10 10
8 8
13
19 19
20 20
19 19
20 20
22 22
10 10

426 473

Unskills Total Labour Remark


29 29
14 14
25 25
10 10
8 8
6 6
12 12
10 10
5 5
2 2
5 5

126
Details of Measurement
Contractor: Pro Solutions Pvt. Ltd.

Additional Works:
S.No. Descrition of Works Unit Quantity Rate Amount Remarks

1 Landslide clearing and track cleaning along Hr 10 6500 65,000.00


staff quarter to Budhikhola by Excavator

2 Track cleaning along Budhikhola to Forebay by Hr 5 6500 32,500.00


Excavator
3 Landslide Clearing,track cleaning etc by Back Hr 10 2400 24,000.00
Hoe loader (JCB) at Head work Access Road
121,500.00
Details of Measurement for Additional Works
Contractor: Pro Solutions Pvt. Ltd.

Item No: 7 Landslide clearing and track cleaning along staff quarter to Budhikhola by Excavator
S.No. Descrition of Works In hour Remark
1 Earthwork Excavation in Boulder Mix Soil 10

Item No.8 Track cleaning along Budhikhola to Forebay by Excavator


S.No. Descrition of Works In Hour Remarks
Track cleaning along Budhikhola to Forebay by
1 Excavator 5

Item No.9 Landslide Clearing,track cleaning etc by JCB at Head work Access Road
S.No. Descrition of Works In Hour Remarks
Landslide Clearing,track cleaning etc by JCB at
1 Head work Access Road 10

You might also like