Tentative Guidelines for various items for road work in MoRD data

LSGD DIVISION, ERNAKULAM

Item No Item Can be used for Remarks

New Roads
3.5.1 Excavation in cutting in soil by manual Road sectioning
means Length x ½ width x 0.075 m
3.3 Construction of embankment with Filling with available earth
material obtained from roadway
cutting
3.4 Construction of embankment with Filling with contractors own earth (if
material obtained from borrow pits depth of filling is more than 30 cm, the
remaining depth is taken in this item)
Eg. If depth of filling is 1.0m, 30 cm is
taken in 3.14 and 70 cm is taken in 3.4
4.11.2 Granular sub base/ base/ surface Filling with Quarry waste
course with local materials

(Modified)
3.14 Construction of subgrade and Filling with contractors own earth for
shoulders subgrade and shoulders.
(1) For subgrade, length x 3.10x 0.3
(2) 2x length x shoulder width x 0.15
3.15.2 Compacting original ground Compacting subgrade using available soil

4.10 Construction of shoulders Earthen shoulders


4.9 Wet mix macadam, mechanical mix Width is taken as 3.10 m. Average depth
is taken for payment
5.1.1a Prime coat SS-1, low porosity, on After the construction of WMM, prime Bitumen cost is revised as per
granular base, dosage 0.70- 1.0 kg/m2 coat is applied and kept for 24 hrs Circular
without any traffic DB3/6512(B)/2013/CE/LSGD
dtd 1/9/2016
5.2.3a Tack coat RS-1, on granular surface, After 24 hrs, tack coat is applied Bitumen cost is revised as per
dosage 0.25 to 0.3 Kg/m2 Circular
DB3/6512(B)/2013/CE/LSGD
dtd 1/9/2016
5.9.1.2a 20 mm thick open graded premix Chipping carpet Bitumen cost is revised as per
chipping carpet using bitumen S-65, by Circular
manual means DB3/6512(B)/2013/CE/LSGD
dtd 1/9/2016
5.12.A.3.2a Seal coat , by manual means, using Seal coat Bitumen cost is revised as per
bitumen S-65 Circular
DB3/6512(B)/2013/CE/LSGD
dtd 1/9/2016
Retarring
5.5.B.2a Modified penetration macadam 75 mm Pot hole filling Bitumen cost is revised as per
thick, using bitumen S-65 Circular
DB3/6512(B)/2013/CE/LSGD
dtd 1/9/2016
5.2.1a Tack coat, RS-1 on bituminous surface, On the day of retarring, tack coat is Bitumen cost is revised as per
dosage 0.2 to 0.25 kg/m2 applied before laying chipping carpet Circular
DB3/6512(B)/2013/CE/LSGD
dtd 1/9/2016
5.9.1.2a 20 mm thick open graded premix Chipping carpet Bitumen cost is revised as per
chipping carpet using bitumen S-65, by Circular
manual means DB3/6512(B)/2013/CE/LSGD
dtd 1/9/2016
5.12.A.3.2a Seal coat , by manual means, using Seal coat Bitumen cost is revised as per
bitumen S-65 Circular
DB3/6512(B)/2013/CE/LSGD
dtd 1/9/2016
Cement Concrete Roads
3.5.1 Excavation in cutting in soil by manual Road sectioning
means Length x ½ width x 0.075 m
OD (3.4) Construction of embankment with For filling contractors own earth , Roller, dozer, grader and water
material obtained from borrow pits, by consolidation by ramming tanker excluded
manual means
OD (11.4.1) Cement concrete M10, using 40mm For base layer Formwork excluded, Cement
graded broken stones content changed to 170kg/m3
OD (11.4.3) Plain Cement concrete M20, (1:2:4), For top layer Formwork excluded, Cement
using 20mm broken stones content changed to 320 kg/m3,
40mm aggregate excluded,
20mm -0.54 and 10mm 0.36
Drain
3.5.1 Earth work excavation
OD (11.4.1) Cement concrete M10 (1:3:6), using For bottom layer Formwork excluded
40mm broken stones

11.4.2.1 Cement concrete M15 (1:2.5:5) using Sides of drain , plastering is to be


40mm broken stones avoided

OD (11.4.3) Plain Cement concrete M20, (1:2:4), For wearing coat, 5cm thick Formwork excluded, Cement
using 20mm broken stones content changed to 320 kg/m3,
40mm aggregate excluded,
20mm -0.54 and 10mm 0.36
11.4.4 RCC M20 (1:2:4), 20 mm broken stone Covering slabs

11.8 TMT reinforcement


For culverts having span up to 1.5m, the above items shall be used. For slabs having vehicular traffic, 13.1.2 and 13.3 shall be used
instead of 11.4.4 and 11.8

Bridges/ culverts having span > 1.50 m


11.1.1 Earth work excavation

11.2.1 Sand filling in foundation


OD (11.4.1) Cement concrete M10 (1:3:6), using For foundation Formwork excluded
40mm broken stones
11.4.1 Cement concrete M10 (1:3:6), using For foundation With formwork
40mm broken stones
12.5.1.1 Cement concrete M15 (1:2.5:5) using Abutments
40mm broken stones

12.5.3 RCC M20 (1:2:4), 20 mm broken stone Bed blocks


12.7 TMT reinforcement Reinforcement for abutments and bed
blocks
13.1.2 RCC M25 (1:1½:3), 20 mm broken Slab
stone

13.3 TMT reinforcement Reinforcement for slab

Side wall
3.5.1 Earth work excavation

OD (8.7.2) Dry rubble masonry For foundation works and for sidewalls Converted to m3
up to 3.0 m
OD (12.4.3.3) Random rubble masonry in CM 1:6 For side walls up to 5.0 m Cement content is taken from
CPWD specification item no.
3.11
12.3 Plastering with CM 1:4, 15 mm thick on
stone masonry
12.5.3 RCC M20 (1:2:4), 20 mm broken stone For belt concrete

12.7 TMT reinforcement

MoRD roads Over head 10% Road, drain, side wall and culverts having
span up to 1.5 m
MoRD protection works Over head 15% Protection works like aprons, etc
MoRD bridges Over head 20% Culverts having span greater than 1.5 m
and for bridges

For bridges having span up to 15 m can only be taken in MoRD specification