What defines a “Project”?

Business scope: Waste to Energy, Renewable


Energy, Power Generation,
Petrochemical
Stage 1
What is the source material? MSW, Biomass, Natural Gas, other
……………………………………….
Do signed purchase/supply agreements for the materials exist? Y/N (verified)
Do signed Power purchase agreements exist? Y/N (verified)
Length of the Agreements? ? years
In the case of waste Projects, is there a waste analysis? Y/N (verified)
Has a FEED study been completed? Y/N (verified)
Has a preliminary design been completed? Y/N (verified)
By whom? Is there a copy? Y/N (verified)
Has the principle supply technology been decided? Y/N (verified)
Does a Mass Balance for the technology exist? Y/N (verified)
Are there reference sites for the technology? Y/N (verified)
Does land exist for the project? Y/N (verified)
Does a Land Purchase/Lease Pre- Agreement exist? Y/N (verified)
Does the site have appropriate zoning permission? Y/N (verified)
Has a Preliminary Business Plan been submitted? Y/N (verified)
Do we have P&L, Cash Flow projections? Y/N (verified)
Has financing been agreed in principle Y/N (verified)
Is there a copy of the financing offer Y/N (verified)

Stage 2
Are there Building Regulation Approvals? Y/N (verified)
Does the Project have EIA approval? Y/N (verified)
Has an EPC contractor been appointed Y/N (verified)