MFJO770 / MVCP00096 : VAPOUR RECOVERY UNITY : ACTIVITY SCHEDULE

Client: JOHN ZINK HAMWORTHY COMBUSTION


Project Details

PO No. : Planned: 13-Nov-18 CDD: 13-Nov-18


Equipment: VAPOUR RECOVERY UNIT Qty: 1 Nos.
Inspection by: MFME/ASME AI/JZHCL/CLIENT RT :
no. of Planned Actual
SR.NO. Activity Description days From To From To
1 ADSORBER
1 MATERIAL PROCUREMENT 85 23-May-18 16-Aug-18
2 VESSEL FABRICATION 81 10-Jun-18 30-Aug-18
3 SECONDARY STRUCTURE FABRICATION 64 17-Jun-18 20-Aug-18
4 PAINT JOB MEETING 0 9-Aug-18 9-Aug-18
5 HYDRO TESTING 1 1-Sep-18 2-Sep-18
6 PAINTING 10 4-Sep-18 14-Sep-18
7 PACKING 3 15-Sep-18 18-Sep-18
2 ABSORBER
1 MATERIAL PROCUREMENT 85 23-May-18 16-Aug-18
2 VESSEL FABRICATION 81 10-Jun-18 30-Aug-18
3 SECONDARY STRUCTURE FABRICATION 64 17-Jun-18 20-Aug-18
4 PAINT JOB MEETING 0 9-Aug-18 9-Aug-18
5 HYDRO TESTING 1 1-Sep-18 2-Sep-18
6 PAINTING 10 4-Sep-18 14-Sep-18
7 PACKING 3 15-Sep-18 18-Sep-18
3 SEPERATOR
1 MATERIAL PROCUREMENT 85 23-May-18 16-Aug-18
2 VESSEL FABRICATION 81 10-Jun-18 30-Aug-18
3 SECONDARY STRUCTURE FABRICATION 64 17-Jun-18 20-Aug-18
4 PAINT JOB MEETING 0 9-Aug-18 9-Aug-18
5 HYDRO TESTING 1 1-Sep-18 2-Sep-18
6 PAINTING 10 4-Sep-18 14-Sep-18
7 PACKING 3 15-Sep-18 18-Sep-18
4 KOD
1 MATERIAL PROCUREMENT 85 23-May-18 16-Aug-18
2 VESSEL FABRICATION 81 10-Jun-18 30-Aug-18
3 SECONDARY STRUCTURE FABRICATION 64 17-Jun-18 20-Aug-18
4 PAINT JOB MEETING 0 9-Aug-18 9-Aug-18
5 HYDRO TESTING 1 1-Sep-18 2-Sep-18
6 PAINTING 10 4-Sep-18 14-Sep-18
7 PACKING 3 15-Sep-18 18-Sep-18
5 VENT STACK
1 MATERIAL PROCUREMENT 30 20-Jun-18 20-Jul-18
2 VENT STACK FABRICATION 18 12-Jul-18 30-Jul-18
4 PAINT JOB MEETING 0 15-Jul-18 15-Jul-18
5 PAINTING 9 1-Aug-18 10-Aug-18
6 PACKING 4 11-Aug-18 15-Aug-18
6 INTERCONNECTING PIPES
1 MATERIAL PROCUREMENT 61 20-Jun-18 20-Aug-18
2 PIPING FABRICATION 71 1-Jul-18 10-Sep-18
3 SECONDARY STRUCTURE FABRICATION 60 1-Jul-18 30-Aug-18
4 PAINT JOB MEETING 1 20-Aug-18 21-Aug-18
5 HYDRO TESTING 19 11-Sep-18 30-Sep-18
6 PAINTING 20 20-Sep-18 10-Oct-18
7 PACKING 19 1-Oct-18 20-Oct-18
7 ALL INDIVIDUAL SKIDS
1 MATERIAL PROCUREMENT 99 23-May-18 30-Aug-18
2 PIPING FABRICATION 81 1-Jul-18 20-Sep-18
3 STRUCTURAL FABRICATION 40 1-Jul-18 10-Aug-18
4 PAINT JOB MEETING 1 1-Sep-18 2-Sep-18
5 HYDRO TESTING OF PIPING SPOOLS 12 18-Sep-18 30-Sep-18
6 PAINTING 14 1-Oct-18 15-Oct-18
8 FINAL ASSEMBLY
1 FINAL ASSEMBLY OF INDIVIDUAL PACKAGES WITH E & I WORKS 17 10-Oct-18 27-Oct-18
2 PNEUMATIC TEST OF INDIVIDUAL PACKAGES 10 21-Oct-18 31-Oct-18
9 PACKING
1 PACKING OF INDIVIDUAL PACKAGES 12 1-Nov-18 13-Nov-18