Professional Documents
Culture Documents
Construction
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
Chapter 14 UK tunnels: geotechnical monitoring and
encountered conditions
UK Km 10 , 15 20 , , 2 5 30 , 35 , , , , 40 , , , , 45 , 50- 55 60
Fr«nctiPK I 45 40 35 ' 30 ' 25 20 15 10 ' 5 0 ' ' I
- 200 1
' ' ' ' 1
' 1
' ' ' ' ' ' ' ' ' ' ' ' ' ' 1
' ' ' ' ' 1 1 1
' ' ' ' ' ' ' 1 ' ' • ' ' >—< ' ' >-L
GEOLOGICAL SECTION
219
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
proved suitable for rapid excavation by machine during the 14.2 TBM tunnels
1974-75 works. To meet the very high sustained rates of progress required
The evidence suggested that the optimum tunnelling by the programme, the TBMs had to be of a type which
horizon would be within the unweathered Chalk Marl would allow the erection of the linings to proceed concur
some 5-15 m above the base of the Glauconitic Marl. In rently with face excavation. This called for a telescopic
the UK sector, the tunnels would be kept at least 10 m TBM, in which the front body contained the excavating
below the base of weathering, as identified from the bore cutterhead and the rear body contained the grippers. The
holes and at least 18 m below the sea-bed or base of front body had to be capable of being pushed forward 1.5
superficial deposits (Fig. 14.1). m, using the gripper unit as a reaction point, while a 1.5 m
long ring was being built concurrently at the rear of the
TBM, about 13 m behind the face. The service tunnel and
14.1.3 Project programme
running tunnel machines were designed to achieve ring-
The project programme called for all bored tunnelling to
l build cycle times of 18 and 22.5 minutes respectively.
be carried out in a 3 /z year period, between December
These times were achieved in practice.
1987 and June 1991. This requirement dictated the need
for six TBMs capable of rates of advance of 5 m per hour On the UK side, six TBMs (Figs 14.2, 14.3 and 14.4)
for the service tunnels and 4 m per hour for the running were employed to drive a total distance of 84 km. All six
tunnels. The programme also demanded an early start-up TBMs were erected and launched from erection chambers
of the TBM drives which in turn led to the adoption of the in the underground marshalling area at Shakespeare Cliff.
fast-track construction of the Shakespeare Underground Three TBMs were driven seawards initially on a downhill
Development. This was carried out by roadheaders apply grade and three landwards on a uphill grade emerging at
ing the New Austrian Tunnelling Method (NATM) and Sugarloaf Hill some 8 km further west of Shakespeare
primary shotcrete lining; the secondary lining being de Cliff. The combined weight of the six machines was 6500
layed until completion of tunnelling and removal of asso tonnes and the total value including necessary spares was
ciated construction plant and equipment. £60 million.
On this basis, it was decided that the most suitable The back-up equipment on sledges behind the TBMs was
tunnelling system would be an open, full-face TBM, used typically 200 m long and contained segment handling and
in conjunction with unbolted, expanded precast concrete erection equipment and muck disposal conveyors, together
with electro hydraulic power packs, ventilation equipment,
linings.
drainage and water supply and a complex electric power
supply system.
14.1.4 Excavation of cross-tunnels and From the TBM cab, the operator controlled the excava
pumping stations tion and alignment of the TBM using a ZED 260 laser
With a compressive strength of approximately 7 MN/m , 2
guidance system. The cab was equipped with CCTV moni
the Chalk Marl is hard to dig by hand (London Clay has a tors that showed the conveyor operations, and with VDU's
2
strength of about 0-2 MN/m ). For this reason a number that displayed the operational status of the TBM. Loading
of experiments were carried out which involved cutting the of the survey information into the inboard computer could
Chalk Marl with small track-mounted roadheaders. None be made by way of a remote station further back of the
of these proved successful and hence all cross-tunnels TBM sledges.
(crosspassages, piston relief ducts etc.) were generally
hand dug by the miners using pneumatic spades. For the 14.2.1 Spoil handling
complex undersea pumping stations NATM was em The spoil handling was to be carried out by conveyors that
ployed to excavate the shafts and intersection chambers. loaded the Chalk Marl from the cutting head into 14 m 3
The crosspassages, which housed temporary substa side tipping skips. These tipped into a bunker storage
tions and stage pumping stations, were constructed from system at the Shakespeare marshalling area, which then
the service tunnel to within 2 m of the running tunnels. delivered the material by means of a conveyor to the
The construction of these advanced with the tunnel surface. Here it was carried by a conveyor system to the
drive, lagging some 2-3 km behind the advancing face of landfill lagoons behind the new sea wall (see Chapter 12).
the TBM. The remaining cross-tunnels were constructed
much later to minimise disruption to the logistics support
ing the drive. In total, on the UK side there were 245 14.2.2 Tunnel linings
crosspassages and 106 piston relief ducts, involving 42000 Geotechnical studies had suggested that the expanded
3
m of excavation. lining would be suitable for some 95% of the drives. The
method of expansion chosen was the use of a wedge-
shaped key, supplied in three different sizes to cater for
14.1.5 Working environment variations in cut diameter (Fig. 14.5). Each segment had to
Evidence of a safe working environment in the tunnels and have four 20 mm thick pads on its back to provide initial
at the work faces, was provided by a comprehensive ar contact with the excavated profile, leaving a 20 mm void
rangement of remote sensors, connected by means of a after expansion of the ring. The annular void was then
telemetry system to the Control Centre located above filled with grout to provide full contact with the ground.
ground at Shakespeare Cliff. These monitored the air tem This enabled the lining, which was not designed to be
perature and humidity, in addition to the concentrations of watertight, to control the water ingress to manageable
oxygen, hydrogen, carbon monoxide, methane and oxides amounts.
of nitrogen in the air. Alarms were set at levels which were An initial provision of 5% of the total drive length was
designed to allow corrective action to be taken to prevent made for areas of potential faulted and broken ground.
a situation (e.g. a fire) developing where personnel and the Conventional bolted and gasketed spheroidal graphite cast
tunnels would be put at risk. iron linings were provided for these areas.
220
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
seal
13-15 m
221
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
222
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
14.3 Geotechnical monitoring of tunnel (c) ground treatment of fractured rock and/or zones of
high water inflow to locally improve its mechanical
drives properties and reduce its permeability.
14.3.1 General
Despite the extent of the previous site investigation, this Due to the increased risk (e.g. use of open-face TBMs,
still resulted in boreholes being located at only about 1 km excavation of large caverns by NATM), 30 geologists were
223
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
TBM performance
224
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
1986 1987
Marine Service T u n n e l 4 J a n . 88
Marine R u n n i n g T u n n e l N o r t h
Marine R u n n i n g T u n n e l South
L a n d Service T u n n e l
Land Running T u n n e l N o r t h
L a n d R u n n i n g T u n n e l South
225
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
employed on the UK side compared with six geologists on The TBMs were specified, however, to be capable of
the French side. In total, 3468 geological logs of the UK withstanding inundations arising from encounters with
TBM drives were made (equivalent to one report per unsealed boreholes or open fissure within the TBM face,
190 m of drive length). On each side of the Channel one or inundation caused by passing close to an unsealed
geologist was specifically trained in micropalaeontology, borehole; which could burst into the excavation at the tail
enabling rapid assessment of the encountered versus pre of the TBM before the lining was placed. All marine TBMs
dicted stratigraphy to be made. had the capability of shutting off the face by retracting the
spoil conveyor and closing a door which was controlled by
14.3.2 Exploratory probing the TBM driver pressing an inundation button. The annular
In early 1988, a specific study was made of the risk of gap around the outside of the TBM could also be closed
inundation and of the requirements for probing. In parallel off by applying enhanced pressures to the grippers with the
with this study, trials were carried out to prove both the whole activity being completed within 15 to 20 seconds.
capability of drilling equipment, the results obtainable In the event of an inrush of water at the rear, pumps capable
from various down-the-hole logging tools, and the poten of handling up to 900 litres/minute would be started and
tial of seismic tomography. an evacuation alarm sounded.
The study identified six possible sources of geological Forms of probing carried out during progress of the
hazards which could be located and/or investigated by service tunnel drives included:
probing, namely: (a) advance probing ahead of the TBM face
(a) Water-bearing fissures (b) vertical downwards probing
It was recognized that undetected water-bearing fis
sures could be encountered in the hand-mined sec (c) sideways probing behind the TBM drive.
tions, as well as in the TBM drives. However, the This exploratory probing (Figs 14.7 and 14.10) proved
greatest risk of sudden inundation was in the TBM to be one of the major successes of the project with the total
drives. length drilled on the UK side almost equalling the distance
(b) Site investigation boreholes across the Channel.
Numerous boreholes had been drilled in the Channel
over a period of many years, and the locations of the 14.3.2.1 Advance probing ahead of the T B M face
early ones were not precisely known. The study Extensive forward probing was carried out ahead of the
showed that five boreholes, drilled and grouted in tunnel face to check the geology and locate areas of fault
1972-73, were within 70 m of a running tunnel, the ing and broken ground and/or zones of high water ingress.
closest being 26 m although the locations of these The probing system consisted of two Diamec 260 drilling
holes was known only to within ±10 m. rigs located at the front of the TBM which were folded
away under the conveyor head assembly during mining
(c) Areas of deep weathering operations. The conveyor was withdrawn from the TBM
Several boreholes had indicated greater depths of face cone to give access to the face for the probing opera
weathering, with the strata above the Chalk Marl tion. Strict isolation procedures were enforced before any
being more prone to weathering. Of particular concern entry into the head. Drilling rods were made of aluminium,
was potential weathering associated with the Fosse to allow, if necessary, for safe abandonment ahead of the
Dangeard (see below). TBM face.
(d) Proximity to the Grey Chalk All probes were normally 56 mm in diameter and gener
The Grey Chalk above the Chalk Marl; due to its ally 120-200 m in length (max. 260 m), and were destruc
increased calcium carbonate content, was generally tively bored. Drilling parameters monitored on a regular
stronger, more brittle and jointed and hence more basis included water outflow and salinity, the penetration
permeable than the Chalk Marl. rate and the nature of the drilling returns with any anoma
lies being noted. When the probe entered the Glauconitic
(e) Proximity to the Gault Clay Marl, as evidenced by a change in colour of the drilling
The Gault Clay, an overconsolidated mudrock, is returns from light grey to dark green, the probing was
prone to swelling and instability. Therefore it was to terminated.
be avoided if possible. This concern was more related Although automatic recorders were initially used to
to the stability of the excavation rather than to inun measure the thrust, torque, water inflow/outflow and pene
dation. tration rates, electrical/mechanical problems associated
(f) Proximity to the Fosse Dangeard palaeovalley system with these devices led to excessive stoppages and down
The Fosse Dangeard is an ancient offshore valley time and hence they were replaced by more conventional
system extending down to 80 m below seabed, and methods (measurement by stopwatch and bucket). Such
located 500 m south of the tunnel between chainage methods were not only more reliable but sometimes pro
kms 38 and 42. The valley is infilled with silts and vided better quality information e.g. water outflow, where
sandy clays. A 10 m deep subsidiary channel, extend the automatic recorders became insensitive to the minor
ing off the main palaeovalley system, crosses the route flows experienced.
at chainage km 39. This was considered to warrant Samples of rock cuttings obtained by sieving the drilling
very close examination, and much use was made of returns (Fig. 14.8) were sent up to surface for on-site
knowledge of the geology acquired during the ad microfossil analysis (Chapter 26). This enabled both the
vance of the service tunnel. stratigraphic level of the tunnel and the likely path of the
probe to be determined, the latter being verified on occa
The study concluded that the risk of inundation was very sion by the use of downhole survey methods and face
small, provided that adequate probing was carried out. mapping.
226
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
1 ^ 0 1 2 3 4 5m
SCALE
In the Marine Service Tunnel advance probing was sys Geological descriptions of these cores were completed in
tematic and continuous as a consequence of the increased the tunnel upon retrieval. The cores were then despatched to
level of risk (i.e. wide spaced boreholes, shallow cover to the surface for detailed core logging, laboratory analysis and
sea-bed, early downhill gradient). detailed microfossil examination. This enabled comparison
Over the low cover section (i.e. less than 30 m cover), of the actual geology to that predicted on the basis of the
dual 100-140 m long probes inclined upwards and out borehole and geophysical evidence e.g. stratigraphical levels,
wards at a gentle angle (usually 2-4°) were employed. calcimetry etc. Drilling was carried out during the same shift
Drilling also took place through a standpipe to enable the as a forward probe so as to minimise TBM downtime.
hole to be shut off if any large quantities of water were Downward probing was more frequent in the Marine
encountered. However, with increasing cover and confi Service Tunnel with the 22 km of undersea drive being
dence, supported by data provided by the drive, this was covered by some 48 holes spaced at intervals ranging from
substituted by a single 200-240 m long hole drilled ahead 200-600 m. Figure 14.9 indicates the Channel-wide accu
of the face. This enabled the entire weekly production to racy of the geophysical prediction in relation to the en
be covered by one probe, taking 8 hours to complete (4 countered geology. Tunnel realignments were carried out
hours setup time, 4 hours drilling time). In all, downtime on the UK side seawards of chainage km 21.8 (realignment
associated with probing accounted for 7% lost production 1) when the Glauconitic Marl was found to be 8 m lower
time. As essential TBM maintenance was carried out on than predicted and again beyond km 36 (realignment 2)
the probing shifts this figure was, in practice, even smaller. when the boundary was found to be 6-7 m higher than
Results from the probing are shown in Fig. 14.15. predicted. In the former case, the discrepancy occurred at
The Land Service Tunnel was driven uphill and thus the boundary between the inshore and offshore geophysi
advance probing was limited to those areas where prob cal surveys and incorrect velocity assumptions probably
lems were anticipated e.g. anticipated zones of faulting account for the anomaly. In the latter case, the large
such as the Lydden Fault. Regular face inspection was, difference is probably attributable to the absence of any
however, undertaken with the knowledge that any major control boreholes in the area. The discrepancies on the UK
inflow of water would run back down the tunnel from the side exacerbated the tunnelling problems at both locations;
face and could be pumped out from the Shakespeare Un at the former location the tunnel crown lay much closer to
derground Development. the Grey Chalk (a more jointed and permeable strata),
while at the later location Glauconitic Marl was encoun
14.3.2.2 Vertical d o w n w a r d p r o b i n g tered in the face which resulted in spalling of the sidewalls
These probes were drilled in the build area some 16m back and excessive pick wear.
from the TBM face. These provided 35 mm diameter cores In the Land Service Tunnel little or no downward probing
down through the Chalk Marl and Glauconitic Marl into was undertaken as a consequence of the greater accuracy
the underlying Gault Clay (including Bed 6a). of prediction associated with the more closely spaced site
227
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
350
300
250
200
150
100
50
Negligible 0.0661/min/m 0.0251/min/m Negl igible
0
i i i i 30
i i i i i i i i i i 60
i i i i i i i i i i 90
i i i i i i i i i i i i i i i i i i i i i i i i i i i i i i180
iiiiiiitiiiiiiiiiiii i
120 150 210 240
Distance (m from face) Left Hand Probe
•j m •
5 5 H B P * < T F T M
Figure 14.8 Advance probing. Top: typical plot of advance probe showing penetration rate, water outflow and cutting
returns; bottom: sampling cutting returns from advance probing.
228
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK T U N N E L S : G E O T E C H N I C A L MONITORING
D i f f e r e n c e a c t u a l to p r e d i c t e d d e p t h (m)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
- 1 0 —
19 21 2 3 2 5 27 29 31 3 3 3 5 37 39 41 4 3 4 5 47 49 51 5 3 55 57
chainage km
ing downtime associated with this activity. A typical geo some 16 m back from the face, may have been influenced
logical record is presented in Fig. 14.12. by the nature of the tunnelling operations (e.g. action of
Basic parameters recorded included: TBM grippers against tunnel sidewalls opening up joints
and increasing potential for major overbreak) and time
(a) rock type, strength and weathered state (e.g. greater degree of overbreak during mainte
(b) discontinuity details; including the nature and orien nance/probing shift when TBM standing). These factors
tation of bedding, jointing and faulting e.g. number of had to be considered during subsequent analysis of this
joint sets, spacing and persistence of joints and bed data.
ding planes, throw/mineralisation of faults etc. Better quality data was normally provided by logging of
either the cross-tunnels (i.e. crosspassages, piston relief
(c) estimate of water inflow entering the face or build ducts and pumping stations) which were excavated by the
area. Estimates of water inflow entering the build area miners using pneumatic spades, or the NATM excavations
inevitably on occasion included water emanating such as the UK Crossover. Greater emphasis with more
from behind the previously built rings regular inspection was placed on those areas of increased
(d) estimate of Rock Mass Quality Q (NGI) based on the risk e.g. Fosse Dangeard.
above observations
(e) nature and volume of overbreak around the tunnel 14.3.4 T h e T M L Channel Tunnel Geological
periphery. Database
A standard database program, DataEase, was used as a data
It should be emphasised that the above observations storage and analysis facility for certain Geological infor
(Fig. 14.13), particularly those made in the build area mation (Figure 14.14). Geological face records, forward
229
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
3.0
probing results, vibrating wire strain gauge data, and the
O
results of micropalaeontology and calcimetry analysis
South
were entered into the database. DataEase was already
2.5 - * North
being used on other parts of the project for staff records,
engineers' shift reports, the drawing office drawing regis
ter etc and it was realised early on in the project that there
* * was a great deal of geological information from the Marine
* Service Tunnel drive that would need analysing prior to
the start of the marine running tunnel drives. It was very
o <p o time consuming trying to leaf through the hundreds of A3
0.5 o * g sized geological logs in order to pick out geological trends
o o
and locations of high water inflows/large overbreak. Using
the database to printout graphs of various geological pa
25 26
22 23 24 rameters enabled the geologists to easily pick out the areas
chainage km of poor ground ahead of the running tunnel TBMs. It also
30 allowed the immediate presentation of the findings as high
O S o u t h (Packer test)
quality graphical plots to construction management. Pro
* N o r t h (Packer test) duction of stereonets from the discontinuity data was used
for stability analysis of the hand excavated tunnels.
20 The relational database was fast and simple to set up. It
had a large storage capacity and could be run on standard
386/486 personal computers of which the TML Geotech
nical Department had three, one of which was dedicated to
the database. Built-in mathematical functions allowed cal
culations to be done by the computer on data that was
entered by the user. The advantage of using a database over
***** a * a spreadsheet program was that the database was designed
* o *
L11H0LOGIC A
OtSCRlPtlON
SAMPLE
4\ OEiCRIPIION ,4 ONA .
PHOTOGRAPH
DESCRIPTION j m .
None tuKc^l
A ICR -IF R
T E
STABILITY . - ~
OVERQREAK a/O o/B , face. <a~d -=>'c/eLj*tf± SL.^K
«°0 /OO 1
JOINTING OE T AILS
3 * SI
SUMMARY WEATHERING GRAOE CHECKED
7
GEOTECHNICAL
w RECORD
230
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
Notes
General V a l u e s i n parentheses represent m a x i m u m observed Water D r y g r o u n d refers t o less than 0.01 l / m i n o n average
values D a m p g r o u n d refers t o range 0 . 0 1 - 0 . 0 2 l / m i n o n average
Seeps refers t o less than 0.05 l / m i n o n average
Tunnel M S T : service
B u i l d water l i k e l y t o i n c l u d e some water e m a n a t i n g f r o m
M R T N : r u n n i n g tunnel n o r t h
ungrouted rings outbye and around T B M shield i n b y e
M R T S : r u n n i n g t u n n e l south
Overbreak Overbreak recorded i n the b u i l d area represents o n l y that N/A N o t applicable because t o o f e w logs available
observed. Observed overbreak reduces once fingers/hood
i n place. Overbreak i n face includes s p a l l i n g f r o m face
mation, thereby saving time and reducing the chance of could be sorted quickly and the results of concern identi
data entry error. fied and checked.
Data could also be imported from and exported to spread Once the geologist returned from underground, the face
sheets (e.g. Lotus 1-2-3, Quattro Pro), graphics programs records were drawn up onto a standard proforma and then
(e.g. Lotus Freelance, Harvard Graphics) and other data checked by the senior geologist and agreed with Eurotun
formats. The vibrating wire strain gauge information from nel. Once checked, the data were entered on to the database
the instrumented parts of the tunnels that was read by a in a form that outwardly mimicked the paper log - a
datalogger was downloaded directly into the database process that took less than a minute per log. Each day, the
where it was analysed and reported from. During this database was automatically edited for data entry mistakes
process there was almost no user interaction involved. and any required analysis was undertaken (producing
Being in a database format, the huge quantities of data stereonets, graphs of water inflow etc).
231
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
One-to-Many Relationship
MAIN FORM SUB-FORM
GEOLOGY JOINT
FIELDS FIF.LDS
TUNNEL
DATE OF LOG
RING NUMBER LOOKUP
T1ME OF LOG ^
LOG TYPE
ROCK TYPE JOINT NUMBER
GEOLOGIST DIP
T U N N E L ORIENTATION DIRECTION
RQD IRREGULARITIES
WATER INFLOW APERTURE
VOLUME OF OVERBREAK
NUMBER OF JOINTS
NUMBER OF JOINT SETS Number of Join! Records
FAULTS per Geological Log
232
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
2
Although a large amount of staff time was taken up in intermittently approaching 3 J/m (Chapter 25), such as in
entering and editing the data the database proved an invalu an area of structural folding adjacent to chainage km 23.
able tool. Its main benefits over manual presentation were: Joints recorded at the tunnel face/sidewalls and in
crosspassages were generally planar, smooth and tight.
(a) The production of high quality data plots and printouts Some degree of openness generally up to 5 mm and occa
that could be presented immediately to senior man sional clay infill, was sometimes recorded along joints.
agement without the need for drafting (many dead Such occurrences were both limited and discontinuous in
lines for internal reports were only met due to this nature, being usually confined to lengths up to 100 mm
facility). along any given joint.
(b) The flexibility it allowed in the interpretation and Major joint sets observed comprised a subhorizontal set
presentation of data. generally associated with bedding, complementary sets
striking subparallel to the tunnel and dipping above 60° to
(c) It produced plots and listings from edited data which the NNE and SSW and a shallow set dipping 10^5° in a
only required the minimum of further editing. general SSW direction (Fig. 25.1). Less prominent sets
were also recorded e.g. dipping 40-70° southeastwards.
14.4 UK marine drives: encountered
tunnelling conditions 14.4.1.3 Faulting
14.4.1 General Evidence of major faulting was not observed although
A summarised description of the ground conditions en several minor local faults and/or slickensided 'shear joints'
countered during progress of the marine drives as related with clay veneer, calcite and pyrite infill were sometimes
to the amount of cover above the tunnel crown and height noted e.g. adjacent chainage km 28 where disturbed and
of tunnel above the Gault Clay/Bed 6a material is illus broken ground was met.
trated on Fig. 14.15.
Information shown includes:
14.4.2 Encountered ground conditions:
(a) results of advance probing in the Marine Service overview
Tunnel 14.4.2.1 Early part of drive to chainage km 2 3 . 4
(b) Marine Service Tunnel: water inflow and overbreak In all three marine tunnels, ground conditions were in
itially favourable, similar to those in the earlier 1974 drive,
(c) Marine Running Tunnel North: water inflow and but quickly deteriorated from about chainage km 20.4 and
overbreak thereafter up to chainage km 23.4. The drive was slowed
by overbreak and by seepage inflow.
(d) measured salinity of the water entering the tunnels and
Jointing was more frequent and sometimes open, associ
flowing out of probe holes
ated with the low cover to sea-bed and zones of structural
(e) measured salinity of the water entering the tunnels and disturbance. This led to downward percolation of seawater
flowing out of probe holes since passage of the face into the tunnel and development of high water pressures in
of the Marine Service Tunnel. the surrounding rock mass. This, together with the adverse
nature of the jointing, gave rise to block fallout around the
Of particular interest is the good correlation between the tunnel periphery.
outflow from the advance probe and the inflows observed In the service tunnel, porewater containing 4000-8000
at the face of the Marine Service Tunnel. Further details of mg/l of chloride were quickly replaced by seawater i.e.
the conditions encountered are given in Table 14.4. 19600 mg/l; the time taken to do so reflecting the local
permeability conditions above the tunnel crown. Where
14.4.1.1 Strata types permeability was high, even the initial salinity was high
The strata met during tunnelling predominantly comprised e.g. face chainage m 20751 where a chloride content of
weak to moderately weak unweathered Chalk Marl, mid 16619 mg/l was measured (Fig. 14.15).
to dark grey in colour and sometimes containing lighter Wedge-type failures of the crown and shoulders were
grey moderately strong sponge beds. commonly observed in the build area, the shape of the
The service tunnel also encountered Glauconitic Marl/Bed blocks being defined by two joint sets i.e. a subhorizontal
6a material between km 26.2 and km 29.1 as it deviated bedding set and a steeply dipping set aligned subparallel
further north and below the level of the UK Crossover; Bed to the tunnel wall (Fig. 14.16).
6a being in the face between km 26.4 and 27.8. 3
Block sizes were typically 0.2-0.5 m but when TBM
Glauconitic Marl was again encountered between chain- progress was slowed, larger volumes of overbreak would
age kms 34.7 and 37, this unit was also present in both 3
occur i.e. up to 2.7 m . This made expansion of the con
running tunnels between chainage kms 33.8 and 36.8, crete rings difficult until trailing steel fingers (and later a
where it remained below axis level. complete thin steel hood) were fitted at the back of the
TBM to restrain blocks from falling (Fig. 14.16) and allow
14.4.1.2 Jointing and rock mass characteristics safe erection of the unbolted ring. The hood successfully
The rock was blocky and jointed with general RQD values contained the broken ground, reduced the overbreak and
above 90%. Information from vertical probes and side prevented unacceptable distortion of the expanded lining.
probes drilled along the length of the drive indicated a Similar hood and finger arrangements were fitted to both
typical joint spacing of 1 to 3 joints per metre for the Chalk running tunnels before this area of unstable ground was trav
Marl. A similar joint spacing was indicated by the site ersed. The historical development of the hood/finger arrange
investigation boreholes. ment in all three marine tunnels is outlined in Table 14.5.
Geological logging of the exposed face and tailskin area The ground conditions described above were further
indicated comparable joint frequencies of 1 to 2 J/m 2
aggravated by the following geological factors:
233
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
80 120
40
30
20 height of tunnel
above Gault/6A
10
0
realignment 1 realignment 2 Ljlu—. . , , , eu. ,
-10
19 21 23 25 27 29 31 33 35 37 39 41 43 19 21 23 25 27 29 31 33 35 37 39 41 43
chainage km chainage km
(a) (b)
Mi > A
19 21 23 25 27 29 31 33 35 37 39 41 43 21 23 25 27 29 31 33 35 37 39 41 43
chainage km chainage km
(c) (d)
120
Marine Running Tunnel North hood installed ch 2 3 3 7 7
100
fingers fitted ch 20772
80
Ground treatment
60
km 22.7 - 23.4
i
21 23 25 27 29 31 33 35 37 39 41 43 21 23 25 27 29 31 33 35 37 39 41 43
chainage km chainage km
(e) (f)
+
—
MRT •ample*
Advance probe
***** o
•
1-3 d a y s
3-100 days
& Sideprobes >100 d a y s
19 21 23 25 27 29 31 33 35 37 39 41 43
22 23
chainage km chainage km
(9) (h)
Figure 14.15 Ground conditions in the undersea tunnels, (a) height (m); (b) inflow into face (l/min), Marine Service
Tunnel; (c) outflow from advance probes (l/min/m); (d) inflow into build area (l/min), Marine Service Tunnel; (e) inflow into
3
build area (l/min), Marine Running Tunnel North; (f) overbreak in build area ( m ) , Marine Service Tunnel; (g) salinity
(mg/l chloride); (h) salinity with time (mg/l chloride).
234
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
Table 14.5 Development of hood and finger arrangement (a) Low Cover Section: chainage km 20.4 to 21.8
in marine tunnels Along the early part of the drive up to chainage km
21.8, the vertical probes indicated the service tunnel
Tunnel Chainage Modification to be generally 3-4 m (up to 8 m) higher as compared
Service 20774 4 fingers installed to the anticipated geology. This resulted in the tunnel
Tunnel 20779 3 fingers installed (total = 7) being entirely located within the higher Chalk Marl
22459 3 fingers removed (total = 4) with its crown lying closer to the overlying Grey
22500 3 fingers replaced (total = 7) Chalk and base of weathering. Consequently more
22512 2 fingers installed (total = 9) permeable and jointed strata was encountered leading
22624 1 finger installed (total = 10) to increased seepage inflow and overbreak.
23311 to 23379 H o o d extended o n north side Immediate improvement was thus sought by steep
23392 to 23454 H o o d extended o n south side ening the tunnel gradient beyond chainage km 21.8 in
order to increase the ground cover and bring the tunnel
Running 19807 H o o d installed profile lower into the more favourable Lower Chalk
Tunnel 20392 Fingers deformed Marl (some 14-15 m thick).
North 20805 Shorter fingers installed Consideration was also given to lowering the marine
22438 Extra fingers added at axis
running tunnel profile below the level of the service
tunnel through the section of difficult ground up to
Running 19748 H o o d installed chainage km 21.8. This was rejected due to problems
Tunnel 19988 Fingers modified associated with construction of the crosspassages and
South piston relief ducts and the effect on the long-term
(a) (c)
Figure 14.16 Overbreak and hood and finger arrangements fitted to TBMs. (a) Typical overbreak observed in build area
of Marine Service Tunnel, (b) Typical overbreak and arrangement of trailing fingers: Marine Service Tunnel, (c) TBM
trailing fingers, (d) Typical overbreak and arrangement of trailing fingers and formers: Marine Running Tunnels.
235
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
14.4.2.2 Chainage k m 23.4 to breakthrough Additional problems also arose due to the presence of a
Beyond chainage km 23.4, up to the end of the service thin layer of compacted remoulded material ('swarf usu
tunnel drive at chainage km 41.6, tunnelling conditions ally 20 mm but up to 60 mm thick in places) representing
were consistently good to very good. Dry conditions or the subsequent degradation of minor overbreak falling
only minor inflows and intermittent overbreak was noted. down and being crushed behind the TBM shield. This
The low salinity of the incoming water, equivalent to the reconstituted material had to be removed by the miners
chemistry of the porewater held in the rocks i.e. using hand pneumatic spades as it emerged from behind
236
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
237
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
Sugarloaf
Portal * Inflow into build O inflow into face
11 12 13 14 15
chainage km
238
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
volume m
4 - ' a-"
SUGARLOAF PORTAL
Crown
TUNNEL DRIVE
Invert
12 13 14 15
Chainage km
Figure 14.21 Land Running Tunnel North: overbreak and face collapse towards the end of the drive.
Figure 14.22 Blocky jointed nature of Gault Clay outcropping in excavations for cut-and-cover section further west of
Sugarloaf portal.
b e c a m e m o r e n o t i c e a b l e c l o s e to the e s c a r p m e n t e d g e . F a c e c o l l a p s e a l s o b e c a m e a r e g u l a r o c c u r r e n c e as m i n o r
F i n g e r s / h o o d a r r a n g e m e n t s installed at the start o f the i n f l o w s o f w a t e r lubricated ' g r e a s y b a c k s ' w i t h i n t h e G a u l t
d r i v e s h a d to restrain b l o c k f a l l o u t i n b o t h s e r v i c e t u n n e l 3
C l a y . T h i s , i n t u r n , g e n e r a t e d l a r g e 0.4 m s i z e d b o u l d e r s
( G a u l t C l a y / G l a u c o n i t i c M a r l ) a n d r u n n i n g tunnels ( g e n o f g l a u c o n i t i c s a n d s t o n e w h i c h c o n s e q u e n t l y b l o c k e d the
erally Glauconitic M a r l / C h a l k Marl). T y p i c a l overbreak h e a d a n d c o n v e y o r s y s t e m a n d h a d to b e h a n d b r o k e n b y
patterns i n relation to the g e o l o g y a r e illustrated o n F i g . miners using pneumatic tools. T h e p r o b l e m s w e r e m o r e
14.23. a d v e r s e w h e r e the G a u l t l a y a b o v e a x i s l e v e l .
239
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
tunnel crown i.e. 6 m. were low i.e. less than 1 Lugeon (approx. 10~ m/s).
On the day shift of 3/11/89, at chainage m 11155, close On the basis of this information and taking account of the
to the breakout following the building of 4 No. cast iron difficulties experienced in the service tunnel, even with
rings, it was found that the TBM head would not turn. A minor amounts of water, a decision was taken to employ
collapse of Gault Clay had occurred at the face and as the ground treatment over the last 0.7 km of each running
head was pulled back to remove this material, the roof of tunnel drive. Holes were thus drilled from the adjacent
Gault Clay with Glauconitic Marl immediately above it service tunnel in advance of the running tunnels and ce
continued to fall in. ment grouted using controlled pressures up to 18 bar (the
The first ring built on that shift i.e. Ring 5237 had to be maximum overburden pressure) and claquage techniques
taken down in order that the TBM could back off from the so as to penetrate the fine fissures (see Chapter 16).
face. The process of pushing and pulling the TBM back The ground conditions encountered in the south running
ward and forward permitted further overbreak in the build tunnel were similar to those met in the north tunnel, albeit
area above Ring 5238. The head was eventually cleared slightly improved towards the Sugarloaf breakout as a
and pushed forward. Approximately 1-2 m of overbreak 3
consequence of the increased ground cover and less weath
was dug out of the invert and Ring 5238 completed on the ered and fractured state of the rock.
backshift.
Although the head could turn, the hoppers again became
blocked with the spoil and the TBM was unable to cut. 14.6 Review of encountered geology and
During the back and nightshift this was cleared and the tunnelling conditions
head was able to cut and two Rings were built i.e. Rings Of particular interest is the extent to which the encountered
5239 and 5240. During the cut two trainloads of skips were geology and tunnelling conditions were as predicted. The
required for one metre of face advance. Following an subject is further discussed in Chapters 29, 31 and 32.
240
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
241
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION
3
Tunnel section Geological provenance Overbreak/face failures (m ) Water (l/min)
3
C h 13800-12800 M i x e d face o f Chalk A v e . 0.06 m (36 A v e . 0.01 m 3
Actual Actual
M a r l ; Glauconitic M a r l records) (2 records) D r y (36 records) D r y (19 records)
and Gault; anticlinal Max. Actual Max.
fold; fresh rock; high 0.11 m C h 3
13016 3
0.02 m C h 13328 0.1 l/min C h 15903
cover 0.1 m C h 3
13017 N i l C h 13715
3
0.1m Ch 13031
3
0.1 m C h 13032
3
0.3 m C h 13196
3
0.22 m C h 13232
3
0.3 m C h 13243
3
0.12 m C h 13327
-3
C h 12800-12200 M i x e d face o f Chalk A v e . 0.05 m (11 N o records A v e . < 0.01 l/min N o records
M a r l and Glauconitic records) (11 records)
M a r l ; fresh rock; high Max. Max.
cover 3
0.03 m C h 12207, 0.1 l/min C h 12205
12408, 12705 0.01 l/min C h 12707
3
0.05 m C h 12360
3
0.06 m C h 12661 (elsewhere = dry)
3
0.2 m C h 12662
3
0.05 m C h 12707
3
C h 12200-11500 M i x e d face o f Chalk A v e . 0.31 m (54 A v e . 0.23 m 3
A v e . < 0.02 l/min A v e . 0.31 l/min
M a r l ; Glauconitic M a r l records) (5 records) (54 records) (5 records)
and Gault; fresh rock; Max. Actual Max. Actual
3
close to escarpment 0.84 m C h 11578 3
> 3 . 0 m C h 11552 0.2 l/min C h 11501 D r y C h 11552
3
edge; high cover 0.73 m C h 11681 3
0.84 m C h 11609 0.3 l/min C h 11548 0.02 l/min C h 11609
3
1.4 m C h 11682 3
2.0 m C h 11624 0.1 l/min C h 11578 0.511/rninCh 11624
3
0.82 m C h 11702 3
0.22 m C h 11696 0.5 l/min C h 11811 1 l/min C h 11696
3
0.75 m C h 11705 3
0.08 m C h 12055 0.04 l/min C h 12010 0.03 l/min C h 12055
3
1.0 m C h 11717 (elsewhere < 0.04
3
0.8 m C h 11765 l/min)
3
C h 11500-11167 M i x e d face o f Chalk A v e . 0.29 m Actual A v e . 0.09 l/min Actual
M a r l ; Glauconitic M a r l (23 records) 0.02 m C h 11296 (23 records) 3
0.1 l/min C h 11296
and Gault; weathered Max. Max.
rock; shallow cover 1.0-1.5 m 3
0.2 l/min C h 11192
C h 11191 0.5 l/min C h 11218
3
0.6 m C h 11212 0.02 l/min C h 11228
3
0.35 m C h 11228 0.02 l/min C h 11289
3
0.40 m C h 11403 0.5 l/min C h 11269
3
0.4 m C h 11409 0.1 l/min C h 11271
242
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING
enced by the pre-existing groundwater chemistry and the largely depends on one's viewpoint with regard to prece
permeability profile to sea-bed. In areas of high permeabil dent experience (e.g. 1974-75 experience at Shakespeare
ity (e.g. the shallow cover section) the change was very Cliff and Sangatte etc.).
rapid (i.e. within less than a day) as compared to the low Despite all of the problems encountered it is a credit to
8
permeability areas <10~ m/s where the change could take the miners and the ingenuity of contractors and designers
several years. alike in overcoming the many difficulties encountered in
Regarding the prediction of overbreak, including its ex the tunnelling works thereby enabling the drives to be
tent, this was a more difficult problem to address as it completed on schedule.
243
Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.