You are on page 1of 7

EPC or EPCM Contracts

Which one can drive stronger outcomes for project owners?

Ron Douglas, Ausenco’s Executive Vice President, Global Project Delivery, explores some of the key
dimensions project owners should consider in choosing their project contracting strategy.

EPC or EPCM? When it comes to contract strategies WHY CHOOSE EPC?


for major projects, Engineering, Procurement and
EPC contract forms are selected to realise the inherent
Construction (EPC) and Engineering, Procurement,
advantages provided by an integrated team across
Construction and Management (EPCM) style contracts
the full life cycle of a project from design concepts
are two of the key options, but which one provides
through to commissioning. Traditional barriers between
better outcomes for project owners?
engineering, procurement and construction contractors
Ausenco’s Executive Vice President, Global Project (or variations of this) are eliminated and the inefficient
Delivery, Ron Douglas has been involved in major layering of owners’ management teams is avoided
projects ranging from the millions to multi-billion dollars enabling rapid and efficient decision and approval
and he believes EPC and EPCM contracts can both processes. This approach seeks to achieve the most
deliver strong outcomes, however careful consideration seamless delivery organisation possible.
should be made of the different levers and potential
An integrated EPC team can design, procure and
outcomes to determine which one is best for each
construct facilities safer, in a shorter duration and with
project.
lower cost in a manner fit for the purpose specified by
In this article he explores some of the key dimensions the owner.
project owners should consider in choosing their project
Budget, schedule and performance risks are transferred
contracting strategy.
from the Owner to the EPC Contractor, enabling the
DEFINITIONS owner to focus on the critical task of developing their
business systems and processes in preparation for
‘EPC’ operating their asset.
Engineering, Procurement and Construction (EPC)
As challenges of projects become more complex, owners
is a contract option in which the EPC Contractor is
can transfer risk to a company capable of delivering a
responsible for all activities from design to procurement
complete package of resources, products, innovations
and construction to deliver the asset to the end user or
and management. In addition to the above, owners
owner.
routinely expect contractors to provide contemporary
It’s also known as Design and Construct (Lump Sum Turn industry efficiencies, latest tools and practices, labour
Key is a form of EPC). relations expertise and risk management. An EPC
approach allows these deliverables to be managed
‘EPCM’
under one aligned team.
Engineering, Procurement, Construction and
Management (EPCM) is a professional services We believe that the EPC approach is responsive to the
appointment whereby the Contractor’s services are critical success factors for new project development,
generally to provide detailed design, procurement, such as:
construction management and project coordination • Creating and maintaining the highest safety
necessary to deliver a project. standards
• Mandating and achieving an aggressive completion
schedule
• Integrating quality into the work from conceptual
design through the final installation
• Delivering a competed project fit for purpose and at
the least capital cost

All rights reserved. © Ausenco 2016 www.ausenco.com


EPC or EPCM Contracts. Which one can drive stronger outcomes for project owners? November 2016

WHY CHOOSE EPCM? IN SUMMARY


EPCM contract forms were traditionally used to enable a EPC is the most direct route to the least cost and highest
project to progress when the scope was unclear or a risk quality contracting option, where aggressive completion
difficult to quantify such that a contractor required to schedules and commitment to peak safety standards
include excessive contingent allowances in the price to complete the mix.
address the risks.
The inherent accountability of an integrated EPC team
These included: naturally delivers value, and the customer realises a
• New or proprietary technologies product that is both fit for purpose and delivers the
• Specific site or country risks highest return on their investment.
• Owner supplementing their existing delivery team.
This framework has shifted in the last 10-15 years such
See overleaf for comparisons of both EPC and EPCM
that the EPCM approach is now prevalent, initially driven
contracting options for Owners along key project
by contractors becoming more sophisticated in their risk
aspects.
analysis and proposing a risk free margin.
Factors influencing this transition were:
• Surge in demand for global engineering and
construction and ability for contractors to nominate
risk free revenue
• Significant size and complexity of projects such that
contractors could not accommodate fixed price risk
on their balance sheet
• Shortage of experienced professionals to perform
the work.
During this transition period an “industry” of Owner
Representative companies has developed to act as the
interface between the Owners and Contractors and
these organisations will continue to actively promote
EPCM contracts to ensure the commercial viability of
their business.
EPCM contracts allow critical path activities to continue
while scope is further defined. Schedule is therefore
shorter as time taken to develop basic design is not
added to the critical path. For more information on EPC and EPCM contract
It is touted that EPCM project costs are less than advantages and disadvantages, contact:
EPC as the contractor’s fee is minimised, however the Ron Douglas,
inefficiencies of layering and bureaucracy of decision Ausenco Executive Vice President,
making processes in EPCM result in inefficient Global Project Delivery
organisation for an extended time and higher costs
Email: ron.douglas@ausenco.com
result. Also, the risk remains with the client and recent
Social: Connect with Ron on LinkedIn
performance history indicates owners are being
impacted by the advice of their representatives.

All rights reserved. © Ausenco 2016 www.ausenco.com


EPC or EPCM Contracts. Which one can drive stronger outcomes for project owners? November 2016

Comparing EPC and EPCM contracting options


Below are comparisons of both EPC and EPCM contracting options for Owners along key project
aspects and the recommended contract types.

Equipment supply and


1 process warranties 2 Project budget cost overruns

EPC or EPCM EPC or EPCM

EPC CONTRACT EPCM CONTRACT EPC CONTRACT EPCM CONTRACT


Single warranty Owner negotiates The cost risk for the The cost risk for the
between Owner and EPC warranties with each project is borne by the project is borne by the
Contractor, usually in the supplier and contractor EPC contractor. owner.
form of a performance directly, often supported
bond. EPC contractor by multiple performance
manages warranties with bonds.
sub-contractors and
suppliers.

3 Project financing 4 Performance risk

EPC or EPCM EPC or EPCM

EPC CONTRACT EPCM CONTRACT EPC CONTRACT EPCM CONTRACT


Usually requires a Project financing can be EPC Contractor A common perception
substantial down any combination of down provides a single point is that with EPCM the
payment by owner payments, accounts of accountability for risk is sublet to each
to EPC contractor, and/or letters of credit performance and individual contractor by
generally requiring all from owner to different warranty of project Terms & Conditions and
financing to be in place suppliers. execution; responsible financial hammers such
at onset of project. for all risk provided by as liquidated damages,
contract documents although many claims
(e.g. schedule, cost and focus on who influenced
quality, as well as other performance (or who
requirements specific to owns the risk). A Project
the process, location or manager or prime
customer). contractor may be hired
as an agent of the owner,
yet unless expectations
are clear, risk-sharinq
becomes indistinct.

All rights reserved. © Ausenco 2016 www.ausenco.com


EPC or EPCM Contracts. Which one can drive stronger outcomes for project owners? November 2016

Accurate and timely


5 measurement of performance 6 Performance incentives

EPC or EPCM EPC or EPCM

EPC CONTRACT EPCM CONTRACT EPC CONTRACT EPCM CONTRACT


With a single contractor Depending on the size From an owner’s Each contractor can
a uniform set of tools and capability of each perspective there is an and should be prepared
can be applied to contractor, the tools used advantage to selecting for incentives related
record and measure to measure and record a contractor willing to to their specific scope
performance. Reporting performance can vary place fee at risk based on of work, plus any global
tools can be integrated from logbooks to highly performance incentives. components such as
across the project automated systems. With EPC this can include safety, cost, quality and
for attributes such If accurate and timely specific milestones schedule. Incentives will
as schedule, cost, performance reporting is along the execution path be successful if they are
materials, labour and expected, the issue rests such as first concrete, designed to reward a
quantities, which with who bears the cost to mechanical completion contractor for exceeding
enhances accuracy conform these assorted or energisation, but expectations, while
through an interactive tools into a consistent can also capture global penalising the same
database. report for the Owner or components such as for not performing to
Project Manager. safety, cost, quality and specified goals.
schedule.

Criticality of project
7 completion schedule
8 Construction work packaging

EPC or EPCM EPC or EPCM

EPC CONTRACT EPCM CONTRACT EPC CONTRACT EPCM CONTRACT


One of the key benefits A hindrance to schedule Work packaging for a Work packages for
with EPC is that the compression under an single EPC contractor contractors must be
construction cycle can EPCM profile involves the can readily adapt to divided into groups
begin concurrently with Bid-Evaluate-Award (BEA) many forms, typically based on both scope and
detailed engineering. cycle associated with driven by scope, commercial content, i.e.
This significantly construction contracts. discipline or schedule the ability to attract a
reduces the cycle An effective and thorough of work. An EPC enables cohesive set of bids for
time to construction BEA cycle consumes the team to plan the evaluation. This may not
completion and allows about 6 to 8 weeks, and work based on the always reflect the optimum
the duration from cannot begin until detailed most efficient menu installation process, and
conceptual planning design is substantially and sequence for can also develop a rigid
to an operating facility complete. If the BEA cycle prefabrication, modules, work process that fosters
to be condensed. As a is compromised, schedule installation and start-up. change orders from
result, schedule critical compression is possible poor definition of
projects are best suited however project costs will subdivided work.
for an EPC application. suffer as a result.

All rights reserved. © Ausenco 2016 www.ausenco.com


EPC or EPCM Contracts. Which one can drive stronger outcomes for project owners? November 2016

Communication of Ratio of administrative, technical &


9 construction issues and changes 10 supervisory personnel to specialists

EPC or EPCM EPC or EPCM

EPC CONTRACT EPCM CONTRACT EPC CONTRACT EPCM CONTRACT


Construction progress, Traditional construction For a project where a single The ratio between
information and contracts bind contractor is responsible field non-manuals and
experience flows quickly communication with formal for EPC, the ratio of field specialists for each
to other team members protocol, where changes, non-manual to specialists contract should fall within
under an EPC approach. issues and reports are should be 15% to 20%. a similar bandwidth as for
Problems are solved accompanied with written This includes all site EPC, however between
rapidly and results are transmittals. This provides personnel, such as clerks, the contractor and owner
available sooner as the a highly accountable record safety professionals, field (or prime) there is often
interface between the of events through the engineers, QA/QC inspectors, duplication in management
E, P and C functions is project, but drives cycle specialist supervisors and administration. This
connected. Cycle times time between questions and site management. In results in a much higher
are reduced, and many and answers to lengthy many cases, non-manual cost for the larger staff,
traditional issues never intervals. It can also prevent employees can fill multiple typically required to fill the
occur as the team works good ideas from fruition roles, reducing the overall void between performance
daily as a cohesive unit. as they get lost though staffing number and reporting and contractor
paperwork. associated costs. accountability.

Modularisation of
11 Material supply cycle 12 components and equipment

EPC or EPCM EPC or EPCM

EPC CONTRACT EPCM CONTRACT EPC CONTRACT EPCM CONTRACT


Procurement of engineered Typically the owner or Modularisation of If modularisation is to
components, equipment EP contractor procures plant components and be applied on an EPCM
and bulk materials can be engineered components equipment should be project, representative(s)
performed on a schedule and equipment for determined by availability from proposed erection
best suited for fabrication, EPCM projects, with bulk of qualified fabrication contractors should be
delivery, installation and materials supplied by either shops, routes of consulted to assure
testing. Considerations the individual contractor or transportation and site effective integration
for commitment and available to all contractors specific conditions such of module issues and
cash flow are built into on a consignment or stock as weather and terrain. An logistics. As the planning
the procurement plan, basis. Material control EPC contractor can review period for module
and control of materials becomes more complex, and module design during the design is typically well
is maintained by a single delays can lead to change constructability process, in advance of the BEA
source throughout the orders or claims. Leveraged to assure that effective cycle for construction, it is
project life. Leveraged procurement does not apply integration of module necessary to perform this
buying provides further well to an EPCM profile. issues and logistics. activity independently.
cost savings.

All rights reserved. © Ausenco 2016 www.ausenco.com


EPC or EPCM Contracts. Which one can drive stronger outcomes for project owners? November 2016

Benefits of innovations
13 and efficiencies 14 Accountability for labour relations

EPC or EPCM EPC or EPCM

EPC CONTRACT EPCM CONTRACT EPC CONTRACT EPCM CONTRACT


With an EPC approach the Contractors engaged in EPC contractors are Each contractor on an
owner has an integrated EPCM are at a disadvantage responsible for the EPCM project will have
team accountable for for the benefits of labour across the their preference for labour
delivering all facets of the innovation, as typically their project. Effective and relations and application of
project in a synchronous focus is on the quickest consistent application work assignments. In many
manner. It is advantageous completion of their contract of labour relations is cases these contractors
for the EPC contractor scope. Willingness to essential in maintaining will employ jurisdictional
to foster innovations accept new and innovative respect with specialist decisions that favour
and efficiencies, as any practices will usually be personnel, including their operation without
improvements between a by-product of improved the momentum that will respect for affect to
the E, P and C functions fee potential. Incentives for deliver the project as other project contractors.
translates into most innovations will be centred expected. Owners may retain a labour
effective, lowest cost on a specific contract in consultant; however it
project delivered in the lieu of a benefit to the total is common practice for
shortest duration. project. each contractor to be
responsible.

15 Demand for skilled resources 16 Percentage of specialty work

EPC or EPCM EPC or EPCM

EPC CONTRACT EPCM CONTRACT EPC CONTRACT EPCM CONTRACT


An EPC contractor capable EPCM contractors usually An EPC contractor is EPCM works well with
of executing substantial have good relationships with challenged executing high specialty applications,
and complex scopes trade(s) sources, as their volumes of specialty work where contractors
usually provides a good smaller team is tailored (e.g. insulation, roofing, possessing unique
draw for skilled labour, as for consistent employment pre-engineered buildings, qualifications, custom
the specialists view them through seasonal changes. containment liners), as both tooling or particular
as a stable source of work This results in a strong direct hire specialists and licenses are best suited
with consistent work draw for labour up to their the contractor’s non-manual over a general contractor.
rules. This can be critical capacity, however unless labour typically do not have The quality of work
when resources are the project scope supports the training required to typically meets or exceeds
challenged, and innovative the dynamics of staffing install such components industry standards,
recruiting actions are multiple contractors, or systems. In such cases, however schedule
necessary to meet the resource recruiting can the EPC Contractor will hire compression is unlikely
staffing plans for large be challenging with less specialty contractors to as the administration
and complex projects. manning for staffing issues. execute unique scopes of multiple specialty
of work. contractors is time and
resource consuming.

All rights reserved. © Ausenco 2016 www.ausenco.com


EPC or EPCM Contracts. Which one can drive stronger outcomes for project owners? November 2016

Management of local community


17 Location of engineering team/s 18 and indigenous peoples

EPC or EPCM EPC or EPCM

EPC CONTRACT EPCM CONTRACT EPC CONTRACT EPCM CONTRACT


Where the engineering EPCM can work An established EPC Hiring local contractors
and detailed design effectively with remote contractor with a formal can fulfil some indigenous
is performed should engineering, as contract labour relations program issues however there can
have minimal impact, if documents should be should be capable of uncertainty around these
effective coordination based on a defined executing an effective contractors having the
and communication scope with clear bid protocol for the hiring, skills and qualifications
is established by specifications. Work can training and involvement required for the project.
the EPC contractor. be executed in an EPCM of local personnel. This With EPCM, the managing
Efficient dialog is regardless of the location includes developing contractor must validate
required early to assure of the design centre; agreements with labour the capabilities of local
constructability issues however contractor leaders to provide access contractors, to assure
and lessons learned expertise should be for indigenous people to that owner or community
are incorporated in a retained during the the project, and the use commitments for
timely fashion. construction. of non-signatory local affairs do not
local contractors for significantly compromise
portions of the work. project execution.

“Build-Own-Operate-Transfer”
19 (BOOT) option

EPC or EPCM

EPC CONTRACT EPCM CONTRACT


The BOOT option is being BOOT applications are
considered by more owners possible under an EPCM
as plant development can contract; however it is more For more information on EPC and EPCM contract
proceed with innovative difficult and costly to align
capital schemes. In a BOOT multiple contractors in a risk
advantages and disadvantages, contact:
option, a high degree of pattern that extends beyond Ron Douglas,
contractor accountability mechanical completion
is required, as the risk of their specific contract.
Ausenco Executive Vice President,
associated with traditional In addition, performance Global Project Delivery
workmanship warranties bonding of contractors
is extended to include can be a concern, as for Email: ron.douglas@ausenco.com
performance expectations many the cost of Social: Connect with Ron on LinkedIn
over some period of an extended risk exceeds
operating cycle. their bond capability.

All rights reserved. © Ausenco 2016 www.ausenco.com

You might also like