You are on page 1of 31

CV.

WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 001/SWPR/WM-S2P/IV/2014
Job Description : Persiapan Date : 7 April 2014
Period : 1 s/d 6 April 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 0,00% 0,00% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14%
B Support/ Bracing 4.247,23 Kg 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09%
##### Main Trolly 851,37 Kg 4,64%
##### Support Water Box 320,53 Kg 1,20%
##### Electric Room 658,34 Kg 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 0,00% 0,82% 0,82%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :
CV. WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 002/SWPR/WM-S2P/IV/2014
Job Description : Persiapan Date : 14 April 2014
Period : 7 s/d 13 April 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% - 0,00% 0,00% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14%
B Support/ Bracing 4.247,23 Kg 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09%
##### Main Trolly 851,37 Kg 4,64%
##### Support Water Box 320,53 Kg 1,20%
##### Electric Room 658,34 Kg 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 0,82% 0,00% 0,82%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :
CV. WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 003/SWPR/WM-S2P/IV/2014
Job Description : Persiapan Date : 21 April 2014
Period : 14 s/d 20 April 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14%
B Support/ Bracing 4.247,23 Kg 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09%
##### Main Trolly 851,37 Kg 4,64%
##### Support Water Box 320,53 Kg 1,20%
##### Electric Room 658,34 Kg 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 0,82% 0,00% 0,82%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :
CV. WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 004/SWPR/WM-S2P/IV/2014
Job Description : Persiapan Date : 28 April 2014
Period : 21 s/d 27 April 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14%
B Support/ Bracing 4.247,23 Kg 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09%
##### Main Trolly 851,37 Kg 4,64%
##### Support Water Box 320,53 Kg 1,20%
##### Electric Room 658,34 Kg 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 0,82% 0,00% 0,82%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :
CV. WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 005/SWPR/WM-S2P/IV/2014
Job Description : Persiapan Date : 30 April 2014
Period : 28 s/d 30 April 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14%
B Support/ Bracing 4.247,23 Kg 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09%
##### Main Trolly 851,37 Kg 4,64%
##### Support Water Box 320,53 Kg 1,20%
##### Electric Room 658,34 Kg 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 0,82% 0,00% 0,82%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 006/SWPR/WM-S2P/V/2014
Job Description : Fabrication, Dismantling and Erection Date : 05 May 2014
Period : 01 s/d 04 May 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14%
B Support/ Bracing 4.247,23 Kg 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09%
##### Main Trolly 851,37 Kg 4,64%
##### Support Water Box 320,53 Kg 1,20%
##### Electric Room 658,34 Kg 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 0,82% 0,00% 0,82%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 007/SWPR/WM-S2P/V/2014
Job Description : Fabrication, Dismantling and Erection Date : 12 May 2014
Period : 05 s/d 11 May 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14%
B Support/ Bracing 4.247,23 Kg 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09%
##### Main Trolly 851,37 Kg 4,64%
##### Support Water Box 320,53 Kg 1,20%
##### Electric Room 658,34 Kg 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 0,82% 0,00% 0,82%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 008/SWPR/WM-S2P/V/2014
Job Description : Fabrication, Dismantling and Erection Date : 19 May 2014
Period : 12 s/d 18 May 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 1.679,04 19,35% 6,99% 1.679,04 19,35% 6,99%
B Support/ Bracing 4.247,23 Kg 23,90% 919,28 21,64% 5,17% 919,28 21,64% 5,17%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09%
##### Main Trolly 851,37 Kg 4,64%
##### Support Water Box 320,53 Kg 1,20%
##### Electric Room 658,34 Kg 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 0,82% 12,17% 12,98%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 009/SWPR/WM-S2P/V/2014
Job Description : Fabrication, Dismantling and Erection Date : 26 May 2014
Period : 19 s/d 25 May 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 1.679,04 19,35% 6,99% 570,08 6,57% 2,37% 2.249,12 25,92% 9,37%
B Support/ Bracing 4.247,23 Kg 23,90% 919,28 21,64% 5,17% 1.654,49 38,95% 9,31% 2.573,77 60,60% 14,48%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 569,51 40,57% 2,47% 569,51 40,57% 2,47%
##### Main Trolly 851,37 Kg 4,64%
##### Support Water Box 320,53 Kg 1,20%
##### Electric Room 658,34 Kg 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 12,98% 14,15% 27,14%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya
Ika Kurniawan Pardi Suhardjo, S.
Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 010/SWPR/WM-S2P/V/2014
Job Description : Fabrication, Dismantling and Erection Date : 31 May 2014
Period : 26 s/d 31 May 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 2.249,12 25,92% 9,37% 2.249,12 25,92% 9,37%
B Support/ Bracing 4.247,23 Kg 23,90% 2.573,77 60,60% 14,48% 2.573,77 60,60% 14,48%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 569,51 40,57% 2,47% 823,34 58,65% 3,57% 1.392,85 99,22% 6,04%
##### Main Trolly 851,37 Kg 4,64% 716,95 84,21% 3,91% 716,95 84,21% 3,91%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 58,66 8,91% 0,25% 58,66 8,91% 0,25%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 27,14% 8,92% 36,06%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :
CV. WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 011/SWPR/WM-S2P/VI/2014
Job Description : Fabrication, Dismantling and Erection Date : 09 Juni 2014
Period : 01 s/d 08 Juni 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 2.249,12 25,92% 9,37% 5.090,00 58,65% 21,20% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 2.573,77 60,60% 14,48% 1.673,47 39,40% 9,42% 4.247,24 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.392,85 99,22% 6,04% 10,99 0,78% 0,05% 1.403,84 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 716,95 84,21% 3,91% 134,42 15,79% 0,73% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 58,66 8,91% 0,25% 234,63 35,64% 0,98% 293,29 44,55% 1,23%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 36,06% 32,37% 68,44%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :
CV. WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 012/SWPR/WM-S2P/VI/2014
Job Description : Fabrication, Dismantling and Erection Date : 16 Juni 2014
Period : 09 s/d 15 Juni 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 293,29 44,55% 1,23% 365,05 55,45% 1,52% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 68,44% 1,52% 69,96%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :
CV. WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 013/SWPR/WM-S2P/VI/2014
Job Description : Fabrication, Dismantling and Erection Date : 23 Juni 2014
Period : 16 s/d 22 Juni 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 69,96% 0,00% 69,96%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 014/SWPR/WM-S2P/VI/2014
Job Description : Fabrication, Dismantling and Erection Date : 30 Juni 2014
Period : 23 s/d 30 Juni 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 69,96% 0,00% 69,96%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 015/SWPR/WM-S2P/VII/2014
Job Description : Fabrication, Dismantling and Erection Date : 07 Juli 2014
Period : 01 s/d 06 Juli 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%
II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%
##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 69,96% 0,00% 69,96%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 016/SWPR/WM-S2P/VII/2014
Job Description : Fabrication, Dismantling and Erection Date : 14 Juli 2014
Period : 07 s/d 13 Juli 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 69,96% 0,00% 69,96%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya
Ika Kurniawan Pardi Suhardjo, S.
Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 017/SWPR/WM-S2P/VII/2014
Job Description : Fabrication, Dismantling and Erection Date : 21 Juli 2014
Period : 14 s/d 20 Juli 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 69,96% 0,00% 69,96%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :
CV. WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 018/SWPR/WM-S2P/VII/2014
Job Description : Fabrication, Dismantling and Erection Date : 28 Juli 2014
Period : 21 s/d 27 Juli 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 69,96% 0,00% 69,96%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :
CV. WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 019/SWPR/WM-S2P/VII/2014
Job Description : Fabrication, Dismantling and Erection Date : 31 Juli 2014
Period : 28 s/d 31 Juli 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 69,96% 0,00% 69,96%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 020/SWPR/WM-S2P/VIII/2014
Job Description : Fabrication, Dismantling and Erection Date : 04 Agustus 2014
Period : 01 s/d 03 Agustus 2014 Rev. :
Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 69,96% 0,00% 69,96%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 021/SWPR/WM-S2P/VIII/2014
Job Description : Fabrication, Dismantling and Erection Date : 11 Agustus 2014
Period : 04 s/d 10 Agustus 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22% 1,00 100,00% 1,22% 1,00 100,00% 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67% 0,50 50,00% 1,84% 0,50 50,00% 1,84%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59% 1,00 100,00% 7,59% 1,00 100,00% 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10%
##### Temporary Support 1,00 Lot 2,45% 1,00 100,00% 2,45% 1,00 100,00% 2,45%
II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%
##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 7.339,12 84,57% 30,56%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 69,96% 13,11% 83,07%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 022/SWPR/WM-S2P/VIII/2014
Job Description : Fabrication, Dismantling and Erection Date : 18 Agustus 2014
Period : 11 s/d 17 Agustus 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22% 1,00 100,00% 1,22% 1,00 100,00% 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67% 0,50 50,00% 1,84% 0,50 50,00% 1,84%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59% 1,00 100,00% 7,59% 1,00 100,00% 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10% 1,00 100,00% 1,10% 1,00 100,00% 1,10%
##### Temporary Support 1,00 Lot 2,45% 1,00 100,00% 2,45% 1,00 100,00% 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 7.339,12 84,57% 30,56% 1.338,91 15,43% 5,58% 8.678,03 100,00% 36,14%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 83,07% 7,49% 90,56%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya
Ika Kurniawan Pardi Suhardjo, S.
Supervisor Controler Project
Date : Date : Date :

CV. WIDARGO MULYO


Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 023/SWPR/WM-S2P/VIII/2014
Job Description : Fabrication, Dismantling and Erection Date : 25 Agustus 2014
Period : 18 s/d 24 Agustus 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22% 1,00 100,00% 1,22% 1,00 100,00% 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67% 0,50 50,00% 1,84% 0,50 50,00% 1,84%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59% 1,00 100,00% 7,59% 1,00 100,00% 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10% 1,00 100,00% 1,10% 1,00 100,00% 1,10%
##### Temporary Support 1,00 Lot 2,45% 1,00 100,00% 2,45% 1,00 100,00% 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 8.678,03 100,00% 36,14% 8.678,03 100,00% 36,14%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60%


##### Clean Up Area
TOTAL PROGRESS 100,00% 90,56% 0,00% 90,56%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :
CV. WIDARGO MULYO
Client Name : PT. Sumber Segara Primadaya
Project Name : Replacing Structure Stacker Reclaimer # 1
Location : PLTU Cilacap 2 x 300 MW, PT. Sumber Segara Primadaya

SUMMARY WEEKLY PROGRESS REPORT


Job No. : 063 / DIRUT-S2P/SPK/IV/2014 Ref. No. : 024/SWPR/WM-S2P/VIII/2014
Job Description : Fabrication, Dismantling and Erection Date : 28 Agustus 2014
Period : 26 s/d 28 Agustus 2014 Rev. :

Actual Progress ( % )
Contract
No Description Unit Weight Up To Last Week This Week Accumulative Remarks
Volume
Qty Prog. Weight Qty Prog. Weight Qty Prog. Weight

I Pekerjaan Persiapan 1,00 Lot 17,68%


##### Mobilisasi & Demobilisasi 1,00 Lot 1,22% 1,00 100,00% 1,22% 1,00 100,00% 1,22%
##### Install & Remove Scaffolding 1,00 Lot 3,67% 0,50 50,00% 1,84% 0,50 50,00% 1,84% 1,00 100,00% 3,67%
##### Safety Tools &Equipment 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Sewa Mobile Crane Cap. 25 Ton 1,00 Lot 7,59% 1,00 100,00% 7,59% 1,00 100,00% 7,59%
##### Remove & Setting Wire Sling Boom SR 1,00 Lot 0,82% 1,00 100,00% 0,82% 1,00 100,00% 0,82%
##### Remove & Setting Counter Weight SR 1,00 Lot 1,10% 1,00 100,00% 1,10% 1,00 100,00% 1,10%
##### Temporary Support 1,00 Lot 2,45% 1,00 100,00% 2,45% 1,00 100,00% 2,45%

II Pekerjaan Fabrikasi dan Erection 16.159,33 Kg 74,72%


##### Counter Weight Mechanism
A Main Frame 8.678,03 Kg 36,14% 8.678,03 100,00% 36,14% 8.678,03 100,00% 36,14%
B Support/ Bracing 4.247,23 Kg 23,90% 4.247,23 100,00% 23,90% 4.247,23 100,00% 23,90%
##### Steel Structure Lantai Tangki Hydrolik Boom 1.403,83 Kg 6,09% 1.403,83 100,00% 6,09% 1.403,83 100,00% 6,09%
##### Main Trolly 851,37 Kg 4,64% 851,37 100,00% 4,64% 851,37 100,00% 4,64%
##### Support Water Box 320,53 Kg 1,20% 320,53 100,00% 1,20% 320,53 100,00% 1,20%
##### Electric Room 658,34 Kg 2,75% 658,34 100,00% 2,75% 658,34 100,00% 2,75%

III Pekerjaan Finishing 1,00 Lot 7,60% 1,00 100,00% 7,60% 1,00 100,00% 7,60%
##### Clean Up Area
TOTAL PROGRESS 100,00% 90,56% 9,44% 100,00%
Prepared by, Checked by, Approved by,
CV. Widargo Mulyo PT. Sumber Segara Primadaya PT. Sumber Segara Primadaya

Ika Kurniawan Pardi Suhardjo, S.


Supervisor Controler Project
Date : Date : Date :