You are on page 1of 15

CONSUMO DIARIO DE FIERRO

PRODUCCIÓN PLANTAS INDUSTRIALES ALMACEN


CARLOS DANY JORGE FREDDY PLANTAS VALE POSIBLE
CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES EXTRAVIADO ADULTERACIÓN OTROS CAMPAMENTO TOTAL PESO (KG)

Acero de Refuerzo 3-8" 8,474.00 10,066.00 26.00 6.00 344.00 21.00 1,900.00 0.00 0.00 20,837.00 105,018.48
Acero de Refuerzo 1-2" 3,557.00 5,712.00 0.00 60.00 223.00 21.00 0.00 53.00 26.00 9,652.00 86,868.00
Acero de Refuerzo 5-8" 1,418.00 451.00 0.00 61.00 83.00 7.00 200.00 0.00 5.00 2,225.00 31,038.75
Acero de Refuerzo 3-4" 187.00 441.00 0.00 0.00 0.00 79.00 0.00 0.00 0.00 707.00 14,253.12
Acero de Refuerzo 1" 20.00 34.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 54.00 1,929.42
Total Var. 13,656.00 16,704.00 26.00 127.00 650.00 128.00 2,100.00 53.00 31.00 239,107.77
Total Peso (Kg) 98,987.58 118,537.47 131.04 1,421.19 4,898.61 1,985.13 12,366.00 477.00 303.75 239,107.77
6,450.84 25,603.83 SUBCONTRATISTAS
VALORIZADO A MARZO 63,962.12 65,293.21 9,500.00 1350 150 VAR
FALTANTE POR VALORIZAR 2,587.21 2,092.28
HABILITADO 25,185.59 29,076.60 15,950.84 266,061.60
STOCK KM 57+800 6,721.04
ACERO ENTREGADO A PLANTAS 4,150.71
ELOY RAMOS 4 D=1" + POZA DE MC 283.32
TOTAL VALORIZADO + HABILITADO 91,734.92 107,617.16 30,345.84 KG
7,916.00 STOCK ALMACEN
CONSIDERANDO 5% DE DESPERDICIO 96,321.67 112,440.26 22,429.84
CARLOS DANY ALMACEN TOTAL
DIFERENCIA POR SUSTENTAR (Kg) 2,665.91 6,097.21 6,435.13 = 15,198.25 FALTA SUSTENTAR 14,351.13 kg
Costo S/. 11,596.73 26,522.84 66,112.39 Costo S/. 7,675.00 kg
241.00 kg
2.91% 5.67% 7,916.00 kg

6,435.13 Almacen
27,992.82 Costo S/.

2.42%
CONSUMO DIARIO DE FIERRO DE 3/8" X 9 MTS
PRODUCCIÓN PLANTAS INDUSTRIALES
ITEM FECHA No.VALE No. FASE FIRMA FIRMA UND CANTIDAD CARLOS DANY JORGE FREDDY PLANTAS
DE DE FESE O AUTORIZADA RECIBI CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES
SALIDA SALIDA TERCEROS POR P/ALMACEN

1 31-Aug-08 000167 1007 Instalacion de Planta Carlos Camacho V. Santiago Herrera VLLS 5.00 5.00
2 31-Aug-08 000167 2301 Acero de Refuerzo Carlos Camacho V. Cristhoper Luque VLLS 446.00 446.00
3 31-Aug-08 000169 1002 Instalacion de Planta Carlos Camacho V. Victor Lazo VLLS 40.00 40.00
5 21-Sep-08 000207 2301 Acero de Refuerzo Santiago Herrera Christopher Luque VLLS 205.00 205.00
6 22-Sep-08 000207 3002 Preparacion en Planta de Suelos Santiago Herrera Christopher Luque VLLS 36.00 36.00
7 23-Sep-08 000207 2301 Acero de Refuerzo Santiago Herrera Christopher Luque VLLS 76.00 76.00
8 25-Sep-08 000289 2300 Acero de Refuerzo Cristhoper Luque Cristhoper Luque VLLS 83.00 83.00
9 31-Oct-08 000534 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 60.00 60.00
10 31-Oct-08 000534 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 26.00 26.00
11 31-Oct-08 000534 2301 Acero de Refuerzo Jacinto Zeña A. Santos Calderon Izquierdo VLLS 186.00 186.00
12 28-Nov-08 000789 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 723.00 723.00
13 30-Nov-08 000845 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 2.00 2.00
14 10-Dec-08 000950 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 2,859.00 1,059.00
15 28-Dec-08 001137 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 159.00 159.00
16 19-Jan-09 001221 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 992.00 892.00
17 30-Jan-09 001341 2301 Acero de Refuerzo Carlos Camacho V. Aldo Uska Paucar VLLS 440.00 440.00
18 31-Jan-09 001392 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 651.00 651.00
19 13-Feb-09 001501 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 307.00 307.00
20 13-Feb-09 001507 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 457.00 457.00
21 19-Feb-09 001573 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 184.00 184.00
22 19-Feb-09 001573 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 4.00
23 20-Feb-09 001588 2301 Acero de Refuerzo Aldo Uska Paucar Aldo Uska Paucar VLLS 78.00 78.00
24 12-Mar-09 001774 2301 Acero de Refuerzo Jacinto Zeña A. Dany Ramirez C VLLS 220.00 220.00
25 12-Mar-09 001774 2301 Acero de Refuerzo Jacinto Zeña A. Victor Lazo VLLS 218.00 218.00
26 12-Mar-09 001774 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 270.00 270.00
27 12-Mar-09 001774 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 883.00 833.00 50.00
28 12-Mar-09 001774 3002 Preparacion en Planta de Suelos Jacinto Zeña A. Aldo Uska Paucar VLLS 26.00 26.00
29 12-Mar-09 001774 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 954.00 954.00
30 12-Mar-09 001774 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 62.00 62.00
31 12-Mar-09 001774 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 12.00
32 14-Feb-09 001778 2302 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 212.00 212.00
33 25-Mar-09 001867 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 104.00 104.00
1 31-Aug-08 000166 1002 Instalacion de Planta Dany Ramirez C. Victor Lazo VLLS 218.00 218.00
2 23-Oct-08 000471 2301 Acero de Refuerzo Dany Ramirez C. Daniel Obregon VLLS 5,758.00 5,758.00
3 8-Dec-08 000899 3001 Procesamiento de Material Dany Ramirez C. Fredy Velille VLLS 6.00 6.00
4 19-Jan-09 001222 2101 Encofrado y Desencofrado Dany Ramirez C. Daniel Obregon VLLS 1,526.00 1,526.00
5 31-Jan-09 001384 2301 Acero de Refuerzo Dany Ramirez C. Rolando Angulo G. VLLS 220.00 220.00
6 7-Feb-09 001448 2301 Acero de Refuerzo Dany Ramirez C. Daniel Obregon VLLS 213.00 213.00
7 9-Feb-09 001490 2301 Acero de Refuerzo Dany Ramirez C. Daniel Obregon VLLS 217.00 217.00
8 13-Feb-09 001500 2301 Acero de Refuerzo Dany Ramirez C. Daniel Obregon VLLS 217.00 217.00
9 13-Feb-09 001500 2301 Acero de Refuerzo Dany Ramirez C. Rolando Angulo G. VLLS 217.00 217.00
10 25-Feb-09 001674 2101 Encofrado y Desencofrado Dany Ramirez C. Cristofer Luque VLLS 225.00 225.00
11 20-Mar-09 001824 2101 Encofrado y Desencofrado Dany Ramirez C. Obregon Loa, Daniel VLLS 438.00 438.00
12 25-Mar-09 001882 2101 Encofrado y Desencofrado Victor Lazo Napan David Huaman VLLS 215.00 215.00
13 28-Mar-09 001933 2101 Encofrado y Desencofrado Dany Ramirez C. Daniel Obregon VLLS 46.00 46.00
14 31-Mar-09 001945 2301 Acero de Refuerzo Dany Ramirez C. Daniel Obregon VLLS 91.00 91.00
15 31-Mar-09 001947 2301 Acero de Refuerzo Dany Ramirez C. Daniel Obregon VLLS 137.00 137.00
16 31-Mar-09 001973 2101 Encofrado y Desencofrado Dany Ramirez C. Daniel Obregon VLLS 108.00 108.00

PRODUCCIÓN PLANTAS INDUSTRIALES


CARLOS DANY JORGE FREDDY PLANTAS
CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES

C. Camacho RESUMEN Total VLLS 20,832.00 8,474.00 10,066.00 26.00 6.00 344.00
20,832.00
Nota: El vale de salida 000167 se descargo 109 varillas de 1/2" siendo de 3/8"
Nota: El vale de salida 000169 se descargo 40 varillas de 3/8" como 1/2"
ALMACEN
VALE POSIBLE
EXTRAVIADO ADULTERACIÓN OTROS

1,800.00

100.00

4.00

50 paraPlanta de Concreto

12.00
ALMACEN
VALE POSIBLE
EXTRAVIADO ADULTERACIÓN OTROS

16.00 1,900.00 0.00


CONSUMO DIARIO DE FIERRO DE 1/2" X 9 MTS
PRODUCCIÓN PLANTAS INDUSTRIALES
ITEM FECHA No.VALE No. FASE FIRMA FIRMA UND CANTIDAD CARLOS DANY JORGE FREDDY PLANTAS
DE DE FESE O AUTORIZADA RECIBI CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES
SALIDA SALIDA TERCEROS POR CONFORME P/ALM. vizcarra

1 31-Aug-08 00167 1007 Instal. de Planta Concreto Carlos Camacho V. Cristopher Luque VLLS 35.00 35.00
3 31-Aug-08 000169 1002 Instalacion de Planta Carlos Camacho V. Victor Lazo VLLS 40.00 40.00
7 31-Aug-08 00167 1003 Instalacion de Planta Carlos Camacho V. Edwin Vizcarra VLLS 40.00 40.00
11 21-Sep-08 00207 3002 Procesamiento de Material Santiago Herrera Christopher Luque VLLS 8.00 8.00
1 31-Aug-08 00166 1002 Instalacion de Planta Dany Ramirez C. Cristofer Luque VLLS 100.00 100.00

PRODUCCIÓN PLANTAS INDUSTRIALES


CARLOS DANY JORGE FREDDY PLANTAS
CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES

C.Camacho RESUMEN Total VLLS 9,652.00 3,557.00 5,712.00 0.00 60.00 223.00
9,652.00 228.00
5,484.00

Nota: El vale de salida 000167 se descargo 109 varillas de 1/2" siendo de 3/8"

Nota: El vale de salida 000169 se descargo 40 varillas de 1/2"


Nota: El vale de salida 000167 de 109 varillas se descargó dos veces
S
ALMACEN
VALE POSIBLE
EXTRAVIADO ADULTERACIÓN OTROS CAMPAMENTO COMENTARIO

VIZCARRA

ALMACEN
VALE POSIBLE
EXTRAVIADO ADULTERACIÓN OTROS CAMPAMENTO

21.00 0.00 53.00 26.00


CONSUMO DIARIO DE FIERRO DE 5/8" X 9 MTS
PRODUCCIÓN PLANTAS INDUSTRIALES
ITEM FECHA No.VALE No. FASE FIRMA FIRMA UND CANTIDAD CARLOS DANY JORGE FREDDY PLANTAS
DE DE FESE O AUTORIZADA RECIBI CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES
SALIDA SALIDA TERCEROS POR CONFORME

2 31-Aug-09 000167 3001 Procesamiento de Mat. Carlos Camacho V. Edwin Vizacarra VLLS 45.00 45.00
3 31-Aug-09 000167 1003 Instalacion de Planta Carlos Camacho V. Edwin Vizacarra VLLS 38.00 38.00

PRODUCCIÓN PLANTAS INDUSTRIALES


CARLOS DANY JORGE FREDDY PLANTAS
CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES

C. Camacho RESUMEN Total VLLS 2,225.00 1,418.00 451.00 0.00 61.00 83.00
2,225.00
ALMACEN
VALE POSIBLE
EXTRAVIADO ADULTERACIÓN OTROS CAMPAMENTO COMENTARIO

VIZCARRA
VIZCARRA

ALMACEN
VALE POSIBLE
EXTRAVIADO ADULTERACIÓN OTROS CAMPAMENTO

7.00 200.00 0.00 5.00


CONSUMO DIARIO DE FIERRO DE 3/4" X 9 MTS
PRODUCCIÓN PLANTAS INDUSTRIALES ALMACEN
ITEM FECHA No.VALE No. FASE FIRMA FIRMA UND CANTIDAD CARLOS DANY JORGE FREDDY PLANTAS VALE
DE DE FESE O AUTORIZADA RECIBI CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES EXTRAVIADO
SALIDA SALIDA TERCEROS POR CONFORME

1 30-Nov-08 000845 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 187.00 187.00
2 10-Dec-08 000950 2301 Acero de Refuerzo Jacinto Zeña A. Aldo Uska Paucar VLLS 79.00 79.00
1 23-Oct-08 000471 2301 Acero de Refuerzo Dany Ramirez C. Daniel Obregon VLLS 441.00 441.00

PRODUCCIÓN PLANTAS INDUSTRIALES ALMACEN


CARLOS DANY JORGE FREDDY PLANTAS VALE
CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES EXTRAVIADO

RESUMEN Total VLLS 707.00 187.00 441.00 0.00 0.00 0.00 79.00
ALMACEN
POSIBLE
ADULTERACIÓN OTROS

ALMACEN
POSIBLE
ADULTERACIÓN OTROS

0.00 0.00
CONSUMO DIARIO DE FIERRO DE 1" X 9 MTS
PRODUCCIÓN PLANTAS INDUSTRIALES
ITEM FECHA No.VALE No. FASE FIRMA FIRMA UND CANTIDAD CARLOS DANY JORGE FREDDY
DE DE FESE O AUTORIZADA RECIBI CAMACHO RAMIREZ SEMINARIO VELILLE
SALIDA SALIDA TERCEROS POR CONFORME

1 31-Aug-08 000167 2301 Acero de Refuerzo Carlos Camacho V. Victor Lazo VLLS 34.00 34.00 4
2 14-Feb-09 001778 2302 Acero de Refuerzo Carlos Camacho V. Uska Paucar, Aldo VLLS 20.00 20.00

PRODUCCIÓN PLANTAS INDUSTRIALES


CARLOS DANY JORGE FREDDY
CAMACHO RAMIREZ SEMINARIO VELILLE

C.Camacho RESUMEN Total VLLS 54.00 20.00 34.00 0.00 4.00


PLANTAS INDUSTRIALES ALMACEN
PLANTAS VALE POSIBLE
INDUSTRIALES EXTRAVIADO ADULTERACIÓN OTROS

PLANTAS INDUSTRIALES ALMACEN


PLANTAS VALE POSIBLE
INDUSTRIALES EXTRAVIADO ADULTERACIÓN OTROS

0.00 0.00 0.00 0.00


CONSUMO DIARIO DE FIERRO
PRODUCCIÓN PLANTAS INDUSTRIALES ALMACEN
CARLOS DANY JORGE FREDDY PLANTAS VALE POSIBLE
CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES EXTRAVIADO ADULTERACIÓN OTROS CAMPAMENTO TOTAL PESO (KG)

Acero de Refuerzo 3-8" 8,474.00 10,066.00 26.00 6.00 344.00 21.00 1,900.00 0.00 0.00 20,837.00 105,018.48
Acero de Refuerzo 1-2" 3,557.00 5,712.00 0.00 60.00 223.00 21.00 0.00 53.00 26.00 9,652.00 86,868.00
Acero de Refuerzo 5-8" 1,418.00 451.00 0.00 61.00 83.00 7.00 200.00 0.00 5.00 2,225.00 31,038.75
Acero de Refuerzo 3-4" 187.00 441.00 0.00 0.00 0.00 79.00 0.00 0.00 0.00 707.00 14,253.12
Acero de Refuerzo 1" 20.00 34.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 58.00 2,072.34
Total Var. 13,656.00 16,704.00 26.00 131.00 650.00 128.00 2,100.00 53.00 31.00 239,250.69
Total Peso (Kg) 98,987.58 118,537.47 131.04 1,564.11 4,898.61 1,985.13 12,366.00 477.00 303.75 239,250.69
6,593.76 25,603.83 SUBCONTRATISTAS
VALORIZADO A MARZO 66,549.33 77,132.94 9,500.00 1350 150 VAR
HABILITADO 25,185.59 25,634.27 16,093.76 266,204.52
STOCK KM 57+800 4,057.92
TOTAL VALORIZADO + HABILITADO 91,734.92 106,825.13 30,762.64 KG
7,916.00 STOCK ALMACEN
CONSIDERANDO 5% DE DESPERDICIO 96,321.67 112,166.39 22,846.64

DIFERENCIA POR SUSTENTAR (Kg) 2,665.91 6,371.08 15,472.13 FALTA SUSTENTAR 14,351.13 kg
Costo S/. 11,596.73 27,714.21 7,675.00 kg
CONSUMO DIARIO DE FIERRO
PRODUCCIÓN PLANTAS INDUSTRIALES ALMACEN
CARLOS DANY JORGE FREDDY PLANTAS VALE POSIBLE
CAMACHO RAMIREZ SEMINARIO VELILLE INDUSTRIALES EXTRAVIADO ADULTERACIÓN OTROS CAMPAMENTO TOTAL PESO (KG)

Acero de Refuerzo 3-8" 8,474.00 10,066.00 26.00 6.00 344.00 21.00 1,900.00 0.00 0.00 20,837.00 105,018.48
Acero de Refuerzo 1-2" 3,557.00 5,712.00 0.00 60.00 223.00 21.00 0.00 53.00 26.00 9,652.00 86,868.00
Acero de Refuerzo 5-8" 1,418.00 451.00 0.00 61.00 83.00 7.00 200.00 0.00 5.00 2,225.00 31,038.75
Acero de Refuerzo 3-4" 187.00 441.00 0.00 0.00 0.00 79.00 0.00 0.00 0.00 707.00 14,253.12
Acero de Refuerzo 1" 20.00 34.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 58.00 2,072.34
Total Var. 13,656.00 16,704.00 26.00 131.00 650.00 128.00 2,100.00 53.00 31.00 239,250.69
Total Peso (Kg) 98,987.58 118,537.47 131.04 1,564.11 4,898.61 1,985.13 12,366.00 477.00 303.75 239,250.69
6,593.76 25,603.83 SUBCONTRATISTAS
VALORIZADO A MARZO 66,549.33 67,385.49 9,500.00 1350 150 VAR
HABILITADO 25,185.59 29,076.60 16,093.76 266,204.52
STOCK KM 57+800 4,057.92
TOTAL VALORIZADO + HABILITADO 91,734.92 100,520.01 37,383.01 KG
7,916.00 STOCK ALMACEN
CONSIDERANDO 5% DE DESPERDICIO 96,321.67 105,546.01 29,467.01

DIFERENCIA POR SUSTENTAR (Kg) 2,665.91 12,991.46 22,092.50 FALTA SUSTENTAR 14,351.13 kg
Costo S/. 11,596.73 56,512.85 7,675.00 kg