You are on page 1of 23

Generators

Protection and switching

© ABB
Generators protection and switching

 The need to guarantee continuity of service increase the use of emergency


supply generators, as an alternative to, or in parallel with the public utility
supply network.

 Typical configurations include:


 Island supply to supply the priority loads in the case of a lack of energy of
the public network;
 Supply to the user installation in parallel with the public supply network.

© ABB
Generators protection and switching

 In case of a short-circuit, the current supplied by the generator is a function


of the parameters of the machine itself, and decreases with time; it is
possible to identify the following successive phases:

 Subtransient phase: with a brief duration (10÷50 ms), characterized by the


subtransient reactance X”d (5÷20% of the rated impedance value), and by
the subtransient time constant T”d (5÷30 ms);

© ABB
Generators protection and switching

Transitory phase: may last up to some seconds (0.5÷2.5 s), and is


characterized by the transitory reactance X’d (15÷40% of the rated
impedance value), and by the transitory time constant T’d (0.03÷2.5 s);

Synchronous phase: may persist until the tripping of external protection,


and is characterized by the synchronous reactance Xd (80÷300% of the
rated impedance value).

© ABB
Generators protection and switching

© ABB
Generators protection and switching

As a first approximation, it can be estimated that the maximum value of


the short-circuit current of a generator Ikg, with rated power Srg, at the
rated voltage of the installation Ur, is equal to:

Where Irg is the rated current of the generator:

© ABB
Generators protection and switching

 The circuit-breaker for the protection of the generator shall be selected


according to the following criteria:

 The set current higher than the rated current of the generator:
I1 ≥ Irg

 Breaking capacity Icu or Ics higher than the maximum value of short-
circuit current at the installation point.

© ABB
Generators protection and switching

 In the case of a single generator: Icu(Ics) ≥ Ikg;


 In the case of n identical generators in parallel: Icu(Ics) ≥ Ikg·(n-1);

© ABB
Generators protection and switching

 In the case of operation in parallel with the network: Icu(Ics) ≥ IkNet, as


the short-circuit contribution from the network is normally greater than the
contribution from the generator.

© ABB
Generators protection and switching

For circuit-breakers with thermomagnetic releases:

Low magnetic trip threshold I3 =2.5/3*In

Frames: XT2 160A, XT3 250A, T5 630A

TMG XT2 In min. 16A max. 160A (I3=3*In)


XT3 In min. 63A max. 250A (I3=3*In)
T5 In min. 320A max. 500A (I3=2.5/5*In)

© ABB
Generators protection and switching

For circuit-breakers with electronic releases:

Ekip G

Frames: XT2 160A, XT4 250A,

Ekip G-LS/I XT2 In min. 10A max. 160A


XT4 In min. 40A max. 250A

© ABB
Generators protection and switching

 For circuit-breakers with electronic releases:


 Trip threshold of the delayed short-circuit protection function (S), set
between 1.5 and 3/4 times the rated current of the generator, according to
the decrement curve of the generator:

I2 = (1.5÷3/4)*Irg

 If the function S is not present, function I can be set at the indicated values:

I3 = (1.5÷3/4)*Irg

© ABB
Generators protection and switching
 Trip threshold of the instantaneous short-circuit protection function (I3)
set at a value greater than the rated short-circuit current of the
generator, so as to achieve discrimination with the devices installed
downstream.

Tripping S function

Selectivity

© ABB
Generators protection and switching
 Example:
 Protection of a generator with Srg = 100 kVA, system with a rated voltage of 440 V.
 Generator parameters:
 Ur = 440 V
 Srg = 100 kVA
 f = 50 Hz
 Irg = 131.2 A
 X’’d = 6.5 % (subtransient reactance)
 X’d = 17.6 % (transient reactance)
 Xd = 230 % (synchronous reactance)
 T’’d = 5.5 ms (subtransient time constant)
 T’d = 39.3 ms (transient time constant)
 From table 2, an SACE Tmax XT2N160 circuit-breaker is selected
© ABB
Generators protection and switching

© ABB
Generators protection and switching

From table 2, an SACE Tmax XT2N160 circuit-breaker is selected,


with In = 160 A, with electronic trip unit Ekip G LS/I.

For correct protection of the generator, following settings are selected:

 Function L: 0.84 – 3s, corresponding to 134.4 A, value greater than


Irg =132 A, according to the formula:

 Function I: 1.5 = 240 A

© ABB
Generators protection and switching

© ABB
Generators protection and switching

© ABB
Generators protection and switching

Generators protection with Ekip G


 Ekip G trip units for SACE Emax 2 provide specific generator protection
functions that are currently provided by an external relay

 The level of accuracy and reliability offered by the Ekip G protections is


comparable or better to the offerings of external relays for generator
protection
Benefits of the Ekip G integrated version over the external relay version include:

 Elimination of external current transformer and voltage transformer

 Reduction of wiring (eliminates time and potential for errors)

 Space saving (size of column, optimization of busbar)

 Ease of installation, testing and set up

 Increased measurement, communication and signaling capabilities

 Simplicity in navigation and troubleshooting

© ABB
Generators protection and switching
Generators protection with Ekip G
Measuring Pro

 Two versions are available and cover the complete series of SACE Emax 2
(E1.2 - E6.2):
 Ekip G Touch LSIG

 Ekip G Hi-Touch LSIG (enhanced protection functions)

 Range of typical electrical parameters:


 400V up to 690V and 250A up to 6300A

 Corresponding to generator power of 170kVA up to 7,5MVA

© ABB
Generator protection with Ekip G

Synchrocheck Module
 Available for SACE Emax 2 with Ekip G trip units
plus the Ekip Measuring Pro Module

 Enables control of the synchronism condition for


placing two lines in parallel

 Monitors the difference between the voltage, phase


and frequency of two systems. When the
synchronism conditions meet the set values​​, the
module enables the circuit-breaker to be closed.
Consent is provided through a contact that can be
integrated into the control circuit for the main
breaker

 Operates by monitoring the status of two busbars;


one directly trough the Ekip Measuring Pro Module,
the other to the single-phase VT signal

© ABB
Generator protection with Ekip G

Synchrocheck Module
Active busbar configuration
 Connection of two active systems, for
example:
 Connection of a generator on a
busbar fed by the low voltage
distribution network

© ABB

You might also like