CALCULATION SUMMARY

Project Name : Videna Project Location: Sistema contra incendios-Velódromo

Drawing No. : Red General City: LIMA, PERÚ

Design Areas
Design Area Calc. Mode Occupancy Area of Total Water Pressure @ Min. Min. Min. Calculated Hose Margin To
Name (Model) Application Source Density Pressure Flow Heads Streams Source

(ft²) (gpm) (psi) (gpm/ft²) (psi) (gpm) # (gpm) (psi)

Required
DesignArea_1 Demand (HW) 0 250 0 100 250 1 0 25
134.6

File: X:\ESSAC\TECNICA\GENERAL\PROYECTOS\001525\TEMPORAL\ACI\05_10\CH\VELÓDROMO\Anexo
Date 16/05/2018 1.tyc3
Page 1
Copyright © 2002-2012 Tyco Fire Protection Products
HYDRAULIC CALCULATIONS
for
Job Information
Project Name : Videna

Contract No. : Red General City: LIMA, PERÚ

Project Location: Sistema contra incendios-Velódromo Date: 27/04/2018

Contractor Information
Name of Contractor: ENGINEERING SERVICES S.A.C.

Address: Av. República de Panamá 4575 Surquillo City: LIMA, PERU LIMA 18

Phone Number: 445 8215 E-mail: www.essacweb.com

Name of Designer: Y. VEGA

Authority Having Jurisdiction: CGBVP

Design
Remote Area Name DesignArea_1

Remote Area Location

Occupancy Classification

Density (gpm/ft²) N/A (In-Rack)

Area of Application (ft²) 0

Coverage per Sprinkler (ft²) N/A (In-Rack)

Number of Calculated Sprinklers 1

In-Rack Demand (gpm)

Special Heads

Hose Streams (gpm) 0

Total Water Required (incl. Hose Streams) (gpm) 250

Required Pressure at Source (psi) 134.6

Type of System Wet

Volume - Entire System (gal) 7104.6 gal

Water Supply Information


Date 01/01/2017

Location

Source W1

Notes

File: X:\ESSAC\TECNICA\GENERAL\PROYECTOS\001525\TEMPORAL\ACI\05_10\CH\VELÓDROMO\Anexo
1.tyc3
Date 16/05/2018 Copyright © 2002-2012 Tyco Fire Protection Products Page 2
Job : Videna Node Labels: Off
Pipe Labels: Off

Diagram for Design Area : DesignArea_1

File: X:\ESSAC\TECNICA\GENERAL\PROYECTOS\001525\TEMPORAL\ACI\05_10\CH\VELÓDROMO\Anexo 1.tyc3


Date 16/05/2018 Copyright © 2002-2012 Tyco Fire Protection Products Page 3
Job : Videna

Hydraulic Analysis for : DesignArea_1


Calculation Info
Calculation Mode Demand
Hydraulic Model Hazen-Williams
Fluid Name Water @ 60F (15.6C)
Fluid Weight, (lb/ft³) N/A for Hazen-Williams calculation.
Fluid Dynamic Viscosity, (lb·s/ft²) N/A for Hazen-Williams calculation.

Water Supply Parameters

Supply 1 : W1 Flow (gpm) Pressure (psi)


0 160
1000 155
1500 140

Supply Analysis
Residual Available
Static Pressure Flow Total Demand Required Pressure
Node at Source Pressure Pressure
(psi) (gpm) (gpm) (psi)
(psi) (psi)
W1 160 155 1000 159.6 250 134.6

Hoses
Inside Hose Flow / Standpipe Demand (gpm) 250

Outside Hose Flow (gpm)

Additional Outside Hose Flow (gpm)

Other (custom defined) Hose Flow (gpm)

Total Hose Flow (gpm) 250

Sprinklers
Ovehead Sprinkler Flow (gpm)

InRack Sprinkler Flow (gpm)

Other (custom defined) Sprinkler Flow (gpm)

Total Sprinkler Flow (gpm)

Other
Required Margin of Safety (psi) 0

W1 - Pressure (psi) 134.6

W1 - Flow (gpm) 250

Demand w/o System Pump(s) N/A

File: X:\ESSAC\TECNICA\GENERAL\PROYECTOS\001525\TEMPORAL\ACI\05_10\CH\VELÓDROMO\Anexo
1.tyc3
Date 16/05/2018 Copyright © 2002-2012 Tyco Fire Protection Products Page 4
Job : Videna

Hydraulic Analysis for : DesignArea_1

File: X:\ESSAC\TECNICA\GENERAL\PROYECTOS\001525\TEMPORAL\ACI\05_10\CH\VELÓDROMO\Anexo
Date 16/05/2018 1.tyc3 Page 5
Copyright © 2002-2012 Tyco Fire Protection Products
Job : Videna

Hydraulic Analysis for : DesignArea_1

Graph Labels
Values
Label Description
Flow (gpm) Pressure (psi)
S1 Supply point #1 - Static 0 160
S2 Supply point #2 1000 155
S3 Supply point #3 1500 140
D1 Elevation Pressure 0 11.7
D2 System Demand 250 134.6

Curve Intersections & Safety Margins


Intersection Safety Margin
Curve Name
Pressure (psi) Flow (gpm) Pressure (psi) @ Flow (gpm)
Supply 159.5 276.3 25 250

Open Heads
Required Calculated
Head Ref. Head Type Coverage K-Factor
Density Flow Pressure Density Flow Pressure

(ft²) (gpm/psi½) (gpm/ft²) (gpm) (psi) (gpm/ft²) (gpm) (psi)

Standpipe
sdn1 0 0 250 100 0 250 100
Demand

File: X:\ESSAC\TECNICA\GENERAL\PROYECTOS\001525\TEMPORAL\ACI\05_10\CH\VELÓDROMO\Anexo
1.tyc3
Date 16/05/2018 Copyright © 2002-2012 Tyco Fire Protection Products Page 6
Job name: Videna Sheet number:___________________

PIPE INFORMATION
Node 1 Elev 1 K-Factor 1 Flow added(q)* Nominal ID Fittings L C Factor total (Pt)
Node 2 Elev 2 K-Factor 2 Total flow (Q) Actual ID quantity x (name) = length F Pf per ft elev (Pe) NOTES
T frict (Pf)

(ft) (gpm/psi½) (gpm) (ft) (ft) (psi) (psi)


(in)

sdn1 15.75 250 100 1x(us.90)=10 3.28 120 100


n75 12.47 250 4.026 10 0.0199 1.4
13.28 0.3
n75 12.47 0 100 1x(us.90)=10 3.28 120 101.7
n74 12.47 250 4.026 10 0.0199 0
13.28 0.3
n74 12.47 0 100 1x(us.90)=10 22.64 120 102
n73 12.47 250 4.026 10 0.0199 0
32.64 0.7
n73 12.47 0 100 1x(elbow.22.5)=2 19.03 120 102.6
n71 12.47 250 4.026 2 0.0199 0
21.03 0.4
n71 12.47 0 100 1x(elbow.22.5)=2 14.99 120 103
n72 12.47 250 4.026 2 0.0199 0
16.99 0.3
n72 12.47 0 100 1x(elbow.22.5)=2 20.08 120 103.4
n60 12.47 250 4.026 2 0.0199 0
22.08 0.4
n60 12.47 0 100 1x(elbow.22.5)=2 25.26 120 103.8
n59 12.47 250 4.026 2 0.0199 0
27.26 0.5
n59 12.47 0 100 1x(elbow.22.5)=2 30.15 120 104.3
n58 12.47 250 4.026 2 0.0199 0
32.15 0.6
n58 12.47 0 100 1x(elbow.22.5)=2 29.93 120 105
n57 12.47 250 4.026 2 0.0199 0
31.93 0.6
n57 12.47 0 100 1x(elbow.22.5)=2 27.86 120 105.6
n56 12.47 250 4.026 2 0.0199 0
29.86 0.6
n56 12.47 0 100 1x(elbow.22.5)=2 22.1 120 106.2
n55 12.47 250 4.026 2 0.0199 0
24.1 0.5
n55 12.47 0 100 1x(us.90)=10 16.48 120 106.7
n68 12.47 250 4.026 10 0.0199 0
26.48 0.5
n68 12.47 0 100 1x(us.90)=10 11.68 120 107.2
n66 12.47 250 4.026 10 0.0199 0
21.68 0.4
n66 12.47 0 100 1x(elbow.22.5)=2 19.59 120 107.7
n65 12.47 250 4.026 2 0.0199 0
21.59 0.4
n65 12.47 0 100 1x(elbow.22.5)=2 22.1 120 108.1
n64 12.47 250 4.026 2 0.0199 0
24.1 0.5
n64 12.47 0 100 1x(elbow.22.5)=2 27.86 120 108.6
n63 12.47 250 4.026 2 0.0199 0
29.86 0.6
n63 12.47 0 100 1x(elbow.22.5)=2 29.93 120 109.2
n62 12.47 250 4.026 2 0.0199 0
31.93 0.6
n62 12.47 0 100 1x(elbow.22.5)=2 30.15 120 109.8
n61 12.47 250 4.026 2 0.0199 0
32.15 0.6
n61 12.47 0 100 1x(elbow.22.5)=2 25.26 120 110.4
n47 12.47 250 4.026 2 0.0199 0
27.26 0.5

© 2006 National Fire Protection Association Page 7


Job name: Videna Sheet number:___________________

PIPE INFORMATION
Node 1 Elev 1 K-Factor 1 Flow added(q)* Nominal ID Fittings L C Factor total (Pt)
Node 2 Elev 2 K-Factor 2 Total flow (Q) Actual ID quantity x (name) = length F Pf per ft elev (Pe) NOTES
T frict (Pf)

(ft) (gpm/psi½) (gpm) (ft) (ft) (psi) (psi)


(in)

n47 12.47 0 100 1x(us.90)=10 4.59 120 111


n46 12.47 250 4.026 10 0.0199 0
14.59 0.3
n46 12.47 0 100 1x(us.90)=10 2.79 120 111.3
n45 12.47 250 4.026 10 0.0199 0
12.79 0.3
n45 12.47 0 100 1x(us.90)=10 57.09 120 111.5
n44 12.47 250 4.026 10 0.0199 0
67.09 1.3
n44 12.47 0 100 1x(us.90)=10 7.22 120 112.9
n43 12.47 250 4.026 10 0.0199 0
17.22 0.3
n43 12.47 0 100 1x(us.90)=10 80.38 120 113.2
n42 12.47 250 4.026 10 0.0199 0
90.38 1.8
n42 12.47 0 100 1x(us.90)=10 7.87 120 115
n41 12.47 250 4.026 10 0.0199 0
17.87 0.4
n41 12.47 0 100 1x(us.90)=10 17.39 120 115.4
n40 12.47 250 4.026 10 0.0199 0
27.39 0.5
n40 12.47 0 100 1x(us.90)=10 14.96 120 115.9
n39 12.47 250 4.026 10 0.0199 0
24.96 0.5
n39 12.47 0 100 1x(us.90)=10 10.5 120 116.4
n38 1.97 250 4.026 10 0.0199 4.5
20.5 0.4
n38 1.97 0 100 1x(us.90)=10 47.9 120 121.4
n37 1.97 250 4.026 10 0.0199 0
57.9 1.2
n37 1.97 0 100 1x(us.90)=10 116.47 120 122.5
n36 1.97 250 4.026 10 0.0199 0
126.47 2.5
n36 1.97 0 100 1x(us.90)=10 45.28 120 125
n35 1.97 250 4.026 10 0.0199 0
55.28 1.1
n35 1.97 0 100 1x(us.90)=10 5.25 120 126.2
n34 1.97 250 4.026 10 0.0199 0
15.25 0.3
n34 1.97 0 100 1x(us.90)=10 5.91 120 126.5
n33 -3.94 250 4.026 10 0.0199 2.6
15.91 0.3
n33 -3.94 0 150 1x(us.90)=14 5.25 120 129.3
n31 -3.94 250 6.065 14 0.0027 0
19.25 0.1
n31 -3.94 0 150 1x(us.90)=14 5.91 120 129.4
n23 1.97 250 6.065 14 0.0027 -2.6
19.91 0.1
n23 1.97 0 150 1x(coupling)=1 8.57 120 126.9
n24 1.97 250 6.065 1 0.0027 0
9.57 0.0
n24 1.97 0 150 1x(elbow.22.5)=3.5 14.24 120 126.9
n25 1.97 250 6.065 3.5 0.0027 0
17.74 0.0
n25 1.97 0 150 1x(elbow.22.5)=3.5 22.22 120 127
n26 1.97 250 6.065 3.5 0.0027 0
25.72 0.1

© 2006 National Fire Protection Association Page 8


Job name: Videna Sheet number:___________________

PIPE INFORMATION
Node 1 Elev 1 K-Factor 1 Flow added(q)* Nominal ID Fittings L C Factor total (Pt)
Node 2 Elev 2 K-Factor 2 Total flow (Q) Actual ID quantity x (name) = length F Pf per ft elev (Pe) NOTES
T frict (Pf)

(ft) (gpm/psi½) (gpm) (ft) (ft) (psi) (psi)


(in)

n26 1.97 0 150 1x(elbow.22.5)=3.5 14.5 120 127


n27 1.97 250 6.065 3.5 0.0027 0
18 0.0
n27 1.97 0 150 1x(elbow.22.5)=3.5 15.45 120 127.1
n28 1.97 250 6.065 3.5 0.0027 0
18.95 0.1
n28 1.97 0 150 1x(elbow.22.5)=3.5 16.93 120 127.1
n29 1.97 250 6.065 3.5 0.0027 0
20.43 0.1
n29 1.97 0 150 1x(elbow.22.5)=3.5 9.9 120 127.2
n30 1.97 250 6.065 3.5 0.0027 0
13.4 0.0
n30 1.97 0 150 1x(us.90)=14 9.01 120 127.2
n14 1.97 250 6.065 14 0.0027 0
23.01 0.1
n14 1.97 0 150 1x(us.90)=14 45.93 120 127.3
n13 1.97 250 6.065 14 0.0027 0
59.93 0.2
n13 1.97 0 150 1x(us.Tee-Br)=30 119.75 120 127.4
n12 1.97 250 6.065 30 0.0027 0
149.75 0.4
n12 1.97 -121.3 200 1x(us.90)=18 93.3 120 127.8
27 1.97 128.7 8.071 18 0.0002 0
111.3 0.0
27 1.97 0 200 1x(us.90)=18 26.93 120 127.9
28 1.97 128.7 8.071 18 0.0002 0
44.93 0
28 1.97 0 200 1x(us.90)=18 5.91 120 127.9
29 -3.94 128.7 8.071 18 0.0002 2.6
23.91 0
29 -3.94 0 200 1x(us.90)=9.1 14.14 150 130.4
30 -3.94 128.7 6.447 9.1 0.0004 0
23.24 0
30 -3.94 0 200 1x(us.90)=9.1 38.13 150 130.4
31 -3.94 128.7 6.447 9.1 0.0004 0
47.23 0.0
31 -3.94 0 200 1x(us.90)=9.1 545.68 150 130.5
32 -3.94 128.7 6.447 9.1 0.0004 0
554.78 0.2
32 -3.94 0 200 1x(us.90)=9.1 245.64 150 130.7
33 -3.94 128.7 6.447 9.1 0.0004 0
254.75 0.1
33 -3.94 0 200 1x(us.Tee-Br)=17.7 318.25 150 130.8
n177 -3.94 128.7 6.447 17.7 0.0004 0
335.94 0.1
n177 -3.94 121.3 200 1x(us.90)=9.1 65.62 150 130.9
n178 -3.94 250 6.447 9.1 0.0013 0
74.72 0.1
n178 -3.94 0 200 1x(us.90)=9.1 78.74 150 131
n179 -3.94 250 6.447 9.1 0.0013 0
87.84 0.1
n179 -3.94 0 200 1x(us.90)=9.1 49.21 150 131.1
n180 -3.94 250 6.447 9.1 0.0013 0
58.31 0.1
n180 -3.94 0 200 1x(us.90)=9.1 43.31 150 131.2
n181 -3.94 250 6.447 9.1 0.0013 0
52.41 0.1

© 2006 National Fire Protection Association Page 9


Job name: Videna Sheet number:___________________

PIPE INFORMATION
Node 1 Elev 1 K-Factor 1 Flow added(q)* Nominal ID Fittings L C Factor total (Pt)
Node 2 Elev 2 K-Factor 2 Total flow (Q) Actual ID quantity x (name) = length F Pf per ft elev (Pe) NOTES
T frict (Pf)

(ft) (gpm/psi½) (gpm) (ft) (ft) (psi) (psi)


(in)

n181 -3.94 0 200 1x(us.90)=9.1 13.12 150 131.3


n182 -3.94 250 6.447 9.1 0.0013 0
22.22 0.0
n182 -3.94 0 200 1x(coupling)=2 3.69 120 131.3
n183 -7.63 250 8.071 2 0.0007 1.6
5.69 0
n183 -7.63 0 150 1x(us.90)=14 3.69 120 132.9
n184 -11.32 250 6.065 14 0.0027 1.6
17.69 0.0
n184 -11.32 0 150 9.19 120 134.6
W1 -11.32 250 6.065 0 0.0027 0
9.19 0.0
n12 1.97 0 200 1x(us.90)=18 180.45 120 127.8
26 1.97 121.3 8.071 18 0.0002 0
198.45 0.0
26 1.97 0 200 1x(us.90)=18 111.2 120 127.9
25 1.97 121.3 8.071 18 0.0002 0
129.2 0.0
25 1.97 0 200 1x(us.90)=18 0.66 120 127.9
24 1.31 121.3 8.071 18 0.0002 0.3
18.66 0
24 1.31 0 200 1x(us.90)=18 309.85 120 128.2
23 1.31 121.3 8.071 18 0.0002 0
327.85 0.1
23 1.31 0 200 1x(us.90)=18 5.25 120 128.2
22 -3.94 121.3 8.071 18 0.0002 2.3
23.25 0
22 -3.94 0 200 1x(us.90)=9.1 147.67 150 130.5
21 -3.94 121.3 6.447 9.1 0.0003 0
156.77 0.1
21 -3.94 0 200 283.5 150 130.6
20 -3.94 121.3 6.447 0 0.0003 0
283.5 0.1
20 -3.94 0 200 1x(us.90)=9.1 21.67 150 130.7
42 -3.94 121.3 6.447 9.1 0.0003 0
30.77 0.0
42 -3.94 0 200 1x(us.90)=9.1 44.73 150 130.7
41 -3.94 121.3 6.447 9.1 0.0003 0
53.83 0.0
41 -3.94 0 200 1x(us.90)=9.1 12.06 150 130.7
40 -3.94 121.3 6.447 9.1 0.0003 0
21.16 0
40 -3.94 0 200 1x(us.45)=4.55 231.71 150 130.7
39 -3.94 121.3 6.447 4.55 0.0003 0
236.26 0.1
39 -3.94 0 200 1x(us.45)=4.55 102.83 150 130.8
38 -3.94 121.3 6.447 4.55 0.0003 0
107.38 0.0
38 -3.94 0 200 1x(us.45)=4.55 176.67 150 130.8
37 -3.94 121.3 6.447 4.55 0.0003 0
181.22 0.1
37 -3.94 0 200 1x(us.45)=4.55 9.7 150 130.9
35 -3.94 121.3 6.447 4.55 0.0003 0
14.25 0
35 -3.94 0 200 1x(us.Tee-Br)=17.7 3.94 150 130.9
n177 -3.94 121.3 6.447 17.7 0.0003 0
21.63 0

© 2006 National Fire Protection Association Page 10


Job name: Videna Sheet number:___________________

PIPE INFORMATION
Node 1 Elev 1 K-Factor 1 Flow added(q)* Nominal ID Fittings L C Factor total (Pt)
Node 2 Elev 2 K-Factor 2 Total flow (Q) Actual ID quantity x (name) = length F Pf per ft elev (Pe) NOTES
T frict (Pf)

(ft) (gpm/psi½) (gpm) (ft) (ft) (psi) (psi)


(in)

* Discharge shown for flowing nodes only

© 2006 National Fire Protection Association Page 11