Vojtech Gall
Gall Zeidler Consultants, Ashburn, Virginia
Nasri Munfah
Parsons Brinckerhoff, New York, New York
ABSTRACT: In the last 20 years the Sequential Excavation Method (SEM) or the New Austrian Tunneling
Method (NATM) has been gaining popularity and use in the United States. Its use is versatile, in various
ground conditions and at various depths. Although many of the projects were successfully completed, the
lack of design guidelines for underground construction and in particular for the SEM construction, in which
it relies on observational method and assessment of the ground behavior at the face, has negatively impacted
the tunneling industry. Recognizing the need to develop design guidelines for underground construction, in
2007 FHWA awarded a contract to Parsons Brinckerhoff to develop and publish a design manual for road
tunnels. As a result of this contract, “Technical Manual for Design and Construction of Road Tunnels—Civil
Elements” was published in November 2008. The Manual provided specific guidelines for SEM construction.
This paper provides a summary of the guidelines for the design and construction of tunnels using Sequential
Excavation Method with emphasis on its technical aspects, contractual issues, and practices in the US based on
the recommendations and guidelines made in the above stated publication.
415
worldwide including the Q system and the Rock Tunnel Support Model
Mass Rating (RMR) system and are used on rock
After assessing the ground support needs, excavation
tunneling projects to establish a geotechnical base-
and support sequences, subdivision into multiple
line and basis for the derivation of excavation and
drifts, as well as the support measures are defined.
support classification.
These are combined in Excavation and Support
Rock mass classification systems aid in the
Classes (ESCs) that form the basis for the Contractor
assessment of the ground behavior and ultimately
to develop a bid as well as to execute the tunnel work.
lead to the definition of the support required to sta-
bilize the tunnel opening. While the above quantita-
Excavation and Support Classes (ESC) and
tive classification systems lead to a numerical rating
Initial Support
system that results in suggestions for tunnel support
requirements these systems cannot replace a thor- Excavation and Support Classes (ESCs) contain
ough design of the excavation and support system by clear specifications for excavation round length, sub-
experienced tunnel engineers. division into multiple drifts, initial support and pre-
All classification systems have in common that support measures to be installed and the sequence of
they should be based on thorough ground investiga- excavation and support installation. They also define
tion and observation. The process from the ground means of additional initial support or local support or
investigation to the final definition of the ground sup- pre-support measures that augment the ESC to deal
port system can be summarized in three models: with local ground conditions that may require such
additional support. They also define supplemental
• Geological Model support if needed.
• Geotechnical Model Initial support is provided early on. In soft
• Tunnel Support Model ground and weak rock it directly follows the exca-
vation of a round length and is installed prior to
Geological Model proceeding to the excavation of the next round in
sequence. In hard rock tunneling initial support is
A desk study of the geological information avail-
installed close to the face. The intent is to provide
able for a project area forms the starting point of
structural support to the newly created opening and
the ground investigation program. Literature, previ-
ensure safe tunneling conditions. Initial support lay-
ous projects, maps and published reports (e.g., from
out is dictated by engineering principles, and risk
the US Geological Survey) form the basis for a desk
management needs.
study. Subsequently and in coordination with initial
The amount and design of the initial support
field observation and mapping results, a geotechnical
was historically motivated mainly by the desire to
investigation program is developed and carried out.
mobilize a high degree of ground self support and
The geological information from the geotechnical
therefore economy. This was possible at the outset of
investigation, field mapping, and the desk study are
SEM tunneling applications in “green field” condi-
compiled in the geological model.
tions where deformation control was of a secondary
importance and tolerable as long as equilibrium was
Geotechnical Model
reached. Nowadays, however, safety considerations,
With the data from the geological model in combi- risk management, robustness and conservatism,
nation with the test results from the ground inves- design life, and the need for minimizing settlements
tigation program and laboratory testing, the ground in urban settings add construction realities that ulti-
response to tunneling is assessed. This assessment mately decide on the layout of the initial support.
takes into account the method of excavation, tunnel Initial support is provided by application of a
size and shape as well as other parameters such as layer of shotcrete to achieve an interlocking support
overburden height, environmental issues, proximity with the ground. Shotcrete is typically reinforced by
of adjacent structures and facilities, and groundwa- steel fibers or welded wire fabric. Plastic fibers are
ter conditions. The geotechnical model assists in used for reinforcement only occasionally although
deriving zones of similar ground response to tun- its application appears to become more frequent.
neling along the alignment and Ground Response With higher support demands of the ground and with
Classes (GRC) are defined. These GRCs form the shotcrete thicknesses of generally 150 mm (6 inches)
baseline for the anticipated ground conditions dur- or greater lattice girders are embedded within the
ing tunneling. Typically, the ground response to an shotcrete to provide for the structural requirements.
unsupported tunnel excavation is analyzed in order Occasionally and if needed by special support needs
to assess the support requirements for the stabiliza- rolled steel sets are used in lieu of, or in combination
tion of the opening. with lattice girders.
416
ROCK BOLTS/DOWELS
STAGGERED C PRE-SPILING
L
TUNNEL
TOP HEADING
THEORETICAL EXCAVATION LINE
90°
LATTICE GIRDER
BENCH
INVERT
Figure 1 and Figure 2 show a prototypical ESC Geological data, Ground Response Classes,
cross section and longitudinal section respectively. Excavation and Support Classes, the Longitudinal
Figure 1 displays a cross section without a closed Tunnel Profile as well as design assumptions and
invert on the left side and ring closure on its right methods are described and displayed in reports that
side. Invert closure is typically required in soft become part of the contract documents. When defin-
ground and weak rock conditions and in squeezing ing the reaches and respective lengths of GRCs and
ground. Figure 2 includes elements of typical initial corresponding ESCs it is understood that these are a
support including rock bolts/dowels, initial shotcrete prognosis and may be different in the field. Therefore
lining and tunnel pre-support. The arrangement of contract documents establish the reaches as a basis
rock bolts/dowels is typical and varies depending and call for observation of the ground response in
on the excavation and support. The table in Figure 2 the field and the need for their adjustment as required
provides details of initial support measures for a pro- by actual conditions encountered. Actual conditions
totypical ESC Class IV. In that sense, conventional must be accurately mapped in the field to allow for a
tunneling is a prescriptive method which defines comparison with the baseline assumptions portrayed
clearly and in detail tunnel excavation and initial in the GRCs.
support means.
Tunnel Excavation, Support, and Pre-Support
Tunnel Profile and Distribution of Excavation Measures
and Support Classes
The use of most common initial support measures,
Contract documents contain all Excavation and along with excavation and support installation
Support Classes (ESCs) assigned along the tunnel sequencing frequently associated with conventional
alignment in accordance with the Ground Response tunnels depending on the basic types of ground
Classes (GRCs) and serve as a basis to estimate exca- encountered, i.e., rock and soft ground were summa-
vation and initial support quantities. A summary lon- rized and presented in the FHWA Technical Manual
gitudinal section along the tunnel alignment shows for Design and Construction of Road Tunnels. These
the anticipated geological conditions, the GRCs with tables indicate basic concepts to derive Excavation
the relevant description of the anticipated ground and Support Classes (ESCs) for typical ground con-
response, hydrological conditions and the distribu- ditions portrayed.
tion of the ESCs. Figure 3 displays a prototypical Table 1 in the manual addresses rock tun-
longitudinal profile with an overlay of GRCs and nels and builds on the use of Terzaghi’s Rock Mass
corresponding ESCs, which form a baseline for the Classification. It distinguished between the follow-
contract documents. ing rock mass qualities:
417
Figure 2. Prototypical Longitudinal Excavation and Support Class (ESC)
+700
ELEVATION (m)
+660
PORTAL PORTAL
+620
+580
STATION: 200 201 202 203 204 205 206 207
200+00
200+54
200+95
201+52
202+37
202+80
204+80
205+90
206+65
207+10
EXPECTED STATION:
GROUND RESPONSE CLASS RT-MS3 RT-MS3 RT-MB3 RT-QZT2 RT-MB2 RT-MB1 RT-MB2 RT-MB3 RT-MS4
WEATHERED WEATHERED FRACTURED WEATHERED WEATHERED
DESCRIPTION METASEDIMENTS METABASALT QUARTZITE
PARTIALLY WEATHERED TO FRESH METABASALT
METABASALT METASEDIMENTS
418
• Intact Rock support earth wedges, etc. form what is often referred
• Stratified Rock to as the “tool box” measures applied as required by
• Moderately Jointed Rock ground conditions.
• Blocky and Seamy Rock
• Crushed, but Chemically Intact Rock Instrumentation and Monitoring
• Squeezing Rock
An integral part of the SEM tunneling is the veri-
• Swelling Rock
fication by means of in-situ monitoring of design
assumptions made regarding the interaction between
Table 2 in the Manual shows elements com-
the ground and initial support as a response to the
monly used in excavation and support classes for soft
excavation process.
ground. It distinguishes among the various ground
For this purpose, a specific instrumentation and
types and the ground water conditions as follows:
monitoring program is laid out. The SEM instrumen-
tation aims at a detailed and systematic measurement
• Stiff cohesive soil—above groundwater table
of deflection of the initial lining. While monitoring
• Stiff cohesive soil—below groundwater table
of deformation is the main focus of instrumentation,
• Well consolidated non-cohesive soil—above
stresses in the initial shotcrete lining and stresses
groundwater table
between the shotcrete lining and the ground are mon-
• Well consolidated non-cohesive soil—below
itored to capture the stress regime within the lining
groundwater table
and between the lining and the ground. Reliability
• Loose non-cohesive soil—above groundwa-
of stress cells, installation complexity and difficulty
ter table
in obtaining accurate readings have nowadays led to
• Loose non-cohesive soil—below groundwa-
the reliance on deformation monitoring only in stan-
ter table
dard tunneling applications. Use of stress cells is typ-
ically reserved for applications where knowledge of
The tables are not meant to be a “cook-book”
the stress conditions is important, for example where
but rather guides to the engineers to determine the
high and unusual in-situ ground stresses exist or high
potential excavation and support classes to be used.
surface loads are present in urban settings.
Monitoring data are collected, processed and
Pre-support Measures and Ground
interpreted to provide early evaluations of:
Improvement: Tool Box Measures
With the significantly increased use of conventional • Adequate selection of the type of initial sup-
tunneling in particular in soft ground and urban port and the timing of support installation in
areas over the past decades, traditional measures conjunction with the prescribed excavation
to increase stand-up time were adopted and further sequence
developed to cope with poor ground conditions and • Stabilization of the surrounding ground by
to allow an efficient initial support installation and means of the self-supporting ground arch
safe excavation. phenomenon
These measures are installed ahead of the tun- • Performance of the work in excavation tech-
nel face. They include ground modification mea- nique and support installation
sures to improve the strength characteristics of the • Safety measures for the workforce and the
ground matrix including various forms of grout- public
ing, soil mixing and ground freezing, the latter for • Long-term stress/settlement behavior for
more adverse conditions. Most commonly methods final safety assessment
include mechanical pre-support measures such as • Assumed design parameters, such as strength
spiling installed ahead of the tunnel face often with properties of the ground and in-situ stresses
distances of up to 18 to 30 m (60 to 100 feet) referred used in the structural design computations
to as pipe arch canopies or at shorter distances, as
short as 3.6 m (12 ft) utilizing traditional spiling Based on this information, immediate decisions
measures such as grouted solid bars or grouted, per- can be made in the field concerning proper excava-
forated steel pipes. Ground improvement and pre- tion sequences and initial support in the range of
support measures can be used in a systematic manner the given ground response classes (GRC) and with
over long tunnel stretches or only locally as required respect to the designed excavation and support
by ground conditions. classes (ESC).
Local non-systematic use of not only pre-
support measures, but additional measures includ-
ing temporary Shotcreting the face, subdivision
into smaller excavation faces (multiple faces), face
419
Figure 4. Prototypical monitoring of a surface settlement point above the tunnel centerline in a
deformation vs. time and tunnel advance vs. time combined graph
420
This pre-qualification can occur very early on dur- Experienced Personnel
ing the design development, but at a minimum it
Because SEM tunneling strongly relies on experi-
should be performed as a separate step prior to solic-
ence and personnel skills, it is imperative that expe-
iting tunnel bids. On critical projects the owner may
rienced personnel be assigned from the start of the
solicit qualifications from contractors as early as the
project, i.e., in its planning and design phase. The
preliminary design stage. This early involvement
SEM tunneling design must be executed by an expe-
also ensures that contractors are aware of the upcom-
rienced designer.
ing work and can plan ahead in assembling a quali-
The SEM tunneling contract documents must
fied work force. Pre-qualification documents identify
identify minimum contractor qualifications regard-
the scope of work and call for a similar experience
less whether the project is executed in a design-
gained on past projects by a tunneling company and
bid-build, design-build or any other contractual
for key staff including project manager, tunnel engi-
framework. For example, if the project uses the
neers, and tunnel superintendents.
design-build framework then it is imperative that the
builder take on an experienced SEM tunnel designer.
Unit Prices
The construction contract documents must spell
To suit the method’s observational character and out minimum qualifications for the contractor’s per-
support its flexibility, it is recommended that SEM sonnel that will initially prepare and then execute
tunneling be procured within a unit price based con- the tunnel work. This is the case for field engineer-
tract. Unit prices also suit the need to install initial ing, field supervisory roles and the labor force that
support in accordance with a classification system must be skilled. Contract documents call for a mini-
and amount of any additional initial or local support mum experience of key tunneling staff by number
as required by field conditions actually encountered. of years spent in the field on SEM tunneling proj-
The following is bid on a unit price basis: ects of similar type. Experienced personnel include
Senior Tunnel Engineers, Tunnel Superintendents
• Excavation and Support on a linear meter and Tunnel Foremen. All of such personnel should
(foot) basis for all excavation and installation have a minimum of ten (10) years SEM tunneling
of initial support per Excavation and Support experience. These personnel are charged with guid-
Class (ESC). This includes any auxiliary ing excavation and support installation meeting the
measures needed for dewatering and ground key requirements of conventional tunneling:
water control at the face.
• Local support measures including: • Observation of the ground
–– Shotcrete per cubic meter (cubic yard) • Evaluation of ground behavior as it responds
installed. to the excavation process
–– Pre-support measures such as spiling, • Implementation of the “right” initial support
canopy pipes and any other support means
such as rock bolts and dowels, lattice gird- Face mapping including all ground exposed
ers, and face dowels are paid for each (EA) should occur for every excavation round and be for-
installed. mally documented and signed off by both the contrac-
–– Instrumentation and monitoring is paid for tor and the owner’s representative. Knowledgeable
either typical instrument section (includ- face mapping, execution of the instrumentation and
ing all instruments) or per each instru- monitoring program and interpretation of the moni-
ment installed. Payment is inclusive of toring results aid in the correct application of excava-
submitted monitoring results and their tion sequencing and support installation.
interpretation. The senior tunnel engineer is generally the
–– Ground improvement measures per unit contractor’s highest authority for the tunneling and
implemented, for example amount of grout supervises the excavation and installation of the ini-
injected including all labor and equipment tial support, installation of any local or additional
utilized. initial support measures and pre-support measures in
• Waterproofing and final lining installed to line with the contract requirements and as adjusted
complete the typical dual lining structure to the ground conditions encountered in the field.
may be procured on either lump sum basis or As a result the ground encountered is categorized in
on a per tunnel meter (foot) basis. accordance with the contract documents into ground
response classes (GRCs) and the appropriate exca-
The anticipated quantity of local support (addi- vation and support classes (ESC) per contract base-
tional or supplemental initial support) measures line. Any need for additional initial support and/or
should be part of the contract to establish a basis for pre-support measures is assessed and implemented.
bid. This task is carried out on a daily basis directly at the
421
active tunnel face and is discussed with the owner’s of risks should be clearly documented and proper
representative for each round. The outcome of this cost of accepting the risk should be included in the
process is subsequently documented on form sheets contract value.
that are then signed by the contractor’s and owner’s
representatives for concurrence. CONCLUSION
This frequent assessment of ground conditions
This paper highlights the recommendations made
provides for a continuous awareness of tunneling
by the FHWA “Technical Manual for Design and
conditions, for an early evaluation of adequacy of
Construction of Road Tunnels: Civil Elements”
support measures and as needed for implementation
for SEM tunneling construction and it includes
of contingency measures that may involve more than
the authors experience and insights on this sub-
additional initial support means. Such contingency
ject. The American Association of State Highway
measures may include heavy pre-support and face
and Transportation Officials (AASHTO), under its
stabilization measures or even systematic ground
Technical Committee T-20 on tunnels, adopted the
improvement measures.
manual and is in the process to publish it under its
To be able to support this on-going evalua-
domain. It is important to recognize that the manual
tion process on the owner’s behalf the construction
consists of guidelines and not code provisions and
management (CM) and inspection team must also
its use by the highway and road authorities of each
include relevant experience in conventional tunnel-
state is not mandatory. However, the lack of any
ing. It is recommended that the field representation
other authorities’ guidelines or codes renders this
includes a designer’s representative who is familiar
manual to be an invaluable source of information for
with the basis of the design. Represented in the field,
the design and construction of tunnels in the United
the designer is able to verify design assumptions,
States.
will aid in the implementation of the design intent,
and will make design changes on the spot if needed.
REFERENCES
Risk Management American Society of Civil Engineers (ASCE)
(2007). “Geotechnical Baseline Reports for
It is recommended that owners should initiate at
Construction – Suggested Guidelines,” NY.
the beginning of every SEM tunneling project a
Federal Highway Administration (FHWA) (2009)
risk management plan. The plan should continue
“Technical Manual for Design and Construction
throughout the design and construction phases. The
of Road Tunnels – Civil Element,” FHWA-
risks should be documented and managed with the
NHI-09-010, Washington, D.C.
best available tools at each phase. A risk register
ITA Working Group 19 (2008) “Conventional
should be established and maintained throughout
Tunnelling in the United States—Contractual
the life of the project. It is a living document that
Issues” V. Gall and N. Munfah.
should be updated regularly and the effectiveness
Underground Construction Association of Society of
of the mitigation measures should be reassessed as
Mining, Metallurgy, and Exploration, Inc (UCA
more information becomes available. Risks should
of SME) (2008) “Recommended Contract
be allocated or shared among the parties on the basis
Practices for Underground Construction.”
of who has better control of the risk. The allocation
422