300𝑚 + 318𝑚
𝑉𝑝𝑎𝑟𝑒𝑑𝑒𝑠 = [( ) × 9,49𝑚 × 0,3𝑚] × 4 = 3.518,89𝑚3
2
𝑉𝑇𝑜𝑡𝑎𝑙 = 30.518,89𝑚3
EXCAVACIÓN Y CARGUÍO
a) Canal
2,1𝑚3 × 60 3
𝑄𝑇 = = 360 𝑚 ⁄ℎ
0,35
3 3
𝑄𝑅 = 360 𝑚 ⁄ℎ × 0,83 × 0,86 × 1 = 256,97 𝑚 ⁄ℎ
𝟐𝟏. 𝟒𝟐𝟎𝒎𝟑
𝑻𝒆𝒙𝒄𝒂𝒗𝒂𝒄𝒊ó𝒏 = 𝟑 = 𝟖𝟑, 𝟑𝟓𝒉
𝟐𝟓𝟕 𝒎 ⁄𝒉
0,8𝑘𝑚
𝑇1 = = 0,16ℎ
5𝑘𝑚/ℎ
2,5𝑘𝑚
𝑇1 = = 0,1ℎ
25𝑘𝑚/ℎ
2,5𝑘𝑚
𝑇1 = = 0,0625ℎ
40𝑘𝑚/ℎ
0,8𝑘𝑚
𝑇1 = = 0,08ℎ
10𝑘𝑚/ℎ
𝑻𝒕𝒓𝒂𝒏𝒔𝒑𝒐𝒓𝒕𝒆 = 𝟎, 𝟏𝟔𝒉 + 𝟎, 𝟏𝒉 + 𝟎, 𝟎𝟔𝟐𝟓𝒉 + 𝟎, 𝟎𝟖𝒉 =0,4025h
𝑉𝑐𝑎𝑚𝑖ó𝑛 = 20𝑚3
𝑉𝑒𝑠𝑝𝑜𝑛𝑗𝑎𝑑𝑜 = 21.420𝑚3 × 1,18 = 25.275,6𝑚3
25.276𝑚3
𝑁º𝑣𝑖𝑎𝑗𝑒𝑠 = = 1.264 𝑣𝑖𝑎𝑗𝑒𝑠
20𝑚3
1.264 𝑣𝑖𝑎𝑗𝑒𝑠
𝑁º𝑣𝑖𝑎𝑗𝑒𝑠 𝑡𝑜𝑡𝑎𝑙 = = 632 𝑣𝑖𝑎𝑗𝑒𝑠 𝑝𝑜𝑟 𝑐𝑎𝑚𝑖ó𝑛
2
𝑻𝒕𝒐𝒕𝒂𝒍 = 𝟔𝟑𝟐 × 𝟎, 𝟒𝟎𝟐𝟓𝒉 = 𝟐𝟓𝟒, 𝟑𝟖𝒉
3,1𝑚3 × 60 3
𝑄𝑇 = = 620 𝑚 ⁄ℎ
0,3
3 3
𝑄𝑅 = 620 𝑚 ⁄ℎ × 0,6 × 0,75 × 0,61 = 170,19 𝑚 ⁄ℎ
𝟐𝟓. 𝟐𝟕𝟔𝒎𝟑
𝑻𝒄𝒂𝒓𝒈𝒂 = 𝟑 = 𝟏𝟒𝟖, 𝟓𝟏𝒉
𝟏𝟕𝟎, 𝟏𝟗 𝒎 ⁄𝒉
b) Tranque
3 3
𝑄𝑅 = 220 𝑚 ⁄ℎ × 1 × 1,15 × 0,92 = 232,76 𝑚 ⁄ℎ
1,1𝑚3 × 60 3
𝑄𝑇 = = 220 𝑚 ⁄ℎ
0,3
𝟐𝟑𝟓. 𝟔𝟎𝟐𝒎𝟑
𝑻𝒆𝒙𝒄𝒂𝒗𝒂𝒄𝒊ó𝒏 = 𝟑 = 𝟏. 𝟎𝟏𝟐, 𝟐𝟏𝒉
𝟐𝟑𝟐, 𝟕𝟔 𝒎 ⁄𝒉
𝟏𝟎𝟖. 𝟑𝟑𝟖𝒎𝟑
𝑻𝒆𝒙𝒄𝒂𝒗𝒂𝒄𝒊ó𝒏 = 𝟑 = 𝟒𝟔𝟓, 𝟒𝟒𝒉
𝟐𝟑𝟐, 𝟕𝟔 𝒎 ⁄𝒉
𝑻𝒆𝒙𝒄𝒂𝒗𝒂𝒄𝒊ó𝒏 𝒕𝒐𝒕𝒂𝒍 = 𝟏. 𝟎𝟏𝟐, 𝟐𝟏𝒉𝟒𝟔𝟓, 𝟒𝟒𝒉 = 𝟏. 𝟒𝟕𝟕, 𝟔𝟔𝒉
0,9𝑚3 × 60 3
𝑄𝑇 = = 76,74 𝑚 ⁄ℎ
30 30
183,3 + 250 + 0,42
3 3
𝑄𝑅 = 76,74 𝑚 ⁄ℎ × 0,61 × 1 × 0,95 = 44,47 𝑚 ⁄ℎ
𝟑𝟖. 𝟒𝟓𝟑, 𝟖
𝑻𝒆𝒙𝒄𝒂𝒗𝒂𝒄𝒊ó𝒏 = 𝟑 𝟖𝟔𝟒, 𝟕𝟏𝒉
𝟒𝟒, 𝟒𝟕 𝒎 ⁄𝒉
CONCLUSIÓN
En relación a los datos recopilados por el catálogo del fabricante y lo expuesto por
el mandante, se evidencia un proyecto con una gran inversión económica, para la puesta en
marcha de las maquinarias, mano de obra y costos variables.
En las excavaciones, se observan diversos tipos de suelos, lo que hacen variar los
rendimientos de las maquinarias, influenciando directamente en los plazos de ejecución y
en los costos del proyecto.