Professional Documents
Culture Documents
Hydrocarbon Exploitation
Production Phase
September - October 2004
Uni vation
Univation
PRODUCTION PHASE
Production Phase
1
Production Phase
It is important to define how the field will be produced and operate and
how the facilities are to be maintained, these two parameters will have a
big impact on the facilities design.
0 5 10 15 20 25 30
2
Operating and Maintenance Objectives
3
Operating Input
Operating Input
4
Maintenance Input
Maintenance Input
¾ Early Failures: may occur almost immediately, and the failure rate is determined
by manufacturing faults or poor repairs.
¾ Random Failures: are due to mechanical faults as the equipment becomes old.
One technique used by maintenance engineers is to record the mean time to failure
(MTF) of equipment items to find out in which period a piece of equipment is likely
to fail.
Equipment items will be maintained in different ways, depending upon their:
5
Equipment Criticality
PRODUCTION
POTENTIAL
10,000 B/D
Univation
6
The Field Life Cycle
Production
Rate
Time
Artificial Secondary
Lift Recovery
Production
System
Reservoir
7
Total Fluid Production System
Reservoir
– Geology, structure and boundaries
– Rock characteristics
– Fluids
Well
– Damaged, fractured, stimulated
– Completion
– Tubulars, restrictions, manifolds
Artificial Lift
Field
– Pipelines, separators, compressors, injection facilities
– During the production phase of a field life, the operator will apply
field management techniques aimed at maximising the profitability of
the project and realising the economical recovery of the hydrocarbons,
while meeting all contractual obligations and working with certain
constraints
8
Resource Allocation
Approach
– Resources should be allocated in a manner consistent with the profit
motive
Profit Motive
– Maximise revenue
– Minimise cost
– Political benefit
– Environmental protection
Resource Allocation
Additional
Benefit
resources
M reduces the
benefit
Maximum return
Maximum available
slope II
Resource Input
Production Phase ©abalt solutions limited 2004 18
9
Optimisation
Production Optimisation
– Operational
– Configurational
Operational Optimisation
Examples
– Re-allocate gas lift
– Re-design ESP
– Alter depth of pump. e.g. rod pump or jet pump
– Turn a well on or off
10
Operational Optimisation
For a system of wells producing oil, water and gas, using gas lift the total revenue
∑ [$ q o, i + $ gp q gp, i - $ w q w, i - $ gi q gi, i ]
is given by:
f = o
wells
– There is a minimum amount of gas that must be added before any oil is
produced – the kick-off gas which may be zero if the well is naturally flowing
and,
– There is a maximum or optimum performance beyond which the addition of
extra gas causes less oil to be produced
Configurational Optimisation
11
Configurational Optimisation
– How the well should perform for the entire period of its operational life?.
– Factors that impact on this are:
• The performance of the reservoir throughout the field life. (pressure support
or lack of it).
• Reservoir constraints. Gas and/or water coning would occur at high rates and
therefore the wells do not need to be designed to handle these rates.
• The fluids handling and how this may change.
• The production problems. Scales, asphaltenes, wax etc. all impact the well
design and productivity.
• The likelihood of interventions. This will allow for a tubing size change or
implementation of artificial lift.
12
Completion Design Process
13
1. Determining the Range of Well Performance
Questions To Be Addressed
– What is the appropriate inflow performance relationship?
– What is the likely range of inflow performance and the impact on the project?
– How will the reservoir drive affect well performance?
– How will the initial reservoir pressure vary?
– What is the likely change in GLR and water cut?
14
2. Determining the Range of Outflow Performance
Data Required…
– Initial view on likely wellhead flowing pressure.
– Desired completion life.
– Answers to questions on inflow performance raised earlier.
Questions To Be Addressed
– Is there an appropriate method for predicting tubing performance
and what are the potential errors and their impact on the
predictions?
– What is the likely range of tubing performance over the area of the
field and with time?
Data Required
– Results from above inflow and outflow analyses.
15
3. Combining the Inflow and Outflow Performance
Questions To Be Addressed
– Is the range of initial rates economically and technically feasible?
– Is the selected WHFP the economic optimum. What are the
repercussions of changing it?
– What is the appropriate tubing size for the range of inflow
performance and production rates?
– Will this tubing size sustain flow at the required rate over the
completion life?
– Is re-completing with a smaller tubing size economically attractive?
– Is artificial lift likely to be a requirement? If so, what is the
conceptual technique?
16
4. Near Wellbore Performance
Questions to Be Addressed
– Identify the potential types of near wellbore damage,
possible stimulation methods and potential sand production
problems?
– Evaluate the sensitivity to perforating techniques?
– Identify if near wellbore performance is a critical factor in the
field development and attempt to quantify the risks?
5. Architecture of Completions
17
5. Architecture of Completions
Data Required
– Formation evaluation data from previous or analogous wells.
– Results from well performance, near wellbore performance and
tubing stress analyses.
– Required completion life.
– Brief evaluation of potential well servicing and workover
philosophies.
Questions To Be Addressed
– Do all the alternative structures satisfy all the requirements?
– Are the completions simple, safe, reliable and flexible?
5. Architecture of Completions
Questions To Be Addressed
– Do the completions have the ability to cope with unforeseen
problems?
– Does the design life of the completion tie in with the
production profile forecasts?
18
6. Tubing Movement & Stress Calculations
19
7. Selection of Tubulars and Materials
Questions To Be Addressed
– Is the data representative of conditions throughout the field?
– Can material of suitable strength be made in the desired corrosion
resistant material?
– Will conditions change with time?
– Have all the fluids likely to be used been considered?
– Does the selected material and completion life provide the lowest
risk and best economic return?
– Is the lead time on the selected material compatible with project
timing?
20
9. Well Servicing & Workover Philosophy
21
Completion Technology
22
Completion technology - Intervention Issues
For Instance:
23
Univation
Field Optimisation
Production Debottlenecking
Production operations
Production Debottlenecking
• If the reservoir is performing better than expected it may pay to increase plant
capacity.
• If, however, it is just a temporary production peak such a modification may not be
worthwhile.
24
Production Debottlenecking
Production Debottlenecking
– These issues can often be addressed both by surface and subsurface options,
though the underlying justification remains the same; the NPV of a
debottlenecking exercise (net cost of action versus the increase in net revenue)
must be positive.
25
Production Debottlenecking
– It is not always easy to predict how a change in one part of a processing chain
will affect the process as a whole.
Production Debottlenecking
26
Produced Water Treatment
– Extra tankage or other low maintenance options are usually too heavy
or take up too much room on an offshore platform.
27
Gas Handling
Gas Handling
28
Updating the Reservoir Model
29
Well Management – Example Problems
30
Well Management - Downtime
31
Well Management – Adding Value by Thinking !
A
PRE-PRODUCTION
DECOMMISSION
OPEX $
PRODUCING TIME
32
Field Rehabilitation Targets
33
Accelerated & Additional Reserves
PRE-PRODUCTION
PLATEAU
DECOMMISSION
CASHFLOW
EXPOSURE
BUILD DECLINE
UP
TIME
CASH SURPLUS
PAYOUT
34
Questions asked during Production Optimisation?
35
Workover & Well Intervention
II
Workovers
“…any work performed after the initial completion that alters the
well performance or mechanical structure”.
36
Well Servicing & Workovers
During the conceptual design stage it is important to identify any potential reasons
for workovers and the applicable techniques.
When reviewing the impact of well problems and workover techniques on the
initial completion design, it is important to recognise the risk associated with that
problem and the potential consequences.
Optimising the completion design around potential well problems and workover
techniques is, like many other issues, a question of balancing risk against likely
consequence.
37
Potential Well Problems
How to Solve it: The only workover technique that can mitigate the effects of
falling reservoir pressure is to recomplete the well with either smaller tubing or
some form of artificial lift.
Poor Permeability:
Fields with low reservoir permeability suffer a rapid decline once the
fluids near the wellbore are produced.
Matrix acidising is only effective in this situation if formation damage
is also present.
How to solve it: The most effective method of improving productivity
in these types of reservoir is to utilise a large hydraulic fracture
treatment.
38
Potential Well Problems
Wellbore Restrictions:
Typical causes of restrictions include scale, sand, paraffin and asphalt etc. Many of
these problems may not be apparent during early field life but can become a
significant problem as the field matures.
How to solve it: A number of techniques, both mechanical and chemical, exist to
remove the restriction.
However, these workover techniques are remedial techniques and consideration
should always be given to the prevention of the problem.
39
Potential Well Problems
40
Potential Well Problems
Excessive gas production from a well can result from solution gas in the oil evolving
as the pressure declines, or as a result of gas encroachment from the gas cap.
With pressure decline in saturated oil reservoirs, the gas evolved across the
reservoir may migrate to the gas cap.
However, the gas evolved near the wellbore as the oil is produced causes an
increase in gas saturation and allows the gas to be produced with the oil.
High gas/oil ratios (GORs) in this case are a function of the reservoir
drive mechanism and cannot usually be remedied by a workover.
An increase in GOR can also occur from a lowering of the gas cap
into the producing zone and through channels in the cement or casing
leaks. This increase in GOR can be temporarily remedied by
squeeze cementing and lowering the perforated interval.
41
Potential Well Problems
Mechanical Failures:
A poor primary cement job which leaves channels behind the casing
can lead to the influx of unwanted fluids and in certain instances
casing collapse.
The repair of cementing failures can be achieved using a number of
different techniques.
42
Well Servicing & Workover Techniques
Wireline Operations
It has relatively low cost and ability to be run through a lubricator on the Xmas
tree with the well under pressure.
Slickline.
– This is a solid single strand of wire, the commonest size being 0.108in
Braided line.
– This wireline consists of stranded wire resulting in a higher load capacity than
slickline. Commonly used sizes are 3/16 and 5/16in
Electric line.
– This consists of stranded wire and a conductor capable of transmitting an
electrical signal to the surface.
43
Wireline Operations
Wireline Operations
44
Coiled Tubing Units (CTU)
They have traditionally been used for well clean-out, well kick-off and spotting of
acid.
CTU applications are limited by the tensile capacity of the tubing, the lifting
capacity of the rig and the inability to rotate the tubing.
Although not as mobile and easy to rig up as a wireline unit, CTUs ability to convey
fluids and the significant cost advantages over conventional workover rigs has led
to the use of coiled tubing as the preferred technique for a number of well
maintenance problems.
In highly deviated and horizontal wells, it is being used for applications like shifting
sliding sleeves, which cannot be performed by wireline at high angles.
Coiled tubing is being utilised for scale mill outs using downhole motors and
remedial cementing.
Pressure drops in coiled tubing are significant as the fluid has to pass through the
complete length of tubing on the reel irrespective of depth. As a result of this,
circulation rates are limited to a few barrels a minute.
45
Hydraulic Workover Units (HWU)
(HWU)
46
Hydraulic Workover Units (HWU)
Hydraulic workover units have several advantages over conventional workover rigs
and greater capability than coiled tubing:
– The workover operation can be performed under pressure and in certain cases
with the well still flowing. This eliminates the risk of formation damage in
sensitive formations resulting from killing the well prior to a conventional
workover.
– Mobilisation and demobilisation are shorter reducing the overall time a well is
off production.
– The hydraulic workover unit is flexible, with a lifting capacity up to 340 000
lbs, allowing it to handle relatively large tools. The ability to rotate the pipe
enables light drilling and milling work to be performed.
The primary use for HWU was for emergency and non-routine well interventions.
This use has to some extent tarnished the reputation of HWU, in that most of the
experience has been gained under difficult or emergency situations.
Indeed, in many cases HWU was the only appropriate technique to control the
well. However, for some of the reasons outlined above, the HWU is now becoming
the preferred well servicing technique for certain situations.
47
Hydraulic Workover Units (HWU)
Remedial Cementing
48
Remedial Cementing
Rig Workovers
49
Concentric Workovers
Wireline Equipment
50
Wireline Equipment
Wireline Equipment
The most common wireline winch unit is skid mounted and has a double drum, one
with 20 000 ft of 0.108in wire and the second with 15 000 ft of 7/32in wire.
The measuring device, as the name implies, provides the operator with the location
of his tool relative to some datum, usually the swab valve.
– The operator uses this device to locate the tool string, monitor the speed, and
to avoid running the tool string into the stuffing box when pulling out of the
hole.
51
Wireline Equipment
The weight indicator displays the total load or line tension and is
critical to jarring operations to avoid breaking the wire. The device
will also indicate restrictions in the tubing, changes in fluid density
and losses or increases in weight when setting or retrieving downhole
equipment.
The hay pulley guides the wire down from the lubricator and out
parallel to the floor to the winch drum. The hay pulley is attached to
the Xmas tree via the load cell for the weight indicator.
Wireline Equipment
The wireline clamp is used to secure the wire when required e.g.
when removing the lubricator.
The stuffing box provides the pressure seal on the wire and consists
of a packing gland that can be adjusted by means of an external
nut.
– In the event that the wire breaks and is forced out of the packing, there
is a an internal BOP plunger that is designed to seal off the stuffing
box.
52
Wireline Equipment
The BOP can isolate pressure with or without wire in the well. The BOP rams have
resilient seals which can close and seal around a wire, without damaging or cutting
the wire.
Dual BOPs are normally employed for braided line or fishing operations.
Electric Line
The primary use is for cased hole formation evaluation and production logging. It
is also routinely used for perforating, setting bridge plugs and packers etc.
Production logging is the term used for any survey which is run to evaluate the
nature and behaviour of fluids in the well during production or injection.
The applications of production logging include:
– Well test evaluation.
– Determining reservoir characteristics.
– Evaluating completion efficiency.
– Identifying unwanted fluid flow eg thief zones.
– Reviewing stimulation treatments, before and after.
53
Electric Line
There are several other surveys commonly carried out on electric line
which are not generally considered to be production logging. These
include casing corrosion and integrity logs as well as cement bond
logs.
These are generally run before the tubing is run in new wells, or
after the completion has been removed in older wells being worked
over.
Measuring Devices
54
Through Tubing Bridge Plugs
As the name suggests, bridge plugs are run through tubing and other downhole
restrictions and then expand to seal in the casing.
They are primarily used to shut lower watered out zones. There are two main types
available.
– Bridge plugs, e.g. Teledyne Merla plugs, which are set with an explosive
setting tool similar to a standard Baker setting tool.
– These have a diameter before setting of approximately 3 to 4in and expand
up to 4 or 5in and are similar to standard wireline bridge plugs.
These are standard wireline plugs and packers run with a standard wireline
explosive setting tool. The plugs are commonly used to plug and abandon wells
after drilling, or to seal off casing strings.
Wireline set packers can be run with tailpipes, although the length of pipe is
limited by the strength of the wire.
There are more exotic pieces of hardware that can be run with wireline setting
tools, e.g. casing patches.
55
Gas Lift Surveys
Coiled tubing is run and pulled from the well by means of the
injector head. The endless chains and friction blocks are driven by a
hydraulic motor.
Unlike wireline, coiled tubing has initially to be fed or injected into a
pressured well. The injector head also works in reverse and actively
feeds the string out of the well when recovering the tubing.
The coiled tubing reel itself purely acts as a spooling device taking
up the slack or paying out the tubing as required.
56
Coiled Tubing Equipment
57
Coiled Tubing Equipment
CT Equipment
58
Standard Coiled Tubing Operations
Coiled tubing units are routinely used for the following operations:
– Nitrogen lifting.
– Sand lifting.
– Cleaning out the wellbore utilising a downhole motor.
– Circulating fluids.
– Drill stem testing (DST).
– Sand control.
– Corrosion inhibitor placement.
– Spotting acid, Spotting cement.
– Coiled tubing conveyed electric line services.
– Inflatable bridge plugs.
– Fishing operations.
Nitrogen Lifting
Pumping nitrogen down coiled tubing to reduce the hydrostatic head of the well
fluids is utilised in a number of well operations.
Lifting unstable wells and circulating out completion fluids following a workover
are common applications.
The injection rate required to bring on the well is a function of the pipe size, depth,
fluid characteristics and reservoir performance.
Coiled tubing can also be used to provide the required underbalance prior to
perforating.
59
Sand Lifting
Coiled tubing can be used to clean out sand fill from sumps that has
occurred during production or as a result of hydraulic fracturing
operations.
Coiled tubing’s ability to maintain circulation while running in or
pulling out of hole make it ideally suited for this application. If
possible sand lifting should be performed with the well flowing.
This may alleviate the need for injecting gel, although cross linked
polymer is usually injected.
This technique is utilised when the deposits in the well are compacted
or cemented and is particularly useful in the removal of insoluble
scale deposits.
A downhole motor is used to drill out the deposit which is then
washed to the surface.
The downhole motor operates on the Moineau principle which utilises
fluid being forced through a progressive cavity to supply the
rotational power.
60
Clean Out
Circulating Fluids
61
Drill Stem Testing
Coiled tubing is often used as a means of artificial lift to assist wells which will
not flow naturally during DSTs.
Two methods are used, downhole jet pumping and nitrogen gas lift.
– The jet pumping method utilises the coiled tubing to both locate the jet pump
module in a landing nipple and subsequently convey the power fluid. The
power fluid is usually water, although a combination of water and nitrogen
can be used for low GOR crudes. Heavy crude oils may also benefit from
applying heat to the power fluid.
– The jet pumping technique is most appropriate for crudes with an API
gravity of 12 or less.
– Nitrogen gas lifting is more suitable for the higher API crudes.
Sand Control
Limitations on pump pressure and rates limit this application to shallow wells less
than 6000 ft.
Both resin coated sand and water activated plastic can be pumped with coiled
tubing.
To place water activated plastic:
– CT is run in the hole to the interval to be treated, and the well fluids are
circulated out to diesel. With the wellbore free of water, the plastic is pumped
through the coiled tubing with the annulus shut off.
– After the plastic is squeezed into the formation, the coiled tubing is shut in for
12 to 24 hours with sufficient wellhead pressure to prevent backflow of the
plastic from the formation.
62
Corrosion Inhibitor Placement
Stimulation
Coiled tubing is ideally suited for the selective placement (spotting) of acid and
can be used in a number of applications, including opening perforations and
dissolving acid soluble scale deposits.
Using coiled tubing in this manner avoids having to bullhead the well. Coiled tubing
allows acid to be circulated across the perforations and take the returns back up
the tubing.
In this way smaller amounts of acid can be used at lower pressures and the contact
time with the production tubing is reduced.
63
CT Conveyed Electric Line Services
Inflatable bridge plugs can be run through on coiled tubing, set in production liner
and subsequently retrieved.
The bridge plugs, manufactured by Lynes and Baker Oil Tools, consist of an
inflatable element that is set by pumping down the tubing and a hydraulic
disconnect which is activated by dropping a ball down the tubing and pressuring
up.
The tool has the advantage of being able to pass through restrictions in the tubing
and set in relatively large diameters.
64
Fishing Operations
Hydraulic snubbing units are made up from modular units which can be easily
transported and rigged up.
When locating the unit, care should be taken to ensure that the structure or
wellhead can support the weight of the unit together with any forces generated
during the snubbing operation. A hydraulic workover unit (HWU) consists of the
following components
– The hydraulic jack assembly, guide tube, window, travelling and stationary
slips, rotary table and power tongs.
– The work basket and control panel.
– Hydraulic power pack and accessories.
– Circulating swivel, kelly hose and pumps.
– BOP stack.
65
BOP Stack Configuration
66
Hydraulic Snubbing Unit
Between the two stripper rams is an equalising loop. This loop runs from below the
lower stripper ram to below the upper ram and is used to equalize the pressure
above the lower ram before opening it.
A choke is also included in the loop to regulate the rate of equalisation. These
chokes are changed out to suit the fluid in the well.
The vent line ties in below the upper stripping ram and is run to safe point away
from the snubbing unit. This line is used to bleed down the pressure between each
stripper ram.
The safety rams are located below the stripper rams and are used
to contain the well pressure in the event of a stripper ram failure or
a change in the stack. The safety rams are pipe rams and the
number used in the stack will depend on the well conditions and
planned operations. At least one set of safety rams must be
controlled from the basket.
These are the same as blind rams used in a drilling BOP and are
used to shut in the well when there is no pipe in the stack.
67
Hydraulic Snubbing Unit
Blind/shear rams will cut the pipe and close in the well in a emergency situation.
The ram and blade type must be tested prior to rig-up, to ensure that they will cut
the size and grade of pipe.
Outlet spools provide access to the wellbore and should always be located above
at least one pipe ram preventer and have double valve isolation.
The choke and kill lines are attached to an outlet spool or ram body and as the
name suggests are used to pump fluid into, or take returns from the well. These
lines must have a working pressure equivalent to the BOPs.
The cost of workovers on marginal or satellite developments, both with subsea and
unmanned platforms, is becoming a major factor in the economic viability of these
types of developments.
For many of the well problems outlined some form of remedial workover is
inevitable. Being able to perform the workover under pressure obviously has
advantages in terms of both time savings and reduced potential for formation
damage.
The choice is usually between an HWU and coiled tubing. The question of which
technique is appropriate is dependent on the type of operation and well
conditions.
68
Barrier Philosophy
Barriers:
In general, the well should have two reliable independent barriers
between reservoir and environment at all times.
Barrier Philosophy
Well Integrity:
Leaks of hydrocarbons or other damaging fluids should be
prevented during the life of the well.
Well Monitoring:
It is vital to be able to detect a leak of hydrocarbons from the
production string.
69
Well Control
The completion should have the ability to be plugged deep, if required, during the
life of the well.
When removing the BOPs, prior to installing a tree (conventional), there should be
two independent tested mechanical barriers, plus another barrier (i.e. safety valve)
between reservoir and environment.
When installing a completion, it should always be possible to circulate down and to
shut-in the well at surface.
Stimulation Techniques
III
70
Well Stimulation Objectives
71
Hydraulic Fracturing
Hydraulic fracturing is a stimulation technique which consists in fluid injection into the
formation at high flow rates, causing an increase in pressure and a subsequent
formation breaking.
Hydraulic Fracturing
72
Hydraulic Fracturing
Once pumping stops, the fracture closes. In order to prevent this, it is added propping agent o
the injected fluid to be transported into the fracture. When pumping stops and the fluids flows
back from the well, the propping agent remains in place to keep the fracture opened and
maintain a conductive flow path for the increased formation flow area during production.
Productivity increase is
attached to enhance the
reservoir performance
73
Hydraulic Fracturing Objectives
Productivity increase is
attached to increase the
Skin or zone of
altered Flowing Pressure Pwf bottom hole flowing
permeability pressure (BHP)
74
Hydraulic Fracturing Objectives
Productivity increase is
attached to reservoir
area in contact with the
“highway” to the well.
Productivity increase is
attached to reservoir area in
contact with the chemical
75
Hydraulic Fracturing Objectives
76
Hydraulic Fracturing Objectives
{ }
Production increase
Production increase
calculations
assumptions
• Steady state production
• Same drawdown for each production rate
• Single phase flow
• No skin damage for production before frac
77
Hydraulic Fracturing Objectives
104
Oil Flowrate
102
Without fracture
101 0
10 20 30
Time (months)
10000 1/4”
1/4”
3/8”
3/8”
7/16”
7/16”
8000
Productivity Index
6000
0.58 bpd/psi
4000
0 1000 2000 3000 4000 5000 6000
Oil flowrate (bpd)
78
Hydraulic Fracturing Design
• Production engineering
• Rock Mechanics
• Fluid Mechanics
• Selection of optimum materials
• Operations
79
Fracture Design Base Sequence
•Determine the injection rates, fluids and proppant volumes required and
fracture conductivity obtained.
•Calculated the NPV and perform a sensitivities analysis for and optimum
treatment design.
Geomechanical
80
Fracture Design - Input data
Reservoir
Fracture Fluids
81
Fracture Design - Input data
Completion
•Completion Schematic.
•Tubular and Connections Ratings
•Completion components specifications
82
Rock Mechanics in Hydraulic Fracturing
83
Rock Mechanics in Hydraulic Fracturing
Tortuosity
Minimum horizontal
stress
84
Rock Mechanics in Hydraulic Fracturing
Methods to determine stress orientation
85
Rock Mechanics in Hydraulic Fracturing
Geometry models
2D Model
The fracture height estimated remains constant for the simulation. The
fracture length grows from a line source of perforations, and all layers have
the same penetration. The simulation can be approximated by the average
modulus of all the layers.
•KGD the fracture height is relatively large compared with its length.
•PKN the fracture length is the much large compared with its height.
86
Rock Mechanics in Hydraulic Fracturing
Geometry models
Pseudo 3D model
The fracture initiates in the zone with the lower in-situ stress. The height growth
is determined by the bounding layers’ stress and other mechanical properties.
With a relatively low stress contrast, the two fractures join rapidly and behave
as a single fracture. The height growth depends on the stress and modulus
profile of the layers. The P3D model is a common geometry model for fracture
design.
Fracturing fluids
87
Fracturing fluids
100
80
Water
% Treatments
60
Oil
40
20
0
56 60 64 68 72 76 80 84 88 92 96 00 04
Year
Fracturing fluids
Oil fluids
• Non-damaging to clays
• Compatible with formation fluids
Water fluids
• Safe
• Available
• Economical
• Controlled break times
• Broad temperature range
88
Fracturing fluids-Viscosity
Viscosity
Newtonian Fluid
Viscosity = Stress / Shear Rate
Non-
Non-Newtonian Fluid
Viscosity µ= k/γ(1-n)
Power law Model of Viscosity used in Fracture Simulations
γ = Shear rate
k = Consistency Index.
n = Fluid Behaviour index
Fracturing fluids
• Polymers
• Cross linkers
• pH Control
• Gel Breakers
• Clay Control
• Surfactants
• Fluid loss Additives
• Biocides
89
Fracturing fluids - Polymers
+ H2O
90
Fracturing Fluids – Hydroxypropyl Guar (HPG)
91
Fracturing Fluids - Hydroxyethyl Cellulose (HEC)
92
Fracturing Fluids – LGC
• Borate
• Zirconium
• Titanium
Crosslink Reaction
• Antimony
• Aluminum
93
Fracturing Fluids – Crosslinked Frac fluids
CMHPG Zr 275
CMHPG Zr 400
G,HPG B 350
G,HPG B 300
G B 200
G Zr 275
G B+Zr 300
HPG Ti 300
pH8.1 pH9.1
350 pH9.5
200
150
100
50
94
Fracturing Fluids – Gel breakers
The most widely used fracturing fluid breakers are oxidizers and
enzymes.
Enzymes
• Soluble / 60 -140 °F / pH 4 -8
• Encapsulated / 75 - 175 °F / pH 4 –9
Oxidizers (Soluble and encapsulated)
• Ammonium peroxydisulfate
• Calcium peroxide
• Sodium bromate
Oxidizer: Its decomposition produces highly reactive sulphate
radicals that attack the polymer, reducing its molecular weight and its
viscosifyng ability.
95
Fracturing Fluids – Fluid loss
Fluid Loss
Fluid loss to the formation during a fracturing treatment is a
filtration process that is controlled by a number of parameters,
including fluid composition, flow rate and pressure, and reservoir
properties such as permeability, pressure, fluid saturation, pore
size and the presence of micro fractures.
Fluid Loss
Loss
Fracturing fluid
Uncontaminated Formation
96
Fracturing Fluids – Fluid loss
Spurt
Volume Lost
Cw
time
97
Fracturing Fluids – Low Polymer/High T
PrimeFRAC
Stable Low Polymer Rheology Over a Broad Temperature Range
(30 ppt polymer, Fann50 B5Bob, API Testing)
800
700
Viscosity @ 100 sec-1 (cp)
600
500
400 350°F
300 300°F
200 YF850HT -
300°F
100 250°F
0
0 50 100 150 200
Time (minutes)
Viscoelastic Surfactant
+ NH4Cl
e.g., KCl
Electrolyte
MgCl2
+ +
=
+ + +
+ + +
+ + +
+ + +
+ + + +
+ + + + +
+
+ + + + + + +
+ + + + + +
+ +
+
+ + +
+
+ + + +
+
+ + +
+
+ + + + + +
+ + + +
+
+
+ + +
+
+ + +
+
+ + + + +
+ + + +
+ + + + +
+ + + + +
+ + + +
+ + + + + +
+ + + + + +
+ +
+ + + +
+ +
+
+ + + + + +
+ +
+
+ +
+
+
+
+ + + +
+ +
+
+
+
+ +
+ +
+
98
Fracturing Fluids – Viscoelastic
z Dilution
z Breakers Available to
Hasten Fluid Recovery
99
Production increase
Q f ⎛ after frac ⎞
PI = ⎜ ⎟⎟
Qi ⎜⎝ before frac ⎠
6
of Productivity Index, J/J0
5
Folds of Increase
0
0 2 4 6 8 10
CfD
100
Conductivity considerations
Overview
101
Sandstone vs. Carbonate Acidizing
Sandstone:
• A small fraction of the matrix is soluble
• Relatively slow reacting acid dissolves the permeability damaging
minerals Wellbore
Damaged
Carbonate: zone
Key Issues
102
Candidate Selection
103
Data Sources
100
• WOC/GOC
offset well
10
Water oil contact
Gas-oil contact
1
0 20000 40000 60000 80000
Cumulative Oil, Bbls
100000 120000
Offset
Data Sources
104
Near-wellbore damage limits production
105
Sandstone Acidizing - Primary design considerations
Methodology
• Identify the damage mechanism
• Determine the mineralogy
• Know the well parameters
• Know the well fluids
• Select the specific system
• Apply the treatment
• Follow the results
106
Sandstone Acidizing – design - Mineralogy
107
Sandstone Acidizing – design/sandstones acids
Sandstones acids
The most common acids are Hydrochloric acid, HCl, and
Hydrofluoric Acid, HF.
HCl is used to dissolve carbonate minerals.
Mud Acid (Hydrofluoric/ Hydrochloric) is used to attack silicate
minerals such as clays and feldspars.
The regular mud acid is 12%HCl –3%HF
Some weak organic acid are used in special applications such high
temperature wells.
Sandstones acids
Usually sandstone acidizing means the use of fluids containing
Hydrofluoric Acid.
Sandstone acidizing differs drastically from carbonate acidizing.
In carbonate acidizing large quantities of rock are dissolved to
increase formation permeability.
In sandstone acidizing, the near-wellbore reaction removes the skin
damage caused by drilling, completion, fines migration, clay swelling,
etc.Only 1-2 inches of the wellbore are affected.
108
Sandstone Acidizing – HF reactions
HF reactions
Due to mineralogical differences, HF chemical reactions in sandstones
acidizing are very complex.
Carbonate acidizing involves only one reaction: the reaction of acid
with carbonate minerals to form calcium salts, water and carbon
dioxide .
109
Sandstone Acidizing - design
•Dissolving carbonates
•Pushing fluids out of the way
•Preparing formation through ion exchange
110
Sandstone Acidizing – design
111
Sandstone Acidizing – design
112
Acidizing Additives
Inhibitors
Surfactants
Foaming Agents
Mutual Solvents
Anti-sludge Agents
Non-Emulsifiers
Iron Control
Friction Reducers
Clay Control
Specialty Additives
Acid placement is one of the Five Stars for good matrix treatment design.
• Treatment strategy
• Formation damage characterization
• Placement technique
• Fluid volume and contact time
• Fluid compatibility
Several placement techniques are available
• Mechanical methods
• Bridging agents and diverters
• Self-selective fluids
113
Fluid Placement - Diversion
114
Fluid Placement - Diversion
Advantages:
• Less sensitive to chemical composition of fluid and temperature.
Disadvantages:
• Requires special equipment.
115
Diversion
Chemical Methods
Bridging agents (solids, bridge natural fractures) External
Particulates (Matrix) diverters
• Water Soluble
• Oil soluble
Viscous plugs Internal diverters
• Reactive
• Viscous-elastic surfactants
Foam
Advantages
– Don’t require rigs or special downhole tools.
Disadvantages
– Compatibility between diverter and fluids
• Solubility (T, fluid type)
• Dispersability
• Chemical
– Careful design required to match rock pore size distribution.
116
External Chemical Diversion
Physical requirements
– Low cake permeability
– Minimal matrix invasion
– Well dispersed material
Chemical requirements
– Compatibility
– Cleanup
– Constant cake properties
− ∆P Constant with temperature
− ∆P Constant with fluid type
Flow Redistribution
117
Oil Soluble Diverting Agents
118
Carbonate Field Test Results
119
Foam Mobility
120
Foam Diversion Process: Step 2
Foam injection
– Foam bank is formed in both layers
121
Foam Diversion Process: Step 4
Shut-in period
– Foam dissipates rapidly in damaged zone
122
Foam Diversion
Thief Zone
123
Damaged Fractures in a Horizontal Well
124
Dual Inflatable Packer
Downhole equipment
BHA
– Double check valve
– BHA fishing diagram
– Operating specifications
Nozzle design
DSP
125
Downhole Sensor Package (DSP)
DSP Components
M echanical
release sub
Cable clamp and assembly
check valve assembly
Pressur e and
temperature sensors
T reatment
ports/nozzle
126
Execution Precautions
Safety Considerations
Flow back
Unspent acid
Masks
Pin hole development
Swivel leaks
Communication devices
Gas detectors - H2S
Leather gloves/eye wash bottles/eye goggles
127
Foam diversion CT Rig Up
Nitrogen /Foam
generation
package
DSP configuration
CT Connector
CT Connector
FLOW BY HOUSING
CCL Schlumberger
Schlumberger FTPT
(optional) GRC
FTPT-ECCL
EPG-520
PEH-FTPT
gauge
Bullnose
Bullnose
128
Pressure Control Equip. Configuration
Stimulation of Carbonates
129
Alternative Dissolution Patterns
130
Acid Systems
Fracture Acidizing
131
Factors Influencing the Success of
Fracture Acidizing Treatments
Fluid-Loss Problems
132
Design
133
Design
Design
134
Design
Design
135
Design
Tip Screen-
Screen -out (TSO)
Screen-out
•The tip screen-out fracturing technique applies hydraulic
fracturing technology to create a wide, short, fracture that yields
high production rates with reduced pressure drops. It can be a
highly effective technique in controlling sand and stimulating
maximum production from weak formations.
Job execution
Strategic Locations
on a Pressure Response Curve
1- Formation Breakdown
2- Propagation
3- Instantaneous Shut-In
4- Closure Pressure From Fall-Off
136
Job execution
Near Wellbore friction
•Three mechanisms exist that are known to cause a rapid
pressure increase with time during a fracturing treatment: near
wellbore or perforation restriction, complex fracture geometry
and screen-out mode.
Job execution
137
Job execution
Pump Truck
Job execution
Equipment
138
Job execution
Equipment
Reference treatment
Qmax: 60 bbl/min
hhp used: 17600
hhp Available: 20000
Volume: 3.2 million lb proppant
Job execution
Equipment
Reference numbers
Qmax: 60 bbl/min
hhp Available: 13400
Volume: 12.7 million lb
proppant
139
Job execution
Job execution
140
Production Operations
IV
Production Operations
141
Production Operations
Production Operations
Product quality: is not limited to oil and gas quality; certain effluent streams will
also have to meet a legal specification. For example, in disposal of oil in water,
the legislation in many offshore areas demands less than 40 ppm (parts per
million) of oil in water for disposal into the sea. In the UK, oil production platforms
are allowed to flare gas up to a legal limit.
142
Production Operations
Production Operations
143
Production Operations
Production Operations
144
Production Operations
Production Operations
145
Production Operations
Production Operations
Pump
Gas Liquid
Separator
Test
Separator
146
Production Operations
Production Operations
147
Production Operations
Production Operations
148
Production Operations
Production Operations
149
Production Operations
Production Operations
150
Production Operations
Logistics refers to the organization of transport of people, and supply and storage
of materials. The transport of people is linked to the mode of manning the
operation, and is clearly much simplified for an unmanned operation.
For a typical operation in the North Sea, the transport of personnel to and from
the facilities is by helicopter. The transport of materials is normally by supply boat.
The storage of chemicals, lubricants, aviation fuel and diesel fuel is normally on the
platforms, with chemicals kept in bulk storage or in drums depending on the
quantities. A typical diesel storage would be adequate to run back-up power
generators for around a week, but the appropriate storage for each item would
need to be specified in the FDP.
Production Operations
151
Production Operations
Production Optimization
V
152
Production Optimization
During the production phase of the field life, the operator will apply
field management techniques aimed at maximising the profitability
of the project and realising the economical recovery of the
hydrocarbons, while meeting all contractual obligations and working
within certain constraints. Physical constraints include the reservoir
performance, the well performance, and the capacity and
operability of the surface facilities. The company will have to
manage internal factors such as manpower, cash supply and the
structure of the organisation. In addition, the external factors such as
agreements with contractors and the national oil company or
government, environmental legislation and market forces must be
managed throughout the production lifetime.
Production Optimization
153
Production Optimization
Production Optimization
154
Production Optimization
Production Optimization
155
Production Optimization
Production Optimization
During production, the operating conditions of any artificial lift technique will be
optimised with the objective of maximising production.
Sand production from loosely consolidated formations may lead to erosion of
tubulars and valves and sand-fill in both the sump of the well and surface
separators. In addition, sand may bridge off in the tubing, severely restricting flow.
The presence of sand production may be monitored by in-line detectors.
During production, the "health" of the well is monitored by measuring:
¾ Production rates (oil, water, gas)
¾ Pressures (tubing head and downhole)
¾ Sand production
156
Production Optimization
Production Optimization
157
Infill Drilling
VI
Infill Drilling
Oil and gas reservoirs are rarely as simple as early maps and sections imply. Even
though this is often recognized, development proceeds with the limited data
coverage available. As more wells are drilled and production information is
generated, early geological models become more detailed and the reservoir
becomes better understood. It may become possible to identify reserves which are
not being drained effectively and which are therefore potential candidates for
infill drilling. Infill drilling means drilling additional wells, often between the
original development wells. Their objective is to produce yet unrecovered oil.
158
Infill Drilling
Infill Drilling
159
Infill Drilling
In the case of attic/cellar oil, and isolated fault blocks or layers it is clear that
hydrocarbon reserves will not be recovered unless accessed by a well. The
economics of the incremental infill well may be very straightforward; a simple
comparison of well costs (including maintenance) against income from the
incremental reserves.
Infill Drilling
Reserves which have been bypassed by a flood front are more difficult to recover.
Water will take the easiest route it can find through a reservoir. In an
inhomogeneous sand, injected water or gas may reach producing wells via high
permeability layers without sweeping poorer sections. In time, a proportion of the
oil in the bypassed sections may be recovered, though inefficiently in terms of
barrels produced per barrel injected. Drilling an infill well to recover bypassed oil
will usually generate extra reserves as well as some accelerated production (of
reserves that would eventually have been recovered anyway). To decide whether
to drill additional wells it is necessary to estimate both the extra reserves
recovered, as well as the value of accelerating existing reserves.
160
Infill Drilling
Infill Drilling
161
Infill Drilling
Incremental Development
VII
162
Incremental Development
Most oil and gas provinces are developed by exploiting the largest
fields first, since these are typically the easiest to discover.
Development of the area often involves installing a considerable
infrastructure of production facilities, export systems and processing
plant. As the larger fields decline there may be considerable
working life left in the infrastructure which can be exploited to
develop smaller fields that would be uneconomical on a stand-alone
basis.
Incremental Development
163
Incremental Development
Incremental Development
Production
& Processing
Facilities
Production
&
Control Subsea
Export Satellite
SATELLITE DEVELOPMENT
164
Incremental Development
Incremental Development
165
Incremental Development
Incremental Development
166
Production Phase ©abalt solutions limited 2004 333
167