You are on page 1of 35

CERC Terms & Conditions of

Tariff 2009-14

System Operators’ Course


Background
• Till March 2001, Tariff of ISGS was fixed
by GoI through a notification.
• First Tariff regulations issued by CERC on
31-03-01 for the control period April’2001-
March’2004
• Tariff regulations for April2004-March 2009
issued in March 2004
• Tariff regulations for April2009-March 2014
issued in Jan 2009
What are Terms and Conditions of Tariff?

• Rules for determining the Tariff of ISGS


and Transmission licensees.
• Applicable to
– a) Generating Stations supplying to more than
one beneficiary (Thermal, Hydro, CCGT)
– (NTPC, NLC, NHPC, DVC, NEEPCO)
• b) Inter State Transmission System
• Tariff of Nuclear power stations is fixed by
DAE.
Some Imp Definitions and terminology
• Control Period : Period for which tariff is specified (April 2009-
March 2014)
• MYT : Multi Year Tariff: The tariff spread over useful life of the
equipment
• Beneficiary : Person purchasing power from the ISGS
• Cut off date :Last day of FY after 2 years from the CoD.
• Date of Commercial Operation: date from which Tariff recovery
starts
• ‘Infirm power’ : Power injected before CoD.
• ‘Inter-State generating station’ or ‘ISGS’ : Gen Stns supplying
power to more than one state.
• ‘Useful life’: Life of the system from CoD used for computing
Depreciation and determination of Tariff norms.
• ( Coal/Gas based/ Substation=25 yrs, Hydro/Line 35 yrs)
• ‘Design energy' means the quantum of energy which can be
generated in a 90% dependable year with 95% installed
capacity of the hydro generating station;
Steps in Tariff and Collection
Audited Costs
Apply for Tariff fixation (6 months before)

Bench mark norms


Tariff fixation of Project Cost

CoD Billing by the ISGS/ ISTS Accounting in REA

Filing of AddCap+ deferred Liabilities


Cut off Date Audited Costs
+actual Expenditure

Truing up by CERC

Adjustment of Excess or
Beneficiaries Interest Rates
Deficit collection
High lights
Regulation 39
Income from UI, Incentive & non-core business
–Not a pass through

Regulation 26 (ii)B
Min Boiler efficiency, Max. Design unit Heat Rate etc. are defined
for different type of boilers and coals defined for new Thermal
Gen stations to discourage procurement of inefficient Boilers.
Total Project Cost considered for Tariff fixation
Project Exp.

Asstets
IDC not in Use

Profit in Sale
FERV of
Infirm power
Capital
Rs.
Initial Spares Cost

Addl
Cap Debt:Equity
Ratio

Rehab &
Resettle Loan Equity
(hydro)
RGGYY
(hydro)
Components of Tariff
Tariff

Capacity Energy
Charges Charges

Interest on Maint. Primary Fuel


Loan Depreciation Spares

O&M Normative Lime Stone


expenses Seconday (if
Return on Oil Cost applicable)
R&M
Equity
Allowence
Equity Rate of RoE Return Equity

Loan Rate of Interest Interest on Loan

Rate of Depreciation
Loan +Equity Depreciation

Type/Size of Unit/ / Normative O&M Exp


Tr. system O&M Exp

Maint. spares
O&M Exp Normative % Spares

Working Capital Interest on


Interest rates
Working Capital

Seondary Oil rate Sec. Oil rates Sec Oil


Cost of 1.5* month primary fuel
Stock
* 2 months for non-pit head stns.

O&M Exp

Cost of 2 months Sec oil Stock

Working Capital
O&M Exp for 1 month

Interest rates
Cost of Maint. Spares (as a % of
O&M ch.)

Interest on Working Capital


2 months receivables
Time Lines in Tariff Period
Project schedule to determine addl. RoE
Construction
Period Control
Control Control
Period 1 Period 5
Period 2
Control
Period 4

2-3 months 10-12 yrs Tariff after


Renovation and
2-3 months
Modernisation
2-4 years 2+ years

Depreciation in straight Line method (12 years)


Drawl of Start up power (2-3 months)
1st Trial synchronisation

Cut-Off Date for addl . Capitalisation

Apply for True I Up of Tarriff

Eligibility for R&M


CoD

End of Loan repayment


Start date (2- 4 years)

End of Useful Life


Project
Bench marking Model for Generating Stations
Benchmarking by CERC
Developed as per National Tariff policy, for facilitatting
prudence checks in line with Clause 7(2)
of the TCT regulations
Fuel /Technology
Green Field/ Exisitng
Size of Unit Bill of Quantities
No. of Units
Evacuation Voltage Level • Boiler Efficiency
• Steam Generator
• Turbine Generator Island
• Turbine Heat Rate
Fuel Linkage
• Fuel Oil Handling & Storage system
Plant Location (Pit Head/ Non Pit Head)
• Coal Handling System
Month/Year of Award
• Chimney
Boiler Configuration
• Ash Handling System Total Unit cost
• C & I Package
• Civil Works
• Cooling Tower
Distance of Water Source (River) • Switchyard Package
Calorific Value • Initial Spares
Ash Content • Mode of Unloading Fuel Oil
Moisture Content in Coal

Indeces for Steel, Cement, Labour


Generous set
of assumptions

Source: CERC Explanatory Memorandum ( 8th Dec.’09)


Bench marking Model for Transmission lines
Benchmarking by CERC

Voltage class
No. of circuits
Conductor type
No. of Conductors
Insulator type

Line length Bill of Quantities


Wind zones & Terrain
No. of Towers • Conductor length
Types of Terrains
No. of River crossings • Earthwire length
• No. of insulators Total cost / Cost per ckm
• Qty. of Hardware

• Tower Weights
Unit cost based
on historical data and • Foundation Volume
Application of PV
Formula and
indices

Generous set
of assumptions

Source: CERC Explanatory Memorandum ( 8th Dec.’09)


Plant Availability Factor

DCi = Average declared capacity (in ex-bus MW),


N= No. of Days in the period
IC = Installed Capacity
Aux = Normative auxiliary energy consumption in percentage.

For Thermal Plants, DCi is the Max Pk hour MW schedule given by RLDC

For Hydro Plants DCi is the MW delivered for atleast 3 hours certified by RLDC
Availability Calculation of
Transmission System
Availability = (100-100*NAFM)
Where NAFM= Non-availability factor in per unit for the month
1) For AC system
[ Σ ( OHL x CktkmL x NSCL ) + Σ ( OHT x MVA T x 2.5 ) +Σ ( OHR x MVAR R x 4 ) ]
THM x [ Σ (Cktkml xNSCL ) + Σ (MVAT x 2.5 ) + Σ (MVARR x 4 ) ]

Where
OHL, OHT & OHR = Outage hours for Line or Transformer or Reactor
Cktkm = Length of a transmission line circuit in km
NSC = Number of sub-conductors per phase
MVA = MVA rating of a transformer / ICT
MVAR = MVAR rating of a bus reactor,
THM = Total hours in the month

2) NAFM for each HVDC system


NAFM = [ Σ (TCR x hours) ] ÷ [ THM x RC ]
• TCR = Transmission capability reduction of the system in MW
• RC = Rated capacity of the system in MW.
Computation of monthly Capacity charges payable
AFC = Annual fixed cost specified for the year, in Rupees.
NAPAF = Normative annual plant availability factor in percentage
NDM = Number of days in the month
NDY = Number of days in the year
PAFM = Plant availability factor achieved during the month, in percent:
PAFY = Plant availability factor achieved during the year, in percent

For Thermal Gen. Stns. less than ten (10) years old:
Monthly capacity Charges = AFC x ( NDM / NDY ) x ( 0.5 + 0.5 x PAFM / NAPAF )
For Thermal Gen. Stns. Older than ten (10) years:
Monthly capacity Charges = AFC x ( NDM / NDY ) x ( PAFM / NAPAF )

For Hydel Plants


Monthly capacity Charges = AFC x 0.5 x NDM / NDY x ( PAFM / NAPAF )

For Transmission charges of ISTS :


Monthly transmission Charges = AFC x ( NDM / NDY ) x ( TAFM / NATAF )
Energy Charges Rate
Aux = Normative auxiliary energy consumption in percentage.
CVPF = Gross calorific value of primary fuel as fired, in kCal per unit
CVSF = Calorific value of secondary fuel, in kCal per ml.
ECR = Energy charge rate, in Rupees per kWh sent out.
GHR = Gross station heat rate, in kCal per kWh.
LC = Normative limestone consumption in kg per kWh.
LPL = Weighted average landed price of limestone in Rupees per kg.
LPPF = Weighted average landed price of primary fuel, in Rupees per unit
SFC = Specific fuel oil consumption, in ml per kWh.
For Coal based and Lignite fired stations
ECR = { (GHR – SFC x CVSF) x LPPF / CVPF + LC x LPL } x 100 / (100 – Aux)
For gas and Liquid fuel based stations
ECR = GHR x LPPF x 100 / {CVPF x (100 – Aux) }
For Hydel Plants
ECR = AFC x 0.5 x 10 / { DE x ( 100 – Aux ) x ( 100 – FEHS )}
Secondary Oil
Regulation 20
• Secondary fuel charges de-linked from
Energy Charges and put in Fixed charges
• Sec Oil Exp.= SFC x LPSFi x NAPAF x 24 x NDY x IC x 10
• Secondary oil consumption halved to
1ml/u
• Actual Expenses based on landed cost to
be adjusted at the FY end.
• Savings in Sec. oil consumption to be
shared with Beneficiaries 50:50
Regulation 17 Depreciation
• Allowed up to maximum of 90% of the capital
cost and salvage value is 10%
• 5.28% for 1st 12 years Balance depreciable
value spread over the balance useful life
• IT eqpt.=15% ; PLCC=6.33 ; Motor
vehicles=9.5% ; AC=9.5%
• Bldgs= 3.34%
• Land under lease=3.34%
• Temp erections=100%

• Advance Against Depreciation removed


Sample Calculation of Tariff – CERC Norms 2009-14
Case Study :
A Project Consisting 1 No. 400KV D/C Transmission Line of 75 km line length and
4 Nos of 400KV Bays.
Capital Cost of the Project : Rs 100 Cr
Adopting Debt : Equity Ratio of 70 : 30
Loan (Debt) Amount : Rs 70 Cr
Equity Amount : Rs 30 Cr

CALCULATION OF TARIFF for 2009-10 (For illustration purpose only)


Interest on Loan : 70 x 0.095 = 6.65 Cr
( IOL @ 9.5%)
Return on Equity : 30 x 0.17481 = 5.24 Cr
(ROE @ 17.481% {15.5%/ 16% before MAT})
Depreciation : 100 x 0.0528 = 5.28 Cr
(Depreciation @ 5.28% {Building : 3.34%, TL/SS : 5.28% ,
PLCC : 6.33 % and balance spread over after 12 Years})
O&M Expenses = 2.57 Cr
4 No * 52.40 Lakh/Bay (400KV)
75 Km * 0.627 Lakh/Km (400KV D/c Twin)
Interest on Working Capital @ 12.25% = 0.41 Cr
( WC=2 Month Receivables + 1 Month O&M + 15% O&M for spares)
TOTAL TARIFF = Rs. 20.15 Cr / year
Will Tariff be paid after ‘Useful life’?
 Yes. Tariff is receivable by the Owner
 ‘Depreciation’ component will not be receivable
 Eligible for Renovation and Moderation
 Asset can be written off and new project can be constructed or
R&M can be taken up
 Allowance for R&M Rs.5Lac/MW/yr as Fixed Ch.
 R&M as a separate project

‘useful life’ in relation to a unit of a generating station and transmission


system from the COD shall mean the following, namely:-
(a) Coal/Lignite based station :25 years
(b) Gas/Liquid fuel based station :25 years
(c) AC and DC sub-station: 25 years
(d) Hydro generating station : 35 years
(e) Transmission line : 35 years
Some TCT clauses
relevant to System
Operation
Commercial Declaration
‘Date of commercial operation’ or ‘COD’ means
(a) in relation to a unit or block of the thermal generating station, the date
declared by the generating company after demonstrating the maximum
continuous rating (MCR) or the installed capacity (IC) through a
successful trial run after notice to the beneficiaries, from 0000 hour of
which scheduling process as per the Indian Electricity Grid Code (IEGC)
is fully implemented, and in relation to thegenerating station as a whole,
the date of commercial operation of the last unit or block of the generating
station;
(b) in relation to a unit of hydro generating station, the date declared by the
generating company from 0000 hour of which, after notice to the
beneficiaries, scheduling process in accordance with the Indian Electricity
Grid Code is fully implemented, and in relation to the generating station as
a whole, the date declared by the generating company after
demonstrating peaking capability corresponding to installed capacity of
the generating station through a successful trial run, after notice to the
beneficiaries:
hydro generating station with pondage : If insufficient reservoir or pond level
-demonstrate peaking capability equivalent to installed capacity
run-of-river hydro generating station - demonstrate peaking capability as
and when sufficient inflow is available.

c) element of the transmission system : first day of a calendar month


Infirm power
‘Infirm power’ means electricity injected into the
grid prior to the commercial operation of a unit or
block of the generating station;
11. Sale of Infirm Power. Supply of infirm power
shall be accounted as Unscheduled Interchange
(UI) and paid for from the regional or State UI
pool account at the applicable frequency-linked
UI rate:
Provided that any revenue earned by the
generating company from sale of infirm power
after accounting for the fuel expenses shall be
applied for reduction in capital cost:
Maintaining Fuel Stock
18 1(a) Coal-based/lignite-fired thermal generating stations

(i) Cost of coal or lignite and limestone, if applicable, for 1½


months for pithead generating stations and two
months for non-pit-head generating stations, for
generation corresponding to the normative annual plant
availability factor;

Open-cycle Gas Turbine/Combined Cycle thermal


generating stations
Fuel cost for one month corresponding to the normative
annual plant availability factor, duly taking into account
mode of operation of the generating station on gas fuel
and liquid fuel;

Liquid fuel stock for ½ month corresponding to the


normative annual plant availability factor, and in case of
use of more than one liquid fuel, cost of main liquid fuel.
Declared Capability in Fuel
Shortage Conditions
21(4) In case of fuel shortage in a thermal
generating station, the generating company may
propose to deliver a higher MW during peak-
load hours by saving fuel during off-peak hours.
The concerned Load Despatch Centre may then
specify a pragmatic day-ahead schedule for the
generating station to optimally utilize its MW and
energy capability, in consultation with the
beneficiaries. DCi in such an event shall be
taken to be equal to the maximum peak-hour
expower plant MW schedule specified by the
concerned Load Despatch Centre for that day.
Declared Capability in Fuel
Shortage Conditions
Pk hours to be specified in RPC forum
DC not to be revised during Pk hours
DC can not be reduced Unless Unit trips
If unit trips, maximum possible DC to be given in
other units
In such case max DC during pk hrs to be specified
as DC for the day
To Check Gaming by Generator
DC can not be increased
For Hydro Stations
• DCi = Declared capacity (in ex-bus MW) for the
ith day of the month which the station can deliver
for at least three (3) hours, as certified by the
nodal load dispatch centre after the day is over.
• (8) The concerned Load Despatch Centre shall
finalise the schedules for the hydro generating
stations, in consultation with the beneficiaries,
for optimal utilization of all the energy declared
to be available, which shall be scheduled for all
beneficiaries in proportion to their respective
allocations in the generating station.
Sharing of ISTS charges
(1) Regional Tr. Ch of a Beneficiary
=(Agreed Pooled Assets+ Associated Tr. System+ IR
link)
Total ISGS capacity
X (Wt. Avg. Entitlement from all ISGS+LTA+ MTOA)
(2) IR link sharing :
SR-WR, NR-WR, ER-NER = 50:50
NR-ER by NR, SR-ER by SR, WR-ER by WR
(3) ICT and Down Stream N/W charges by Respective
Beneficiary
(4) Unpooled ATS : by respective Beneficiaries
Transmission charges in absence of a
Beneficiary
Regulation 33 (7)
• A new clause is added with regard
payment of Tr. Charges by the generator
incase of non-identification of beneficiary
for its capacity.
• “Transmission charges corresponding to
any plant capacity for which a beneficiary
has not been identified and contracted
shall be paid by the concerned generating
company”.
Effect of PoC Regualtions (Sharing of
Inter state Transmission charges and losses)
Salient features of PoC Regulations
 Notified on 15.06.2010 and shall come into force from 01.01.2011

 Transmission charges for the Assets of POWERGRID shall continue to be


determined by CERC

 Existing methodology for Sharing of Transmission Charges is replaced


(Regulation 33 of Terms & Conditions of Tariff, 2009 : Repealed )

 Sharing based on Point of Connection (PoC) Tariffs based on load flow


analysis

 PoC are identified against all the USERS of the ISTS network known as
Designated ISTS Customers (DICs)
1) Generating Stations
2) SEBs/STUs
3) Bulk consumer directly connected with ISTS
4) Any designated entity representing aforementioned physically connected entity
Proposed Changes in Fixed Charge
Recovery
For incentivising Peak Availability
• Annual Fixed charge for the peak hours
• Annual Fixed charge for the off-peak hours
in (1): (2.4) ratio
Different Norms for Fixed charges specified based
on classification of
 Peaking Stations
 Other than Peaking Stations
For Thermal, Hydro and CCGT
 Norms for Pumped Storage Hydro
Generating Stations introduced
Tariff Policy 2006
 Provisions of “Tariff Policy” of Jan 2006 state:

 “Even for the Public Sector Projects, tariff of all new


generation and transmission projects should also be
decided on the basis of competitive bidding after a period of
five years or when Regulatory Commission is satisfied that
the situation is ripe to introduce such competition.”

 “Tariff of the projects to be developed by CTU/STU after the


period of five years or when the Regulatory Commission is
satisfied that the situation is right to introduce such
competition would also be determined on the basis of
Competitive Bidding.”

Competitive Bidding in :
 Power plant setup
 Transmission system construction
Tariff Competitive Bidding
• For Old projects, tariff will be continued to
be fixed.
• For New projects awarded under
Competitive Bidding, Quoted Tariff as per
final award will be used got payment of
charges
References :
• Terms and Conditions for Renewable Energy
• RLDC fee and Charges
• Statement of Objects and Reasons for Terms and
Conditions of Tariff regulations
• Indian Electricity Grid Code 2010
• CERC order dt Benchmarking of Thermal projects
• CERC order dt Benchmarking of Transmission projects
• CERC (Terms and Conditions for Tariff determination
from Renewable Energy Sources) Regulations, 2009.
• Tariff Notification for Generating Companies – Govt. of
India

You might also like