HOJA DE METRADOS
1-ESTRUCTURAS

SALA DE TEÑIDOS - BAÑOS

UBICACIÓN: DIST. SAN JERONIMO, PROV. CUSCO, DPTO. Cusco


ABERTURA O DESCUENTOS
ITEM Y DESCRIPCION
CANT L A H SUB-TOT CANT CLASEL A H SUB TOT

02.00.MOVIMIENTO DE TIERRAS
02.01 EXCAVACION PARA CIMIENTOS-ZAPATAS EN TERRENO NORMAL

EJE 1,2 2.00 5.80 0.40 0.50 2.32 2.00 P-1 0.80 0.40 0.50 0.32
4.00 2.85 0.40 0.50 2.28 1.00 P-2 0.90 0.40 0.50 0.18

suma 4.60 suma 0.50

02.03.ELIMINACION DE MATERIAL EXEDENTE


1.25
03.00.CONCRETO SIMPLE
03.01.SOLADO E=10CM
EJE 1,2 2.00 5.80 0.40 4.64 2.00 P-1 0.80 0.40 0.50 0.32
4.00 2.85 0.40 4.56

suma 9.20 suma 0.32

03.02.CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON ,30% PIEDRA


EJE 1,2 2.00 5.80 0.40 0.50 2.32 2.00 P-1 0.80 0.40 0.50 0.32
4.00 2.85 0.40 0.50 2.28 1.00 P-2 0.90 0.40 0.50 0.18

suma 4.60 suma 0.50

03.03.ENCOFRADO Y DESENCOFRADO SOBRECIMIENTO


EJE 1,2 2.00 5.80 0.50 11.60 2.00 P-1 0.80 0.50 1.60
4.00 2.85 0.50 11.40 1.00 P-2 0.90 0.50 0.90

suma 23.00 2.50

03.04.CONCRETO 1:8+25% P.M. PARA SOBRECIMIENTO


EJE 1,2 2.00 5.80 0.15 0.35 0.61 2.00 P-1 0.80 0.15 0.35 0.08
4.00 2.85 0.15 0.35 0.60 1.00 P-2 0.90 0.15 0.35 0.05

suma 1.21 suma 0.13

HOJA DE METRADOS

1
2

TOTAL UND

4.1 M3

5.1 M3

8.9 M2

4.1 M3

20.5 M2

1.1 M3