Rate Analysis for Pile

E700194.648, N1927757.887
Datum level +5.899
Sand Layer +5.899 -1.500
Sandy Silt -1.500 -25.500
Completely weathered Rock -25.500 -26.750
Highly weathred Rock -26.750 -37.000
Total Bored Length

Pile Dia 1.10 m


Grade of Concrete M50-C
Liner Thk 8 mm

Liner Thk 10 mm

S.No Description of Item UOM Nos


1 Materials
10mm liner Structural steel MT 1
8mm liner Structural steel MT 1
Liner Fabrication MT 1
Concrete
Concrete up to Datum level Cum 1
Reinforcement MT 1

Polymer Kg 1
Sonic Tubes Rm 4
Fuel Charges Ltr 1

2 Machinery( for boring and Concreting )


Hire and running charges of Tripod and Day 1
Mechanical Winch machine
Hire and running charges of light crane for Hr 3
lowering reinforcement cage
Loader I cum bucket capacity. Hr 2
Tipper 5.5 cum capacity for disposal of muck Hr 2
from pile bore hole
Hire and running charges of Pump Day 1
Consumables

3 Labour
Supervisor Shift 3
Winch Operators Shift 4
Unskilled labour Shift 12

4 Subcontract
Chipping of Concrete Cum 1
Reinforcement Cage preparation MT 1
Concreting Cum 1
7.399
24.000
1.250
10.250
42.899

1000mm 6.899 -25.50 32.399


dia
1500mm 6.899 -8.00 14.899
dia

1,818,605 14,161,829 12,343,224


Qty Total Qty Rate Amount Remarks

5.51 5.51 56,000 308,643


7.03 7.03 56,000 393,751
12.54 12.54 14,000 175,598

41.72 41.72 12,000 500,623


4.17 4.17 48,000 200,249

25.03 25.03 500 12,516 0.6kg/cum


43.40 173.60 300 52,079
120.00 108.00 73 7,884

6.00 6.00 5,000 30,000

1.00 3.00 1,500 4,500


6.00 12.00 650 7,800
6.00 12.00 650 7,800
6.00 6.00 625 3,750
5,385

6.00 18.00 842 15,147


6.00 24.00 718 17,226
6.00 72.00 635 45,738

0.48 0.48 1,500 713


4.17 4.17 3,500 14,602
41.72 41.72 350 14,602
6.899 -8
6.899