You are on page 1of 2

ADVANCE POLYELECTRIC SYSTEMS, INC.

25-B Bayani St., Brgy. San Isidro, Galas, Quezon City


Tel. No. 413-3806 / Telefax No. 731-5238

______________________________________________________________________
REF: QPE10-124
September 18, 2010

FRONTIER POWER TECHNOLOGIES


Aguilar Compound, 683 Magsaysay Road,
Bgy. San Antonio,
San Pedro, Laguna

Attention : MIKE KAQUILALA


Subject : INSTALLATION OF 1500KW PRIME GENSET AND
CONSTRUCTION OF GENSET HOUSE
Project : FORT BONI

Dear Sir:

We are pleased to submit our quote for the above stated subject as follows:
Supply of labor and materials with technical supervision and use of tools for the following scope of works:

Fort Boni PS New 1500KW GENSET Schedule of Quantities


ITEM
NO. DESCRIPTION UNIT QTY UNIT PRICE TOTAL
A GENERAL ITEMS
1. Mobilization/Demobilization Lot 1 50,000.00 50,000.00
2 Implementation of construction Health and Safety Lot 1 30,000.00 30,000.00
Program
3 Permits Lot 1 100,000.00 100,000.00
Sub-total 180,000.00
B ELECTRO-MEECHANICAL-CIVIL WORKS (Design,
Supply, Construction and Installation)
1 Design, supply and construction of genset house Lot 1 1,260,000.00 1,260,000.00
rated for 1500 KW
2 Genset house soundproofing ( 50mm thk Rockwool Lot 1 700,000.00 700,000.00
type, 2-hours fire rated)
3 Supply and installation of main feeder breaker Lot 1 375,000.00 375,000.00
(3200At) rated for genset to be located at existing
MCC (GCB)
4 Re-routing / tapping of existing tapping point of Lot 1 150,000.00 150,000.00
1135KW genset (existing) to other side of MCC
busbar
5 Supply and installation of mechanical and electrical Lot 1 250,000.00 250,000.00
interlocking device system for Meralco and genset
power switching
6 Fuel Tank, Transfer pump and Fuel piping Lot 1 400,000.00 400,000.00
7 Exhaust muffler Lot 1 300,000.00 300,000.00
8 Radiator duct Lot 1 80,000.00 80,000.00
9 3,200AT, ACB, ATS Lot 1 950,000.00 950,000.00
10 Supply and installation of 8 sets:3x250mm² THHN Lot 1 795,000.00 795,000.00
from genset to GCB
11 Supply and installation of 8 sets:3x250mm² THHN Lot 1 4,257,000.00 4,257,000.00
from GCB to MTS
12 Supply and installation of 8 sets:3x250mm² THHN Lot 1 1,175,000.00 1,175,000.00
from MTS to existing MDP
13 Testing and commissioning (ASSIST) Lot 1 50,000.00 50,000.00
Sub-total 10,742,000.00
Grand-total 10,922,000.00

TERMS AND CONDITIONS:


A. Payment : 30% Downpayment balance thru progress billing
B. Completion : Within 90 days from receipt of PO, downpayment
and approval of shopdrawings whichever comes latest.
C. Warranty : One (1) year on materials against force majeure
D. Validity : One (1) month from receipt of this quote.

Thank you very much for giving us the opportunity to quote. We look forward to have a good working
relationship with you.

Truly yours,

MANOLITO M. GAMBOA
General Manager