UNID CANT V. UNIT. VALOR HASTA ACTA CANTI. VALOR CANTI. VALOR
%
CONT CONT TOTAL ANTERIOR EJECUT. TOTAL EJECUT. TOTAL CANTI VALOR TOTAL EJECUTADO
1,01 Replanteo Ejes de Obra m2 460,63 $3.587 $1.652.280 0,00 460,6 $1.652.280 461 $1.652.280 0 0 100%
1,02 Descapote y Nivelación de Terrenom3 149,64 $1.394 $208.598 0,00 139 $193.766 139 $193.766 11 14.832 93%
1,03 Cerramiento de obra en tela verdemlh=2.00mts
114,00 $7.224 $823.536 0,00 117 $845.208 117 $845.208 -3 -21.672 103%
1,04 Campamento de Obra ( 12 x 4 ) m2 48,00 $104.405 $5.011.460 0,00 48 $5.011.460 48 $5.011.460 0 0 100%
3,01 Muros en Bloque # 5 m2 337,92 $21.927 $7.409.572 0,00 200 $4.385.400 200 $4.385.400 138 3.024.172 59%
You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
ACTA PARCIAL DE PAGOS
UNID CANT V. UNIT. VALOR HASTA ACTA CANTI. VALOR CANTI. VALOR
%
CONT CONT TOTAL ANTERIOR EJECUT. TOTAL EJECUT. TOTAL CANTI VALOR TOTAL EJECUTADO
3,02 Pañete de Muros m2 503,09 $14.017 $7.051.813 0,00 200,3 $2.807.605 200 $2.807.605 303 4.244.207 40%
4,01 Antepisos de Nivelación E= 0,07 m2 486,57 $15.869 $7.721.379 0,00 205,4 $3.259.493 205 $3.259.493 281 4.461.887 42%
6,01 Puntos sanitarios de 4" Und 38,00 $61.684 $2.343.992 0,00 10 $616.840 10 $616.840 28 1.727.152 26%
6,02 Bajantes Sanitarios ml 34,00 $24.294 $825.996 0,00 15 $364.410 15 $364.410 19 461.586 44%
6,03 Puntos Hidráulicos de 1/2" Und 63,00 $26.816 $1.689.408 0,00 20 $536.320 20 $536.320 43 1.153.088 32%
6,05 Tubería de 1/2" Hidráulica ml 114,60 $4.596 $526.702 0,00 53 $243.588 53 $243.588 62 283.114 46%
6,06 Tubería Hidráulica de 1" ml 30,96 $7.222 $223.593 0,00 7 $50.554 7 $50.554 24 173.039 23%
6,07 Tubería de 3/4" Hidráulica ml 45,00 $5.895 $265.275 0,00 12 $70.740 12 $70.740 33 194.535 27%
6,08 Caja Sanitarias de 80x80 Und 9,00 $260.311 $2.342.799 0,00 9 $2.342.799 9 $2.342.799 0 0 100%
6,09 Instalación de tubería Sant. de 4" ml 29,50 $25.028 $738.326 0,00 30 $750.840 30 $750.840 -1 -12.514 102%
6,10 Instalación de tubería ALL. de 4" ml 99,90 $25.028 $2.500.297 0,00 99,9 $2.500.297 100 $2.500.297 0 0 100%
8,01 Aseo de obra Día 24,00 $41.842 $1.004.208 0,00 10,00 $418.420 10 $418.420 14 585.788 42%
$327.938.968 $236.239.477 $236.239.477 $91.699.491