You are on page 1of 2

ACTA PARCIAL DE PAGOS

. O B R A C O N T R A T A D A CANTIDAD PRESENTE TOTAL EJECUTADO POR EJECUTAR


ITEM ACTIVIDAD EJECUTADA LIQUIDACION LA PRESENTE

UNID CANT V. UNIT. VALOR HASTA ACTA CANTI. VALOR CANTI. VALOR
%
CONT CONT TOTAL ANTERIOR EJECUT. TOTAL EJECUT. TOTAL CANTI VALOR TOTAL EJECUTADO
1,01 Replanteo Ejes de Obra m2 460,63 $3.587 $1.652.280 0,00 460,6 $1.652.280 461 $1.652.280 0 0 100%
1,02 Descapote y Nivelación de Terrenom3 149,64 $1.394 $208.598 0,00 139 $193.766 139 $193.766 11 14.832 93%
1,03 Cerramiento de obra en tela verdemlh=2.00mts
114,00 $7.224 $823.536 0,00 117 $845.208 117 $845.208 -3 -21.672 103%
1,04 Campamento de Obra ( 12 x 4 ) m2 48,00 $104.405 $5.011.460 0,00 48 $5.011.460 48 $5.011.460 0 0 100%

Excavaciones para Zapatas H= 3


2,01 m3 394,71 $25.127 $9.917.878 0,00 405 $10.176.435 405 $10.176.435 -10 -258.557 103%
mts. Incluye Retiro de Escombros

Concreto Ciclópeo 17,5 Mpa.


2,02 m3 63,51 $150.675 $9.569.369 0,00 60 $9.040.500 60 $9.040.500 4 528.869 94%
Base de Zapatas
Zapatas en Concreto para
2,03 m3 43,54 $424.380 $18.477.505 0,00 45 $19.097.100 45 $19.097.100 -1 -619.595 103%
Columnas
2,04 Columnas en Concreto Reforzado ml de 1 x 0,4
58,72 $275.831 $16.196.796 0,00 55 $15.170.705 55 $15.170.705 4 1.026.091 94%
2,05 Columnas Redondas de 0,5 ml 55,29 $214.533 $11.861.530 0,00 53 $11.370.249 53 $11.370.249 2 491.281 96%
2,06 Columnas Redondas de 0,4 ml 18,00 $170.467 $3.068.406 0,00 17,5 $2.983.173 18 $2.983.173 1 85.234 97%
2,07 Columnas Redondas de 0,6 para sobreml cimiento
12,43 $262.255 $3.259.830 0,00 13 $3.409.315 13 $3.409.315 -1 -149.485 105%
2,08 Columnas Cuadradas de 0,4 x 0,3 ml 90,24 $99.925 $9.017.232 0,00 90 $8.993.250 90 $8.993.250 0 23.982 100%
2,09 Columnas Cuadradas de 0,6 x 0,3 ml 87,48 $141.020 $12.336.430 0,00 88 $12.409.760 88 $12.409.760 -1 -73.330 101%
2,10 Rellenos Compactados con Material m3de Excavación
287,66 $13.904 $3.999.625 0,00 300 $4.171.200 300 $4.171.200 -12 -171.575 104%
Excavaciones para cimentación,
2,11 Viga de Amarre, Incluye Retiro m3 38,73 $23.112 $895.128 0,00 40 $924.480 40 $924.480 -1 -29.352 103%
de Escombros
Viga de Amarre Inferior 0,5 X 0,40
2,12 Incluye Concreto de Limpieza ml 182,28 $107.952 $19.677.491 0,00 100 $10.795.200 100 $10.795.200 82 8.882.291 55%
(Solado)
Piso en Concreto E= 0,10 (Incluye
2,13 Relleno Compactado en Grava m2 658,41 $44.335 $29.190.607 0,00 350 $15.517.250 350 $15.517.250 308 13.673.357 53%
Seleccionada E=0,20)
2,14 Placa de entre piso en metaldeckm2 492,68 $75.124 $37.012.092 0,00 245 $18.405.380 245 $18.405.380 248 18.606.712 50%
2,19 Muros y Placas en Concreto Ascensor
m3 5,26 $576.643 $3.033.142 0,00 3 $1.729.929 3 $1.729.929 2 1.303.213 57%
2,21 Acero de 3/8" a 1" kg 33270,00 $2.848 $94.752.960 0,00 22000 $62.656.000 22.000 $62.656.000 11.270 32.096.960 66%

3,01 Muros en Bloque # 5 m2 337,92 $21.927 $7.409.572 0,00 200 $4.385.400 200 $4.385.400 138 3.024.172 59%

You created this PDF from an application that is not licensed to print to novaPDF printer (http://www.novapdf.com)
ACTA PARCIAL DE PAGOS

. O B R A C O N T R A T A D A CANTIDAD PRESENTE TOTAL EJECUTADO POR EJECUTAR


ITEM ACTIVIDAD EJECUTADA LIQUIDACION LA PRESENTE

UNID CANT V. UNIT. VALOR HASTA ACTA CANTI. VALOR CANTI. VALOR
%
CONT CONT TOTAL ANTERIOR EJECUT. TOTAL EJECUT. TOTAL CANTI VALOR TOTAL EJECUTADO
3,02 Pañete de Muros m2 503,09 $14.017 $7.051.813 0,00 200,3 $2.807.605 200 $2.807.605 303 4.244.207 40%

4,01 Antepisos de Nivelación E= 0,07 m2 486,57 $15.869 $7.721.379 0,00 205,4 $3.259.493 205 $3.259.493 281 4.461.887 42%

6,01 Puntos sanitarios de 4" Und 38,00 $61.684 $2.343.992 0,00 10 $616.840 10 $616.840 28 1.727.152 26%
6,02 Bajantes Sanitarios ml 34,00 $24.294 $825.996 0,00 15 $364.410 15 $364.410 19 461.586 44%
6,03 Puntos Hidráulicos de 1/2" Und 63,00 $26.816 $1.689.408 0,00 20 $536.320 20 $536.320 43 1.153.088 32%
6,05 Tubería de 1/2" Hidráulica ml 114,60 $4.596 $526.702 0,00 53 $243.588 53 $243.588 62 283.114 46%
6,06 Tubería Hidráulica de 1" ml 30,96 $7.222 $223.593 0,00 7 $50.554 7 $50.554 24 173.039 23%
6,07 Tubería de 3/4" Hidráulica ml 45,00 $5.895 $265.275 0,00 12 $70.740 12 $70.740 33 194.535 27%
6,08 Caja Sanitarias de 80x80 Und 9,00 $260.311 $2.342.799 0,00 9 $2.342.799 9 $2.342.799 0 0 100%
6,09 Instalación de tubería Sant. de 4" ml 29,50 $25.028 $738.326 0,00 30 $750.840 30 $750.840 -1 -12.514 102%
6,10 Instalación de tubería ALL. de 4" ml 99,90 $25.028 $2.500.297 0,00 99,9 $2.500.297 100 $2.500.297 0 0 100%

7,03 Acometida del contador al tablero


ml 143,25 $23.272 $3.333.714 0,00 143,5 $3.339.532 144 $3.339.532 0 -5.818 100%

8,01 Aseo de obra Día 24,00 $41.842 $1.004.208 0,00 10,00 $418.420 10 $418.420 14 585.788 42%
$327.938.968 $236.239.477 $236.239.477 $91.699.491

TOTAL COSTOS DIRECTOS 236.239.477,37


COSTOS INDIRECTOS:
(+) ADMINSTRACION: 23.623.947,74
(+) IMPREVISTOS: 11.811.973,87
(+) UTILIDAD: 23.623.947,74
SUBTOTAL COSTOS DIRECTOS+ INDIRECTOS 295.299.346,71
(-) AMORTIZACION DE ANTICIPO: (15%) 44.294.902,01
(-) OTRAS RETENCIONES (MUNICIPALES O
DEPARTAMENTALES)
50.200.888,94
(+) IVA SOBRE LA UTILIDAD: 4.488.550,07
TOTAL A PAGAR EN LA PRESENTE ACTA 205.292.105,83