Professional Documents
Culture Documents
110401542
1. Earthmoving Materials
and Operations
Dr. Khaled Hyari
Department of Civil Engineering
Hashemite University
Earthmoving
١
Earthmoving II
• Earthmoving Management:
– Accurate estimating of work quantities and job
conditions
– Proper selection of equipment
– Competent job management
• Equipment Selection:
– What are the factors that affect equipment
selection?
1-٣
Earthmoving III
1-٤
٢
Production of Earthmoving Equipment
1-٥
1-٦
٣
Production of Earthmoving Equipment III
1-٧
• Example:
A loader cycle time for loading a truck is
12 minutes. Each load is 3 m3 . Estimate
loader production assuming poor job
conditions and fair management
conditions
1-٨
٤
Production of Earthmoving Equipment V
• Solution:
1-٩
Earthmoving Materials
• Soil and rock are the materials that make up the
crust of the earth
٥
Soil Volume-Change Characteristics
• Soil Conditions
– Bank: Material in its natural state before
disturbance (in place)
• Unit volume is Bank Cubic Meter (BCM)
1 - ١٢
٦
Soil Volume-Change Characteristics III
Example 2-1
1 - ١٤
٧
Soil Volume-Change Characteristics V
Example 2-2
• Find the shrinkage of a soil that weights
1661 kg/m3 in its natural state and 2077
kg/m3 after compaction
1 - ١٦
٨
Soil Volume-Change Characteristics VII
It means that:
1 - ١٧
• Load factor
– Used to convert loose volume to bank
volume
1 - ١٨
٩
Soil Volume-Change Characteristics IX
• Shrinkage factor
– Converts bank volume to compacted
volume
1 - ١٩
Example
• A soil weights 1163 kg/LCM, 1661
kg/BCM, and 2077 kg/CCM
1 - ٢٠
١٠
Soil Volume-Change Characteristics XI
Solution
1 - ٢١
1 - ٢٢
١١
Soil Volume-Change Characteristics XIII
• Problem 8
A soil weights 1483 kg/m3 loose, 1839
kg/m3 in its natural state, and 2106 kg/m3
compacted. Find the soil’s load factor and
shrinkage factor
1 - ٢٣
Solution
Load factor = weight in loose unit volume
weight in bank unit volume
١٢
Spoil Banks
Spoil Banks II
• Angle of repose: Is the angle that the sides of a
spoil bank or pile naturally form with the
horizontal when the excavated soil is dumped
onto the pile
–Represents the equilibrium position of the soil
–Varies with the soil’s physical characteristics
and its moisture content
1 - ٢٦
١٣
Spoil Banks III
1 - ٢٧
Spoil Banks IV
١٤
Spoil Banks V
• Example:
Find the base width and height of a
triangular spoil bank containing 76.5 BCM
if the pile length is 9.14 m, the soil’s angle
of repose is 37°, and its swell is 25%
1 - ٢٩
Spoil Banks VI
Solution:
1 - ٣٠
١٥
Spoil Banks VII
• Example:
Find the base diameter and height of a
conical spoil pile that will contain 76.5
BCM of excavation if the soil’s angle of
repose is 32 and its swell is 12%
1 - ٣١
Solution:
١٦
Estimating Earthwork Volume
1 - ٣٣
• Pit Excavation:
– Volume = Horizontal Area of Excavation x
Average Depth of Excavation
Example 2-6:
Estimate the volume of excavation required (bank
measure) for the basement shown below
7.63 m
1.8 m 2.3 m
1 - ٣٤
١٧
Estimating Earthwork Volume III
Solution:
=146.6 BCM
1 - ٣٥
• Trench Excavation
– Volume = Cross-Sectional Area x Length of
the Trench
Example 2-7:
Find the volume (bank measure) of
excavation required for a trench 0.92 m
wide, 1.83 m deep and 152 m long
1 - ٣٦
١٨
Estimating Earthwork Volume V
Solution:
= 255 BCM
1 - ٣٧
• Large Areas:
– Divide the large area into a grid
– Indicate the depth of excavation or fill at each
grid intersection
– Assign the depth at each corner or segment
intersection a weight according to its location:
• 1 for corner points
• 2 for border points (intersection of 2
segments)
• 4 for interior points (intersection of 4
segments)
1 - ٣٨
١٩
Estimating Earthwork Volume VII
1 - ٣٩
2 - ٤٠
٢٠
Estimating Earthwork Volume IX
Solution:
Sum of weights = 4 + 10 × 2 + 6 × 4 = 48
1 - ٤١
1 - ٤٢
٢١
Estimating Earthwork Volume XI
1 - ٤٣
B = [ 4 V ÷ (L × tan R) ]1/2
= 3.8 m
H = (B × tan R ) ÷ 2
= (3.8 × tan 32 ) ÷ 2
= 1.19 m
1 - ٤٤
٢٢
Estimating Earthwork Volume XIII
• Example
A ditch having a cross-sectional area of
4.6 m2 is being excavated in common
earth. The soil’s angle of repose is 35° and
its swell is 25%. Find the height and width
of the spoil bank that will result from trench
excavation
1 - ٤٥
• Solution:
= 5.73 m
1 - ٤٦
٢٣
Mass Diagram
1 - ٤٧
Mass Diagram II
Typical Mass Diagram
1 - ٤٨
٢٤
Mass Diagram III
• Characteristics:
– The vertical coordinate of the mass diagram represents
the cumulative earthwork volume from the origin to that
point
– Within a cut, the curve rises from left to right
– Within a fill, the curve falls from left to right
– A peak on the curve represents a point where the
earthwork changes from cut to fill
– A Valley (low point) represents a point where the
earthwork changes from fill to cut
– When a horizontal line intersects the curve at two or more
points, the accumulated volumes at these points are
equal. (Balance Line)
1 - ٤٩
Mass Diagram IV
1 - ٥٠
٢٥
Mass Diagram V
Construction Use of a Mass Diagram
This image cannot currently be display ed.
1 - ٥١
Mass Diagram VI
٢٦
Mass Diagram VII
– Repeat this process for sections 2,3, and 4
– Since the mass diagram has a negative value
from point D to the end, the ordinate at point E
represents the volume of material that needs to
be borrowed (38,230 BCM)
– Average haul distance within a balanced section
is approximately the length of the horizontal line
located midway between the balance line and the
turning point of the section (For section 1, length
of line FG = 549 meters)
1 - ٥٣
٢٧