PUBLICATIONS

SPP Briefing Paper

Volume 11:18 June 2018

THE NORTH WEST REDWATER STURGEON


REFINERY: WHAT ARE THE NUMBERS FOR
ALBERTA’S INVESTMENT?

Brian Livingston

SUMMARY
Since 2006, the government of Alberta has tried to increase the volume
of raw bitumen upgraded and refined in the province. More specifically,
the Alberta Petroleum Marketing Commission (APMC) and Canadian
Natural Resources Ltd. (CNRL) have entered into agreements with a
facility northeast of Edmonton called the North West Redwater (NWR)
Sturgeon Refinery. The NWR Sturgeon Refinery is designed to process
79,000 barrels per day (bpd) of feedstock, consisting of 50,000 bpd of
bitumen and 29,000 bpd of diluent (referred to as dilbit). The refinery
will produce petroleum products consisting of approximately 40,000
bpd of low sulphur diesel, 28,000 bpd of diluent and 13,000 bpd of
other lighter petroleum products. It will also be able to capture 1.2 million
tonnes per year of carbon dioxide emitted from the refinery’s operations.
This captured carbon dioxide will be compressed, put into a pipeline
and then injected into an existing oil field in order to achieve increased
production of crude oil (referred to as enhanced oil recovery or EOR). It
is the first refinery built in Canada since 1984, and the first one in Canada
to refine bitumen into petroleum products such as diesel fuel. It differs
from the upgrader built in Lloydminster which only upgrades bitumen
into synthetic crude oil that requires further refining at a conventional
refinery in order to produce petroleum products.
This paper gives a description of the structure of this support by APMC
and CNRL using a mechanism whereby those two parties agree to enter
into tolling agreements to process the diluted bitumen feedstock into
refined petroleum products for sale. Under the tolling agreement, APMC
and CNRL retain ownership of the diluted bitumen as it is refined into
petroleum products. APMC and CNRL then sell such petroleum products,

http://dx.doi.org/10.11575/sppp.v11i0.53039 w w w. policyschool.ca
and pay a tolling fee to the NWR Sturgeon Refinery for the refining service
provided. The paper also uses an economic model in Excel to give a projection of
the economics of this facility for the first full year of operation. The objective is to
put numbers to a project that has been the subject of much qualitative discussion.
The Excel economic model contains base case assumptions for a number of
variables such as the capital cost of the refinery, the financing costs associated
with such capital costs, the operating costs of the refinery, the cost of the diluted
bitumen feedstock and the price of the petroleum products produced by and
sold from the refinery.
Based on these base case assumptions, the Excel economic model shows that in
the first full year of operation of the NWR Sturgeon Refinery in 2019, the two toll-
paying entities, APMC and CNRL, are projected to lose a cash amount of about
$24 million (about $1 per barrel of diluted bitumen supplied). This loss is based
on a comparison to the toll payers’ alternative of just selling the diluted bitumen
feedstock at market prices.
The paper then uses the economic model to do a sensitivity analysis to show
the effect of a lower or higher price of diluted bitumen feedstock, as well as
the effect of a lower or higher price of the produced petroleum products. If the
cost of the diluted bitumen feedstock were lower, or the price of the petroleum
products were higher, then APMC and CNRL would earn a profit. If the converse
occurred (feedstock costs higher or petroleum product price lower), then the
loss to APMC and CNRL would be greater than $24 million.
Finally, the paper attempts to create a template for governments to use when
they consider whether or not to provide financial assistance to various projects.

1
I. INTRODUCTION
In the last 50 years in Alberta, the production of oil and gas from conventional sources
has declined, and the production of bitumen from the oilsands in northeastern Alberta
has increased (Alberta Energy, 2018). Current production of bitumen from the oilsands in
2016 was 2.5 million barrels per day, a number that may increase to as much as 3.7 million
barrels per day by 2030 (CAPP, 2017).

The government of Alberta has taken a keen interest in the oil and gas industry ever since
the first discovery was made over a century ago. Given the rise in bitumen production,
it has focused its more recent policies on the development and production of bitumen.
More specifically, it has focused on the upgrading of such bitumen into more value-added
products. This paper describes one such policy initiative, namely the Alberta government’s
involvement with a publicly owned company named Canadian Natural Resources Ltd.
(CNRL) and a private company named North West Refining who are 50/50 partners in the
North West Redwater Partnership which owns the refinery. The three entities are involved
in the construction and anticipated operation of a facility named the North West Redwater
(NWR) Sturgeon Refinery.

Before looking at the specifics of the Alberta government policy and the NWR Sturgeon
Refinery, it is helpful to look at the historical background for bitumen production in Alberta.

II. THE HISTORY OF BITUMEN PRODUCTION IN ALBERTA

(a) The Characteristics of Bitumen

The existence of the oilsands in Alberta has been known for centuries, and predates the
discovery of conventional oil and gas in Alberta. Early explorers in northeast Alberta could
literally smell the raw bitumen at the surface, and observed that the Indigenous people used
the bitumen to seal their canoes.

Notwithstanding this early awareness of the oilsands, the commercial development of


bitumen has been a long and involved process. A good summary of the history is contained
in an article in the Edmonton Journal (2013).

The main reason for this difficulty in development is that bitumen is fundamentally
different from most conventional oil. It is referred to as heavy – not only because it weighs
a lot, but also because it is extremely viscous. It resembles peanut butter, versus the corn
oil-like viscosity of most conventional oil (BP, 2011).

The extreme viscosity is due to the fact that many of the hydrogen atoms in the bitumen
have evaporated, leaving behind a crude oil with a higher carbon-to-hydrogen ratio.

2
(b) Initial Production of Bitumen in the 1970s and 1980s

The consequence of this greater viscosity is that it is more difficult and more expensive
to transport and refine bitumen into petroleum products than to transport and refine
conventional crude oil into petroleum products. The first commercial production of bitumen
commenced in the late 1960s by Great Canadian Oil Sands (GCOS), whose operations were
eventually taken over by the present-day Suncor Energy Inc. (2018a).

Raw bitumen had no value at that time since it could not be used as a feedstock in
most refineries. As a result, the GCOS facility included an industrial process known as
upgrading, in which the raw bitumen was upgraded into synthetic crude oil that could be
used as feedstock for most refineries.

Several other bitumen operations commenced in the next 30 years: Syncrude, Shell Albion,
CNRL Horizon and Nexen Long Lake. Each bitumen-producing operation included
an upgrader to produce synthetic oil. In addition, a stand-alone upgrader that upgrades
bitumen into synthetic crude oil was built in Lloydminster and is currently operated by
Husky Energy.

Starting in the 1980s, some refineries in the Gulf Coast and Midwest areas of the United
States added specialized equipment known as cokers (to reduce the carbon content) or
hydrotreaters (to increase the hydrogen content). This specialized equipment permitted the
refining of diluted bitumen directly into petroleum products. The incentive to make this
capital investment in specialized equipment was that the cost of bitumen feedstock was
significantly less than conventional crude (referred to as the heavy oil discount).

In essence, these investments in various U.S. refineries collectively created several virtual
upgraders that could convert previously worthless bitumen into more valuable petroleum
products.

Alberta producers of bitumen were now able to sell diluted bitumen into a newly created
bitumen market in the United States. The bitumen had to be mixed with light hydrocarbons
called diluent in order to reduce the viscosity and thereby permit the diluted bitumen to
flow in a pipeline and be shipped to these U.S. refineries. This explains why Imperial’s
Kearl and Cold Lake operations plus Suncor’s Fort Hills mine do not have upgraders, and
therefore sell diluted bitumen into the United States and other markets.

The following chart summarizes the production and use of bitumen in Alberta.

3
Source: Alberta Energy Regulator

(c) Canadian Refined Product Markets


The refined products infrastructure in Western Canada was built on an east-west axis. Most
of the supply of petroleum products in the four western provinces comes from three large
refineries in or near Edmonton. The current demand/supply balance is such that the supply
from these three refineries is less than total Western Canada demand. The balance of supply
comes from the Parkland (formerly Chevron) refinery in Burnaby plus imports, primarily
from the United States. This situation is known as import parity, in that the marginal barrel
of supply comes from imports into the Vancouver area. Very little infrastructure exists that
can export petroleum products out of Alberta into the northern United States, other than
rail and trucking.

Historically, the feedstock for these three refineries has come from conventional and
synthetic light crude oil. This conventional and synthetic feedstock supply has been stable
for decades and continues to be stable today. As a result, there was very little incentive to
invest in the equipment necessary to refine diluted bitumen into petroleum products. The
higher cost of construction of this type of equipment in the Alberta market was another
deterrent to making such investments. The equipment at the three refineries is relatively
simple from a chemical engineering perspective, and does not include the cokers and
hydrotreaters necessary to process diluted bitumen as feedstock. As a result, there is very
little refining capacity in Canadian refineries that will permit the processing of diluted
bitumen as a feedstock.

Some of the diluted bitumen that is processed in Canada is for asphalt production at the
Imperial refinery at Strathcona and the Husky Energy asphalt plant in Lloydminster with a
processing capacity of 29,000 bpd (Husky Energy, 2017a).

4
Most of the diluted bitumen used in in the Shell Albian upgrader is upgraded to synthetic
crude and then used as feedstock for the Shell Scotford refinery, Suncor’s Edmonton
refinery has a coking facility and can process 29,000 bpd of bitumen, which is about 20 per
cent of that refinery’s capacity (Suncor, 2017). In addition, Imperial Oil’s Sarnia refinery
has a coking facility that has enabled it to process raw bitumen (Wikipedia, 2018a).

The Husky upgrader at Lloydminster commissioned in 1994 is the only stand-alone


upgrader in Canada, with an ability to process 82,000 bpd of heavy oil.

(d) The Canadian Market for Diluted Bitumen


The lack of investment in Canadian upgrader capacity or refineries that could use diluted
bitumen as a feedstock, combined with the increase in bitumen since the 1990s, meant that
there was an excess of diluted bitumen supply in Alberta.

The consequence was that this excess supply was earmarked for export, primarily to the
United States. As a result, and in contrast to the refined products market, the crude oil
transportation infrastructure for the shipment of diluted bitumen has grown primarily on a
north-south axis since the 1990s.

The destinations for these diluted bitumen exports are refineries in the United States. Most
of these U.S. refineries have been in existence for a long time, and are located in either the
Gulf Coast (Texas or Louisiana) or in the Midwest (Illinois, Wisconsin, Minnesota, Ohio or
Colorado). Not by coincidence, these locations are close to areas of large population (Texas
alone has a population two times as large as all of Western Canada). This large population
creates a high demand for petroleum products (much higher than Western Canada demand).
As a result, many of these refineries have a very large capacity. ExxonMobil’s Baytown
refinery, for example, has a capacity of 561,000 bpd, or three times the 185,000 bpd
capacity of Imperial’s Strathcona refinery (ExxonMobil, 2017).

These refineries are also close to various sources of feedstock supply. Gulf Coast refineries
in particular have flexibility of supply since they have access to ocean tankers as well as
pipelines. For several decades, much of the supply to these Gulf Coast refineries has been
heavy crudes from Mexico (called Maya) or Venezuela. In order to process this heavy oil
feedstock, these refineries invested in more complex cokers and hydrotreaters to use the
cheaper heavy oil as feedstock. More recently, production of Maya crude has declined due
to the natural decline of the Mexican oil fields, and production from Venezuela has declined
due to domestic turmoil. As a result, U.S. refiners have looked to Canadian diluted bitumen
as a substitute supply. Canadian diluted bitumen has created a new benchmark called
Western Canadian Select (WCS), with an accompanying quoted price in oil markets.

The fact that many of these refineries were very large meant that these investments were
made on an incremental brownfield basis versus a brand new greenfield basis. Combined
with the fact that productivity in the Gulf Coast was higher than in the Alberta market,
this meant that the cost of increasing the capacity to use heavy oil as a feedstock was
significantly less for Gulf Coast refineries than it would have been for Canadian refineries.
This lower cost is often expressed as cheaper by so many cents on the dollar for the
equivalent investment in capacity.

5
The bottom line result is that while the U.S. refiners invested in more complex refinery
configurations with higher processing capability that use cheaper feedstocks like WCS and
Maya, Canada did not (Wikipedia, 2018b).

(e) Strategies of Canadian Heavy Oil Producers


Many Canadian companies have employed other strategies to deal with their bitumen
production. Given the above discussion on relative cost of investment in diluted bitumen
feedstock, it is not surprising that these strategies involve using refineries in the United
States that have been adapted to use diluted bitumen as a feedstock.

Cenovus Energy Inc. (2017) produced about 150,000 bpd of bitumen in 2016. Cenovus also
has a 50 per cent interest in two refineries in the United States (one in Illinois, the other
in Texas) operated by ConocoPhillips (now Phillips 66). These two refineries have a total
refining capacity of 460,000 bpd and a heavy crude processing capacity of 255,000 bpd.
Cenovus processes a portion of its bitumen production into refined petroleum products in
these two refineries.

Husky Energy (2017b) produced 170,000 bpd of bitumen and heavy oil in 2016, an amount
that is expected to increase in the future. It has also acquired refining capacity in existing
refineries in the United States. It owns a refinery in Ohio in which it is currently making
investments to increase the refinery’s ability to process an additional 40,000 bpd of heavy
Canadian crude. It also owns 50 per cent of a refinery in Ohio in which recent investments
will increase the refinery’s ability to process an additional 65,000 bpd of heavy Canadian
crude, some of which will come from Husky’s Canadian heavy oil operations.

More recently, in August 2017 Husky purchased a refinery in Superior, Wisconsin with a
capacity of 50,000 bpd that can convert heavy oil into petroleum products (Healing, 2017).

Finally, Suncor has invested in refining capacity of 98,000 bpd in Colorado that can process
diluted bitumen as feedstock.

The key message of these strategies is that Cenovus, Husky and Suncor have chosen to
capture the benefits of upgrading a significant portion of the bitumen they produce by using
existing large-scale refineries in the United States with the accompanying economies of
scale and the benefits of lower incremental investment in cokers and hydrotreaters. Other
bitumen producers have chosen to export their bitumen to other refiners in the United States
that have invested in their existing refineries so as to be able to refine bitumen.

The United States has recently increased its production of light oil from the Permian Basin
in Texas by several million barrels per day. Since many of the Texas-based refineries are
equipped to process diluted bitumen, this increase in production of light oil will mean
that the United States will continue to be a major importer of heavier crudes that suit the
configuration of its refineries, but a larger exporter of light crude and refined products
(IEA, 2017).

6
III. THE ALBERTA GOVERNMENT’S REACTION TO BITUMEN EXPORT
The government of Alberta noticed the decline in the percentage of bitumen processed in
Alberta. When he was running for the leadership of the Conservative party in 2006, Ed
Stelmach said: “Shipping raw bitumen is like scraping off the topsoil, selling it, and then
passing the farm on to the next generation” (Steward, 2011).

As a result, the Alberta government embarked on a policy to encourage the upgrading of


bitumen in Alberta. More specifically, it asked bitumen producers to pay the royalty on
such production in actual barrels of bitumen, a process referred to as bitumen royalty-in-
kind (BRIK). The theory was that Alberta could then use this BRIK bitumen to guarantee a
long-term supply of bitumen that would encourage investors to build stand-alone upgraders/
refineries in Alberta. There was an initial optimism that several upgraders would be built as
a result of BRIK.

The recession of 2008 changed the optimism for the construction of upgraders or heavy
oil refineries. The Alberta government concluded that additional support was required
to encourage investment. Eager to keep one of former premier Stelmach’s signature
commitments, the government proceeded to sweeten the deal to keep the one remaining
project afloat — the North West Upgrader in Sturgeon County.1

IV. THE ECONOMICS OF REFINING BITUMEN

(a) The Basic Economic Decision

The decision whether or not to refine bitumen into petroleum products is a choice
between two alternatives. The first choice would be just to mix the bitumen with lighter
hydrocarbons such as naphtha (referred to as diluent) and load it into a pipeline at a
terminal such as the one at Hardisty, Alberta. There is currently a diluted bitumen market
in Canada that uses a posted benchmark price known as Western Canadian Select (WCS) at
Hardisty to determine the price of diluted bitumen (Oil Sands, 2018a).

1
See Morton (2015) on the policy and political process over several years that lead to the agreements supporting the
NWR Sturgeon Refinery. Morton, who was Minister of Finance for Alberta when the NWR Sturgeon Refinery deal was
negotiated, describes how the Alberta government came to assume the risks for both revenues from upgrading and capital
and operating costs.

7
The second choice is to refine the diluted bitumen into petroleum products.

An Excerpt from the Auditor General’s Report on the Choice to Refine Diluted Bitumen into
Petroleum Products

The refined product will typically have a higher market value than the bitumen the government
supplies to the refinery—but the difference between the market price and the bitumen cost has
to be greater than the toll for the government to make a profit. One risk in this scenario comes
from the fact that the market price of refined oil is unpredictable, so a profit after the toll is
paid is uncertain. A second risk is that increases in the construction costs of the refinery lead to
increases in the toll as [the NWR Sturgeon Refinery] seeks to recover costs. A larger toll makes
it harder for the government to make a profit.

Source: Report of Alberta Auditor General. Chapter on the Sturgeon Refinery, February 2018

The rest of this paper seeks to quantify the numbers in the above diagram.

(b) Factors Affecting the Economics of Refining Diluted Bitumen

As with any investment, several risks must be taken in a decision to upgrade or refine
bitumen. The most important of these risks are:

1. the anticipated revenue stream from the sale of petroleum products;


2. the feedstock costs of the diluted bitumen;
3. the capital costs of building the refinery;
4. the operating costs of operating the refinery;
5. the cost of financing such capital costs; and
6. the reliability of the operation, referred to as the utilization factor.

The construction of an economic model for the NWR Sturgeon Refinery requires the
making of assumptions for each of these items.

8
(c) Anticipated Revenue Stream
(i) Volumes of Petroleum Products Produced
The first step in determining a revenue stream is to make an assumption about the volumes
of petroleum products to be produced. An upgrader uses bitumen as a feedstock and
upgrades it to synthetic crude that is similar in composition and value to conventional
crude. A refinery uses conventional crude as feedstock and refines it into petroleum
products such as diesel fuel. The NWR Sturgeon Refinery is a heavy oil refinery designed
to perform both these functions by converting bitumen into petroleum products such as low
sulphur diesel fuel, distillate and other light petroleum products, mostly diesel fuel.

The NWR Sturgeon Refinery is designed to use the following feedstock and produce the
following petroleum products.

Feedstock Petroleum Products


50,000 bpd bitumen 40,250 bpd low sulphur diesel
29,000 bpd diluent 8,790 bpd low sulphur VGO
3,363 bpd of propane/butane
28,266 bpd of diluent

4,500 tons of CO2 per day

Note that the diluent in is almost balanced by the diluent out. Therefore, the main economic
activity is the transformation of 50,000 bpd bitumen into 52,403 bpd of petroleum products.
The increase in volume is due to the addition of hydrogen as part of the refining process
(North West Refining, 2018a).

(ii) Prices for Petroleum Products


The second assumption to be made is the sale prices for the various petroleum products.
The pricing of petroleum products is usually described as a percentage above a benchmark
crude price. This percentage is usually referred to as the crack spread, since it is the
difference in price caused by the refining process that “cracks” (the jargon of chemical
engineers) the feedstock molecules into petroleum products. For North America petroleum
products, that benchmark is the price of West Texas Intermediate, or WTI. The base case
assumptions are as follows, with prices shown as a percentage of WTI:

Petroleum Product Percentage of WTI


Low Sulphur Diesel 140 per cent
Low Sulphur VGO 105 per cent
Propane/Butane 85 per cent
Diluent 105 per cent

CO2 net sale proceeds $15/tonne

9
The assumption for the diesel crack spread is a critical one for the NWR Sturgeon Refinery.
The higher the crack spread, the more the revenue.

In order to test the validity of this assumption, it is useful to look at actual industry
experience. For example, there is a benchmark for wholesale diesel fuel known as the
Chicago ultra-low sulphur diesel to determine the price of diesel fuel. The price for diesel
received by a refinery is the wholesale price, not the retail price paid by the final consumer.
The graph below illustrates the historical prices for these two benchmarks in the most
recent six quarters, based on data obtained from Husky Energy.

Benchmark Prices
80

70

60

50
Wholesale diesel in Chicago
$ US/bbl 40

30 West Texas Intermediate


for Crude
20

10

0
June Sept Dec Mar June Sept
30/16 30/16 31/16 31/17 30/17 30/17

Source: Q3 2017 Husky Energy MD&A, 3

The data in this graph indicate an average crack spread for diesel of about 130 per cent in
the past six quarters. The crack spread in the third quarter of 2017 widened to 145 per cent,
likely due to the closing of refineries in Houston as a result of Hurricane Harvey.

A second data point is to use the petroleum product prices published by the Kent Group
(2018). The prices from that source are closer to home, and give wholesale diesel prices
(referred to as rack prices) for Calgary and Edmonton. The data show a higher crack
spread for the sale of wholesale diesel out of Calgary and Edmonton in the range of 150
per cent or more.

This higher crack spread assumes that the seller of diesel will realize the full rack price.
It is entirely possible that a new entrant into the diesel market such as the NWR Sturgeon
Refinery may have to range further away from these two cities in order to market its diesel
production. The new NWR Sturgeon Refinery production may have a sufficient effect on
the existing diesel wholesale market in Western Canada so that it changes from import
parity to export parity. In other words, the marginal barrel in this Western Canada market
may be destined for export. Given that NWR Sturgeon Refinery is a new entrant and does
not have existing domestic customers, it may have to export a significant portion of its

10
diesel production, which would be at a lower price than the Calgary and Edmonton market
for two reasons.

First, it costs money to transport the diesel to more distant customers, whether by rail
or by truck. These transportation costs will reduce the netback proceeds that a refiner
realizes. Second, the upper northern states of Montana, Wyoming, Idaho and North and
South Dakota already have diesel supply from existing refineries in Billings, Montana and
Colorado. Exports of diesel into the United States will have to compete with this existing
U.S. supply, and will therefore likely result in a reduced price.

As a third data point, the Dominion Bond Rating Service (DBRS) used an assumption of a
crack spread for diesel of 130 per cent over WTI when it performed its economic analysis to
rate the senior bonds issued by the NWR Sturgeon Refinery (DBRS, 2017a).

Given all this uncertainty, it makes sense to use a base case crack spread of 140 per cent,
with a sensitivity case using 130 per cent and 150 per cent.

Finally, an assumption of $15 per tonne is a reasonable one to use for the sale price of CO2
(Skinner, 2015).

(d) Feedstock Costs

As mentioned above, there is currently a diluted bitumen market in Canada that uses a
benchmark price known as Western Canadian Select (WCS) to determine the price of
diluted bitumen. The WCS price has historically moved in conjunction with WTI. The
graph below illustrates the historical prices for these two benchmarks in the most recent six
quarters, based on data obtained from Husky Energy.

Benchmark Prices
60

50

40

West Texas Intermediate


$ US/bbl 30 for Crude
Western Canadian Select
20 for Bitumen

10

0
June Sept Dec Mar June Sept
30/16 30/16 31/16 31/17 30/17 30/17

Source: Q3 2017 Husky Energy MD&A, 3

11
The data in this graph indicate that in the past six quarters, the average heavy oil discount
has been about US$12/barrel, with a high of US$15/barrel and a low of US$10/barrel.

Again, it makes sense to use additional market data to determine a base case number for
the heavy
Again, oil discount.
it makes sense to The data frommarket
use additional a service
datacalled Oil Sands
to determine Magazine
a base case number shows real-
for the
heavy oil discount. The data from a service called Oil Sands Magazine
time prices for WTI and WCS, both at Hardisty in Alberta and Cushing in Oklahoma.forThe
shows real-time prices
WTI and WCS,
difference both at
between theHardisty in Alberta
two locations forand
WCSCushing in Oklahoma.
is presumably dueThe
to difference
the cost of between
transporting
the two locations for WCS is presumably due to the cost of transporting the diluted bitumen
the diluted bitumen from the gathering point at Hardisty to the central location
from the gathering point at Hardisty to the central location in Cushing. These transportation in Cushing.
These transportation
costs are in the order ofcosts are intothe
US$8/bbl order ofifUS$8/bbl
US$12/bbl transportedto by
US$12/bbl if transported
pipeline, and US$16/bbl to by
pipeline,
US$18/bbl andif US$16/bbl
transported to
by US$18/bbl
rail (Paul andif Farhatha,
transported by rail (Paul and Farhatha, 2018).
2018).

Thelast
The lastyear
year shows
shows aawide
widevariation in in
variation thethe
heavy oil discount
heavy from US$10/barrel
oil discount to
from US$10/barrel to US$30/
US$30/barrel, as shown below. The heavy oil discount was widest in the first quarter of 2018
barrel,
(likelyas
dueshown
to the below. The
outage of theheavy oil pipeline),
Keystone discount but
washas
widest in the
recently first quarter
narrowed of 2018
to a range of
(likely
US$15due to theper
to US$18 outage
barrelofinthe
MayKeystone pipeline),
of 2018 (Oil but has recently narrowed to a range of
Sands, 2018b).
US$15 to US$18 per barrel in May of 2018 (Oil Sands, 2018b).

US$/bbl

Source: Oil Sands Magazine

a thirdOildata
AsSource: Sands Magazine
point, the DBRS used an assumption of a heavy oil discount of US$15/
barrel when it performed its economic analysis to rate the senior bonds issued by the NWR
Sturgeon
As a thirdRefinery (DBRS,
data point, 2017b).
the DBRS used an assumption of a heavy oil discount of US$15/barrel
when it performed its economic analysis to rate the senior bonds issued by the NWR Sturgeon
The heavy(DBRS,
Refinery oil discount
2017b).has been a topic of much public discussion in recent times. The
economic rationale for the expansion of the Kinder Morgan pipeline has been to increase
The heavy
market oil discount
access has been acustomers
to new tidewater topic of much so public discussion
that export in recent
of diluted times. The
bitumen will not just
economic rationale for the expansion of the Kinder Morgan pipeline has been to increase
depend on U.S. customers. The belief is that this increased access to tidewater
market access to new tidewater customers so that export of diluted bitumen will not just will decrease
the heavyonoil
depend discount
U.S. from
customers. itsbelief
The current high
is that thisamount.
increased access to tidewater will decrease the
heavy oil discount from its current high amount.
Given all this uncertainty, it makes sense to use a base case heavy oil discount of US$18/
Given with
barrel, all thissensitivity
uncertainty, it makes
cases usingsense to use a base
US$21/barrel case
and heavy oil discount of US$18/barrel,
US$15/barrel.
with sensitivity cases using US$21/barrel and US$15/barrel.

12
(e) The Capital Costs of a Refinery
The capital cost of a refinery will often use a metric of unit costs referred to as dollars per
flowing barrel. This metric takes the capital cost and divides by the refining capacity in
barrels per day.

As with many investments, it is useful to start with a comparable investment already done.
Real estate agents use this comparable concept when they appraise the value of a house.

As mentioned above, a recent comparable is when Husky purchased an existing refinery


in Superior, Wisconsin in November of 2017. Husky has stated it will make a further
investment in the first half of 2018 to increase the heavy oil processing capacity of the
refinery. The purchase price was US$527 million (approximately Cdn$670 million) for a
refinery that can refine 50,000 bpd of heavy oil into refinery products. Doing the math, this
gives a metric of about Cdn$13,000 per flowing barrel. A project to increase the heavy oil
processing capacity at the Superior refinery is expected to be completed in the first half of
2018 (Husky Energy, 2017c).

(f) The Operating Costs of a Refinery


Again, it is useful to look at an existing facility in order to obtain a comparable metric for
operating costs. A comparable would be the operating costs of the Husky Lloydminster
upgrader. Husky used a figure of about $10/bbl in a presentation for the first half of 2017
(Husky Energy, 2018a).

(g) Financing Costs


An investor financing a refinery would normally use a mixture of debt and equity to fund
the capital cost. Given the risks and uncertainties of revenue, capital costs and operating
costs, it would be reasonable to expect debt to fund 25 per cent and equity 75 per cent, as
used by other public refining companies such as Suncor.

As will be seen below, the financing of the NWR Sturgeon Refinery is not a normal
financing structure.

(h) Reliability
The nameplate capacity of any refinery is reduced by a factor known as the utilization
factor. For example, a refinery with a nameplate capacity of 50,000 bpd and a utilization
factor of 90 per cent will only actually produce an average of 45,000 bpd. Utilization
factors vary for various facilities due to mechanical turn-around frequency and duration
and other downtime caused by poor reliability. Many conventional refineries have a
utilization factor of over 90 per cent, whereas bitumen upgraders operated by Syncrude
have an historical utilization factor ranging from 71 per cent to 88 per cent (Suncor, 2018b).

13
Based on market observations over the past 10 years from comparable refineries, DBRS
assumed a 90 per cent utilization rate under the base case and stress-tested this factor to 85
per cent (DBRS, 2017c).

In conclusion, a reasonable assumption is 90 per cent, with some sensitivity to see the effect
if the utilization factor is less than 90 per cent.

V. THE DEAL WITH THE GOVERNMENT OF ALBERTA AND THE NWR


STURGEON REFINERY

(a) Sources of Information

The main sources of financial information for the NWR Sturgeon Refinery are a May 2017
ratings report from the DBRS (2017d) and the financial statements of Canadian Natural
Resources Ltd. (CNRL) for the period from 2015 to 2017.

The DBRS report offers many details of the deal between the NWR Sturgeon Refinery, the
government of Alberta and CNRL. The NWR Sturgeon Refinery has a website that will
periodically update the construction status of the project, but the website does not offer any
financial data. The last update on the NWR Sturgeon Refinery website was in May of 2018.

CNRL has stated that the completion of the NWR Sturgeon Refinery will create demand
for 79,000 barrels per day of diluted bitumen that will not require export pipelines, which
will help reduce pricing volatility in all western Canadian heavy crude oil (CNRL, 2018a).

(b) Legal Structure of the NWR Sturgeon Refinery


The simplified diagrams below illustrate the various legal relationships in the NWR
Sturgeon Refinery, namely:

1. the NWR Sturgeon Refinery is owned by the North West Redwater Partnership, which
in turn is indirectly owned 50 per cent by Canadian Natural Resources Ltd. (CNRL),
and 50 per cent by North West Refining Inc., a private company that was the original
proponent of the facility. These owners provided the equity financing for the NWR
Sturgeon Refinery, which was about five per cent of the project’s financing;

2. as described in more detail further on in the paper, the debt financing has two
components; namely

a) senior debt financing from bondholders and banks, representing 85 per cent of the
project’s financing; and

b) subordinated debt financing advanced 50 per cent by the Alberta Petroleum


Marketing Commission (APMC) and 50 per cent by CNRL, representing about 10
per cent of the project’s financing.

14
Ownership and Debt Financing

North West Refining


APMC CNRL
Inc.

50% of 50% 50%


Subordinated Equity Equity
Debt

50% of
Subordinated
Debt
Debt Senior Debt
North West Redwater Partnership
Lenders

NWR Sturgeon
Refinery

3. The(3)
tolling agreement
The tolling in which
agreement APMC
in which APMC (75 percent)
(75 per cent)and
andCNRL
CNRL (25cent)
(25 per per cent)
agree agree
to to
supply diluted bitumen feedstock and pay the costs of processing by the NWR
supply diluted bitumen feedstock and pay the costs of processing by the NWR Sturgeon Sturgeon
Refinery.
Refinery.
Tolling Agreements

Tolling Agreements

APMC CNRL

75% of 25% of
Tolling Payment Tolling Payment

North West Redwater Partnership

NWR Sturgeon
Refinery

15 (c) Technical Structure of the NWR Sturgeon Refinery


(c) Technical Structure of the NWR Sturgeon Refinery

The proponents of the NWR Sturgeon Refinery have envisioned more than an upgrader.
Their vision is to have a full refinery that can take diluted bitumen as its only feedstock and
process it directly into finished petroleum products that can be sold.

In simplest terms, the NWR Sturgeon Refinery consists of two processing units. The first
unit processes the raw diluted bitumen into a feedstock that the second unit can refine into
petroleum products.

The second unit is the simpler part of the refinery. It can operate if conventional crude
or synthetic crude were the only feedstock. The unit was tested in November 2017 using
synthetic crude as a feedstock and produced some amount of diesel fuel that the NWR
Sturgeon Refinery donated to various local community service vehicles. This production
using synthetic crude is part of the commissioning and start-up process, in that it allows
for testing and adjustments in the units that are functioning as at March 2018 (North West
Refining, 2017a).

The NWR Sturgeon Refinery made its first diesel from synthetic oil in November of 2017
and has produced about 2.2 million barrels of diesel fuel since December of 2017, or about
15,000 barrels of diesel a day (North West Refining, 2018b).

All of the processing facilities in the first unit of the NWR Sturgeon Refinery were
completed in May of 2018. These various processing facilities will go through a
commissioning and start-up procedure in the coming months. As of May 2018, 1,400
workers were on site (North West Refining, 2018c).

CNRL (2018b) has indicated that project completion of the NWR Sturgeon Refinery that
will enable it to process diluted bitumen is targeted for the fourth quarter of 2018.

(d) Capital Cost

The capital cost of the NWR Sturgeon Refinery was originally estimated to be $4.0 billion
in 2008, and first operation planned to be in 2016 (Morton, 2015).

Costs have risen since that date to $8.5 billion in 2013, $9.4 billion in 2017 and most
recently, $9.7 billion in April of 2018, with commercial operation estimated to be in the
fourth quarter of 2018 (CNRL, 2018c; Graney, 2018).

It is interesting to contrast this $9.7 billion capital cost for the NWR Sturgeon Refinery with
the previously mentioned $670 million purchase of a similar 50,000 barrel per day refinery
in Wisconsin by Husky Energy. The unit cost for the NWR Sturgeon Refinery using the
79,000 barrels per day of diluted bitumen is projected to be $123,000 per flowing barrel,
versus the $13,000 per flowing barrel for the Wisconsin refinery.

16
(e) Financing
(i) General Structure
NWR Sturgeon Refinery has funded the project, including all the financing costs and
working capital requirements, through a mixture of equity capital, subordinated debt and
senior secured bonds with staggered maturities, supported by a $3.5 billion revolving senior
secured syndicated credit facility (DBRS, 2017e).

The original plan for financing the capital cost of $4 billion was to use the equity from
the original owners (North West Refining Inc. and CNRL) for 20 per cent and the senior
debt holders for 80 per cent. When the capital cost increased to $9.7 billion, the senior debt
holders continued to require 20 per cent of the financing to be other than senior debt. It
would appear that the original equity investors (particularly North West Refining Inc.) have
declined to advance additional financing (DBRS, 2017f). In 2013, APMC and CNRL agreed
to make up this financing shortfall by each advancing debt in the form of subordinated
debt in the amount of $350 million each, plus additional debt if needed (Alberta Auditor
General, 2018a) .

(ii) Equity Financing


The original equity actually advanced by North West Refining Inc. and CNRL was about
$638 million (DBRS, 2017g).

The terms of the tolling agreements state that APMC and CNRL as toll payers will pay a
return on this equity until the equity is repaid (also required under the terms of the tolling
agreements). The terms of the tolling agreements also state that this original equity amount
was to increase by accruing a 10 per cent rate of return from the date of advance until April
2013. At that date, APMC and CNRL agreed to advance funds by way of subordinated
debt, and the rate of return on equity was reduced from 10 per cent to five per cent. As
a result, at Nov. 30, 2013, the original equity financing by North West Refining Inc. and
CNRL had funded and accrued equity of approximately $824 million. This equity will
continue to earn a five per cent return until it is repaid as set out in the tolling agreements.
The accrued five per cent return will increase the value of the funded and accrued equity to
about $1 billion on June 30, 2018 (Alberta Auditor General, 2018b).

The interesting thing to note is that the equity investors are treated as being entitled to a
guaranteed return on their investment, which is unusual for normal equity investments.

(iii) Senior Debt Financing


The senior secured debt consists of bonds issued to the public (mostly large institutions),
plus a senior credit facility with financial institutions such as banks. The notes to CNRL’s
financial statements in the past three years show the following tranches of senior bonds:

17
Senior Bonds
Tranche Amount, Cdn$M Interest Rate Issue Date Maturity Date
A $500 3.20% 2014 2023
B initial $500 4.05% 2014 2043
B reopen $300 4.05% 2015 2043
C $500 2.10% 2015 2021
D $500 3.70% 2015 2043
E $500 3.20% 2015 2025
F $550 4.25% 2016 2028
G $500 4.75% 2016 2036
H $500 4.15% 2016 2032
I $500 4.35% 2016 2038
J $750 2.80% 2017 2026
K $750 3.65% 2017 2034
Total $6,350

Senior Credit Facility


The senior credit facility stood at $2,112 on March 31, 2018, as stated on the notes to the
Q1 2018 financial statements of CNRL (2018d). It is reasonable to assume that in order
to finance the capital costs to complete the NWR Sturgeon Refinery, the senior credit
facility will be drawn to the amount of $2,650 million when the NWR Sturgeon Refinery
commences operations (now scheduled for the fourth quarter of 2018).

The senior credit facility provides flexibility between bond issuances and can be renewed
each year during construction such that the facility’s maturity will always be between three
and four years. In May 2017, DBRS (2017h) stated that the NWR Sturgeon Refinery planned
to reduce the $3.5 billion senior credit facility to approximately $1.5 billion when the project
is near the commercial operating date (now scheduled for the fourth quarter of 2018).

However, CNRL’s Q4 2017 financial statements indicated that subsequent to Dec. 31, 2017,
the NWR Sturgeon Refinery extended $2,000 million of the $3,500 million revolving
syndicated senior credit facility to June 2021. The remaining $1,500 million was extended
on a fully drawn non-revolving basis maturing February 2020. This indicates that the
senior credit facility will continue to be a source of financing for at least two more years
(CNRL, 2017a).

The senior credit facility is assumed to have an interest rate of four per cent.

18
(iv) Subordinated Debt
As mentioned above, the capital cost of the NWR Sturgeon Refinery increased from $5.7
billion to $8.5 billion in early 2014 (DBRS, 2017i).

In order to finance the 20 per cent of this increase that would not be financed by senior debt,
APMC and CNRL agreed to advance money in the form of debt that was subordinated to
the senior debt. The advance was in the amount of $350 million each, and had an interest
rate of prime plus six per cent. Given the current prime rate in Canada as at May 31, 2018
of 3.45 per cent, this equates to an interest rate of 9.45 per cent. This high interest rate
indicated that there was considerable risk associated with this subordinated debt.

APMC and CNRL also agreed to advance more than the $350 million each if there were no
other sources of financing (Alberta Auditor General, 2018c; DBRS, 2017j).

As at March 31, 2018, the amount of subordinated debt advanced by APMC and CNRL was
$432 million each, plus accrued interest of $111 million, resulting in a total advance of $543
million for each of APMC and CNRL (2018e).

It is reasonable to assume that in order to finance the capital costs to complete the NWR
Sturgeon Refinery, APMC and CNRL will have to advance additional amounts as
subordinated debt, and that the accrued interest will continue to increase. A reasonable
assumption is that the total amount advanced by each of APMC and CNRL as at the date
the NWR Sturgeon Refinery commences operations (scheduled for the fourth quarter
of 2018) will be $450 million each, and that the accrued interest will be $121 million
each. The resulting total of $571 million each greatly exceeds the $350 million originally
contemplated in 2014.

(v) Final Debt and Equity


Based on the above, it is possible to make a reasonable estimate for the final financing
numbers when the NWR Sturgeon Refinery begins to operate in the fourth quarter of 2018.
These reasonable assumptions are as follows (all numbers Cdn$ billion).

Source of Financing CNRL Q1 2018 Final Reasonable Estimate


Senior Bonds $6.350 $6.350
Credit Facility $2.112 $2.650
Subordinated Debt $1.086 $1.142
Equity $1.000 $1.030

Total $10.720 $11.172

As can be seen, the financing is almost entirely debt. This high proportion of debt would
never be possible in a normal refinery that would have to take all the risks associated with
capital costs, operating costs and fluctuating crack spreads between the price of bitumen
and the price of diesel.

19
The DBRS (2017k) has rated the senior secured bonds as A low, based on the support the
Alberta government has given through APMC as described in the next paragraphs.

(f) Processing Agreements


(i) General Structure
The essence of the allocation of risk between the NWR Sturgeon Refinery as builder and
operator, and between APMC and CNRL as the supplier of diluted bitumen feedstock,
is contained in the processing agreements (PAs). As will be seen below, the PAs and
associated agreements transfer virtually all of the various risks (capital cost and associated
financing costs, operating costs, utilization factor, volume and price risk for produced
petroleum products and feedstock price risk) from the NWR Sturgeon Refinery to APMC
and CNRL.

The PAs entered into by APMC and CNRL with the NWR Sturgeon Refinery are
somewhat unusual. Rather than using a specific dollar amount per barrel, the agreements
require APMC (75 per cent) and CNRL (25 per cent) to pay a tolling fee that covers all
costs of the facility, both capital and operating. This obligation means that APMC and
CNRL bear all the risk of an increase in capital costs and any increase in operating costs.
The DBRS report confirms in several locations that in its view, the toll payers APMC and
CNRL have assumed all the risk for capital costs (including overruns), operating costs and
crack spread movements.

(ii) Capital Costs


For capital costs, the PAs require APMC and CNRL to pay all interest and principal
repayments for all debt, namely senior bonds, senior credit facility and subordinated
debt. The more than doubling of the capital cost has therefore more than doubled the debt
financing costs contained in the tolling agreement. The payments for the repayment of the
subordinated debt will be made in 120 monthly instalments starting in 2019. The payments
of the return of equity will not commence until the subordinated debt has been repaid.
These repayments of equity are expected to commence in 2029, and be completed in about
2060. As mentioned above, the equity still outstanding will earn a five per cent return on
equity until the equity is repaid (DBRS, 2017l).

(iii) The Debt Service Obligation (DSO)


The PAs contain a provision (referred to as the debt servicing obligation, or DSO) that
requires APMC and CNRL as toll payers to pay all financing costs associated with the
senior bonds and senior credit facility, including interest, repayment of principal and other
financing costs. In effect, it is a guarantee by APMC and CNRL of the senior bonds and
senior credit facility issued by the NWR Sturgeon Refinery. This DSO is a key feature
DBRS uses in its conclusion to rate the senior bonds at a credit rating (A low) slightly below
the province of Alberta (AA high). As DBRS (2017m) pointed out in various parts of its
May 2017 rating report:

20
1. The risk to [senior] bond holders is minimized by the projected cash flow as per the
DBRS base case, the priority of debt service and the toll payers’ unconditional DSO.

2. These DSOs are intended to be irrevocable and unconditional contractual commitments


with NWR in respect of the [NWR Sturgeon Refinery’s] debt (APMC (75 per cent) and
CNRL (25 per cent)) and are payable whether or not the upgrader-refinery operates.
The DSOs also survive the termination of the PAs (or bankruptcy by NWR). The DSO
commences at the earlier of COD [the date of first commercial operation] or June 1, 2018,
whether or not the upgrader-refinery has achieved COD.

3. The DSO is an unusual level of recourse that is not normally present in a typical
project bond.

4. DBRS notes that, according to the PA, the DSO is unconditional and shall not be reduced
or affected in any way, including the lack of proceeds of refined products.

The most recent statement as to when the NWR Sturgeon Refinery will commence
commercial operations (the commercial operations date or COD) is the fourth quarter of
2018. The processing agreements define the commercial operation date (COD) as occurring
when the NWR Sturgeon Refinery operates at a rate of at least 50 per cent of its design
capacity of 79,000 barrels per day for a period of at least 30 consecutive days (APMC,
2018a; CNRL, 2018f).

Given the experience of start-up for other similar bitumen processing facilities, it is
reasonable to expect that even when commercial operations start, it will likely be several
months before the NWR Sturgeon Refinery is able to process 79,000 barrels per day of
diluted bitumen, its nameplate capacity. Furthermore, it likely will be at least two months
after commercial operation before APMC and CNRL will realize any revenues. The reason
for this is that it will take that long before the diluted bitumen can be refined into petroleum
products that will be sold and the revenues collected for such sale. Given all this, it is
reasonable to assume that APMC and CNRL will receive little if any cash revenue before
the end of 2018.

As a result, APMC and CNRL will have to pay interest and principal repayment costs on
the senior bonds and the senior credit facility starting on June 1, 2018. Interest payments
alone will be in the order of $25 million per month. The requirement to set aside amounts
for principal repayment will be in the order of $15 million per month. This means that for
the seven months after June 1, 2018, APMC and CNRL will have to pay out at least $280
million (seven months times $25 million plus $15 million) in 2018, with little or no revenue
to fund these payments. Prior to the COD, any revenues from the current processing of
synthetic crude into 15,000 bpd of diesel should be roughly equal to the commissioning,
startup and operating costs of the NWR Sturgeon Refinery, and such revenues will be used
for that purpose,.

In effect, it is as if one is renting an apartment, but has to start paying rent even though the
apartment is not finished and ready for moving in.

21
Section 13.2(a) of the processing agreement states that APMC and CNRL will only have
to start paying all the other components of the tolling fee, namely subordinated debt
charges, equity charges and operating costs, when the commercial operation date of the
NWR Sturgeon Refinery occurs. This implies that prior to the commercial operation date,
all these costs will either continue to be accrued after June 1, 2018, or will be paid out of
further draws of cash from the senior credit facility (APMC, 2018b).

(iv) Operating Costs


For operating costs, Schedule 1 of the PAs requires APMC and CNRL to pay all operating
costs (APMC, 2018c).

Approximately half are on a flow-through basis (pay 100 per cent of costs as incurred).
The other half are on a benchmarked basis (pay 100 per cent of costs as calculated by
comparison to external benchmarks for those kinds of costs) (DBRS, 2017n).

One can look at the material published by Husky Energy (2018b) to obtain a reasonable
assumption for these cash operating costs. A reasonable estimate is $10 per barrel operating
costs, annual maintenance capex costs of $20 million, and major turnarounds every four
years costing $80 million.

(v) Other Features of the Processing Agreement


APMC and CNRL are required to pay the tolling fee covering all of the above items even
if the NWR Sturgeon Refinery cannot run during a force-majeure event. The ownership of
feedstock supplies and refined products always belongs to APMC and CNRL, who will bear
all commodity risks. If the gross margin on the sale of petroleum products is insufficient to
cover the tolling fee, APMC and CNRL will be required to cover any shortfall amount by
cash payment.

While it is not an event of default, if the facility performance of the NWR Sturgeon
Refinery falls below a rolling average of 80 per cent for an 18-month period, or throughput
falls below 25 per cent for three consecutive months as a result of a site-specific labour
disruption, the payment of the return on equity will be suspended (but debt service and
operating expenses will continue to be paid) (DBRS, 2017o).

22
VI. ECONOMIC MODEL

(a) Assumptions for Economic Model

One can use Microsoft Excel to construct an economic model using the above data and
assumptions to analyze the economic effect on the toll payers APMC and CNRL. The link
to this model is as follows:

https://www.policyschool.ca/wp-content/uploads/2018/06/Spreadsheet-for-NWR-
Economics.xlsx

1. The following are the base case assumptions:

Feedstock volumes are 79,000 barrels per day of diluted bitumen, petroleum products
produced of

40,250 bpd low sulphur diesel


8,790 bpd low sulphur VGO
3,363 bpd of propane/butane
28,266 bpd of diluent

2. Utilization factor of 90 per cent.

3. Revenues are based on volume of various petroleum products multiplied by prices for
each petroleum product. The key assumption is the diesel price to WTI price crack
spread ratio. The base case assumption is 140 per cent.

4. Feedstock costs for diluted bitumen of US$18/barrel discount to WTI.

5. WTI price of US$60/barrel.

6. Assuming US$60/barrel WTI, this gives a base case diluted bitumen to diesel crack
spread of US$42/barrel calculated as follows:

Discount of WCS to WTI US$18/barrel


140 per cent diesel/WTI means 40 per cent times US$60/barrel equals
US$24/barrel
Total increase in value US$42/barrel

Cdn$/US$ FX rate of $0.80

7. Senior debt financing costs based on issued $6.35 billion senior bonds and $2.65 billion
senior credit facility and interest rates as issued.

8. Subordinated debt financing costs based on $1.142 billion subordinated debt and prime
plus six per cent interest rate.

23
9. Equity outstanding of $1.03 billion earning a return of five per cent.

10. Cash operating costs of $10/barrel plus annual maintenance capex of $20 million and
turnaround capex every four years of $80 million.

(b) Results of Economic Model


(i) Base Case
Using these assumptions, the economic model shows the annual cash flows received by the
toll payers APMC and CNRL. The cash flows are the amount that the toll payers would
receive as an alternative to just selling their diluted bitumen at the Hardisty WCS price. In
other words, it shows the value added (or cost) that occurs as a result of refining the diluted
bitumen into petroleum products.

The following chart shows the results of the economic model for 2019 using the base
case assumptions. The column on the left shows the revenues from the sale of the various
petroleum products such as diesel and other products in the amount of about $2.4 billion.
The stacked column on the right shows all the costs associated with making the petroleum
products, namely diluted bitumen feedstock, operating costs and the various financing costs
for debt and equity. The total cost amount is slightly greater than $2.4 billion, resulting in a
base case negative cash flow of about $24 million per year.

3000 Diluted Bitumen


Feedstock
Operating Costs
2500
Equity Cost
2000
Subordinated Debt
Repayment
$ Million 1500
Subordinated debt
interest
1000 Senior debt
repayment
500 Senior debt interest

Total Revenues
0
Revenues Costs
2019 Results for Toll Payers for Base Case

The economic model also shows that the results for the 10 years from 2020 to 2030 would
be very similar to 2019.

24
(ii) Market Price Sensitivities
The economic model clearly shows that the revenue amounts will vary greatly if one
assumes a change in market conditions, namely the two spread amounts (WCS/WTI
discount, or diesel/WTI crack spread). The following table shows the cash flow numbers
using the sensitivities outlined above.

130% diesel/WTI 140% diesel/WTI 150% diesel/WTI


US$15/barrel -$221 million -$121 million -$22 million
US$18/barrel -$124 million -$24 million +
$75 million
US$21/barrel -$26 million +73 million +172 million

It is interesting to view these two crack spread assumptions in light of the recent dispute
between Alberta and British Columbia regarding the expansion of the Kinder Morgan Trans
Mountain pipeline. The objective of such expansion is to get more diluted bitumen to Asian
markets and therefore reduce the WCS/WTI discount. Conversely, if Alberta were to reduce
the shipment of petroleum products to British Columbia, as it had indicated it might do,
this action would divert petroleum product sales from British Columbia to the remaining
Western Canada market, and therefore would likely reduce the price of diesel sold in that
market. Either outcome would reduce the cash flows to APMC and CNRL.

(iii) Other Sensitivities


Reducing the assumption for WTI pricing from US$60/barrel to US$50/barrel would
reduce the cash flow by $78 million per year. The reason for the reduction is that the
reduction in WTI pricing would reduce the diluted bitumen to diesel crack spread in actual
dollars per barrel.

As a further sensitivity, each drop of 10 per cent in utilization factor would result in a
decrease in cash flow of $90 million per year. The reason for the drop is that the drop in
utilization factor would result in a reduced production of petroleum products and therefore
reduced revenue. The costs would not be reduced as much, since all financing costs must be
paid regardless of production volumes.

In an extreme case, there is the possibility that the NWR Sturgeon Refinery would cease
operations permanently and go bankrupt. This would mean no revenues, and no cash
operating costs. If this event ever occurs, the DSO would require APMC and CNRL to pay
the approximately $9 billion of principal on senior bonds and senior credit facility plus the
interest on such principal. As stated, there would be no revenue to offset these costs, and
therefore the loss to APMC and CNRL would be much greater.

(c) Conclusions of Economic Model

The economic model shows that the cost/benefit analysis for APMC and CNRL is very
dependent on the state of market prices for diluted bitumen and diesel. The higher the

25
spread between these two prices, the better the economics – the lower the spread, the worse
the economics.

VII. REACTION TO NWR STURGEON REFINERY

(a) Background

The NWR Sturgeon Refinery has been the subject of discussion for several years. The
Globe and Mail contained the following extract:

“Earlier this year, North West Upgrading chairman Ian MacGregor said the refinery project
would have never got off the ground without Alberta government involvement ... On
Wednesday, Wildrose party finance critic Rob Anderson said he wants to see more bitumen
processing in Alberta. But he said when a project is only viable because a government
participates, ‘then that should be a huge red flag for people’” (Cryderman, 2013).

(b) Review by Alberta Auditor General in February of 2018

According to the Calgary Herald, “Just last week, Alberta’s auditor general complained
that the Crown corporation overseeing the project, the Alberta Petroleum Marketing
Commission, is keeping Albertans in the dark about the financial risks of the project. ‘I’ll
be blunt, Albertans are not being fully informed about this very significant endeavour,’ said
Merwan Saher who, tellingly, is rarely blunt about anything” (Thomson, 2018a).

26
Review by Alberta Auditor General in February of 2018

On Feb. 22, 2018, the Auditor General of Alberta issued a specific report on the NWR Sturgeon
Refinery. Among its many findings were the following:

1. Albertans should also receive sufficient public reporting on this arrangement to be able to
keep current with the risks they assume and the benefits they receive.

2. Given the nature of the agreement, the level of public reporting from the APMC is not
good enough. The agency is acting as steward of the province’s resources, and Albertans
have a right to know how it is using those resources. They are currently not receiving that
information.

3. The agency has an obligation to report on its agreements to Albertans, whose resources it
uses.

4. In 2011, the estimated NPV for the government was a range of $200 million to $700 million
over the life of the project. As of early 2017, that estimate covering the 30-year term is now
under $200 million.

5. Potential benefits in the public sector are more complicated because they may involve
policy objectives, such as job creation and economic diversification. The APMC needs
to work with the Department of Energy to determine what risks and benefits of this
arrangement could be reported, when to report them publicly and who should report what.

6. The APMC, after it begins to supply bitumen and receive proceeds from the sale of refined
products, will be reporting the profit or loss as a result of the agreement. Albertans will
then get an annual picture of the financial results over the life of the agreement.

7. Because of the structure of the NWRP arrangement, there is no plausible scenario where it
would make financial sense to pull out of it. Albertans’ resources are therefore committed.
Strong oversight and risk management are consequently all the more important.

8. An analysis of lessons learned from the Sturgeon refinery contracting processes could be
very important to help with any future decisions on contracts for value-added activities,
including a processing agreement related to phase two of the Sturgeon refinery.

9. We recommend that the Alberta Petroleum Marketing Commission prepare a business


plan and an annual report that are made publicly available to Albertans. The APMC must
be able to demonstrate it has given appropriate consideration to the nature and extent of
information it will share with Albertans.

(c) Reaction of the NWR Sturgeon Refinery

The backers of the NWR Sturgeon Refinery have proposed future expansions in two
phases, each involving an additional processing capacity of 50,000 barrels of bitumen per
day. It is also reasonable to expect that the Alberta government should make a careful
review of the go-forward economics of future tolling arrangements before agreeing to
support future phases 2 and 3 of the NWR Sturgeon Refinery.

27
A recent Financial Post article stated:

“A proposal to build the second phase of the Sturgeon Refinery, the first new refinery
in Alberta in the last 30 years, is being withdrawn as the company behind the project
evaluates the changing economic environment facing the oil industry ... ‘We think it’s
the right thing to do,’ North West Refining president and CEO Ian MacGregor told the
Financial Post on Friday, adding that he expected construction of the first phase to finish by
the summer ...

“Canadian Natural has taken a similar wait-and-see approach: ‘I think our plan here is let’s
just make sure the plant runs effectively and efficiently. And when we see that, then we’ll
make a decision whether or not to participate in any kind of expansion, if it makes sense,’
Canadian Natural Resources Ltd. executive vice-chairman Steve Laut said on an earnings
call Thursday” (Morgan, 2018).

(d) The Alberta Government’s Reaction

The government of Alberta recently made the following announcement, according to the
Calgary Herald:

“On Monday, [Premier Rachel] Notley announced, among other things, a $1-billion plan
to help spur the partial upgrading of bitumen in Alberta. The idea is to put up to $800
million in loan guarantees and $200 million in grants over a period of eight years to
entice companies to open facilities to turn heavy bitumen into a lighter product for easier
shipment through pipelines (if only she could get more pipelines built, that is. And while
we’re in parentheses, we could argue this is another example of how we aren’t diversifying
away from our fossil fuel economy but trying to add value to it).

“‘This will attract two to five partial upgrading facilities in Alberta representing up to
$5 billion in private investment and create 4,000 jobs in construction,’ said an optimistic
government background paper” (Thomson, 2018b).

Chris Varcoe (2018) offered another comment in the Calgary Herald:

“But grand plans to move Alberta up the energy value chain don’t mention the risks
involved, such as the province’s ill-fated experience with the bi-provincial upgrader in the
1990s. The province invested $404 million in capital costs in the project at Lloydminster,
only to sell its stake four years later for only $32 million ... Nor do they mention Alberta’s
involvement in the Sturgeon Refinery, which saw the project’s price tag jump from $5.7
billion to $9.4 billion.”

Bloomberg reported that: “Alberta’s government’s C$1 billion-dollar pledge (US$780


million) will help support the construction of smaller and cheaper varieties of upgraders.
The so-called partial upgraders would process the sticky oil just enough so that it can flow
freely through pipelines without adding ultra-light condensate. The government expects
that as many as five private investors will infuse about C$5 billion in the sector ... Since

28
partial upgrading would reduce or eliminate the need for the condensate that makes up
about a third of the heavy oil-sands crude, it would free up pipeline space and produce
a grade of oil that’s easier to refine and more valuable than the heavy grades produced”
(Tuttle, 2018).

VIII. CONCLUSIONS AND LESSONS FOR FUTURE GOVERNMENT ASSISTANCE


In essence, it would appear that the NWR Sturgeon Refinery could be viewed as Alberta’s
equivalent of the Quebec and federal governments’ investment in Bombardier, or the
federal and Newfoundland government’s support of the Muskrat Falls electric project in
Newfoundland. The federal and Quebec governments have given financial assistance to
Bombardier in order to support their industrial strategy of having an aerospace industry
in Quebec. The federal and Newfoundland governments have given financial assistance
to the Muskrat Falls project to support their industrial strategy of having more electrical
generation in Newfoundland and Labrador. The government of Alberta has given financial
assistance to the NWR Sturgeon Refinery in order to support its strategy of having bitumen
refined in Alberta. This note has attempted to put a dollar amount on the cost of that
financial support.

Specifically, the cash flows to APMC and CNRL will be slightly negative (minus $24
million) in 2019. The variation in the market prices for WCS/WTI discount and diesel/WTI
crack spreads could change this number for 2019 from -$221 to +$172 million. In addition,
a failure to achieve a 90 per cent utilization factor will reduce the 2019 cash flows by $90
million for each 10 per cent reduction in utilization factor. The government of Alberta bears
75 per cent of these risks and returns.

In each case, it is the government’s prerogative to make such a choice. But it should also be
the government’s obligation to explain and justify such choice.

As long ago as the 1970s when Peter Lougheed was premier, various Alberta governments
have tried different mechanisms to encourage investment with the goal of diversifying
Alberta’s economy. These mechanisms include government subsidies, guarantees and other
methods to encourage investment (often from the private sector) when ordinary market
forces and economics are not sufficiently robust to cause such investment to occur.

This paper has attempted to put numbers on one such government initiative designed to
assist a private sector investment. The purpose of doing so is to improve the debate over the
merits of such government incentives. It is hoped that it might provide a template for the
assessment of the merits of such government assistance to investments in future projects,
preferably before the project is approved rather than after.

The recommended lessons for government would be as follows:

1. Avoid entering into open-ended guarantee agreements that expose governments to


unlimited risks for things such as capital cost overruns, operating cost risks, guaranteed
returns on debt and equity, and commodity market risks.

29
2. The corollary of recommendation one is to limit government aid to a fixed and capped
amount. Do several variations to show sensitivity for key assumptions.

3. Make such numbers public.

4. In particular, governments should explain why such assistance is needed, and should
explain what larger government benefits will result, and more importantly, the dollar
amount of the benefit. For example, if job creation is a benefit, the government should
state the cost per job created.

30
REFERENCES
Alberta Energy. 2017. http://www.energy.alberta.ca/OilSands/791.asp

Alberta Energy Regulator. 2018. https://www.aer.ca/data-and-publications/statistical-reports/


crude-bitumen-demand

Alberta Petroleum Marketing Commission. 2014. “Seconded Amended and Restated Agreement
to Process Crown Royalty Bitumen.” April 7. Retrieved from http://apmc.alberta.ca/EV/
Documents/APMCAgreement2Process.pdf

Auditor General of Alberta. 2018. Report of the Auditor General. February. Retrieved from
https://www.oag.ab.ca/webfiles/reports/FullReport_Feb2018.pdf

Barnes, Dan. 2013. “Alberta’s Oil Sands Epic Stretches Back More Than a Century,”
Edmonton Journal. Oct. 30. Retrieved from http://www.edmontonjournal.com/business/
history+Alberta+oilsands+epic+stretches+back+more+than/9109610/story.html

British Petroleum. 2011. “Heavy Oil vs. Light Oil,” Presentation. Alaska Oil and Gas
Association. March. Retrieved from http://www.aoga.org/wp-content/uploads/2011/03/
HRES-3.10.11-Lunch-Learn-BP-Heavy-Oil1.pdf

Canadian Association of Petroleum Producers. 2017. “Crude Oil Forecast, Markets and
Transportation.” June. Retrieved from https://www.capp.ca/publications-and-statistics/crude-
oil-forecast

Canadian Natural Resources Ltd. 2018. “Canadian Natural Resources Limited Announces 2017
and Fourth Quarter Year-End Results,” Press Release. March 1. Retrieved from https://www.
cnrl.com/upload/media_element/1141/03/0301_q4-17-front-end.pdf

Canadian Natural Resources Ltd. 2018. “Management’s Discussion and Analysis for the
Three Months Ended March 31, 2018.” Retrieved from https://www.cnrl.com/upload/
report/100/02/0503_interim-management-discussion-and-analysis.pdf.pdf

Canadian Natural Resources Ltd. 2018. Quarterly Reports. Retrieved from https://www.cnrl.
com/investor-information/quarterly-reports#2018

Cenovus Energy Inc. 2017. Annual Information Form for 2016 as filed on SEDAR. Feb. 16.

Cryderman, Kelly. 2013. “Alberta Refinery Project Delayed as Costs Soar by 50% to
$8.5-Billion,” The Globe and Mail. Dec. 4. Retrieved from https://www.theglobeandmail.
com/report-on-business/industry-news/energy-and-resources/alberta-refinery-project-
delayed-as-costs-soar-by-50-per-cent-to-85-billion/article15776482/

Dominion Bond Rating Service. 2017. “DBRS Assigns Ratings of A (low) to North West
Redwater Partnership Debt Issuance, Stable Trends.” May 8. Retrieved from https://www.
dbrs.com/research/310934/dbrs-assigns-ratings-of-a-low-to-north-west-redwater-partnership-
debt-issuance-stable-trends

31
ExxonMobil Corporation and Imperial Oil Limited. 2017. Form 10-K.

Graney, Emma. 2018. “Sturgeon Refinery Costs Balloon Again to $9.7 Billion,” Calgary Herald.
April 10. Retrieved from http://calgaryherald.com/news/politics/sturgeon-refinery-costs-
balloon-again-to-9-7-billion/wcm/14a3d513-f3db-44cf-9c99-02baa4c1b027

Healing, Dan. 2017. “Husky to Buy U.S. Refinery for $435 Million,” Calgary Herald. Aug. 14.
Retrieved from http://calgaryherald.com/business/energy/husky-to-buy-u-s-refinery-for-435-
million

Husky Energy Inc. 2017. Annual Information Form for 2016 as filed on SEDAR. Feb. 24.

Husky Energy, 2017. Annual Report, 2017. Retrieved from http://www.huskyenergy.com/


downloads/abouthusky/publications/annualreports/HSE_Annual2017.pdf

Husky Energy. 2018. Corporate Presentation. April 26. Retrieved from http://www.huskyenergy.
com/downloads/InvestorRelations/Presentations/Corporate_Presentation.pdf

International Energy Agency. 2017. “Global Shifts in the Energy System,” World Energy
Outlook 2017. Retrieved from https://www.iea.org/weo2017/

Kent Group. 2018. Petroleum Price Data. Retrieved from https://charting.kentgroupltd.com

Morgan, Geoffrey. 2018. “North West Refining Withdrawing Proposal to Expand Sturgeon
Refinery – For Now,” Financial Post. March 2. Retrieved from http://business.financialpost.
com/commodities/energy/north-west-refining-withdrawing-proposal-to-expand-sturgeon-
refinery-for-now

Morton, Ted. 2015. “The North West Sturgeon Upgrader: Good Money After Bad?” School of
Public Policy Research Papers, vol. 7, issue 3. Retrieved from https://www.policyschool.ca/
wp-content/uploads/2016/03/north-west-sturgeon-upgrader-morton.pdf

North West Refining. 2017. “Now Flowing: First Diesel at Sturgeon Refinery.” Press Release.
Dec. 12. Retrieved from http://nwrsturgeonrefinery.com/news/now-flowing-first-diesel-at-
sturgeon-refinery/

North West Refining. 2018. “Project Update: Construction Complete, Commissioning


Well Underway at Sturgeon Refinery.” Press Release. May 16. Retrieved from
https://nwrsturgeonrefinery.com/news/project-update-construction-complete-commissioning-
well-underway-at-sturgeon-refinery/

North West Refining. 2018. “Sturgeon Refinery, Maximizing the Value.” Retrieved from
https://nwrsturgeonrefinery.com/project/maximizing-the-value/

Oil Sands Magazine. n.d. Real-Time Prices and Stock Quotes. Retrieved from
http://www.oilsandsmagazine.com/energy-statistics/real-time-oil-prices-wti-brent-wcs-
energy-stocks#prices

32
Paul, Anirban and Ahmed Farhatha. 2018. “Canadian Railways in a Catch-22 over Crude
Shipment,” Reuters. March 27. Retrieved from https://finance.yahoo.com/news/canadian-
railways-catch-22-over-124824995.html

Skinner, Thom. 2015. Investor Presentation, CO2 Solutions. January. Retrieved from
http://www.co2solutions.com/uploads/file/910cd54e1543af4406b8a1cf401bdfe91334c6a0.pdf

Steward, Gillian. 2011. “Canadian Jobs Lost Down the Pipeline,” Toronto Star. Aug. 1. Retrieved
from https://www.thestar.com/opinion/editorialopinion/2011/08/01/steward_canadian_ jobs_
lost_down_the_pipeline.html

Suncor Energy Inc. 2018. Investor Presentation. Retrieved from https://www.suncor.com/-/.../


Investor.../Presentations.../Investor-Relations-Presentations/20172018

Suncor Energy Inc. 2018. “The Oil Sands Story: 1960s, 1970s & 1980s.” Retrieved from
http://www.suncor.com/about-us/history/the-oil-sands-story

Thomson, Graham. 2018. “Notley Tries to Diversify the Economy Where Others have Failed,”
Calgary Herald. Feb. 27. Retrieved from http://calgaryherald.com/news/politics/graham-
thomson-premier-rachel-notley-tries-to-diversify-the-economy-where-others-have-failed/
wcm/7f271ae4-d557-4b80-8f85-752d35d9a061

Tuttle, Robert. 2018. “Oilsands Upgraders May Make a Comeback Amid Pipeline
Crisis,” Bloomberg. March 12. Retrieved from https://www.bloomberg.com/news/
articles/2018-03-12/oil-sands-upgraders-may-make-a-comeback-amid-pipeline-crises

Varcoe, Chris. 2018. “Anchors Aweigh, We’re All Aboard Alberta’s Energy Subsidy Boat,”
Calgary Herald. March 8. Retrieved from http://calgaryherald.com/business/energy/varcoe-
anchors-aweigh-were-all-aboard-albertas-energy-subsidy-boat

Wikipedia. 2018. Western Canadian Select. Retrieved from https://en.wikipedia.org/wiki/


Western_Canadian_Select

33
About the Author

Brian Livingston is an Executive Fellow with The School of Public Policy at the University of Calgary. He has a BSc
in Mechanical Engineering from Queen’s University and a JD from the University of Toronto Law School. He spent
30 years of his working career in the oil and gas business in a variety of different capacities. He recently published
a paper for The School of Public Policy titled “The Alberta Electrical Grid: What to Expect in the Next Few Years”.

34
ABOUT THE SCHOOL OF PUBLIC POLICY

The School of Public Policy has become the flagship school of its kind in Canada by providing a practical, global and
focused perspective on public policy analysis and practice in areas of energy and environmental policy, international policy
and economic and social policy that is unique in Canada.

The mission of The School of Public Policy is to strengthen Canada’s public service, institutions and economic performance
for the betterment of our families, communities and country. We do this by:

• Building capacity in Government through the formal training of public servants in degree and non-degree programs,
giving the people charged with making public policy work for Canada the hands-on expertise to represent our vital
interests both here and abroad;
• Improving Public Policy Discourse outside Government through executive and strategic assessment programs, building
a stronger understanding of what makes public policy work for those outside of the public sector and helps everyday
Canadians make informed decisions on the politics that will shape their futures;
• Providing a Global Perspective on Public Policy Research through international collaborations, education, and community
outreach programs, bringing global best practices to bear on Canadian public policy, resulting in decisions that benefit
all people for the long term, not a few people for the short term.

The School of Public Policy relies on industry experts and practitioners, as well as academics, to conduct research in their
areas of expertise. Using experts and practitioners is what makes our research especially relevant and applicable. Authors
may produce research in an area which they have a personal or professional stake. That is why The School subjects all
Research Papers to a double anonymous peer review. Then, once reviewers comments have been reflected, the work is
reviewed again by one of our Scientific Directors to ensure the accuracy and validity of analysis and data.

The School of Public Policy


University of Calgary, Downtown Campus
906 8th Avenue S.W., 5th Floor
Calgary, Alberta T2P 1H9
Phone: 403 210 3802

DISTRIBUTION DATE OF ISSUE


Our publications are available online at www.policyschool.ca. June 2018

DISCLAIMER MEDIA INQUIRIES AND INFORMATION


The opinions expressed in these publications are the authors' alone and For media inquiries, please contact Morten Paulsen at 403-220-2540.
therefore do not necessarily reflect the opinions of the supporters, staff, Our web site, www.policyschool.ca, contains more information about
or boards of The School of Public Policy. The School's events, publications, and staff.

COPYRIGHT DEVELOPMENT
Copyright © Livingston 2018. This is an open-access paper distributed For information about contributing to The School of Public Policy, please
under the terms of the Creative Commons license CC BY-NC 4.0, which contact Sharon deBoer-Fyie by telephone at 403-220-4624 or by e-mail
allows non-commercial sharing and redistribution so long as the original at sharon.deboerfyie@ucalgary.ca.
author and publisher are credited.

ISSN
ISSN 2560-8312 The School of Public Policy Publications (Print)
ISSN 2560-8320 The School of Public Policy Publications (Online)

35
RECENT PUBLICATIONS BY THE SCHOOL OF PUBLIC POLICY

OPENING CANADA’S NORTH: A STUDY OF TRADE COSTS IN THE TERRITORIES


https://www.policyschool.ca/wp-content/uploads/2018/06/Opening-Canadas-North-Fellows-Tombe.pdf
G. Kent Fellows and Trevor Tombe | June 2018

SOCIAL POLICY TRENDS: EMERGENCY SHELTER CAPACITY BY CITY IN ALBERTA, 2017


https://www.policyschool.ca/wp-content/uploads/2018/06/Social-Trends-Provincial-Funded-Shelter-Shares-June-2018.pdf
Margarita Wilkins and Ronald Kneebone | June 2018

WHERE IN THE WORLD ARE CANADIAN OIL AND GAS COMPANIES? 2015
https://www.policyschool.ca/wp-content/uploads/2018/06/2015-Where-in-the-World-Larson.pdf
Braeden Larson | June 2018

ENERGY AND ENVIRONMENTAL POLICY TRENDS: THE GROWING OPPORTUNITY FOR LNG IN CHINA
https://www.policyschool.ca/wp-content/uploads/2018/06/LNG-in-China-Policy-Trends-FINAL.pdf
Jennifer Winter | June 2018

NORTH AMERICAN FREE TRADE UNDER ATTACK: NEWSPRINT IS JUST THE TIP OF THE ICEBERG
https://www.policyschool.ca/wp-content/uploads/2018/05/Free-Trade-Under-Attack-Beaulieu.pdf
Eugene Beaulieu | May 2018

SOCIAL POLICY TRENDS: RECESSIONS, DRUGS AND THEIR IMPACT ON PROPERTY CRIME IN CALGARY
https://www.policyschool.ca/wp-content/uploads/2018/05/Social-Trends-Crime-May-18-RevisionFINAL-VERSION.pdf
Margarita Wilkins and Ronald Kneebone | May 2018

THE NAFTA NEGOTIATIONS — AND CANADA’S PRIORITY WATCH LIST DESIGNATION: IT’S ALL ABOUT THE LEVERAGE
https://www.policyschool.ca/wp-content/uploads/2018/05/NAFTA-and-the-PWL-Stephens-final.pdf
Hugh Stephens | May 15, 2018

FISCAL POLICY TRENDS: WHO WILL PAY THE INTEREST ON ALBERTA’S PUBLIC DEBT?
https://www.policyschool.ca/wp-content/uploads/2018/05/Fiscal-Trends-AB-Public-Debt-Bazel-Crisan-Dahlby.pdf
Philip Bazel, Daria Crisan and Bev Dahlby | May 2018

SOCIAL POLICY TRENDS: SOCIAL ASSISTANCE CASELOADS IN ALBERTA BY FAMILY COMPOSITION


https://www.policyschool.ca/wp-content/uploads/2018/04/Social-Trends-AB-SA-by-Family-Type-Final.pdf
Margarita Wilkins and Ronald Kneebone | April 2018

THE ALBERTA ELECTRICAL GRID: WHAT TO EXPECT IN THE NEXT FEW YEARS
https://www.policyschool.ca/wp-content/uploads/2018/04/AB-Electrical-Grid-Livingston.pdf
Brian Livingston | April 2018

CANADA’S REFUGEE STRATEGY: HOW IT CAN BE IMPROVED


https://www.policyschool.ca/wp-content/uploads/2018/04/Canadas-Refugee-Strategy-Vineberg.pdf
Robert Vineberg | April 2018

AN INTERNATIONAL COMPARISON OF TAX ASSISTANCE FOR R&D: 2017 UPDATE AND EXTENSION TO PATENT BOXES
http://www.policyschool.ca/wp-content/uploads/2018/04/Tax-Assistance-Lester-Warda.pdf
John Lester and Jacek Warda | April 2018

FISCAL POLICY TRENDS: THE PATH TO BALANCE OR THE ROAD TO RUIN?


http://www.policyschool.ca/wp-content/uploads/2018/03/Fiscal-Trends-Path-to-Balance-Dahlby.pdf
Bev Dahlby | March 2018

36