You are on page 1of 2

Mineral 18,000,000 ton/año MINERAL

Pala Cargador
Estéril 25,000,000 ton/año
Hidráulica Frontal
TOTAL 43,000,000 ton/año Balde (yd3) 21 15
m3/yd3 0.7646 0.7646
días/año 365 Balde (m3) 16.06 11.47

Mineral 49,315 ton/día Densidad (ton/m3) 2.7 2.7


Estéril 68,493 ton/día Esponjamiento 1.4 1.4
TOTAL 120,548 ton/día
Balde (ton) 30.97 22.12
hrs/día 24
F. Llenado 0.9 0.8
Mineral 2,055 ton/hr UT 0.85 0.7
Estéril 2,854 ton/hr FO 0.83 0.83
TOTAL 4,909 ton/hr DF 0.75 0.7

T ciclo (seg) 35 40
seg/hr 3600 3600

cuantos ciclos x hr 103 90


Productividad Ef. (ton/hr) 1,827.45 780.35
2,607.80
ESTERIL
Pala Cargador
Hidráulica Frontal
21 15
0.7646 0.7646
16.06 11.47

2.4 2.4
1.4 1.4

27.53 19.66

0.9 0.8
0.85 0.7
0.83 0.83
0.75 0.7

30 40
3600 3600

120 90
1895.14 693.65
3,976.07

You might also like