02.05 VEREDAS
03 CONSTRUCCION DE DESARENADOR
03.01 DESARENADOR
03.02.02 CIMIENTO
03.02.04 COLUMNAS
03.02.05 PINTURA
06.02.01.02 REHABILITACION DE CAJAS DE CONTROL CON COMPUERTA TIPO TARJETA Und 7.00
06.02.04 VARIOS
COSTO DIRECTO
UTILIDAD 7%
SUB TOTAL
IGV. 18 %
PRESUPUESTO DE CANAL DE RIEGO
COSTO DE EJECUCIÓN DE OBRA
UPUESTO DE CANAL DE RIEGO
PRECIO PARCIAL
S/. 4,959.84
S/. 181,250.26
S/. 39,927.93
S/. 25,548.56
S/. 44,647.53
S/. 47,139.15
S/. 23,987.09
S/. 29,569.87
S/. 21,782.40
S/. 7,141.12
S/. 1,937.79
S/. 7,551.60
S/. 5,151.89
S/. 7,787.47
S/. 2,270.32
S/. 1,419.69
S/. 2,761.65
S/. 871.72
S/. 464.09
S/. 16,962.72
S/. 16,962.72
S/. 428.40
S/. 51,588.58
S/. 4,874.12
S/. 46,714.46
S/. 9,226.04
S/. 24,442.62
S/. 13,045.80
S/. 284,759.67
S/. 25,451.82
S/. 19,933.18
S/. 330,144.67
S/. 59,426.04
UPUESTO DE CANAL DE RIEGO
S/. 389,570.71
METRADO POR MEJORAMIENTO DE CANAL
Presupuesto de Mejoramiento de Canal
01 OBRAS PRELIMINARES
Partida N°: 01.01
Descripción: TRAZO Y REPLANTEO
Unidad. m
DESCRIPCION LONG
CALLE MENESES 142.95
SECTOR DE DESARENADOR 32.00
TOTAL 174.95
Calle Progresiva Longitud (m) Ancho (m) Alto (m) Volumen (m3)
Meneses 0+004.65 0.00 1.30 0.15 0.00
Meneses 0+092.61 87.96 1.30 0.15 17.15
Meneses 0+101.82 0.00 1.30 0.20 0.00
Meneses 0+137.90 36.08 1.30 0.15 7.04
Av. Arequipa 0+147.60 0.00 1.30 0.15 0.00
Canal Existente 0+179.60 0.00 1.30 0.15 0.00
Total 24.19
Calle Progresiva Longitud (m) Ancho (m) Alto (m) Volumen (m3)
Meneses 0+004.65 0.00 1.20 0.07 0.00
Meneses 0+092.61 87.96 1.20 0.07 7.39
Meneses 0+101.82 0.00 1.20 0.07 0.00
Meneses 0+137.90 36.08 1.20 0.07 3.03
Av. Arequipa 0+147.60 0.00 1.20 0.07 0.00
Canal Existente 0+179.60 32.00 1.20 0.07 2.69
Total 13.11
Calle Progresiva Longitud (m) Ancho (m) Alto (m) Volumen (m3)
Meneses 0+004.65 0.00 1.20 0.16 0.00
Meneses 0+092.61 87.96 1.20 0.50 52.78
Meneses 0+101.82 0.00 1.20 0.50 0.00
Meneses 0+137.90 36.08 1.20 0.50 21.65
Tubo PVC 124.04 A=.0087 -1.08
Av. Arequipa 0+147.60 0.00 1.20 0.16 0.00
Canal Existente 0+179.60 32.00 1.20 0.16 6.14
Total 79.49
Factor de Compactación 1.30
Total 103.34
Total 52.12
Distancia a Botadero 6 .00 Km
Total (m3-Km) 312.71
Calle Progresiva Longitud (m) Ancho (m) Alto (m) Área (m2)
Meneses 0+004.65 0.00 0.15 0.40 0.00
Meneses 0+092.61 87.96 0.15 0.40 5.28
Meneses 0+101.82 0.00 0.15 0.40 0.00
Meneses 0+137.90 36.08 0.15 0.40 2.16
Av. Arequipa 0+147.60 0.00 0.15 0.40 0.00
Canal Existente 0+162.60 15.00 0.15 0.40 0.90
Total 8.34
DESARENADOR
Estrcutura Longitud (m) Ancho (m) Área (m2) Tipo de Estructura Observaciones
Desarenador 17.35 1.60 27.76 Desarenador Colindante a Av. Arequipa
Total 27.76
Estructura Longitud (m) Ancho (m) Alto (m) N° Veces Volumen (m3)
Estructura Longitud (m) Ancho (m) Alto (m) N° Veces Volumen (m3)
Estructura M2
Apuntalamiento 18.00
Estructura 5.00
Estructura N° Veces Longitud (m) Alto (m) Ancho (m) Volumen (m3)
Muro Lateral Desar. 2.00 3.30 2.00 0.15 1.98
Muro Rebose Desar. 1.00 1.00 1.20 0.15 0.18
Columnas 12.00 0.40 1.10 0.15 0.79
Vigas de Amarre 6.00 0.50 0.20 0.25 0.15
Total 3.10
CIMIENTOS
Partida N°: 03.02.02.01
Descripción: ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS
Unidad. m2
Caras laterales de
3.90 0.80 1.00 3.12
Cimentación
Total 3.12
Estructura N° Veces Longitud (m) Alto (m) Ancho (m) Volumen (m3)
Ciment. Muro 1.00 3.90 0.80 0.80 2.50
Total 2.50
Estructura N° Veces Longitud (m) Alto (m) Ancho (m) Volumen (m3)
Ciment. Muro 1.00 3.90 0.50 0.30 0.59
Total 0.59
Total 3.60
Estructura N° Veces Longitud (m) Alto (m) Ancho (m) Volumen (m3)
Ciment. Muro 2.00 0.35 4.50 0.15 0.47
Total 0.47
Unidad. m2
METRADO POR MEJORAMIENTO DE CANAL
Presupuesto de Mejoramiento de Canal
DESCRIPCION Und CANT
CALLE ATAHUALPA m2 290.00
TOTAL m2 290.00
TOTAL M3 71.27
TOTAL
Unidad. m
Unidad. m
Observaciones
Entre Calles Bolognesi y Colón
Entre Calles Bolognesi y Colón
En Calle Colón
Entre Calles Colón y Arequipa
En Av. Arequipa
Canal Existente
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
Observaciones
Entre Calles Bolognesi y Colón
Entre Calles Bolognesi y Colón
En Calle Colón
Entre Calles Colón y Arequipa
En Av. Arequipa
Canal Existente
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
Observaciones
Entre Calles Bolognesi y Colón
Entre Calles Bolognesi y Colón
En Calle Colón
Entre Calles Colón y Arequipa
En Av. Arequipa
Canal Existente
Observaciones
Entre Calles Bolognesi y Colón
Entre Calles Bolognesi y Colón
En Calle Colón
Entre Calles Colón y Arequipa
En Av. Arequipa
Canal Existente
Observaciones
Entre Calles Bolognesi y Colón
Entre Calles Bolognesi y Colón
En Calle Colón
Entre Calles Colón y Arequipa
120.00
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
120.00
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
18
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
ɸ 5/8"
144.00
120.00
264
1.60
422.4
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
LADO DERECHO
Ubicación
Entre Calles Bolognesi y Colón
Entre Calles Bolognesi y Colón
En calle Colon
Entre Calles Colón y Arequipa
En Av. Arequipa
Ubicación
Entre Calles Bolognesi y Colón
Entre Calles Bolognesi y Colón
En calle Colon
Entre Calles Colón y Arequipa
En Av. Arequipa
Ubicación
Entre Calles Bolognesi y Colón
Entre Calles Bolognesi y Colón
En calle Colon
Entre Calles Colón y Arequipa
En Av. Arequipa
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
Observaciones
Colindante a Av. Arequipa
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
555.36
ɸ 3/8"
79.20
27.00
86.40
192.60
0.56
107.86
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
3
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
9.77
CANT
3.36
2.16
3.42
0.83
9.77
2.76
CANT
2.16
0.60
2.76
1,891.52
TOTAL (Kg)
21.00
20.00
41.00
TOTAL (Kg)
17.16
17.16
34.32
CANT
656.00
1,235.52
85.80
1,891.52
POR MEJORAMIENTO DE CANAL
esto de Mejoramiento de Canal
CANT
42.00
1.44
9.00
50.00
0.75
103.19
Partida 01.01 TRAZO Y REPLANTEO Rend:
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio
Mano de Obra
47 00002 CAPATAZ hh 0.100 0.0027 20.30
47 00104 TOPOGRAFO hh 1.000 0.0267 20.00
47 00003 PEON hh 3.000 0.0800 14.30
Materiales
29 00105 CORDEL m 0.0500 0.15
30 00106 YESO DE 28 Kg bol 0.0010 12.00
54 00127 PINTURA ESMALTE gln 0.0002 52.00
Equipo
30 00108 ESTACION TOTAL CON MIRA TOPOGRAFICA he 0.500 0.0133 14.60
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 1.72
49 00107 NIVEL he 0.500 0.0133 11.20
Materiales
02 00037 TUBO PVC D= 400 MM m 0.0200 200.00
Sub paratida
21 00039 CONCRETO F´C = 175 KG/CM2 m3 1.000 0.0200 343.30
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 0.3000 7.97
48 00058 MOTOBOMBA ELECTRICA CENTRIFUGA 3 HP - SUCCION hm 0.500 0.0400 10.00
49 00015 MINICARGADOR, 53.8 KW, 818 kg hm 1.000 0.0800 95.00
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 0.0300 72.82
MARTILLO NEUMATICO 29 Kg hm 2.000 1.6000 7.80
COMPRESORA NEUMATICA hm 1.000 0.8000 70.00
CORTADOR DE CONCRETO hm 0.500 1.3330 5.42
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 2.45
Materiales
05 00045 AGUA m3 0.0360 6.80
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 3.60
48 00071 COMPACTADORA VIBRAT. DE PLANCHA 7 HP hm 1.000 0.0444 12.70
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 54.42
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 43.54
48 00071 COMPACTADORA VIBRAT. DE PLANCHA 7 HP hm 1.000 2.6667 12.70
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 0.35
48 00010 CAMION VOLQUETE 15 M3. hm 2.000 0.0107 170.00
49 00011 CARGADOR SOBRE LLANTAS 160-195 HP 3.5 yd3 hm 1.000 0.0053 160.00
Materiales
04 00021 ARENA GRUESA m3 0.032 60.30
05 00042 PIEDRA CHANCADA DE 1/2'' - 3/4'' m3 0.033 70.00
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 0.306 18.20
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.000 9.81
48 00040 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 1.000 0.010 15.00
49 00038 VIBRADOR A GASOLINA 1 3/4", 4HP hm 1.000 0.010 9.80
Materiales
17 00005 TUBERIA PVC D= 500mm, Clase 5 und 1.0500 166.93
ANILLO DE JEBE und 0.3300 20.00
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 44.09
49 00006 MONTACARGAS 2.5-3 TN hm 1.000 0.2000 48.00
49 00011 CARGADOR SOBRE LLANTAS 160-195 HP 3.5 yd3 hm 0.500 0.1000 160.00
Materiales
02 00033 ALAMBRE NEGRO RECOCIDO N°8 kg 0.3000 3.55
02 00037 CLAVOS PARA MADERA C/C 3-4" kg 0.3500 4.20
03 00035 ESTACA DE FIERRO 3/8"X0.60M und 0.0500 0.98
43 00036 MADERA PARA ENCOFRADO p2 4.2400 5.10
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 58.40
48 00034 SIERRA CIRCULAR hm 0.500 0.4444 7.50
Materiales
04 00021 ARENA GRUESA m3 0.6500 60.30
05 00042 PIEDRA CHANCADA DE 1/2'' - 3/4'' m3 0.6600 70.00
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 9.5000 18.20
34 00041 GASOLINA 84 OCTANOS gln 0.3300 10.50
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 227.35
48 00040 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 1.000 0.8000 15.00
49 00038 VIBRADOR A GASOLINA 1 3/4", 4HP hm 1.000 0.8000 9.80
Materiales
02 00043 ALAMBRE NEGRO RECOCIDO # 16 kg 0.1000 3.55
03 00044 ACERO DE REFUERZO FY=4200 GRADO 60 kg 1.0300 3.60
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 1.18
Materiales
02 00125 VARILLA LISA 3/8" kg 0.2000 3.80
50 00124 PLANCHA METALICA E= 1/8", CON MARCA SUPERFICIAL Y REL kg 0.6000 2.90
51 00122 PERFIL ANGULO 1 1/2" x1/2" x 3 mm kg 18.0000 3.80
51 00122 CANAL U 3" x 5 lb/pie kg 24.0000 3.80
51 00123 SOLDADURA DE ELECTRODO kg 0.5000 5.80
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 38.56
49 00121 MOTOSOLDADORA DE 250 AMP. hm 0.250 0.3333 120.00
sub partida
CONCRETO F´C = 210 KG/CM2 m3 0.0500 478.98
ACERO DE CANAL Kg 5.0000 5.29
Materiales
04 00021 ARENA GRUESA m3 0.6500 60.30
05 00042 PIEDRA CHANCADA DE 1/2'' - 3/4'' m3 0.6600 70.00
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 11.0000 18.20
34 00041 GASOLINA 84 OCTANOS gln 0.3300 10.50
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 227.35
48 00040 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 1.000 0.8000 15.00
49 00038 VIBRADOR A GASOLINA 1 3/4", 4HP hm 1.000 0.8000 9.80
Materiales
02 00033 ALAMBRE NEGRO RECOCIDO N°8 kg 0.7500 3.55
02 00037 CLAVOS PARA MADERA C/C 3-4" kg 0.2000 4.20
43 00036 MADERA PARA ENCOFRADO p2 7.3040 5.10
53 00070 PETROLEO D-2 gln 0.1545 10.20
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 23.85
48 00034 SIERRA CIRCULAR hm 0.500 0.3300 7.50
Partida 02.05.02 CONCRETO MONOLITICO FROTACHADO EN VEREDAS f´c= 175 kg/cm2 E =2´´ Rend:
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio
Mano de Obra
47 00002 CAPATAZ hh 0.200 0.0800 20.30
47 00020 OPERARIO hh 2.000 0.8000 19.18
47 00003 PEON hh 4.000 1.6000 14.30
Materiales
04 00046 ARENA FINA m3 0.0260 76.26
04 00021 ARENA GRUESA m3 0.0440 60.30
05 00045 AGUA m3 0.0480 6.80
05 00042 PIEDRA CHANCADA DE 1/2'' - 3/4'' m3 0.0880 70.00
17 00008 ADOQUINES DE CONCRETO 0.10X0.20X0.06 (ROJO), f´c=420 kg und 0.1000 1.00
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 0.7800 18.20
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 39.84
48 00040 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 0.360 0.1400 15.00
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 10.0000 421.28
Materiales
04 00021 ARENA GRUESA m3 0.59 60.30
05 00045 AGUA m3 0.23 6.80
05 00042 PIEDRA CHANCADA DE 1/2'' - 3/4'' m3 0.63 70.00
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 8.05 18.20
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 167.00
48 00040 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 1.000 0.6700 15.00
49 00038 VIBRADOR A GASOLINA 1 3/4", 4HP hm 1.000 0.6700 9.80
Materiales
04 00046 ARENA FINA m3 0.0260 76.26
04 00021 ARENA GRUESA m3 0.0440 60.30
05 00045 AGUA m3 0.0500 6.80
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 0.5000 18.20
SIKATOP 77 gal 0.1500 80.00
SIKADUR 32 Kg 0.1600 89.00
02 00125 VARILLA LISA 3/8" kg 2.0000 3.80
50 00124 PLANCHA METALICA E= 1/8", CON MARCA SUPERFICIAL Y REL kg 12.0000 2.90
51 00122 PERFIL ANGULO 1/2" x1/2" x 3 mm kg 6.0000 3.80
51 00123 SOLDADURA DE ELECTRODO kg 1.0000 5.80
54 00095 PINTURA ANTICORROSIVA gln 0.0600 35.87
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 110.59
49 00121 MOTOSOLDADORA DE 250 AMP. hm 0.500 0.5000 120.00
Materiales
04 00046 ARENA FINA m3 0.0260 76.26
04 00021 ARENA GRUESA m3 0.0440 60.30
05 00045 AGUA m3 0.0500 6.80
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 0.5000 18.20
SIKATOP 77 gal 0.1500 80.00
SIKADUR 32 Kg 0.1600 89.00
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 102.81
49 00121 MOTOSOLDADORA DE 250 AMP. hm 0.250 0.3333 120.00
sub partida
DEMOLICION MANUAL m3 0.12 150.70
02 00033 ENCOFRADO Y DESENCOFRADO m2 0.8500 81.35
CONCRETO F´C = 210 KG/CM2 m3 0.3100 515.78
ACERO DE CANAL Kg 25.0000 5.29
Materiales
04 00046 ARENA FINA m3 0.0260 76.26
04 00021 ARENA GRUESA m3 0.0440 60.30
05 00045 AGUA m3 0.0500 6.80
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 0.5000 18.20
SIKATOP 77 gal 0.1500 80.00
SIKADUR 32 Kg 0.1600 89.00
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 121.88
49 00121 MOTOSOLDADORA DE 250 AMP. hm 0.250 0.3333 120.00
sub partida
DEMOLICION MANUAL m3 0.24 152.33
02 00033 ENCOFRADO Y DESENCOFRADO m2 3.2000 81.35
CONCRETO F´C = 210 KG/CM2 m3 0.6200 379.65
ACERO DE CANAL Kg 80.0000 5.29
TAPAS DE INSPECCION 0.60 X 0.60 Und 2.0000 265.12
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 21.51
Partida 03.01.04.05 TECHO DE PLANCHA ESTRIADA DE 3/16" PARA PROTECCIÓN DE CANAL Rend:
Materiales
Plancha estriada de 3/16" (por m2) Kg 39.2500 3.80
Soldadura Supercito 1/8" Kg 0.4000 11.80
Perfil T 1 1/2" x 1 1/2" x 3 mm Kg 2.8350 3.80
PERFIL ANGULO 1 1/2" x 1 1/2" x 3 mm Kg 1.8900 3.80
Bisagras metalicas Und 2.0000 12.71
PINTURA ANTICORROSIVA gln 0.0600 35.87
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 113.44
49 00121 MOTOSOLDADORA DE 250 AMP. hm 0.600 1.2000 120.00
Materiales
04 00021 ARENA GRUESA m3 0.35 60.30
05 00045 AGUA m3 0.29 6.80
05 00042 PIEDRA CHANCADA DE 1/2'' - 3/4'' m3 0.40 70.00
05 00114 PIEDRA GRANDE (MAX 8¨) m3 0.35 60.00
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 5.50 18.20
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 99.61
48 00040 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 1.000 0.5333 15.00
49 00038 VIBRADOR A GASOLINA 1 3/4", 4HP hm 1.000 0.5333 9.80
Materiales
04 00021 ARENA GRUESA m3 0.59 60.30
05 00045 AGUA m3 0.23 6.80
05 00042 PIEDRA CHANCADA DE 1/2'' - 3/4'' m3 0.63 70.00
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 8.05 18.20
Equipo
48 00040 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 1.000 0.40 15.00
49 00038 VIBRADOR A GASOLINA 1 3/4", 4HP hm 0.500 0.20 9.80
03.02.03.01 MURO DE LADRILLO KK DE ARCILLA SOGA 24X14X9 J=1.5, PARA ALINEAMIENTO DE FACHADA Rend:
Código Descripción Insumo Unidad Cuadrilla Cantidad Precio
Mano de Obra
47 00002 CAPATAZ hh 0.100 0.0700 20.30
47 00020 OPERARIO hh 1.000 0.7300 19.18
47 00003 PEON hh 1.000 0.7300 14.30
Materiales
02 00037 CLAVOS PARA MADERA C/C 3-4" kg 0.0200 4.20
04 00021 ARENA GRUESA m3 0.0400 60.30
05 00045 AGUA m3 0.0140 6.80
17 00115 LADRILLO MECANIZADO TIPO IV 24X14X9 CM und 39.0000 1.80
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 0.4500 18.20
43 00036 MADERA PARA ENCOFRADO p2 0.6000 5.10
Materiales
02 00037 CLAVOS PARA MADERA C/C 3-4" kg 0.0250 4.20
04 00046 ARENA FINA m3 0.0200 76.26
05 00045 AGUA m3 0.0050 6.80
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 0.1200 18.20
43 00036 MADERA PARA ENCOFRADO p2 0.6000 5.10
Materiales
43 00116 LIJA PARA MADERA und 0.0200 1.70
54 00117 PINTURA LATEX gln 0.0500 40.00
54 00118 SELLADOR BLANCO gln 0.0350 25.00
Materiales
04 00046 ARENA FINA m3 0.0260 76.26
04 00021 ARENA GRUESA m3 0.0440 60.30
05 00045 AGUA m3 0.0500 6.80
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 0.5000 18.20
SIKATOP 77 gal 0.1500 80.00
SIKADUR 32 Kg 0.1600 89.00
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 102.81
49 00121 MOTOSOLDADORA DE 250 AMP. hm 0.250 0.3333 120.00
sub partida
DEMOLICION MANUAL m3 0.12 150.70
02 00033 ENCOFRADO Y DESENCOFRADO m2 0.8500 81.35
CONCRETO F´C = 210 KG/CM2 m3 0.3100 515.78
ACERO DE CANAL Kg 25.0000 5.29
Materiales
04 00046 ARENA FINA m3 0.0260 76.26
04 00021 ARENA GRUESA m3 0.0440 60.30
05 00045 AGUA m3 0.0500 6.80
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 0.5000 18.20
SIKATOP 77 gal 0.1500 80.00
SIKADUR 32 Kg 0.1600 89.00
02 00125 VARILLA LISA 3/8" kg 2.0000 3.80
50 00124 PLANCHA METALICA E= 1/8", CON MARCA SUPERFICIAL Y REL kg 12.0000 2.90
51 00122 PERFIL ANGULO 1 1/2" x 1 1/2" x 3 mm kg 6.0000 3.80
51 00123 SOLDADURA DE ELECTRODO kg 1.0000 5.80
54 00095 PINTURA ANTICORROSIVA gln 0.0600 35.87
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 110.59
49 00121 MOTOSOLDADORA DE 250 AMP. hm 0.500 0.5000 120.00
Materiales
02 00037 TUBO PVC SAL D= 160 mm m 1.0500 22.47
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 14.20
Materiales
02 00037 TUBO PVC SAL D= 6" m 1.0500 25.30
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 11.37
Materiales
02 00125 VARILLA LISA INOXIDABLE 3/8" kg 0.3000 3.80
50 00124 PLANCHA METALICA E= 1/8", CON MARCA SUPERFICIAL Y REL kg 0.7500 2.90
51 00122 PERFIL ANGULO 1 1/2" x1/2" x 3 mm kg 25.0000 3.80
51 00122 CANAL U 3" x 5 lb/pie kg 30.0000 3.80
51 00123 SOLDADURA DE ELECTRODO kg 0.8000 5.80
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 38.56
49 00121 MOTOSOLDADORA DE 250 AMP. hm 0.250 0.1250 120.00
sub partida
CONCRETO F´C = 210 KG/CM2 m3 0.1000 515.78
ACERO DE CANAL Kg 9.0000 5.29
Materiales
04 00021 ARENA GRUESA m3 0.61 60.30
05 00042 PIEDRA CHANCADA DE 1/2'' - 3/4'' m3 0.66 70.00
21 00039 CEMENTO PORTLAND TIPO I (42.5KG) bol 11.50 18.20
34 00041 GASOLINA 84 OCTANOS gln 0.33 10.50
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.00 238.79
48 00040 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 1.000 0.80 15.00
49 00038 VIBRADOR A GASOLINA 1 3/4", 4HP hm 1.000 0.80 9.80
Materiales
SIKADUR 32 Kg 0.0600 89.00
SIKATOP 77 Kg 0.0600 80.00
Equipo
37 00001 HERRAMIENTAS MANUALES %mo 3.0000 4.74
0.05
0.53
1.14
1.72
0.01
0.01
0.01
0.03
0.19
5.16
0.15
0.39
2.14
0.32
3.07
4.58
7.97
4.00
4.00
6.87
6.87
0.13
0.40
7.60
8.13
26.97
Propuesta
10.00 m3/DIA
Parcial
1.62
25.44
45.76
72.82
2.18
12.48
56.00
7.22
77.88
150.70
0.16
2.29
2.45
0.07
0.07
2.52
210.00 m2/DIA Expediente Técnico
Parcial
0.08
0.73
0.61
2.18
3.60
0.24
0.24
0.11
0.56
0.67
4.51
Propuesta
7.50 m3/DIA
Parcial
8.66
45.76
54.42
1.63
1.63
56.05
Expediente Técnico
3.0 m3/DIA
Parcial
5.41
38.13
43.54
1.31
33.87
35.18
78.72
0.01
0.08
0.15
0.11
0.35
0.01
1.82
0.85
2.68
3.03
Propuesta
300.00 m2/dia
Parcial
0.05
0.51
0.42
1.14
2.12
1.93
2.31
5.57
9.81
0.29
0.15
0.10
0.54
12.47
0.11
1.53
1.07
2.71
175.28
6.60
181.88
0.08
2.56
15.00
17.64
202.23
2.03
19.18
22.88
44.09
1.32
9.60
16.00
26.92
71.01
9.0000 m2/DIA Expediente Técnico
Parcial
1.80
17.05
14.13
25.42
58.40
1.07
1.47
0.05
21.62
24.21
1.75
3.33
5.08
87.69
10.0000 m3/DIA Expediente Técnico
Parcial
3.25
61.38
25.44
137.28
227.35
39.20
46.20
172.90
3.47
261.77
6.82
12.00
7.84
26.66
515.78
0.06
0.61
0.51
1.18
0.36
3.71
4.07
0.04
0.04
5.29
16 Und/DIA Propuesta
Parcial
5.08
19.18
14.30
38.56
0.76
1.74
68.40
91.20
2.90
165.00
1.16
10.00
11.16
23.95
26.45
50.40
265.12
10.0000 m3/DIA Expediente Técnico
Parcial
3.25
61.38
25.44
137.28
227.35
39.20
46.20
200.20
3.47
289.07
6.82
12.00
7.84
26.66
543.08
1.42
12.85
9.58
23.85
2.66
0.84
37.25
1.58
42.33
0.72
2.48
3.20
69.38
1.62
15.34
22.88
39.84
1.98
2.65
0.33
6.16
0.10
14.20
25.42
1.20
2.10
3.30
68.56
1 Un/DIA Propuesta
Parcial
306.88
114.40
421.28
42.13
42.13
463.41
12.0000 m3/DIA Expediente Técnico
Parcial
89.57
10.65
66.78
167.00
35.43
1.56
44.10
146.51
227.60
5.01
10.05
6.57
21.63
416.23
8 Und/DIA Propuesta
Parcial
10.15
57.54
42.90
110.59
1.98
2.65
0.34
9.10
12.00
14.24
7.60
34.80
22.80
5.80
2.15
113.47
3.32
30.00
33.32
257.37
6 Und/DIA Propuesta
Parcial
13.53
51.15
38.13
102.81
1.98
2.65
0.34
9.10
12.00
14.24
26.08
3.08
10.00
13.08
18.08
69.15
159.89
132.25
379.37
521.34
Propuesta
6 Und/DIA
Parcial
13.53
51.15
57.20
121.88
1.98
2.65
0.34
9.10
12.00
14.24
26.08
3.66
10.00
13.66
36.56
260.32
235.38
423.20
530.24
1,449.14
1,610.75
2.49
19.02
21.51
0.65
0.65
22.16
Parcial
8.12
76.72
28.60
113.44
149.15
4.72
10.77
7.18
25.42
2.15
199.39
3.40
86.40
89.80
402.63
15.00 m3/DIA Expediente Técnico
Parcial
1.02
20.52
17.01
61.06
99.61
21.11
1.94
28.00
21.00
100.10
172.15
2.99
8.00
5.23
16.22
287.98
0.81
17.07
21.15
57.20
96.23
35.43
1.56
44.10
146.51
227.60
6.00
1.96
7.96
331.79
1.42
14.00
10.44
25.86
0.08
2.41
0.10
70.20
8.19
3.06
84.04
109.90
1.62
30.69
11.44
43.75
0.11
1.53
0.03
2.18
3.06
5.93
49.68
20.0000 m2/DIA Propuesta
Parcial
0.81
7.67
5.72
14.20
0.03
2.00
0.88
2.91
17.11
6 Und/DIA Propuesta
Parcial
13.53
51.15
38.13
102.81
1.98
2.65
0.34
9.10
12.00
14.24
26.08
3.08
10.00
13.08
18.08
69.15
159.89
132.25
379.37
521.34
8 Und/DIA Propuesta
Parcial
10.15
57.54
42.90
110.59
1.98
2.65
0.34
9.10
12.00
14.24
7.60
34.80
22.80
5.80
2.15
113.47
3.32
30.00
33.32
257.37
Propuesta
40 m/DIA
Parcial
0.81
7.67
5.72
14.20
23.59
23.59
0.43
0.43
38.22
Propuesta
50 m/DIA
Parcial
0.65
6.14
4.58
11.37
26.57
26.57
0.34
0.34
38.28
16 Und/DIA Propuesta
Parcial
5.08
19.18
14.30
38.56
1.14
2.18
95.00
114.00
4.64
216.96
1.16
15.00
16.16
51.58
47.61
99.19
370.87
10.0000 m3/DIA Expediente técnico
Parcial
3.25
61.38
25.44
148.72
238.79
36.52
46.20
209.30
3.47
295.49
7.16
12.00
7.84
27.00
561.28
30 m2/DIA Propuesta
Parcial
0.27
2.56
1.91
4.74
5.34
4.80
10.14
0.14
0.14
15.02