MINUTES OF MEETING
Ite Discussion - Action Items Responsibility Due Status
m Date
No.
1 SAFETY
MONTH Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17
PSI 92.71
92.71% 93.93% 91.00% 93.36% 92.57% 92.74% 92.65% 91.99% 93.76% 94.63%
SCORE %
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
Reporting Period
Manpower
Manpower
Man- Man-
Man- Man-
Hours Hours
Ind
Dir
2 of 12
2 of 12
2 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
3 of 12
3 of 12
3 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
4 of 12
4 of 12
4 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
Doc Date
Description Area Status
# Submitted
5 of 12
5 of 12
5 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
6 of 12
6 of 12
6 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
1.9 PMT asked for Safety barrication for the open Arkad Open
trenches to avoid any incident.
2 PROJECT CONTROL
7 of 12
7 of 12
7 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
2.1
Actual/Forecas
Milestone Plan
t
Engineering & Procurement
Establish Design Site Office and Facilities 16-Dec-15 16-Dec-15A
Detail Design Kick-off Meeting 16-Dec-15 18-Dec-15A
Provide Document Control Index (DCI) 16-Mar-16 16-Mar-16A
Complete 30% Detailed Engineering Design 01-Mar-16 16-Mar-16A
Complete Issued For Construction Drawings for Civil Works 31-Mar-16 11-Jun-16A
Complete the Alignment Sheet and Right of Way Construction 30-Apr-16 18-Jun-16A
Complete 60% Detailed Engineering Design 28-Jun-16 30-Jun-16A
Complete 90% Detailed Engineering Design 20-Nov-16 16-Feb-17A
Complete P.O. Placement for all Major Items 06-July-16 18-Jan-17A
Complete P.O. Placement for all Other Materials 22-Aug-16 28-Jan-18
Complete Issued For Construction (IFC) Drawings 31-Oct-16 30-Jan-18
Construction
Construction Kick-off meeting 31-May-16 31-May-16A
8 of 12
8 of 12
8 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
9 of 12
9 of 12
9 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
2.2
AREA B MANPOWER
10 of 12
10 of 12
10 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
11 of 12
11 of 12
11 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
3 QUALITY CONTROL
3.1
P. Q. I
12 of 12
12 of 12
12 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
13 of 12
13 of 12
13 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
3.3 Concrete Mix Design- Saudi Ready-Mix None Dec 10, Closed
design intended for Rabigh has been 2017
approved.
14 of 12
14 of 12
14 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
15 of 12
15 of 12
15 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
3.6 SAPMT raised a concern regarding the progress of weld repair joints on the mainline.
Request contractor to add summary of repair status in this minutes.
16 of 12
16 of 12
16 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
17 of 12
17 of 12
17 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
18 of 12
18 of 12
18 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
19 of 12
19 of 12
19 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
20 of 12
20 of 12
20 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
4 CONSTRUCTION
4.1
Varianc
Activity UOM Plan Actual
e
Access Road KM 137.55 157.65 20.10
SAPMT will check for the no. of PMCC to hand PMT Open
over the access road to operation
21 of 12
21 of 12
21 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
4.2
Varianc
Activity UOM Plan Actual
e
FJC Jt 2,532.00 2,122.00 -410.00
4.3
Varianc
Activity UOM Plan Actual
e
Trenching KM 54.68 26.87 -27.81
22 of 12
22 of 12
22 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
4.4
Varianc
Activity UOM Plan Actual
e
Pipe lowering KM 41.31 9.65 -31.66
Arkad to expedite the rock breaking activity to Arkad Dec 31, Open
accelerate the pipe lowering. 2017
23 of 12
23 of 12
23 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
4.5
Varianc
Activity UOM Plan Actual
e
Tie-In KM 33.60 0.00 -33.60
4.6
Varianc
Activity UOM Plan Actual
e
Concrete pre-cast M3 1,097.28 595.00 -502.28
24 of 12
24 of 12
24 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
4.7
Varianc
Activity UOM Plan Actual
e
Steel Structure Fab Ton 86.64 85.74 -0.90
4.8
Road Pipe
Detour Restoratio
Crossing cutting & Lowering & Removing of detour
road n of Road
Trenching Backfill
STA-357+215 23-Oct-17 26-Oct-17 28-Oct-17 2-Dec-17 19-Dec- 2017
STA-345+399 4-Oct-17 10-Oct-17 12-Oct-17 17-Oct-17 13-Nov-17
STA-284+063
25 of 12
25 of 12
25 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
STA-218+570
19-Dec-
STA -217+285 17
STA -184+
4.9 SAPMT Pointed that Shoulder blinkers for Dec 30, Open
crossings Km 345 are not restored 2017
Arkad to re-instate the blinkers Arkad
Next Progress Meeting: Jan 08th , 2018, 01 : 00PM to be held@ SAPMT-THARB Conference Room.
26 of 12
26 of 12
26 of 12
MGS PIPELINE PHASE II, PACKAGES 01,
WESTERN REGION PIPELINE PROJECT AREA B
CONTRACT NO. 6600036451 / BI10-01810-002
Weekly Construction Progress Meeting
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
MINUTES OF MEETING
Item Discussion - Action Items Responsibility Due Status
No. Date
27 of 12
27 of 12
27 of 12