You are on page 1of 26

Part 3

Construction

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
Chapter 14 UK tunnels: geotechnical monitoring and
encountered conditions

C. D. Warren, P. M. Varley and R. Parkin

14.1 UK tunnelling system 14.1.2 Anticipated geology


14.1.1 General Site investigations have been carried out across the Chan­
A major element of the UK underground construction nel since 1875. Well over 100 boreholes have been sunk
works was the requirement for 84 km of tunnels to be and various geophysical surveys undertaken including the
constructed by tunnel boring machines (TBMs). The over­ most recent in 1986-87 and 1988-89. All the available
all arrangement called for the boring of two 8.2 m (outside data indicated that the tunnelling could be confined mainly
diameter) running tunnels spaced 30 m apart and a 5.2 m to the Chalk Marl on the UK side, where the geological
diameter service tunnel located centrally between them structure was relatively simple with no major fault dis­
(Fig. 14.1), 3.3 m diameter crosspassages connecting all placements. The largest faults and greater degree of secon­
three tunnels at intervals of 375 m throughout the drive and dary folding was found to occur on the French side, where
2 m diameter piston relief ducts passing between the they were aligned parallel to the axis of the main Quenocs
running tunnels every 250 m had also to be excavated Anticline e.g. major faults at chainage km 47 (8-10 m
(Chapman etal, 1992). downthrow south) and 49.6 (3-5 m downthrow north).
As far back as the 1880s, when the Beaumont-English The Chalk Marl is a clayey carbonate mudstone some
tunnel boring machine was used for the first Channel 25-30 m thick, found in layers which can range from
Tunnel attempt, it was believed by engineers that a tunnel moderately strong carbonate beds to a weak clay-rich
boring machine was the most economic solution. In the material. It is essentially impermeable with any water
1980s, the same was true but the choice had narrowed to restricted to discontinuities, such as faults or fissures, and
that between different types of TBM; a choice governed can be considered an excellent tunnelling medium, as it is
by two main factors: the anticipated geology and the both easy to excavate and possesses sufficient strength to
project programme. stand with minimal support. The Chalk Marl had also

UK Castle Hill Portal Service tunnel

I Shakespeare Cliff TYPICAL SECTIONS

UK Km 10 , 15 20 , , 2 5 30 , 35 , , , , 40 , , , , 45 , 50- 55 60
Fr«nctiPK I 45 40 35 ' 30 ' 25 20 15 10 ' 5 0 ' ' I
- 200 1
' ' ' ' 1
' 1
' ' ' ' ' ' ' ' ' ' ' ' ' ' 1
' ' ' ' ' 1 1 1
' ' ' ' ' ' ' 1 ' ' • ' ' >—< ' ' >-L
GEOLOGICAL SECTION

Figure 14.1 Geological section and tunnel alignment (as built).

219

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

proved suitable for rapid excavation by machine during the 14.2 TBM tunnels
1974-75 works. To meet the very high sustained rates of progress required
The evidence suggested that the optimum tunnelling by the programme, the TBMs had to be of a type which
horizon would be within the unweathered Chalk Marl would allow the erection of the linings to proceed concur­
some 5-15 m above the base of the Glauconitic Marl. In rently with face excavation. This called for a telescopic
the UK sector, the tunnels would be kept at least 10 m TBM, in which the front body contained the excavating
below the base of weathering, as identified from the bore­ cutterhead and the rear body contained the grippers. The
holes and at least 18 m below the sea-bed or base of front body had to be capable of being pushed forward 1.5
superficial deposits (Fig. 14.1). m, using the gripper unit as a reaction point, while a 1.5 m
long ring was being built concurrently at the rear of the
TBM, about 13 m behind the face. The service tunnel and
14.1.3 Project programme
running tunnel machines were designed to achieve ring-
The project programme called for all bored tunnelling to
l build cycle times of 18 and 22.5 minutes respectively.
be carried out in a 3 /z year period, between December
These times were achieved in practice.
1987 and June 1991. This requirement dictated the need
for six TBMs capable of rates of advance of 5 m per hour On the UK side, six TBMs (Figs 14.2, 14.3 and 14.4)
for the service tunnels and 4 m per hour for the running were employed to drive a total distance of 84 km. All six
tunnels. The programme also demanded an early start-up TBMs were erected and launched from erection chambers
of the TBM drives which in turn led to the adoption of the in the underground marshalling area at Shakespeare Cliff.
fast-track construction of the Shakespeare Underground Three TBMs were driven seawards initially on a downhill
Development. This was carried out by roadheaders apply­ grade and three landwards on a uphill grade emerging at
ing the New Austrian Tunnelling Method (NATM) and Sugarloaf Hill some 8 km further west of Shakespeare
primary shotcrete lining; the secondary lining being de­ Cliff. The combined weight of the six machines was 6500
layed until completion of tunnelling and removal of asso­ tonnes and the total value including necessary spares was
ciated construction plant and equipment. £60 million.
On this basis, it was decided that the most suitable The back-up equipment on sledges behind the TBMs was
tunnelling system would be an open, full-face TBM, used typically 200 m long and contained segment handling and
in conjunction with unbolted, expanded precast concrete erection equipment and muck disposal conveyors, together
with electro hydraulic power packs, ventilation equipment,
linings.
drainage and water supply and a complex electric power
supply system.
14.1.4 Excavation of cross-tunnels and From the TBM cab, the operator controlled the excava­
pumping stations tion and alignment of the TBM using a ZED 260 laser
With a compressive strength of approximately 7 MN/m , 2
guidance system. The cab was equipped with CCTV moni­
the Chalk Marl is hard to dig by hand (London Clay has a tors that showed the conveyor operations, and with VDU's
2
strength of about 0-2 MN/m ). For this reason a number that displayed the operational status of the TBM. Loading
of experiments were carried out which involved cutting the of the survey information into the inboard computer could
Chalk Marl with small track-mounted roadheaders. None be made by way of a remote station further back of the
of these proved successful and hence all cross-tunnels TBM sledges.
(crosspassages, piston relief ducts etc.) were generally
hand dug by the miners using pneumatic spades. For the 14.2.1 Spoil handling
complex undersea pumping stations NATM was em­ The spoil handling was to be carried out by conveyors that
ployed to excavate the shafts and intersection chambers. loaded the Chalk Marl from the cutting head into 14 m 3

The crosspassages, which housed temporary substa­ side tipping skips. These tipped into a bunker storage
tions and stage pumping stations, were constructed from system at the Shakespeare marshalling area, which then
the service tunnel to within 2 m of the running tunnels. delivered the material by means of a conveyor to the
The construction of these advanced with the tunnel surface. Here it was carried by a conveyor system to the
drive, lagging some 2-3 km behind the advancing face of landfill lagoons behind the new sea wall (see Chapter 12).
the TBM. The remaining cross-tunnels were constructed
much later to minimise disruption to the logistics support­
ing the drive. In total, on the UK side there were 245 14.2.2 Tunnel linings
crosspassages and 106 piston relief ducts, involving 42000 Geotechnical studies had suggested that the expanded
3
m of excavation. lining would be suitable for some 95% of the drives. The
method of expansion chosen was the use of a wedge-
shaped key, supplied in three different sizes to cater for
14.1.5 Working environment variations in cut diameter (Fig. 14.5). Each segment had to
Evidence of a safe working environment in the tunnels and have four 20 mm thick pads on its back to provide initial
at the work faces, was provided by a comprehensive ar­ contact with the excavated profile, leaving a 20 mm void
rangement of remote sensors, connected by means of a after expansion of the ring. The annular void was then
telemetry system to the Control Centre located above filled with grout to provide full contact with the ground.
ground at Shakespeare Cliff. These monitored the air tem­ This enabled the lining, which was not designed to be
perature and humidity, in addition to the concentrations of watertight, to control the water ingress to manageable
oxygen, hydrogen, carbon monoxide, methane and oxides amounts.
of nitrogen in the air. Alarms were set at levels which were An initial provision of 5% of the total drive length was
designed to allow corrective action to be taken to prevent made for areas of potential faulted and broken ground.
a situation (e.g. a fire) developing where personnel and the Conventional bolted and gasketed spheroidal graphite cast
tunnels would be put at risk. iron linings were provided for these areas.

220

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

seal
13-15 m

Figure 14.2 Howden Marine Service Tunnel TBM.

Figure 14.3 Robbins-Markham Marine Running Tunnel TBM.

F o l l o w i n g e a r l y e x p e r i e n c e w i t h the s e r v i c e tunnel l i n ­ 14.2.3 Grouting


i n g s , a h y b r i d l i n i n g o f precast c o n c r e t e a n d s p h e r o i d a l G r o u t i n g m e t h o d s e m p l o y e d o n the d r i v e s w e r e b o t h tra­
graphite cast i r o n s e g m e n t s w a s d e s i g n e d , to a l l o w the ditional (using pan-type paddle mixers and Craelius
rapid c o n s t r u c t i o n o f o p e n i n g s f o r crosspassages, piston p u m p s ) a n d m o r e m o d e r n (e.g. a c o n t i n u o u s s y s t e m using
relief ducts a n d p u m p i n g stations. a S c h w i n g m i x e r and p u m p arrangement). Grouts used

221

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

Figure 14.4 Howden Land Running Tunnel TBM.

Figure 14.5 Expanded concrete wedge-block lining (running tunnel).

222

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

included Pozament GP3 and Ordinary Portland Cement


(OPC), with various other retarding and accelerating agents
being added in order to obtain the necessary properties.
In practice, primary grouting of the rings up to axis level
was completed within 48 m of the build area in the Marine
Service Tunnel (invert and up to axis level being grouted
within 12 m) and within 15 m in the Land Service Tunnel.
In all four running tunnels, primary grouting was nor­
mally complete within 10-18 m of the build area, an upper
grouting platform being employed to gain access to the
crown area. Such platforms close to the build area were
only installed in both marine running tunnels after early
problems had been experienced with water ingress and
overbreak, the original intention having been to carry out
grouting some 80-100 m further back.
Any leaks or areas missed during the primary grouting
were dealt with at the rear of the TBM, from a proof
grouting platform.

14.2.4 TBM drives


The longest of the six drives was the Marine Service Tunnel
at 21.7 km. The two marine running tunnels were 18 and
19 km long, and all the land tunnels were about 8 km long.
The two service tunnel machines at 5.38 m and 5.76 m
outer diameter were both supplied by James Howden of
Glasgow who also supplied both land running tunnel ma­
chines at 8.7 m outer diameter. The two marine running
tunnel machines at 8.36 m outer diameter were supplied I I j ! i i I I I I I I I I | I I i I I I I I I I I I I I I i I M ! I I I | I I I I I I I I
NOiJ F M A M J J A S O N D U F M A M J J A S O N o i j F M A M J J A S O N D J F M A M J J A
by Robbins Markham Joint Venture. i l l !

1988 1989 1990 1991


The Marine Service Tunnel TBM, the first on the project
to be commissioned, began to cut rock on 29 Nov. 1987; Figure 14.6 UK tunnel drives: planned vs. actual
the other five started progressively between August 1988 progress.
and November 1989. At peak, five TBMs were in opera­
tion concurrently between August 1989 and September
1990. Each drive was manned on a three eight-hour shift centres on the UK side and consequently there was still an
basis, seven days per week. Shift changes took place at the element of risk attached to the tunnel drives. This was dealt
TBM. with by using the service tunnel, centrally placed between
In order to sustain the progress, the gangs included a the running tunnels, as a pilot tunnel and probing ahead of
maintenance team; the aim was to keep TBM downtime its face. Thus both Land and Marine Service Tunnel drives
below 10% which was generally achieved. Initial progress were commenced at an early date so as to:
on each of the marine drives was slow as the TBMs (a) establish the geology along the route
encountered wet blocky ground; however this improved as
better ground conditions were met and working methods (b) identify zones of broken ground and/or water-bearing
and equipment were refined. fissures.
Over the final six months of the marine running tunnel
drives, the work forged ahead of programme as rates of The miners, engineers and geologists who worked in the
progress of over 350 m per week were consistently pilot tunnels were therefore the real pioneers, gathering
achieved. New production records were repeatedly estab­ information from the exposed virgin ground and pointing
lished through the period, culminating in an advance of the way for others to follow.
428 m by the Marine Running Tunnel South TBM in the Geological information was derived from the detailed
week ending 24 March 1991. The overall average progress mapping of the rock exposed in the face or by way of
for all machines was 150 m/week. exploratory probing carried out from within the tunnels.
The breakthrough of the Marine Running Tunnel South This data then enabled designers, engineers and tunnellers
in June 1991 marked the completion of the tunnel drives. alike to respond to the encountered conditions, thereby
By that date a total of 84 km of bored tunnel had been allowing appropriate measures to be taken well in advance
driven by the UK side, and 3.9 million cubic metres of rock of the main running tunnel drives. Such measures in­
had been excavated. cluded:
Details of the bored tunnel progress and drive data is (a) modification to the tunnel alignment
shown on Fig. 14.6 and Tables 14.1-14.3.
(b) optimisation of the tunnelling system and methods

14.3 Geotechnical monitoring of tunnel (c) ground treatment of fractured rock and/or zones of
high water inflow to locally improve its mechanical
drives properties and reduce its permeability.
14.3.1 General
Despite the extent of the previous site investigation, this Due to the increased risk (e.g. use of open-face TBMs,
still resulted in boreholes being located at only about 1 km excavation of large caverns by NATM), 30 geologists were

223

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

Table 14.1 Summary of drives data

Description MST MRTN MRTS LST LRTN LRTS Totals

T B M manufacturer Howden Robbins-Mark Robbins-Mark H o w d e n Howden Howden


ham ham
T B M cost (million £) 4.82 9.27 9.27 4.82 8.03 8.03
T B M erection duration 89 112 111 93 118 98
(days)
Cut rock date 29 N o v . 1987 27 Feb. 1989 30 M a y 1989 30 Sept. 1988 2 A u g . 1989 20 N o v . 1989
Start o f driving date (first 4 Jan. 1988 27 Feb. 1989 16 June 1989 30 Sept. 1988 2 A u g . 1989 27 N o v . 1989
cut)
C o m m i s s i o n chainage 20 500 20 400 20 400 18 537 18 431 18 475
Commissioning average rate 43 46 39 45 42 39
(m/week)
5 k m f r o m adit A 2 27 Jan. 1989 12 A p r . 1990 14 M a y 1990 N / A N/A N/A
E n d date (last ring built b y 30 Oct. 1990 22 A p r . 1991 17 M a y 1991 9 N o v . 1989 11 Sept. 1990 20 N o v . 1990
machine)
Breakthrough date 1 D e c . 1990 22 M a y 1991 28 June 1991 9 N o v . 1989 11 Sept. 1990 20 N o v . 1990
Trailing edge ring 1 (ch) 19 841 19 571 19 531 19 075 19 072 19 004
Leading edge last ring (ch) 41 611 37 222 38 334 11 145 11 161 11 145
D r i v e n distance (m) 21 770 17 651 18 803 7930 7911 7859 81 924
Rings built 14 478 11 716 12 474 5252 5240 5207 54 367
Distance f r o m adit A 2 (m) 22 310 17 921 19 033 8156 8140 8156
Length o f crossover N/A 162m/108R 162 m / 1 0 8 R N/A N/A N/A
P C C rings (m/rings) 13 363 10712 11 670 5027 4925 4918 50615
Opening set rings 521 319 321 163 148 148 1620
P R D opening set rings N/A 224 234 N/A 92 92 642
H e a v y duty C I rings 394 354 141 62 75 49 1075
Opening set numbers 115 77 80 36 36 36 380
P R D opening set numbers N/A 71 76 N/A 31 31 209
Shield length (m) 13.52 14.11 14.11 13.52 14.03 14.03
Cut diameter (m) 5.38 8.36 8.36 5.76 8.72 8.72
Internal diameter (m) 4.8 7.6/7.78 7.6/7.78 4.9 7.6 7.6
Segment thickness (m) 270 270/360 270/360 410 540 540
R i n g length (m) 1.5 1.5 1.5 1.5 1.5 1.5
V o l u m e o f rock/ring ( m ) 3
34.10 82.33 82.33 39.09 89.58 89.58
T o t a l v o l u m e o f rock ( m ) 494 895 983 704 1 044 743 206 637 472 448 469 343 3 672 770
Bulking factor o n excavation 1.9 1.9 1.9 1.9 1.9 1.9
Bulking factor as 1.24 1.24 1.24 1.24 1.24 1.24
compacted behind sea wall

TBM performance

T B M availability overall (%) 73.4 65.4 71.7 67.2 77.6 81.9


T B M utilization overall (%) 50.0 43.4 48.1 49.3 47.0 55.3

Production time allocation (hrs)

R i n g building 11 064 8173 8325 5072 4570 4971


Head and shield delay 484 895 624 231 206 212
Erectors and crane delays 1608 769 683 432 428 337
C o n v e y o r delays 524 741 502 253 210 207
T B M miscellaneous delays 289 2607 1905 118 433 424
T B M maintenance delays 3969 1499 1184 1972 984 461
Probing 1868 0 0 49 0 0
T r a i n delays 4269 2037 2047 1324 1810 1121
Service delays 459 60 48 93 52 125
G r o u n d delays 427 126 168 212 505 345
Other delays 910 1932 1817 228 716 820

224

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

Table 14.2 Progress records

Description MST MRTN MRTS LST LRTN LRTS Totals

Best shift (8 hours) 24 m 30 m 30 m 21 m 21 m 25.5 m


4 Feb. 1989 1 F e b . 1991 22 Feb. 1991 30 Mar. 1989 30 Mar. 1990 7 June 1990
Best 24 hours 60.1 m 70.9 m 75.5 m 56 m 52 m 59.4 m 214.3 m
8 Feb. 1989 31 Jan. 1991 24 Feb. 1991 17 A p r . 1989 23 A p r . 1990 8 June 1990 23 A p r . 1990
Best week - M o n d a y 293 m 409 m 426 m 267 m 308 m 320 m 1210m
to Saturday 5 Feb. 1989 10 Mar. 1991 24 Mar. 1991 14 M a y 1989 15 A p r . 1990 10 June 1990 6 M a y 1990
Best calendar month 997 m 1637 m 1718m 923 m 1043 m 1222 m 4481 m
A p r . 1989 Mar. 1991 Mar. 1991 A p r . 1989 Mar. 1990 June 1990 Mar. 1990
Best project month 1042 m 1862 m 1911 m 1007 m 1178 m 1164 m 5170 m
A p r . 1989 Mar. 1991 Mar. 1991 J u l . 1989 A p r . 1991 June 1990 A p r . 1990
A c h i e v e d average 142 156 179 137 134 151
m/week in U K
Ring cycle average 46 43 41 58 54 58
(min)
B l o c k y ground 76 82 130 117 104 125
average rate (m/week)
Ring cycle blocky 85 71 63 82 89 91
ground (min)
A c h i e v e d average 111 149 159 72 77 68
m/week in France

Table 14.3 UK TBM tunnels: history and progress

1986 1987

Main geotechnical events

Marine Service T u n n e l 4 J a n . 88

Marine R u n n i n g T u n n e l N o r t h

Marine R u n n i n g T u n n e l South

L a n d Service T u n n e l

Land Running T u n n e l N o r t h

L a n d R u n n i n g T u n n e l South

Problems with blocky ground: marine tunnels chainage m 20400-23400


land tunnels chainage m 12000-breakout

Main geotechnical events


1 7 Feb. 1986: Tender advertisement for UK TBMs
2 21 Aug. 1987: Development Study 17 Report issued
3 Mar. 1988: First problems experienced with overbreak and saline water ingress in MST (chainage m 20400)
4 4 June 1988: Steel trailing fingers fitted to MST TBM (chainage m 20772)
5 Sept.-Oct. 1988: Ground treatment trial at undersea cross-passage (chainage m 20661)
6 Sept. 1988: Downward realignment of undersea tunnels beyond km 21.8 after probe shows Gault Clay to be 8 m lower than predicted
7 Nov. 1988: MST driven through 35 m long unprobed section (chainage m 23251-23286) to see if forward probes exacerbating overbreak
8 9 Dec. 1988: Stainless steel hood fitted to MST TBM (chainage m 23700)
9 Dec. 1988-Mar. 1989: Sideprobes drilled from MST across to crown of MRT through wet section
10 Sept.-Oct. 1989: Major modifications to MRT TBMs (upper slat conveyor removed and grout platform moved forward)
11 15 May 1989: Start of excavation UK Crossover
12 July 1989: Problems with overbreak and face collapse in LST as Glauconitic Marl and blocky Gault Clay encountered beyond chainage m 13800
13 3 Nov. 1989: Ground collapse into face of LST TBM immediately adjacent Sugarloaf shaft
14 Jan.-Mar. 1990: Ground treatment of MRTs from MST (chainage m 22700-23400)
15 Aug.-Sept. 1990: MRTs pass through UK Crossover Cavern
16 30 Oct. 1990: Contact made with French TBM by forward probe drilled from face of MST
17 I Dec. 1990: Breakthrough between UK and French sides

225

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

employed on the UK side compared with six geologists on The TBMs were specified, however, to be capable of
the French side. In total, 3468 geological logs of the UK withstanding inundations arising from encounters with
TBM drives were made (equivalent to one report per unsealed boreholes or open fissure within the TBM face,
190 m of drive length). On each side of the Channel one or inundation caused by passing close to an unsealed
geologist was specifically trained in micropalaeontology, borehole; which could burst into the excavation at the tail
enabling rapid assessment of the encountered versus pre­ of the TBM before the lining was placed. All marine TBMs
dicted stratigraphy to be made. had the capability of shutting off the face by retracting the
spoil conveyor and closing a door which was controlled by
14.3.2 Exploratory probing the TBM driver pressing an inundation button. The annular
In early 1988, a specific study was made of the risk of gap around the outside of the TBM could also be closed
inundation and of the requirements for probing. In parallel off by applying enhanced pressures to the grippers with the
with this study, trials were carried out to prove both the whole activity being completed within 15 to 20 seconds.
capability of drilling equipment, the results obtainable In the event of an inrush of water at the rear, pumps capable
from various down-the-hole logging tools, and the poten­ of handling up to 900 litres/minute would be started and
tial of seismic tomography. an evacuation alarm sounded.
The study identified six possible sources of geological Forms of probing carried out during progress of the
hazards which could be located and/or investigated by service tunnel drives included:
probing, namely: (a) advance probing ahead of the TBM face
(a) Water-bearing fissures (b) vertical downwards probing
It was recognized that undetected water-bearing fis­
sures could be encountered in the hand-mined sec­ (c) sideways probing behind the TBM drive.
tions, as well as in the TBM drives. However, the This exploratory probing (Figs 14.7 and 14.10) proved
greatest risk of sudden inundation was in the TBM to be one of the major successes of the project with the total
drives. length drilled on the UK side almost equalling the distance
(b) Site investigation boreholes across the Channel.
Numerous boreholes had been drilled in the Channel
over a period of many years, and the locations of the 14.3.2.1 Advance probing ahead of the T B M face
early ones were not precisely known. The study Extensive forward probing was carried out ahead of the
showed that five boreholes, drilled and grouted in tunnel face to check the geology and locate areas of fault­
1972-73, were within 70 m of a running tunnel, the ing and broken ground and/or zones of high water ingress.
closest being 26 m although the locations of these The probing system consisted of two Diamec 260 drilling
holes was known only to within ±10 m. rigs located at the front of the TBM which were folded
away under the conveyor head assembly during mining
(c) Areas of deep weathering operations. The conveyor was withdrawn from the TBM
Several boreholes had indicated greater depths of face cone to give access to the face for the probing opera­
weathering, with the strata above the Chalk Marl tion. Strict isolation procedures were enforced before any
being more prone to weathering. Of particular concern entry into the head. Drilling rods were made of aluminium,
was potential weathering associated with the Fosse to allow, if necessary, for safe abandonment ahead of the
Dangeard (see below). TBM face.
(d) Proximity to the Grey Chalk All probes were normally 56 mm in diameter and gener­
The Grey Chalk above the Chalk Marl; due to its ally 120-200 m in length (max. 260 m), and were destruc­
increased calcium carbonate content, was generally tively bored. Drilling parameters monitored on a regular
stronger, more brittle and jointed and hence more basis included water outflow and salinity, the penetration
permeable than the Chalk Marl. rate and the nature of the drilling returns with any anoma­
lies being noted. When the probe entered the Glauconitic
(e) Proximity to the Gault Clay Marl, as evidenced by a change in colour of the drilling
The Gault Clay, an overconsolidated mudrock, is returns from light grey to dark green, the probing was
prone to swelling and instability. Therefore it was to terminated.
be avoided if possible. This concern was more related Although automatic recorders were initially used to
to the stability of the excavation rather than to inun­ measure the thrust, torque, water inflow/outflow and pene­
dation. tration rates, electrical/mechanical problems associated
(f) Proximity to the Fosse Dangeard palaeovalley system with these devices led to excessive stoppages and down­
The Fosse Dangeard is an ancient offshore valley time and hence they were replaced by more conventional
system extending down to 80 m below seabed, and methods (measurement by stopwatch and bucket). Such
located 500 m south of the tunnel between chainage methods were not only more reliable but sometimes pro­
kms 38 and 42. The valley is infilled with silts and vided better quality information e.g. water outflow, where
sandy clays. A 10 m deep subsidiary channel, extend­ the automatic recorders became insensitive to the minor
ing off the main palaeovalley system, crosses the route flows experienced.
at chainage km 39. This was considered to warrant Samples of rock cuttings obtained by sieving the drilling
very close examination, and much use was made of returns (Fig. 14.8) were sent up to surface for on-site
knowledge of the geology acquired during the ad­ microfossil analysis (Chapter 26). This enabled both the
vance of the service tunnel. stratigraphic level of the tunnel and the likely path of the
probe to be determined, the latter being verified on occa­
The study concluded that the risk of inundation was very sion by the use of downhole survey methods and face
small, provided that adequate probing was carried out. mapping.

226

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

1 ^ 0 1 2 3 4 5m

SCALE

Figure 14.7 Arrangement of probing rigs in service tunnel.

In the Marine Service Tunnel advance probing was sys­ Geological descriptions of these cores were completed in
tematic and continuous as a consequence of the increased the tunnel upon retrieval. The cores were then despatched to
level of risk (i.e. wide spaced boreholes, shallow cover to the surface for detailed core logging, laboratory analysis and
sea-bed, early downhill gradient). detailed microfossil examination. This enabled comparison
Over the low cover section (i.e. less than 30 m cover), of the actual geology to that predicted on the basis of the
dual 100-140 m long probes inclined upwards and out­ borehole and geophysical evidence e.g. stratigraphical levels,
wards at a gentle angle (usually 2-4°) were employed. calcimetry etc. Drilling was carried out during the same shift
Drilling also took place through a standpipe to enable the as a forward probe so as to minimise TBM downtime.
hole to be shut off if any large quantities of water were Downward probing was more frequent in the Marine
encountered. However, with increasing cover and confi­ Service Tunnel with the 22 km of undersea drive being
dence, supported by data provided by the drive, this was covered by some 48 holes spaced at intervals ranging from
substituted by a single 200-240 m long hole drilled ahead 200-600 m. Figure 14.9 indicates the Channel-wide accu­
of the face. This enabled the entire weekly production to racy of the geophysical prediction in relation to the en­
be covered by one probe, taking 8 hours to complete (4 countered geology. Tunnel realignments were carried out
hours setup time, 4 hours drilling time). In all, downtime on the UK side seawards of chainage km 21.8 (realignment
associated with probing accounted for 7% lost production 1) when the Glauconitic Marl was found to be 8 m lower
time. As essential TBM maintenance was carried out on than predicted and again beyond km 36 (realignment 2)
the probing shifts this figure was, in practice, even smaller. when the boundary was found to be 6-7 m higher than
Results from the probing are shown in Fig. 14.15. predicted. In the former case, the discrepancy occurred at
The Land Service Tunnel was driven uphill and thus the boundary between the inshore and offshore geophysi­
advance probing was limited to those areas where prob­ cal surveys and incorrect velocity assumptions probably
lems were anticipated e.g. anticipated zones of faulting account for the anomaly. In the latter case, the large
such as the Lydden Fault. Regular face inspection was, difference is probably attributable to the absence of any
however, undertaken with the knowledge that any major control boreholes in the area. The discrepancies on the UK
inflow of water would run back down the tunnel from the side exacerbated the tunnelling problems at both locations;
face and could be pumped out from the Shakespeare Un­ at the former location the tunnel crown lay much closer to
derground Development. the Grey Chalk (a more jointed and permeable strata),
while at the later location Glauconitic Marl was encoun­
14.3.2.2 Vertical d o w n w a r d p r o b i n g tered in the face which resulted in spalling of the sidewalls
These probes were drilled in the build area some 16m back and excessive pick wear.
from the TBM face. These provided 35 mm diameter cores In the Land Service Tunnel little or no downward probing
down through the Chalk Marl and Glauconitic Marl into was undertaken as a consequence of the greater accuracy
the underlying Gault Clay (including Bed 6a). of prediction associated with the more closely spaced site

227

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

Face Chainage 31B91m 28.10.89


400

350

300

250

200

150

100

50
Negligible 0.0661/min/m 0.0251/min/m Negl igible
0
i i i i 30
i i i i i i i i i i 60
i i i i i i i i i i 90
i i i i i i i i i i i i i i i i i i i i i i i i i i i i i i180
iiiiiiitiiiiiiiiiiii i
120 150 210 240
Distance (m from face) Left Hand Probe

•j m •

5 5 H B P * < T F T M

Figure 14.8 Advance probing. Top: typical plot of advance probe showing penetration rate, water outflow and cutting
returns; bottom: sampling cutting returns from advance probing.

i n v e s t i g a t i o n b o r e h o l e s a n d the i n f o r m a t i o n d e r i v e d f r o m n o t e d , a n d adjacent to the U K C r o s s o v e r , w h e r e the p i l o t


the adjacent cliffs. t u n n e l h a d d e v i a t e d further north a n d b e l o w the l e v e l o f
the r u n n i n g tunnels.
14.3.2.3 S i d e w a y s p r o b i n g I n the L a n d S e r v i c e T u n n e l , s i d e w a y s p r o b i n g w a s c o n ­
T h e s i d e w a y s p r o b i n g e x t e n d e d across to the c r o w n o f b o t h f i n e d to the last 0.7 k m , c l o s e to the e s c a r p m e n t e d g e
r u n n i n g tunnels ( F i g . 14.10) a n d w a s g e n e r a l l y c o n f i n e d adjacent the S u g a r l o a f portal, w h e r e g r o u n d c o v e r w a s
to t h o s e areas w h e r e d i f f i c u l t g r o u n d h a d a l r e a d y b e e n s h a l l o w a n d there w a s a p o s s i b i l i t y o f e n c o u n t e r i n g w e a t h ­
n o t e d d u r i n g p r o g r e s s o f the s e r v i c e t u n n e l d r i v e , o r w h e r e ered and broken rock.
information w a s lacking.
T h e g e o l o g i c a l descriptions f r o m the 35 m m diameter cores 14.3.3 Geological inspection of strata in the
r e c o v e r e d f r o m the probes together w i t h m e a s u r e m e n t o f tunnel
water o u t f l o w , salinity a n d p e r m e a b i l i t y ( F i g . 14.11) enabled I n a d d i t i o n to the a b o v e e x p l o r a t o r y p r o b i n g , r e g u l a r d e ­
assessments to b e m a d e o n the need f o r a d v a n c e p r o b i n g in tailed i n s p e c t i o n w a s carried o u t o f the g r o u n d e x p o s e d in
the r u n n i n g tunnels, o r f o r a n y g r o u n d pre-treatment. the face a n d s i d e w a l l s o f the tunnel b o r e a n d t a i l s k i n area.
I n the M a r i n e S e r v i c e T u n n e l s i d e w a y s p r o b i n g w a s U n l e s s g r o u n d c o n d i t i o n s s o w a r r a n t e d , face e n t r y w a s
c o n f i n e d t o t h e l e n g t h u p to k m 2 8 , w h e r e i n c r e a s e d w a t e r n o r m a l l y c o n f i n e d to the e n d o f each shift o r d u r i n g a
i n g r e s s a n d a d e t e r i o r a t i o n in g r o u n d c o n d i t i o n s h a d b e e n period o f maintenance or advance probing, thereby limit-

228

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK T U N N E L S : G E O T E C H N I C A L MONITORING

D i f f e r e n c e a c t u a l to p r e d i c t e d d e p t h (m)

1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
- 1 0 —
19 21 2 3 2 5 27 29 31 3 3 3 5 37 39 41 4 3 4 5 47 49 51 5 3 55 57
chainage km

Figure 14.9 Results of downward probes.

PACKER PERMEABILITY TEST

im\\\\\\N ROCK CORES TAKEN S C A L E ° ] ] * * 5m

Figure 14.10 Typical arrangement of sideprobes.

ing downtime associated with this activity. A typical geo­ some 16 m back from the face, may have been influenced
logical record is presented in Fig. 14.12. by the nature of the tunnelling operations (e.g. action of
Basic parameters recorded included: TBM grippers against tunnel sidewalls opening up joints
and increasing potential for major overbreak) and time
(a) rock type, strength and weathered state (e.g. greater degree of overbreak during mainte­
(b) discontinuity details; including the nature and orien­ nance/probing shift when TBM standing). These factors
tation of bedding, jointing and faulting e.g. number of had to be considered during subsequent analysis of this
joint sets, spacing and persistence of joints and bed­ data.
ding planes, throw/mineralisation of faults etc. Better quality data was normally provided by logging of
either the cross-tunnels (i.e. crosspassages, piston relief
(c) estimate of water inflow entering the face or build ducts and pumping stations) which were excavated by the
area. Estimates of water inflow entering the build area miners using pneumatic spades, or the NATM excavations
inevitably on occasion included water emanating such as the UK Crossover. Greater emphasis with more
from behind the previously built rings regular inspection was placed on those areas of increased
(d) estimate of Rock Mass Quality Q (NGI) based on the risk e.g. Fosse Dangeard.
above observations
(e) nature and volume of overbreak around the tunnel 14.3.4 T h e T M L Channel Tunnel Geological
periphery. Database
A standard database program, DataEase, was used as a data
It should be emphasised that the above observations storage and analysis facility for certain Geological infor­
(Fig. 14.13), particularly those made in the build area mation (Figure 14.14). Geological face records, forward

229

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

3.0
probing results, vibrating wire strain gauge data, and the
O
results of micropalaeontology and calcimetry analysis
South
were entered into the database. DataEase was already
2.5 - * North
being used on other parts of the project for staff records,
engineers' shift reports, the drawing office drawing regis­
ter etc and it was realised early on in the project that there
* * was a great deal of geological information from the Marine
* Service Tunnel drive that would need analysing prior to
the start of the marine running tunnel drives. It was very
o <p o time consuming trying to leaf through the hundreds of A3
0.5 o * g sized geological logs in order to pick out geological trends
o o
and locations of high water inflows/large overbreak. Using
the database to printout graphs of various geological pa­
25 26
22 23 24 rameters enabled the geologists to easily pick out the areas
chainage km of poor ground ahead of the running tunnel TBMs. It also
30 allowed the immediate presentation of the findings as high
O S o u t h (Packer test)
quality graphical plots to construction management. Pro­
* N o r t h (Packer test) duction of stereonets from the discontinuity data was used
for stability analysis of the hand excavated tunnels.
20 The relational database was fast and simple to set up. It
had a large storage capacity and could be run on standard
386/486 personal computers of which the TML Geotech­
nical Department had three, one of which was dedicated to
the database. Built-in mathematical functions allowed cal­
culations to be done by the computer on data that was
entered by the user. The advantage of using a database over
***** a * a spreadsheet program was that the database was designed
* o *

to store much larger quantities of data.


24 25 26
22 23 The use of a relational database allowed a number of
chainage km
forms to be linked by simple user defined relationships
Figure 14.11 Results of sideprobes in Marine Service which meant that related forms could iook-up' informa­
Tunnel to chainage km 26. Top: outflow sideprobes tion from each other without having to re-enter the infor-
(l/min/m); bottom: permeability of Chalk Marl (m/s)
7
(x1(T ).

L11H0LOGIC A
OtSCRlPtlON

l^talC. ONE BA~U <JF LYKT^jrij, FRW ik C>-xjiL~ll.'X*. L,~*STO~J±


(sponge bed) J
iTAUC t o *-uiderr»teUj .

SAMPLE

4\ OEiCRIPIION ,4 ONA .
PHOTOGRAPH
DESCRIPTION j m .
None tuKc^l

A ICR -IF R
T E ­

STABILITY . - ~
OVERQREAK a/O o/B , face. <a~d -=>'c/eLj*tf± SL.^K
«°0 /OO 1

JOINTING OE T AILS

J'I(I. V.) /Jo - SOO. P . S T <. of A CRO2,ER.


J - « ( 7 - / - t f 0 S>s ?, S. T. o b .

JS(t<>//YC) C*, P, s.-r.^.

3 * SI
SUMMARY WEATHERING GRAOE CHECKED

GROUNO CQMOITION ROCK QUALITY

MARINE SERVICE TUNNEL FACE

7
GEOTECHNICAL
w RECORD

Figure 14.12 Typical geotechnical log.

230

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

Table 14.4 Marine tunnels: observed inflow and overbreak


3
Chainage (km) Tunnel Water (l/min) Overbreak (m )

Build Face Build Face

Start-20.4 MST D r y (0.4) D r y (0.5) N e g (0.5) N e g (neg)


MRTN D r y (2) Dry(l) N e g (neg) N e g (neg)
MRTS D r y (5) D r y (5) N e g (0.8) N e g (0.3)

20.4-20.9 MST 1.3(10) 1.5 (7) 0.47 (2.5) N e g (1.1)


Z o n e o f l o w cover to seabed MRTN 19.5(116) 10(30) 0.12(0.75) N e g (0.24)
MRTS 10.7 (80) 6.4 (25) 0.20 (0.75) N e g (1.0)

20.9-21.3 MST 2.2 (9) N / A (0.5) 0.18(0.9) N e g (0.15)


Z o n e o f l o w cover to seabed but MRTN 3.5(17) 3.2(10) 0.23 (0.5) N e g (neg)
following modifications to T B M s
MRTS 5.8 (20) 0.8(1) 0.11 (0.3) N e g (neg)

21.3-22.7 MST 2.5(15) 1.1(10) 0.37 (2.0) N e g (0.35)


Shallow cover above tunnel MRTN 3.1 (20) 1.4(4) 0.15(1.0) N e g (0.25)
crown
MRTS 1.4 (7) 3.8(17) N e g (0.4) N e g (0.25)

22.7-23.4 M S T (untreated) 8.6 (88) 9.3(15) 0.55 (2.7) N e g (0.4)


Z o n e o f shallow cover and M R T N (treated) D a m p (0.3) 1.3 (8.5) N e g (0.3) 0.14(0.45)
geological structure
M R T S (treated) D a m p (6) 1.4(5) 0.11 (0.4) 0.27 (0.55)

23.4-27.6 MST 0.8 (35) 1.4(14) N e g (0.4) N e g (0.25)


MRTN D a m p (3.5) D a m p (3) N e g (0.8) N e g (0.15)
MRTS D a m p (5) D a m p (1.3) N e g (0.4) N e g (0.3)

27.6-28.0 MST 1.8(2.0) 18.5(110) N e g (0.4) N e g (0.25)


Z o n e o f geological structure MRTN 13.3 (50) 2.3 (5.5) 0.23 (0.7) 0.11 (0.25)
MRTS 1.7 N/A 0.16 N/A

28.0-end MST Seeps(7) Seeps(18) N e g (0.2) N e g (0.2)


MRTN Dry(l) D r y (seep) N e g (0.45) 0.12(0.2)
MRTS D r y (dry) D r y (seep) N e g (0.2) N e g (0.1)

Notes
General V a l u e s i n parentheses represent m a x i m u m observed Water D r y g r o u n d refers t o less than 0.01 l / m i n o n average
values D a m p g r o u n d refers t o range 0 . 0 1 - 0 . 0 2 l / m i n o n average
Seeps refers t o less than 0.05 l / m i n o n average
Tunnel M S T : service
B u i l d water l i k e l y t o i n c l u d e some water e m a n a t i n g f r o m
M R T N : r u n n i n g tunnel n o r t h
ungrouted rings outbye and around T B M shield i n b y e
M R T S : r u n n i n g t u n n e l south

Overbreak Overbreak recorded i n the b u i l d area represents o n l y that N/A N o t applicable because t o o f e w logs available
observed. Observed overbreak reduces once fingers/hood
i n place. Overbreak i n face includes s p a l l i n g f r o m face

mation, thereby saving time and reducing the chance of could be sorted quickly and the results of concern identi­
data entry error. fied and checked.
Data could also be imported from and exported to spread­ Once the geologist returned from underground, the face
sheets (e.g. Lotus 1-2-3, Quattro Pro), graphics programs records were drawn up onto a standard proforma and then
(e.g. Lotus Freelance, Harvard Graphics) and other data checked by the senior geologist and agreed with Eurotun­
formats. The vibrating wire strain gauge information from nel. Once checked, the data were entered on to the database
the instrumented parts of the tunnels that was read by a in a form that outwardly mimicked the paper log - a
datalogger was downloaded directly into the database process that took less than a minute per log. Each day, the
where it was analysed and reported from. During this database was automatically edited for data entry mistakes
process there was almost no user interaction involved. and any required analysis was undertaken (producing
Being in a database format, the huge quantities of data stereonets, graphs of water inflow etc).

231

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

By (he end of the project a large amount of information


was stored on the computer:
Database Form No. of Records
Geological Face Logs (data from) 4,735
Discontinuity Records 20,746
(orientation, openness etc.)
Forward Probe Reports 82
Quantitative Micropalaeontology 825
Analyses
Probe Water Inflow Chemistries 567
(chlorides, sulphates etc.)
Rock Sample Testing Data 1169
(calcimetry etc.)
Vibrating Wire Strain Gauge 423
Results
Once the data had been entered, the database was inter­
rogated to retrieve the specific information in the format
required. This was done by writing a procedure that que­
ried the database, sorted the required information and
output it to either a computer file or a printer.
The output could then be sent to a disk tile and picked up
by a graphics program where a graph showing the variation
in the above parameters (water inflow, nature of jointing,
volume of overbreak etc.) could be plotted against chain-
age. By the user specifying the location of the information
required, any part of the works could be analysed or
compared. Another procedure was written to query the
database and output joint orientations that could then be
imported into a stereonet producing program (DataFrac).
The database had four main uses:
(a) The rapid reporting of any changes in geological
conditions underground, such as increasing probe
Figure 14.13 Logging environment: Marine Service
water flows, to alert both TML management and the
Tunnel TBM. Top: conditions at the face; bottom:
Eurotunnel geotechnical team.
conditions in the build area.
(b) Production of as-built drawings for the service tunnels
which were used to predict the areas of poor ground (d) To allow the rapid reinterpretation of the geological
in advance of the running tunnels. and geotechnical data in order to provide an explana­
(c) To produce data plots for other contractual reports. tion for the adverse ground conditions.

One-to-Many Relationship
MAIN FORM SUB-FORM

GEOLOGY JOINT

FIELDS FIF.LDS

TUNNEL
DATE OF LOG
RING NUMBER LOOKUP
T1ME OF LOG ^
LOG TYPE
ROCK TYPE JOINT NUMBER
GEOLOGIST DIP
T U N N E L ORIENTATION DIRECTION
RQD IRREGULARITIES
WATER INFLOW APERTURE
VOLUME OF OVERBREAK
NUMBER OF JOINTS
NUMBER OF JOINT SETS Number of Join! Records
FAULTS per Geological Log

Figure 14.14 TML geotechnical database.

232

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

2
Although a large amount of staff time was taken up in intermittently approaching 3 J/m (Chapter 25), such as in
entering and editing the data the database proved an invalu­ an area of structural folding adjacent to chainage km 23.
able tool. Its main benefits over manual presentation were: Joints recorded at the tunnel face/sidewalls and in
crosspassages were generally planar, smooth and tight.
(a) The production of high quality data plots and printouts Some degree of openness generally up to 5 mm and occa­
that could be presented immediately to senior man­ sional clay infill, was sometimes recorded along joints.
agement without the need for drafting (many dead­ Such occurrences were both limited and discontinuous in
lines for internal reports were only met due to this nature, being usually confined to lengths up to 100 mm
facility). along any given joint.
(b) The flexibility it allowed in the interpretation and Major joint sets observed comprised a subhorizontal set
presentation of data. generally associated with bedding, complementary sets
striking subparallel to the tunnel and dipping above 60° to
(c) It produced plots and listings from edited data which the NNE and SSW and a shallow set dipping 10^5° in a
only required the minimum of further editing. general SSW direction (Fig. 25.1). Less prominent sets
were also recorded e.g. dipping 40-70° southeastwards.
14.4 UK marine drives: encountered
tunnelling conditions 14.4.1.3 Faulting
14.4.1 General Evidence of major faulting was not observed although
A summarised description of the ground conditions en­ several minor local faults and/or slickensided 'shear joints'
countered during progress of the marine drives as related with clay veneer, calcite and pyrite infill were sometimes
to the amount of cover above the tunnel crown and height noted e.g. adjacent chainage km 28 where disturbed and
of tunnel above the Gault Clay/Bed 6a material is illus­ broken ground was met.
trated on Fig. 14.15.
Information shown includes:
14.4.2 Encountered ground conditions:
(a) results of advance probing in the Marine Service overview
Tunnel 14.4.2.1 Early part of drive to chainage km 2 3 . 4
(b) Marine Service Tunnel: water inflow and overbreak In all three marine tunnels, ground conditions were in­
itially favourable, similar to those in the earlier 1974 drive,
(c) Marine Running Tunnel North: water inflow and but quickly deteriorated from about chainage km 20.4 and
overbreak thereafter up to chainage km 23.4. The drive was slowed
by overbreak and by seepage inflow.
(d) measured salinity of the water entering the tunnels and
Jointing was more frequent and sometimes open, associ­
flowing out of probe holes
ated with the low cover to sea-bed and zones of structural
(e) measured salinity of the water entering the tunnels and disturbance. This led to downward percolation of seawater
flowing out of probe holes since passage of the face into the tunnel and development of high water pressures in
of the Marine Service Tunnel. the surrounding rock mass. This, together with the adverse
nature of the jointing, gave rise to block fallout around the
Of particular interest is the good correlation between the tunnel periphery.
outflow from the advance probe and the inflows observed In the service tunnel, porewater containing 4000-8000
at the face of the Marine Service Tunnel. Further details of mg/l of chloride were quickly replaced by seawater i.e.
the conditions encountered are given in Table 14.4. 19600 mg/l; the time taken to do so reflecting the local
permeability conditions above the tunnel crown. Where
14.4.1.1 Strata types permeability was high, even the initial salinity was high
The strata met during tunnelling predominantly comprised e.g. face chainage m 20751 where a chloride content of
weak to moderately weak unweathered Chalk Marl, mid 16619 mg/l was measured (Fig. 14.15).
to dark grey in colour and sometimes containing lighter Wedge-type failures of the crown and shoulders were
grey moderately strong sponge beds. commonly observed in the build area, the shape of the
The service tunnel also encountered Glauconitic Marl/Bed blocks being defined by two joint sets i.e. a subhorizontal
6a material between km 26.2 and km 29.1 as it deviated bedding set and a steeply dipping set aligned subparallel
further north and below the level of the UK Crossover; Bed to the tunnel wall (Fig. 14.16).
6a being in the face between km 26.4 and 27.8. 3
Block sizes were typically 0.2-0.5 m but when TBM
Glauconitic Marl was again encountered between chain- progress was slowed, larger volumes of overbreak would
age kms 34.7 and 37, this unit was also present in both 3
occur i.e. up to 2.7 m . This made expansion of the con­
running tunnels between chainage kms 33.8 and 36.8, crete rings difficult until trailing steel fingers (and later a
where it remained below axis level. complete thin steel hood) were fitted at the back of the
TBM to restrain blocks from falling (Fig. 14.16) and allow
14.4.1.2 Jointing and rock mass characteristics safe erection of the unbolted ring. The hood successfully
The rock was blocky and jointed with general RQD values contained the broken ground, reduced the overbreak and
above 90%. Information from vertical probes and side­ prevented unacceptable distortion of the expanded lining.
probes drilled along the length of the drive indicated a Similar hood and finger arrangements were fitted to both
typical joint spacing of 1 to 3 joints per metre for the Chalk running tunnels before this area of unstable ground was trav­
Marl. A similar joint spacing was indicated by the site ersed. The historical development of the hood/finger arrange­
investigation boreholes. ment in all three marine tunnels is outlined in Table 14.5.
Geological logging of the exposed face and tailskin area The ground conditions described above were further
indicated comparable joint frequencies of 1 to 2 J/m 2
aggravated by the following geological factors:

233

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

80 120

70 Fosse Dangeard large inflows from open joints


cover to seabed above , in Glauconitic Marl
60
service tunnel crown
50 t -

40

30

20 height of tunnel
above Gault/6A
10

0
realignment 1 realignment 2 Ljlu—. . , , , eu. ,
-10
19 21 23 25 27 29 31 33 35 37 39 41 43 19 21 23 25 27 29 31 33 35 37 39 41 43
chainage km chainage km
(a) (b)

Marine Service Tunnel

GM : high outflows from


Glauconitic Marl

Mi > A
19 21 23 25 27 29 31 33 35 37 39 41 43 21 23 25 27 29 31 33 35 37 39 41 43
chainage km chainage km
(c) (d)
120
Marine Running Tunnel North hood installed ch 2 3 3 7 7
100
fingers fitted ch 20772

80
Ground treatment
60
km 22.7 - 23.4
i

21 23 25 27 29 31 33 35 37 39 41 43 21 23 25 27 29 31 33 35 37 39 41 43
chainage km chainage km
(e) (f)

20000 r. seawater salinity seawater salinity

O MST/XPs — 0-1 days

+

MRT •ample*
Advance probe
***** o

1-3 d a y s
3-100 days
& Sideprobes >100 d a y s

19 21 23 25 27 29 31 33 35 37 39 41 43
22 23
chainage km chainage km
(9) (h)

Figure 14.15 Ground conditions in the undersea tunnels, (a) height (m); (b) inflow into face (l/min), Marine Service
Tunnel; (c) outflow from advance probes (l/min/m); (d) inflow into build area (l/min), Marine Service Tunnel; (e) inflow into
3
build area (l/min), Marine Running Tunnel North; (f) overbreak in build area ( m ) , Marine Service Tunnel; (g) salinity
(mg/l chloride); (h) salinity with time (mg/l chloride).

234

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

Table 14.5 Development of hood and finger arrangement (a) Low Cover Section: chainage km 20.4 to 21.8
in marine tunnels Along the early part of the drive up to chainage km
21.8, the vertical probes indicated the service tunnel
Tunnel Chainage Modification to be generally 3-4 m (up to 8 m) higher as compared
Service 20774 4 fingers installed to the anticipated geology. This resulted in the tunnel
Tunnel 20779 3 fingers installed (total = 7) being entirely located within the higher Chalk Marl
22459 3 fingers removed (total = 4) with its crown lying closer to the overlying Grey
22500 3 fingers replaced (total = 7) Chalk and base of weathering. Consequently more
22512 2 fingers installed (total = 9) permeable and jointed strata was encountered leading
22624 1 finger installed (total = 10) to increased seepage inflow and overbreak.
23311 to 23379 H o o d extended o n north side Immediate improvement was thus sought by steep­
23392 to 23454 H o o d extended o n south side ening the tunnel gradient beyond chainage km 21.8 in
order to increase the ground cover and bring the tunnel
Running 19807 H o o d installed profile lower into the more favourable Lower Chalk
Tunnel 20392 Fingers deformed Marl (some 14-15 m thick).
North 20805 Shorter fingers installed Consideration was also given to lowering the marine
22438 Extra fingers added at axis
running tunnel profile below the level of the service
tunnel through the section of difficult ground up to
Running 19748 H o o d installed chainage km 21.8. This was rejected due to problems
Tunnel 19988 Fingers modified associated with construction of the crosspassages and
South piston relief ducts and the effect on the long-term

Stainless steel plate


Trailing fingers

(a) (c)

Figure 14.16 Overbreak and hood and finger arrangements fitted to TBMs. (a) Typical overbreak observed in build area
of Marine Service Tunnel, (b) Typical overbreak and arrangement of trailing fingers: Marine Service Tunnel, (c) TBM
trailing fingers, (d) Typical overbreak and arrangement of trailing fingers and formers: Marine Running Tunnels.

235

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

operations. 4000-8000 mg/l chlorides, is a further indication of the


The encountered conditions were in practice more low permeability and negligible downward drainage exist­
adverse in the marine running tunnels through this ing in this area.
length due to their higher crown elevation as com­ Close to chainage km 28, however, there did exist a
pared to the service tunnel. This resulted in a tenfold further localised length of fractured ground where high
7
increase in permeability i.e. from 10~ to 10~ m/s and 6
saline inflow was met in the tunnel. Again, this can be
corresponding increase in inflow. On occasion, where explained by the presence of a geological structure -
ground cover to seabed was below 25 m, build inflows probably associated with minor faulting/folding. A col­
of up to 120 l/min were recorded (as compared to 10 lapse feature was also reported from the 1974 geophysical
l/min in the adjacent service tunnel). evidence. In the service tunnel, flows approaching 110
l/min were observed issuing from open joints/minor faults
(b) A rea of Minor Folding/Faulting: chainage km 22.7 to
in the Glauconitic Marl at the face.
23.4
Occasional problems were also subsequently experi­
Through this zone, tunnelling conditions in the Ma­ enced between chainage kms 34.3 and 37 as the service
rine Service Tunnel deteriorated even though the tun­ tunnel bored through Glauconitic Marl exhibiting vari­
nel was sited low down in the Lower Chalk Marl (the ations in its engineering properties i.e. sometimes unce­
preferred host medium). mented and friable leading to spalling of sidewalls or
In November 1988 a short 35 m section of ground ahead well-cemented and strong requiring frequent replacement
of the TBM was left unprobed in order to evaluate a theory of cutting picks.
that forward probing, and the possible high water pressure
associated with it, was causing hydrofracture of the rock, 14.4.3 Conclusions
exacerbating the overbreak problem. Geotechnical log­ In conclusion, the problems associated with water and
ging of the excavated surfaces in the trial length was overbreak in the marine drives and in particular the section
carried out with records of overbreak, water inflows, up to chainage km 24 can generally be attributed to the
number of joints and the volume of cavity grout injected open nature of the jointing within the rock mass i.e. gen­
being collected. A comparison of the ground conditions erally 2-\ mm. The degree of openness was particularly
through the unprobed length, extending between chainage pronounced where cover to sea-bed was less than 30 to 35
m 23251 and 23286, with that immediately before and m but was further aggravated by geological structure such
after, however, indicated that the drilling water pressures as the occurrence of faulting and folding. No major face
were not having a detrimental effect on the rock mass. collapses occurred on the marine drives.
The high water inflows entering the tunnel appeared to The ground conditions had a direct effect on progress in
be the result of more open jointing brought about by minor that:
flexuring and destressing of the chalk strata. Encountered
-6
permeabilities were generally above 1 0 m/s and hence (a) the wet conditions and broken ground caused prob­
this section of ground was subjected to grout pretreatment lems with spoil clogging up the TBM head, convey­
prior to entry of each running tunnel machine. ors, muckcars, bunkers etc.
The ground treatment was carried out by the injection of (b) the overbreak spoil had to be dug out by hand from
Silacsol T grout into three inclined holes, drilled sideways the build area invert and removed in small muck trays
from the service tunnel to the axis/crown area of each
running tunnel. Every other ring was drilled i.e. 3 m (c) the overbreak void behind the ring had to be firmly
3
spacing and some 80000 m of fissured chalk treated packed to hold the ring in shape prior to grouting
around a 3 m wide annulus. All relevant parameters were (d) in the marine running tunnels, curved aluminium for­
automatically monitored and logged. mer rings were introduced. These formers were se­
The work was commenced on 18th December 1989 and curely attached to adjacent plates of each ring and
was completed by 25th March 1990, immediately prior to helped minimise stepping at the radial joints by hold­
the arrival of each running tunnel boring machine. ing the ring until it was grouted (Fig. 14.16)
The task required the assembly of a large team of drillers
and grouters together with supervisory staff, totalling 92 (e) the amount of grout to be injected was substantially
in number. So as to maintain rail access and material increased and subsequent proof grouting made more
supply to other activities in the service tunnel, including difficult
the main TBM drive itself, the drilling and grouting was (f) more damage to the segments occurred during their
restricted to one side of the tunnel at a time, with the north erection and had to be repaired
side being completed first.
Little or no water was subsequently met when tunnelling (g) the wet saline conditions increased the incidence of
through this zone with both of the marine running tunnel plant breakdown
TBMs achieving better progress. (h) the general nuisance factor of working in wet condi­
This section of ground treatment is discussed fully in tions slowed down the operations and made it more
Chapter 16. difficult to complete repairs, clean up etc.

14.4.2.2 Chainage k m 23.4 to breakthrough Additional problems also arose due to the presence of a
Beyond chainage km 23.4, up to the end of the service thin layer of compacted remoulded material ('swarf usu­
tunnel drive at chainage km 41.6, tunnelling conditions ally 20 mm but up to 60 mm thick in places) representing
were consistently good to very good. Dry conditions or the subsequent degradation of minor overbreak falling
only minor inflows and intermittent overbreak was noted. down and being crushed behind the TBM shield. This
The low salinity of the incoming water, equivalent to the reconstituted material had to be removed by the miners
chemistry of the porewater held in the rocks i.e. using hand pneumatic spades as it emerged from behind

236

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

the shield into the b u i l d area b e f o r e the r i n g c o u l d b e


p l a c e d . O n o c c a s i o n , the p r e s e n c e o f this material in the
c r o w n area resulted in the d o w n w a r d d e f l e c t i o n o f the
installed f i n g e r s / h o o d a r r a n g e m e n t l e a d i n g to f u r t h e r p r o b ­
l e m s w i t h the r i n g b u i l d i n g . I n s u c h instances, s o m e o f the
trailing f i n g e r s had to b e t e m p o r a r i l y r e m o v e d s o as to
release the c o n s t r a i n e d m a t e r i a l e.g. c h a i n a g e m 2 7 7 9 7 in
Running Tunnel North.
I n v i e w o f the a b o v e , the t u n n e l r o u t e adjacent to the
F o s s e D a n g e a r d w a s m o d i f i e d to m a x i m i s e the a m o u n t o f
g r o u n d c o v e r existing a b o v e tunnel c r o w n . T h i s w a s
a c h i e v e d b y m o v i n g the a l i g n m e n t 90 m further n o r t h
t h e r e b y i n c r e a s i n g the m i n i m u m r o c k c o v e r f r o m 22 m to
28 m at c h a i n a g e k m 39, w h e r e a s u b s i d i a r y b u r i e d v a l l e y
associated w i t h the F o s s e crosses o v e r the t u n n e l . N o m a j o r
i n f l o w s o f w a t e r w e r e e n c o u n t e r e d t h r o u g h o u t this l e n g t h .
O n 30 O c t o b e r 1990, contact w a s m a d e w i t h the F r e n c h
T B M b y w a y o f a 56 m m d i a m e t e r p r o b e h o l e d r i l l e d f r o m
the face o f the U K s e r v i c e t u n n e l . F o l l o w i n g s u r v e y i n g o f
this p r o b e , the U K T B M w a s d r i v e n o f f o n a 300 m radius
h o r i z o n t a l c u r v e to a p o s i t i o n adjacent to the F r e n c h T B M ,
the final c o n n e c t i o n b e i n g m a d e b y w a y o f a short h a n d
d u g lateral h e a d i n g ( F i g . 14.17).
T h e historic b r e a k t h r o u g h ( F i g . 14.18) b e t w e e n the U K
and F r e n c h s e r v i c e tunnels o c c u r r e d o n 1 st D e c e m b e r 1990
at c h a i n a g e m 4 1 6 1 1 , s o m e 3 y e a r s a n d a l m o s t 22 k m after
the start o f the s e r v i c e t u n n e l d r i v e f r o m S h a k e s p e a r e C l i f f .
Figure 14.17 Junctioning between UK and French
C o n n e c t i o n b e t w e e n the U K a n d F r e n c h r u n n i n g tunnels
service tunnel TBMs.
o c c u r r e d at c h a i n a g e m 3 7 2 2 2 f o r the n o r t h tunnel o n 2 2 n d
M a y 1991 a n d c h a i n a g e m 38334 f o r the s o u t h t u n n e l o n
28th J u n e 1991. T h e U K T B M s h a d i n i t i a l l y b e e n d r i v e n
d o w n w a r d s o n a 300 m r a d i u s v e r t i c a l c u r v e w i t h g r o u n d
s u p p o r t b e i n g c a r r i e d out u s i n g t e m p o r a r y s e g m e n t s i n the
invert a n d shotcrete a n d fibreglass r o c k b o l t s in the c r o w n .
T h i s a l l o w e d the F r e n c h T B M to m a k e a f u l l face c o n n e c ­
t i o n , w i t h these T B M s b e i n g d r i v e n o v e r the t o p o f the
a b a n d o n e d U K m a c h i n e s ( F i g . 14.19).

14.5 UK land drives: encountered


tunnelling conditions
14.5.1 General
A l l three land t u n n e l s w e r e d r i v e n u p h i l l f r o m S h a k e s p e a r e
C l i f f o n a g r a d i e n t o f 1 in 91 ( F i g . 14.1). G r o u n d c o v e r
a b o v e the t u n n e l s o v e r m o s t o f the d r i v e r e m a i n e d o v e r 100
m but d e c r e a s e d b e y o n d c h a i n a g e k m 11.5 to g e n e r a l l y less
than 30 m as the t u n n e l s a p p r o a c h e d the S u g a r l o a f portal.
B e t w e e n c h a i n a g e k m s 12.2 a n d 11.5, the d r i v e s also
skirted c l o s e a n d i m m e d i a t e l y northeast o f the e s c a r p m e n t
edge.

14.5.2 Encountered ground conditions:


overview
F r o m S h a k e s p e a r e C l i f f to c h a i n a g e k m 13.8, g r o u n d
c o n d i t i o n s e n c o u n t e r e d b y the l a n d d r i v e s w e r e g o o d to
e x c e l l e n t , i.e. g e n e r a l l y d r y u n w e a t h e r e d C h a l k M a r l w i t h
o n l y occasional incidences o f block fallout along closed
joints. Figure 14.18 The breakthrough between the UK and
I n c i d e n c e s o f o v e r b r e a k a p p e a r e d to b e m o r e p r o m i n e n t French service tunnels.
o u t b y e o f c h a i n a g e k m 17, b e i n g c o n c e n t r a t e d at certain
sections, e.g. adjacent c h a i n a g e k m 18.3.
N o e v i d e n c e w a s o b s e r v e d to indicate the o c c u r r e n c e o f S e v e r a l m i n o r faults w e r e , h o w e v e r , o b s e r v e d a l o n g the
the L y d d e n F a u l t , an apparent w a t e r - b e a r i n g structure l e n g t h o f the d r i v e .
w h i c h s u p p o s e d l y cuts across the r o u t e adjacent to c h a i n - B e y o n d c h a i n a g e k m 13.8, all three tunnels e n c o u n t e r e d
age k m 16.5. F o r w a r d p r o b i n g w a s carried out in this area. m i x e d face g e o l o g y as first G l a u c o n i t i c M a r l a n d then

237

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

Sugarloaf
Portal * Inflow into build O inflow into face

11 12 13 14 15
chainage km

Figure 14.20 Ground conditions towards the end of the


Land Service Tunnel. Top: water inflow (l/min); bottom:
3
overbreak ( m ) .

14.5.2.2 Glauconitic Marl


The stronger, more massive, characteristics of this unit,
and in particular the cemented sandstones at its base, led
to large boulders which the TBM hopper/conveyor system
could not cope with. Such boulders were generally promi­
nent where the upper section of the face had collapsed due
Figure 14.19 Breakthrough sequence for both the north
to ravelling back of the underlying Gault Clay. Some
and south running tunnels. overbreak was also experienced in the build area due to the
friable, sandy nature of the Glauconitic Marl. The thick­
ness of the Glauconitic Marl was generally 2-2.5 m close
to the Sugarloaf portal, thickening eastwards to 3-4 m.
Gault Clay entered the face, as a consequence of an anti­
clinal fold centred at chainage km 13.1 and the north­
14.5.2.3 Gault Clay
eastward dip of the strata. Gault Clay, brought up into the
This weak, blocky, highly jointed and fissured calcareous
tunnels by this fold, was generally observed between
mudstone resulted in both overbreak and face collapse
chainage kms 13.4 and 12.8 where it disappeared only to
associated with failure along adversely orientated joints
reappear at chainage km 12.2, rapidly rising to axis level.
(Figs 14.22 and 14.23). Some of the joint surfaces were
Figures 14.20 and 14.21 inclusive illustrate the influence
slickensided. Joint sets included a subhorizontal set, a set
that the mixed face geology had on the land drives.
dipping steeply to the SSE (and less dominantly to the
The progress of all three tunnels was continually ham­
NNW) and a subvertical set dipping either ENE or WSW.
pered by difficulties associated with the blocky nature of
Other minor sets were sometimes present e.g. shallow
the encountered strata. Discontinuity data for the under­
30-45° dips to SSE. Conditions were particularly adverse
land section of tunnels is presented on Fig. 27.3. Problems
where the top of this unit was above or close to tunnel axis
associated with each geological unit are outlined below.
level and where minor water ingress was encountered.
Problems associated with minor heave in the build area
14.5.2.1 Chalk Marl were occasionally reported.
Weak jointed rock gave rise to overbreak in the crown and Table 14.6 presents a summary of the ground conditions
shoulder area above axis level. Overbreak became more encountered in the land tunnels as related to the chainage
frequent close to the edge of the escarpment and west of and geology.
the Canterbury Road where ground cover was low and the Overbreak in the crown and sidewalls again became a
rock weathered. regular occurrence as joints opened up and minor ingress

238

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

volume m

build overbreak ^ face collapse

4 - ' a-"

SUGARLOAF PORTAL
Crown

TUNNEL DRIVE

Invert
12 13 14 15

Chainage km

Figure 14.21 Land Running Tunnel North: overbreak and face collapse towards the end of the drive.

Figure 14.22 Blocky jointed nature of Gault Clay outcropping in excavations for cut-and-cover section further west of
Sugarloaf portal.

b e c a m e m o r e n o t i c e a b l e c l o s e to the e s c a r p m e n t e d g e . F a c e c o l l a p s e a l s o b e c a m e a r e g u l a r o c c u r r e n c e as m i n o r
F i n g e r s / h o o d a r r a n g e m e n t s installed at the start o f the i n f l o w s o f w a t e r lubricated ' g r e a s y b a c k s ' w i t h i n t h e G a u l t
d r i v e s h a d to restrain b l o c k f a l l o u t i n b o t h s e r v i c e t u n n e l 3
C l a y . T h i s , i n t u r n , g e n e r a t e d l a r g e 0.4 m s i z e d b o u l d e r s
( G a u l t C l a y / G l a u c o n i t i c M a r l ) a n d r u n n i n g tunnels ( g e n ­ o f g l a u c o n i t i c s a n d s t o n e w h i c h c o n s e q u e n t l y b l o c k e d the
erally Glauconitic M a r l / C h a l k Marl). T y p i c a l overbreak h e a d a n d c o n v e y o r s y s t e m a n d h a d to b e h a n d b r o k e n b y
patterns i n relation to the g e o l o g y a r e illustrated o n F i g . miners using pneumatic tools. T h e p r o b l e m s w e r e m o r e
14.23. a d v e r s e w h e r e the G a u l t l a y a b o v e a x i s l e v e l .

239

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

inspection of both the face and the ground surface imme­


diately behind the tunnel portal, it became clear that void
migration had developed upwards from the tunnel crown
to the ground surface 5-6 m higher.
A small hole appeared at the surface some 4 m back from
the portal shaft but enlarged quickly to some 8-10 m
diameter as attempts were made to bring the TBM into the
specially prepared shotcrete eye of the shaft. Inspection of
the ground at this location showed it to comprise com­
pletely of highly weathered Chalk Marl above the weak
and moderately weathered Glauconitic Marl close to
crown elevation. It appeared that the weakened and weath­
ered Glauconitic Marl was unable to span the full tunnel
diameter when the head was pulled back and once this had
failed, there was negligible resistance to continued upward
migration of the void through the weathered Chalk Marl
0 1 2 3 4 5 to the ground surface.
' * • » < i m Straw bales and grout were used to stabilise the area prior
(a) to completing the final few metres of the TBM drive after
3
which the hole was then backfilled with 46 m of concrete
and fully grouted.
To prevent similar problems recurring during break­
through of both running tunnel TBMs, 20 m long entry
chambers were constructed back into the main hillside
using NATM techniques. These extended back from the
portal shafts to a position where both cover and rock
quality was considered adequate.
Steps were also taken to exclude the minor amounts of
water and improve the stability of the ground beyond the
end of the chamber by drilling and grouting from each
headwall. A protective hood was formed over the crown
of each tunnel, consisting of 30 m long 75 mm diameter
0 1 2 3 4 5 holes, through which cementitious grout was injected.
Although the service tunnel had successfully traversed
through the ground over the length where low cover ex­
(b)
isted, the fact that its crown was some 3 m lower meant
Figure 14.23 (a) Land Running Tunnel: typical face
that the nature and quality of the Chalk Marl to be encoun­
failure; (b) Land Service Tunnel: typical build overbreak.
tered in the roof of both running tunnels remained un­
known. Hence, cored sideprobes were drilled from the
service tunnel inbye chainage km 11.8 across to the crown
area to investigate the permeability and rock mass charac­
Particular problems were experienced during break­ teristics (weathered state, degree of fracturing etc.) of the
through of the service tunnel into the portal shaft at chain- Chalk Marl. These holes did indeed indicate the Chalk
age m 11148 due to the low amount of cover above the Marl to be weathered although rock mass permeabilities
7

tunnel crown i.e. 6 m. were low i.e. less than 1 Lugeon (approx. 10~ m/s).
On the day shift of 3/11/89, at chainage m 11155, close On the basis of this information and taking account of the
to the breakout following the building of 4 No. cast iron difficulties experienced in the service tunnel, even with
rings, it was found that the TBM head would not turn. A minor amounts of water, a decision was taken to employ
collapse of Gault Clay had occurred at the face and as the ground treatment over the last 0.7 km of each running
head was pulled back to remove this material, the roof of tunnel drive. Holes were thus drilled from the adjacent
Gault Clay with Glauconitic Marl immediately above it service tunnel in advance of the running tunnels and ce­
continued to fall in. ment grouted using controlled pressures up to 18 bar (the
The first ring built on that shift i.e. Ring 5237 had to be maximum overburden pressure) and claquage techniques
taken down in order that the TBM could back off from the so as to penetrate the fine fissures (see Chapter 16).
face. The process of pushing and pulling the TBM back­ The ground conditions encountered in the south running
ward and forward permitted further overbreak in the build tunnel were similar to those met in the north tunnel, albeit
area above Ring 5238. The head was eventually cleared slightly improved towards the Sugarloaf breakout as a
and pushed forward. Approximately 1-2 m of overbreak 3
consequence of the increased ground cover and less weath­
was dug out of the invert and Ring 5238 completed on the ered and fractured state of the rock.
backshift.
Although the head could turn, the hoppers again became
blocked with the spoil and the TBM was unable to cut. 14.6 Review of encountered geology and
During the back and nightshift this was cleared and the tunnelling conditions
head was able to cut and two Rings were built i.e. Rings Of particular interest is the extent to which the encountered
5239 and 5240. During the cut two trainloads of skips were geology and tunnelling conditions were as predicted. The
required for one metre of face advance. Following an subject is further discussed in Chapters 29, 31 and 32.

240

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

Table 14.6 Summary of observed overbreak and water inflow

Tunnel section Geological provenance Overbreak/face failures (m )3


Water (l/min)

Build Face Build Face

Land Service Tunnel


Ch 1907^13800 Chalk M a r l ; fresh rock; A v e . 0.04 m (424 3
Actual Actual Actual
high cover records) Negligible (42 D r y (424 records) D r y (42 records)
3
65 records > 0.1 m records
overbreak Max.
Max. 3
0.1 m C h 17385
3
1.0 m C h 18550
3
0.9 m C h 18598
3
0.6 m C h 17997
3
0.6 m C h 16389
3
0.6 m C h 16387

C h 13800-12800 M i x e d face o f Chalk A v e . 0.07 nr> (39 A v e . 0.1 m (5 3


A v e . < 0.01 l/min A v e . < 0.01 l/min
M a r l ; Glauconitic M a r l records) records) (39 records) (5 records)
and Gault; anticlinal Max. M a x . 0.5 m 3
Max. 0.04 l/min Max.
fold; fresh rock; high 3
0.25 m C h 13017 C h 13186 C h 13288 and 0.02 l/min
cover 3
0.6 m C h 13175 (elsewhere = nil) C h 13290 C h 13186
3
0.35 m C h 13288 0.02 l/min C h 13210,
3
0.22 m C h 13290 C h 13211,
3
0.30 m C h 13334 C h 13228 and
C h 13230

C h 12800-12200 M i x e d face o f Chalk A v e . 0.03 m ( 1 5 J


Actual (2 records) Actual A v e . 0.05 l/min
M a r l and Glauconitic records) N i l C h 12245 D r y (15 records) (2 records)
M a r l ; fresh rock; high Max. N i l C h 12712 Actual
cover 3
0.2 m C h 12260 0.1 l/min C h 12245
3
0.03 m C h 12497 D r y C h 12712
3
0.03 m C h 12499
3
0.04 m C h 12500
3
0.03 m C h 12727
3
0.03 m C h 12789

C h 12200-11500 M i x e d face o f A v e . 0.21 m (63 3


A v e . 0.08 m A v e . 0.17 l/min 3
A v e . 0.25 l/min
Glauconitic M a r l and records) (12 records) (63 records) (12 records)
Gault; fresh rock; close Max. Max. Max. Max.
to escarpment edge; 0.6 n r C h 11623
3
0.35 m C h 11690 3 l/min C h 11591
3
0.5 l/min C h 11625
high c o v e r 3
1.4 m C h 11705
3
0.5 m C h 11696 3 l/min C h 11751 1.5 l/min C h 11690
3
1.0 m C h 11741 0.14 m C h 11886 3
1 l/min C h 11566, D r y C h 11696
3
1.0 m C h 11751 0.02 m C h 12040 3
11653, 11675, 0.8 l/min C h 11886
0.65 m C h 119633
11676, 11697 0.06 l/min C h 12040
0.64 m C h 119643
(elsewhere = nil)
3
1.0 m C h 11978

C h 11500-11147 M i x e d face o f A v e . 0.25 A v e . 0.03 m 3


A v e . 0.4 l/min A v e . 2.34 l/min
(Sugarloaf Portal) Glauconitic M a r l and (41 records) (3 records) (41 records) (3 records)
Gault; weathered rock; Max. Actual Max. Actual
shallow cover 3
0.5 m C h 11167
3
0.1 m C h 11170 5 l/min C h 11184 0.02 l/min C h 11170
3
1.1 m C h 11185 N i l C h 11188 3 l/min C h 11185 2 l/min C h 11188
3
0.5 m C h 11211 N i l C h 11244 1 l/min C h 11240 5 l/min C h 11244
3
1.6 m C h 11240 ( N B Collapse at 5 l/min C h 11271
3
0.7 m C h 11250 Sugarloaf not 0.4 l/min C h 11283
3
0.5 m C h 11264 included)
3
1.2 m C h 11271

14.6.1 Land tunnels 14.6.2 Marine tunnels


T h e o v e r a l l conditions in the land tunnels w e r e in general I n r e s p e c t o f t h e m a r i n e t u n n e l s , the f o l l o w i n g is o f r e l e ­
as p r e d i c t e d , albeit m o r e o n e r o u s t o w a r d s the e n d o f t h e vance.
d r i v e c l o s e t o t h e e s c a r p m e n t e d g e w h e r e the t u n n e l s W a t e r i n f l o w s as e x p e r i e n c e d w e r e g e n e r a l l y i n a g r e e m e n t
e n c o u n t e r e d a m i x e d face g e o l o g y (i.e. C h a l k M a r l / G l a u - w i t h those predicted o n the basis o f the b o r e h o l e i n f o r m a t i o n
7 - 6
conitic M a r l / G a u l t C l a y ) . i.e. permeabilities r a n g i n g from 10~ to 1 0 m / s . E n h a n c e d
O t h e r w i s e , d r y tunnelling conditions p r e v a i l e d w i t h i n the i n f l o w s w e r e e x p e r i e n c e d w h e r e the g r o u n d c o v e r a b o v e
Chalk M a r l with minor overbreak. tunnel c r o w n to sea-bed w a s l i m i t e d (particularly w h e r e the

241

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

Table 14.6 (cont.)

3
Tunnel section Geological provenance Overbreak/face failures (m ) Water (l/min)

Build Face Build Face

Land Running Tunnel North


3
C h 19069-13800 Chalk M a r l ; fresh rock; A v e . 0.1 m Actual Actual Actual
high cover (125 records) 0.14 m 3

D r y (125 records) D r y (19 records)


3
34 records > 0.1 m (19 records) Max.
overbreak Max. 0.1 l/min C h 15903
Max. 3
0.6 m C h 19005
0.5 C h 18831 3
2.0 m C h 18791
0.9 C h 18324
0.6 C h 18333 (elsewhere =
0.9 C h 17994 negligible)
1.0 C h 16645
0.6 C h 14224

3
C h 13800-12800 M i x e d face o f Chalk A v e . 0.06 m (36 A v e . 0.01 m 3
Actual Actual
M a r l ; Glauconitic M a r l records) (2 records) D r y (36 records) D r y (19 records)
and Gault; anticlinal Max. Actual Max.
fold; fresh rock; high 0.11 m C h 3
13016 3
0.02 m C h 13328 0.1 l/min C h 15903
cover 0.1 m C h 3
13017 N i l C h 13715
3
0.1m Ch 13031
3
0.1 m C h 13032
3
0.3 m C h 13196
3
0.22 m C h 13232
3
0.3 m C h 13243
3
0.12 m C h 13327

-3
C h 12800-12200 M i x e d face o f Chalk A v e . 0.05 m (11 N o records A v e . < 0.01 l/min N o records
M a r l and Glauconitic records) (11 records)
M a r l ; fresh rock; high Max. Max.
cover 3
0.03 m C h 12207, 0.1 l/min C h 12205
12408, 12705 0.01 l/min C h 12707
3
0.05 m C h 12360
3
0.06 m C h 12661 (elsewhere = dry)
3
0.2 m C h 12662
3
0.05 m C h 12707

3
C h 12200-11500 M i x e d face o f Chalk A v e . 0.31 m (54 A v e . 0.23 m 3
A v e . < 0.02 l/min A v e . 0.31 l/min
M a r l ; Glauconitic M a r l records) (5 records) (54 records) (5 records)
and Gault; fresh rock; Max. Actual Max. Actual
3
close to escarpment 0.84 m C h 11578 3
> 3 . 0 m C h 11552 0.2 l/min C h 11501 D r y C h 11552
3
edge; high cover 0.73 m C h 11681 3
0.84 m C h 11609 0.3 l/min C h 11548 0.02 l/min C h 11609
3
1.4 m C h 11682 3
2.0 m C h 11624 0.1 l/min C h 11578 0.511/rninCh 11624
3
0.82 m C h 11702 3
0.22 m C h 11696 0.5 l/min C h 11811 1 l/min C h 11696
3
0.75 m C h 11705 3
0.08 m C h 12055 0.04 l/min C h 12010 0.03 l/min C h 12055
3
1.0 m C h 11717 (elsewhere < 0.04
3
0.8 m C h 11765 l/min)

3
C h 11500-11167 M i x e d face o f Chalk A v e . 0.29 m Actual A v e . 0.09 l/min Actual
M a r l ; Glauconitic M a r l (23 records) 0.02 m C h 11296 (23 records) 3
0.1 l/min C h 11296
and Gault; weathered Max. Max.
rock; shallow cover 1.0-1.5 m 3
0.2 l/min C h 11192
C h 11191 0.5 l/min C h 11218
3
0.6 m C h 11212 0.02 l/min C h 11228
3
0.35 m C h 11228 0.02 l/min C h 11289
3
0.40 m C h 11403 0.5 l/min C h 11269
3
0.4 m C h 11409 0.1 l/min C h 11271

tunnel w a s close to the top o f the C h a l k M a r l ) o r w h e r e d r i l l e d in 1986 a n d 1988 as part o f this p r o j e c t , a d o p t e d


p r e v a i l i n g g e o l o g i c a l structure existed. m u c h s h o r t e n e d test lengths (i.e. 4 - 5 m ) e n a b l i n g a better
E v e n o v e r the s h a l l o w c o v e r s e c t i o n , p r e c i s e d e t e r m i n a ­ u n d e r s t a n d i n g o f the p e r m e a b i l i t y p r o f i l e w i t h d e p t h b e l o w
t i o n o f e x p e c t e d w a t e r i n g r e s s w a s d i f f i c u l t as a c o n s e ­ sea-bed.
q u e n c e o f the l o n g p e r m e a b i l i t y test lengths (i.e. 1 5 - 3 0 m ) T h e salinity o f the i n c o m i n g waters entering the tunnel w a s
a d o p t e d in the p r e - 1 9 8 6 b o r e h o l e s . S u b s e q u e n t b o r e h o l e s , as e x p e c t e d , the t i m e taken to revert to seawater being influ-

242

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.
UK TUNNELS: GEOTECHNICAL MONITORING

Table 14.6 (cont.)

Tunnel section Geological provenance Overbreak/face failures 3


(m ) Water (l/min)

Build Face Build Face

Land Running Tunnel South


C h 19004-13800 Chalk M a r l ; fresh rock; A v e . 0.06 m 3
Actual Actual Actual
high cover (93 records) Negligible D r y (93 records) D r y (6 records)
24 records > 0.1 m 3
(6 records)
overbreak
Max.
3
0.5 m C h 17176
3
0.5 m C h 16045

C h 13800-12800 M i x e d face o f Chalk Ave. 0.14m J


N o records A v e . < 0.01 l/min N o records
M a r l ; Glauconitic M a r l (29 records) (29 records)
and Gault; anticlinal Max. Max.
fold; fresh rock; high
3
0.25 m C h 12993 0.01 l/min C h
cover
3
0.39 m C h 13245 13263, 13328,
3
0.25 m C h 13283 13330, 13476
3
0.46 m C h 13292
3
0.5 m C h 13294 (elsewhere = d r y )
3
0.25 m C h 13330
3
0.3 m C h 13454

C h 12800-12200 M i x e d face o f Chalk A v e . 0.03 m J


N o records Actual N o records
M a r l and Glauconitic (6 records) D r y (6 records)
M a r l ; fresh rock; high Max.
3
cover 0.02 m C h 12267
3
0.03 m C h 12269
3
0.04 m C h 12270
3
0.04 m C h 12572
3
0.04 m C h 12876

C h 12200-11500 M i x e d face o f Chalk A v e . 0.27 m J


A v e . 1.74 m A v e . 0.01 l/min A v e . 0.31 l/min
M a r l ; Glauconitic M a r l (22 records) (3 records) (22 records) (3 records)
and Gault; fresh rock; Max. Actual Max. Actual
close to escarpment 3
0.63 m C h 11500 3
3.5 m C h 11724 0.1 l/min C h 12130 D r y C h 11724
edge; high cover 0.55 m ^ C h 11777 1 . 7 m C h 11981 0.02 l/min C h
J
0.1 l/min C h 11981
3
0.45 m C h 12009 3
0.01 m C h 12197 11500, 11630, D r y C h 12197
3
0.55 m C h 12183 11632, 11777
3
0.35 m C h 12184 (elsewhere = d r y )

C h 11500-11147 M i x e d face o f Chalk A v e . 0.45 nr N o records


3
A v e . 0.23 l/min N o records
(Sugarloaf Portal) M a r l ; Glauconitic M a r l (7 records) (7 records)
and Gault; weathered Max. Max.
rock; shallow cover 3
0.4 m C h 11186 0.04 l/min C h 11185
3
0.6 m C h 11261 0.04 l/min C h 11186
3
0.7 m C h 11439 0.5 l/min C h 11261
3
0.29 m C h 11450 1.0 l/min C h 11304
3
0.64 m C h 11498 0.5 l/min C h 11498

enced by the pre-existing groundwater chemistry and the largely depends on one's viewpoint with regard to prece­
permeability profile to sea-bed. In areas of high permeabil­ dent experience (e.g. 1974-75 experience at Shakespeare
ity (e.g. the shallow cover section) the change was very Cliff and Sangatte etc.).
rapid (i.e. within less than a day) as compared to the low Despite all of the problems encountered it is a credit to
8
permeability areas <10~ m/s where the change could take the miners and the ingenuity of contractors and designers
several years. alike in overcoming the many difficulties encountered in
Regarding the prediction of overbreak, including its ex­ the tunnelling works thereby enabling the drives to be
tent, this was a more difficult problem to address as it completed on schedule.

243

Downloaded by [ University of Liverpool] on [15/09/16]. Copyright © ICE Publishing, all rights reserved.

You might also like