Professional Documents
Culture Documents
CASING DRILLING
Drilling with Casing Advances to Floating Drilling Unit TECHNICAL
With Surface BOP Employed CONFERENCE
Edi Sutriono – Santos, Ralph Adams – Santos, Greg Galloway – Weatherford, Ken Dalrymple – Weatherford
Copyright 2003 World Oil Casing Drilling Technical Conference
This paper was prepared for presentation at the World Oil 2003 Casing Drilling Technical Conference, held at the Westchase Hilton, Houston, Texas, March 6 - 7, 2003. The information presented in this
paper does not reflect any position, claim or endorsement made or implied by Gulf Publishing Company, its publications, their officers, editors, or employees. Questions concerning the content of this
paper should be directed to the individuals listed as author/s of this work.
Pilot Hole and laid down and a 26” drilling assembly was made up
On Well-1, the rig was positioned 30 meters off the to wipe the hole. The hole was reamed from 165 meters
proposed well location and an 8 ½”pilot hole was drilled to 274 meters. A wiper trip was made without incident
to 279 meters. No shallow gas was encountered. 45 bbls and the assembly was pulled.
of 15.8 ppg neat cement was pumped while pulling out
of the pilot hole. The rig was positioned over the On the second attempt, the 20” casing was run to bottom
proposed location while picking up the BHA. This without incident. Cementing occurred as normal. The
operation required 10 hours to complete. trouble free time required to run and cement the 20”
casing was 14 hours.
On Well-2, since the first casing string was to be set at
the pilot hole depth, and not in two stages, the 8 ½” pilot From spud until the casing was set and cemented at 274
hole was drilled through a temporary guide base to a meters required a total of 58.5 hours. (Figure 5 Time
depth of 270 meters. No shallow gas was encountered. Analysis both wells)
The hole was displaced with 9.5 ppg mud while pulling
out of the hole. This operation required 4 hours to Well-2 drilling with surface casing
complete. The 17 ½” DrillShoeII was made up on 13-3/8” 72 # N-
80 casing. Two float collars were pre-installed on the pin
Eliminating the requirement for drilling and cementing an end of the first two joints of casing. (Figure 6 DrillShoe
offset pilot hole resulted in timesavings of 6 hours. and float collar) The casing was run to the mud line, the
13 3/8” casing spear with a packoff, suspended from the
Wellbore Geometry top drive, was inserted in the top joint of casing. The 17
½” hole was drilled from 69 meters to 270 meters in a
String Well-1 Well-2 total of 7 hours. This included time for; releasing the
Mud Line 79m 69.4m spear, installing the next joint and inserting the spear; to
Conductor 30” 159m NA ream each joint; and pump sweeps. The ROP was very
Surface 20” 268m 13-3/8” 264m conservative as the main objective was to set the casing
Intermediate 13-3/8” 488m 9-5/8” 499m deep at the pilot hole depth to ensure the LOT would be
Production 9-5/8” 835m 7” liner 684m sufficient to drill to the next casing setting depth.
With the 13 3/8” surface casing replacing the 18 ¾” riser A maximum of 55 RPM was run with the maximum WOB
and the surface BOP application the structural of 5 klbs. The highest torque noted was 3,000 ft.-lbs.
requirements of the 30” conductor was eliminated. The Field experience has shown optimum performance is
20” surface casing was replaced with the 13-3/8” to typically delivered with slow rotation speeds and low to
accommodate the surface BOP structural requirements moderate WOB. In most cases, torque is lower than
and increase the water depth capabilities of the surface experienced with conventional drilling assemblies. This
BOP system. (Figure 4 Well Schematic) is believed to be due the well bore quality delivered by
the stiff casing assembly and improved cuttings removal.
Well-1 Conductor and Surface Casings
Drilling the 36” hole to 165 meters required 8.5 hours. The circulating fluid was seawater with hi-vis sweeps
Running and cementing the 30” casing required a total of pumped prior to connections as required to suspend the
13.5 hours to complete, or a total of 22 hours to pre-drill cuttings in the annulus. The pump rate was maintained
and case the 30” casing string. at 575 GPM, is significantly lower than normal in a 17 ½”
diameter hole. This proved to be sufficient as no hole
A 26” hole was drilled to 274 meters with an IADC 1-1-5 cleaning problems were encountered.
bit in a total of 12.5 hours. Upon reaching TD a hi-vis
sweep was pumped and made a wiper trip to the 30” When drilling with casing a mono-diameter annulus
shoe, pumping out of the hole. The trip back to bottom exists. As a result the annular velocity (AV) is uniform
was without incident; no fill was encountered. A hi-vis along the entire annulus facilitating cuttings removal.
sweep was pumped and displaced with seawater and Flow rate selection should be based on a balance
the hole was displaced to 10 ppg mud. The 26” between optimum well bore cleaning with the fluid
assembly was then tripped out of the hole to run the 20” properties within the uniform AV and ECD management
casing. requirements.
The 20” casing was made up and run in the hole. An The final 6 joints of casing were 72# P110. This casing
obstruction was encountered at the 30” casing shoe the was required to meet the design criteria to drill with a
20” casing would not pass. The 20” casing was pulled surface BOP in shallow water depths. The casing can be
WOCD 0307-01 DRILLING WITH CASING ADVANCES TO FLOATING DRILLING UNIT WITH SURFACE BOP EMPLOYED 3
used as a riser for one well. Subsequent use of the riser thorough risk assessment. Drilling with Casing allowed
is usually permissible but only as casing below the mud the 13-3/8” casing to be drilled in and cemented in a
line.1 single trip. This reduced the time required and reduced
the risk of swabbing the well in while tripping and
The drilling with casing operation for the 13-3/8” casing running casing.
from the sea floor (69 meters) to 270 meters required 9.5
hours including rigging up the drilling with casing
equipment and changing to drill pipe and drill sufficient Acknowledgements
rathole to accommodate the 13 5/8” wellhead and The authors express appreciation to Santos (Madura
landing joint. Offshore) PTY LTD., partners in the wells BPMIGAS and
Talisman Madura and Weatherford International for their
Cementing 13-3/8” casing permission for this paper to be presented. We also thank
After drilling to TD, the casing spear assembly was laid Transocean for permission to use diagrams of the
out and the 13 5/8” Uni-Head, landing joint and cement Surface BOP System.
head were installed. The cementing operation utilized a
standard land rig cement head and standard cement
plugs. The float valves were in place during the drilling References
operation, requiring no additional action to be taken to
prevent the cement from u-tubing. The pumping 1. Shanks, E. Schroeder, J., Ambrose, B., Steddon, R.,
consisted of 80 bbls seawater, followed by 100 bbls 11.0 “Surface BOP for Deepwater Moderate Environment
lead slurry and 86 bbls of 15.8 ppg tail slurry. The Drilling Operations From A Floating Drilling Unit”
cement was displaced with seawater. The plug bumped paper OTC14265 presented at 2002 Offshore
with 1800 psi. Floats were checked and found to be Technology Conference, Houston, Texas, 6-9 May
holding and the cementing equipment was rigged down. 2002
The cementing operation required a total of 4 hours. 2. Wardley, M., Priadi, A. Dalrymple, K., “Drilling with
Casing – Practical, Cost Effective & Here to Stay”
On Well-2, from spud until the casing was drilled down to paper presented at Indonesian Petroleum
a depth of 270 meters and cemented in place required a Association Twenty Eighth Annual Convention and
total of 17.5 hours. This represents a savings of 41 Exhibition October, 2001
hours (70%) compared to Well-1.
Conclusion
Two high impact technologies were used in combination
to save a total of 60.5 hours in the surface hole interval
of the Well-2 well in the Madura strait off the coast of
Indonesia. This represents a 79% timesavings compared
to the direct offset (Well-1) well drilled 5 months earlier.
Both technologies had a significant impact on the
timesavings and they complemented each other
remarkably.
Well-1 Well-2
Well Schematic Well Schematic
0 RKB 0 RKB
MSL MSL
ML = 79 m ML = 69.4 m
30" @ 159 m
200 200
255 m Marker 5
20" @ 268 m 13-3/8" @ 264 m
279 m Marker 5
311 m Marker 6
336 m Marker 6
369 m Marker 7
400 400
13-3/8" @ 488 m
9-5/8" @ 499 m 490 m Paciran Marl Fm
519 m Paciran Marl Fm
600 600
800 800
90.0
80.0
70.0
60.0
50.0
Hours
40.0
30.0
20.0
10.0
0.0
Well-1 Well-2
Figure 5 Time Breakdown Well-1 & Well-2 Pilot hole to Surface Casing Set
WOCD 0307-01 DRILLING WITH CASING ADVANCES TO FLOATING DRILLING UNIT WITH SURFACE BOP EMPLOYED 7
Well-1 Well-2
0 0
300 300
Drill 8 1/2"
Pilot Hole Loss circulation
Drill 12 1/4"" hole
Me Open hole to 17 1/2"
as 400 400
Drill 12 1/4" hole
ur Logs
ed Logs Set 9 5/8" casing at 499 m
De Set 13 3/8" Csg at 488 m
pt 500 500
h
(m Drill 8 1/2" hole to 620 m
) Cut Cores
600 600
Drill 12 1/4" hole
700 700
Logs
Set 7" liner at 684 m
DST
800 800
900 900
1000 1000
0 5 10 15 20 0 5 10 15 20
Days from Spud Days from Spud
Figure 6 DrillShoe and lower float collar Figure 7 BOP Stack suspended in Moon Pool