Consultants
Umited
MASTER PLAN
METHODOLOGIES
4
41
42
43
OVERVIEW
‘A number of tasks and evaluation requirements were undertaken as part of the Master Plan
process unique to Halton Region.
Under any master plan, the methodolcgy for analyzing planning information, developing
water demands and wastewater flows and modelling the systems needs to be developed to
best serve the proponent.
In addition to analysis processes, Halton Region is subject to unique provincial guidelines
designed to ensure optimal water quality in Lake Ontario.
POPULATION AND EMPLOYMENT DATA
This master plan makes use of the planning information derived through the Best Plenning
Estimates process in order to assess growth areas and allocate future water demands and
wastewater flows,
The planning data was developed by Halton Region whereby Region-wide projections were
geographically allocated by Traffic Survey Zones (TSZs). The planning projections including
population and employment data, were developed through analysis of vacant lands. The
data was provided to the Master Plan team in 5-year intervals for separate TSZs covering the
Study Area. Please refer to Figure 4 to review Map divided into TSZs.
In order to further allocate the planning data for modelling purposes, additional GIs
processing was completed to allocate the TSZ data to model node polygons, This process
used the 2007 planning data in TSZs, the Region's land use data, the wastewater model
‘catchments (wastewater node polygon9) and the water node polygons.
WATER AND WASTEWATER SYSTEM MODELS.
Water and wastewater system hydraulic models were again identified as important tools to
complete the Master Plan Update. These tools were used to facilitate the detailed hydraulic
evaluation of alternative servicing scenarios.
Analysis of the infrastructure requirements for this Master Plan Update was undertaken
utilizing the computerized water and wastewater models for the Region's systems.
South Halton Water and Wastewater Master lan Update Page 4-1
Halton Region
288301 0806138
June 2008a a a
MASTER PLAN
Consultant METHODOLOGIES
Umited
4.3.1 Water Model
The original 2002 Master Plan Review model data was converted from WaterCAD to
Infowater from MWH Soft. The water model was updated with new geo-database and
project specific information to ensure completeness. The master plan model utilizes a
skeletonized water system network including major trunk feedermains and watermains,
valves, pumping stations, reservoirs, ard elevated tanks with vrater supply points from the
Water Purification Plants.
The water system was divided into water node polygons. These geographic areas covered
the existing serviced areas of the Study Area, as well as areas that were under development
or that could potentially be developed by the year 2021. The water demands were
calculated for each water node polygon based on residential and employment projections.
The model development included system calibration using system data provided by the
Region.
4.3.2 Wastewater Model
Similarly, the original 2002 Master Plan Review model data was converted from SewerCAD
to Infosewer from MWH Soft. The wastewater model was also updated with new geo:
database and project specific information to ensure completeness. The master plan modal
utlizes a skeletonized wastewater system network including trunk sewers, forcemains and
pumping stations with ultimate outlets at the wastewater treatment plants.
‘The drainage area for the wastewater treatment plants (WWTPs) was divided into individual
sewer catchments (wastewater node polygons). These catchments cover the existing
serviced areas of the study area, as wel as areas that are currently under development or
that might potentially be developed by the year 2021.
The model development included systen calibration using data provided by the Region.
4.4 EVALUATION CRITERIA
The master plan evaluation approach fellowed typical evaluation of impacts under Class EA
evaluation criteria including:
4 Physical and Natural Environment:
- Impact on vegetation, fish and wildlife; surface drainage and groundwater; soil
and geology
= Impact on areas of natural and scientific interest, and environmentally-sensitive
areas
Disruption of topographical features.
+ Social, Economic, and Cultural Evironment:
= _ Impact on existing and proposed development
= Impact on archaeological ard historic sites
South Halton Water and Wastewater Master Plan Update Page 4-3
Halton Region
288301 080613 R
‘dune 2008KM 4 SECTION 4
Consultants
Limited
45
South Haltor
MASTER PLAN
METHODOLOGIES
= Impact on agricultural resources
= Impact on recreational areas
Impact on other utilities
= Coordination with proposed roadway development.
4 Financial Factors:
= Constiuction, operation and maintenance (life-cycle) costs
Best use of existing infrastructure
~ Flexibility for scheduling works.
Technical Factors:
~ Level of service
~ Security and reliability
= Impact on existing infrastructure
~ Constructability
~ Impact on operations and maintenance
Meeting legislated criteria and regulations.
IMPLEMENTATION AND SCHEDULING
It has been determined during this froject, that scheduling of infrastructure upgrades
should be based on, where possible, not exceeding approximately 90% of full capacity. This
approach should coincide with scheduling the future upgrades before flow projections
meet available capacity.
This concept is more easily achieved for the projects further out in the planning horizon.
Given that many upgrades are required in the short term (ie, before 10 years), some
projects have been identified with accelerated schedules and in-service dates as soon as
feasible,
It is also good engineering practice to provide sufficient capacity to meet servicing
requirements beyond the planning horizon, particularly for larger diameter trunk piping and
major structural components of major supply facilities. In addition, the sizing and capacity
determined for 2021 needs must also p‘ovide a sufficient level of service to the new growth
areas, ensure efficient integration wit existing infrastructure, and not negatively impact
current operations of the systems. Even after making this latter allowance, some
infrastructure has been sized to meet needs beyond the planning horizon.
Under the South Halton Master Plan Update, the scope of each project and the timing was
updated from the previous servicing stiategy based on the BPE April 2007 and status of the
current implementation program.
In Water and Wastewater Masies Plan Update Page 4-4
Halton Ragicn
288301 060613
Sune 2008xm SECTION 4
MASTER PLAN
Concultants METHODOLOGIES
Limited
46
The service area was reviewed for each project. Based on the projections for water demand
or wastewater flow requirements of the service area developed from the BPE April 2007, the
project timing requirements were determined.
This process took into consideration a logical extension of growth from the existing
development. The evaluation of timing also took into consideration the availability of and
need to maximize the use of existing Infrastructure and best judgement on reasonable
timing of subsequent expansions.
For the major facility expansions, such as the Burloak WPP and Mid-Halton WWTP, single
larger expansions have been considered to minimize the construction periods at the site
and avoid scheduling subsequent work immediately following completion of the previous
Project.
However, although a one phase large expansion is preferred from a technical point of view
for the Burloak WPP and the Mid-Halten WWTP, a financial affordability analysis has been
undertaken by the Region project tearr and given the significant upfront funding required
for a one phase expansion program, a two phased approach has been identified and
recommended. Capital programs incided in Section 16 of this report reflect this two
phased approach.
Project timing was also integrated with the results of recent studies, Class Environmental
Assessments and reports, and where possible with the 2007 Transportation Master Plan
Update to ensure that underground irfrastructure was not scheduled after completion of
road improvements. This did result in several projects being accelerated.
Total project scheduling has been based on total project delivery requirements including
identifying all project components such as additional studies, Class EA studies, design,
construction and RFP requirements.
WATER AND WASTEWATER SERVICING POLICIES
As part of the overall master planning process, the concepts of water and wastewater
servicing policies were evaluated and considered when developing and evaluating servicing
alternatives.
The range of servicing policy concepts considered are to include:
‘4 Harmonize planning and servicing policies
4 Recognize potential for growth beyond current planning horizons
+ Maximize use of available existing capacity in infrastructure
+ Maintain reserve capacity in infrastructure
‘+ Minimize property requirements for infrastructure
‘¢ Recognize Regional standards and bylaws
+ Endeavour to protect water sources
South Halton Water and Wastewater Master Plan Update Page 4-5
Halton Fegion
253,01 080513
Sune 2008xu
SECTION 4
MASTER PLAN
Consultants METHODOLOGIES
Limited
+ Meet or exceed legislated water quality
Provide reliability and security ir the systems
# Continue to provide adequate level of service with respect to flows, pressures and
storage
¢ Optimize pumping and storage infrastructure to maintain level of service under
‘emergency conditions
‘# Recognize water conservation and efficiency measures
‘¢ Utilize appropriate design and casting
¢ Continue system monitoring
‘Maintain open communications
South Halton Waterand Wastewater Master Pan Update Page 4-6
Halton Region
2883.01 080613
June 2008