Professional Documents
Culture Documents
Hoist Owner:
Hoist Location:
Builder:
Hoist Hirer:
Servicemen:
Authorised by Pat Preston, Manager, CFMEU Environmental & Occupational Health & Safety Unit.
Service and Maintenance Checklist
7. Check that Main Wiring Diagram is Located in Roof Control Panel. Satisfactory
9. Check that Structure Tie Bolts are Correctly Fitted and Tightened. Satisfactory
10. Check that Structure Ties are Installed as per Engineers Design. Satisfactory
11. Check Base Frame Bolts are Correctly Fitted and Tightened. Satisfactory
13. Check that Main Power Supply Cable is Installed Satisfactorily. Satisfactory
15. Inspect Tower Sections for Damage, Deformation, Cracking, etc. Satisfactory
16. Check Base Frame Bolts are Correctly Fitted and Tightened. Satisfactory
17. Check Doorframe Shackles are Tight and Securely Wired. Satisfactory
18. Check that Main Power Supply Cable is installed Satisfactorily. Satisfactory
20. Inspect Tower Sections for Damage, Deformation, Cracking, etc. Satisfactory
22. Check Wire Guide Placement (ie at intervals < 6 metres). Satisfactory
Authorised by Pat Preston, Manager, CFMEU Environmental & Occupational Health & Safety Unit.
23. Check Overrun Buffers/Dampers are installed Correctly. Satisfactory
24. Check that Topmost Tower is not Fitted with a Rack. Satisfactory
Authorised by Pat Preston, Manager, CFMEU Environmental & Occupational Health & Safety Unit.
b) Door "B" Limit. Satisfactory
33. Lubrication:
a) Rack. Satisfactory
Comments:
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
………………………………………………………………………………………………………………………
Signature: ……………………………………..…
Authorised by Pat Preston, Manager, CFMEU Environmental & Occupational Health & Safety Unit.