You are on page 1of 3

The Consultant YAMASITA SENKEI INC

Ms. Yuka Kobayasi


The Contractor RINKAI NISSAN CONSTRUCTION CO. LTD
Mr. H. Isogai
Client UNTL
Project CONSTRUCTION WORK OF NEW BUILDINGS FOR THE FACULTY OF ENGINEERS,
SCIENCE AND THECNOLOGY OF THE NATIONAL UNIVERSITY OF TIMOR
Suppier OGAWA SEIKI CO. LTD
Structure REINFORCED CONCRETE

First day , 2/7/2018

Intern Training for Civil Engineering Students of UNTL from Mr. Sorawan S. Oramahe and Mr.
about all the developers already created by the Project manager.

Intern Training from dari semua lider yang sudah ada di jadwal :

1. Work Supervision From : YSI


2. Building Work Detail Drawing From : Mr. Noval
3. Work Schedule Management From : Mr. Ibros
4. Quality Control Management From : Mr. Andar
5. Safety Control Management From : Mr. Fadil
6. Concrete Work From : Mr. Joel
7. Steel Bar Reinforce Work From : Mr. Pedro
8. Form Work From : Mr. Junito

Counselor from Mr. Junito

Second day, 3/7/2018

A. WORK SUPERVISION
Penjelasan dari semua consultant tentang apa saja yang harus di kerjakan oleh consultant.
Consultant adalah salah satu company yang berkerja sama dengan kontraktor untuk
mengontrol satu project yang sedang dilaksanakan. Semua yang berkaitan dengan project harus
dikerjakan oleh consultant, dari visa, alat, material semua harus di cek oleh konsultant

harus dicek (
should be checked
dari inspeksi external yang dilakukan oleh semua company di Zone A terlihat beberapa
kesalahan yang harus diperkaiki, dari rebar di bagian ... ada yang jaraknya tidak sama, ada juga
tulangan di bagian ... yang kurang (
from the external inspection conducted by all companies in Zone A seen some errors
that must be repaired, from rebar in part ... there is a distance is not the same, there is
also a reinforcement on the part ... less

project yang sedang dilaksanakan ada di area Hera, dengan luas area ? dan
terdiri dari 3 lantai, 2 lantai di bagian depan untuk commom office dan 3
lantai di bagian belakang untuk classroom, project yang dilaksakan hanya
dalam 18 bulan, berdasarkan schedule yang ada. (projects that are being implemented are in
Hera area, with wide area? and consists of 3 floors, 2 floors on the front for the commom office and 3 floors in the
back for the classroom, the project is implemented in just 18 months, based on the existing schedule.

semua material yang digunakan dalam project adalah :


all materials used in the project are:

alat berat yang digunakan dalam project adalah :


heavy equipment used in the project are:

inspeksi yang dilakukan oleh consultant harus sama dengan design yang ada
the inspection conducted by the consultant should be the same as the existing design

dari coran beton pertama di zone A didapat 432 cubic. pasir 50 gram, cement 50 gram, air 50
liter. (
from the first concrete castings in zone A obtained 432 cubic. sand 50 gram, cement 50
gram, water 50 liter.

inspeksi yang dilakukan untuk pondasi girder, rebar dibagian girder mengunakan D25, stirrup,
colom dan beam.
inspection performed for the foundation girder, rebar girder section using D25, stirrup,
colom and beam.

karung goni

Gunny sack
karung goni : digunakan setelah pengecoran selasai agar airnya meresap.
gunny sack: used after foundry to keep the water absorbed.

Submit
Menyerahkan

dari contractor harus melaporkan kesalahan yang sudah diperbaiki untuk dicek kembali oleh
inspector consultant
of the contractor must report an amended error to be checked by the inspector
consultant
dari contractor harus melaporkan kesalahan di lapangan bagian cordinate yang sudah
diperbaiki untuk dicek kembali oleh inspector consultant

of the contractor must report an error in the repaired cordinate section field to be
checked by the inspector consultant

untuk satu formwork yang ada harus mengunakan berapa triplex dan juga besi?
for one formwork there must use how many triplex and also iron?

kenapa besi untuk holo yang sudah dipotong harus disambungkan lagi ?
why iron for the already-cut holo must be connected again?

bagaimana cara pemasangan besi untuk pipa


Indonesian---------------Detect languageAfri kaansAl bani anAmharicAr abic Ar meni anAzer baijaniBanglaBasqueBelar usianBos nianBulgari anBur mes eCatal anC ebuanoC hines e (Si mplified)Chi nese (Traditional)C orsicanCroati anCzec hD anis hD utc hEnglishEs per antoEstoni anFilipinoFi n nishFr enchGalici anGeorgianGermanGr eekGujaratiHaiti an CreoleH ausaHawaiianHebrewHindiHmongHungarianIc elandicIgboIndonesianIrish ItalianJapanes eJ avanes eKannadaKaz akhKhmer Kor eanKur dishKyrg yzLaoLati nLatvi anLithuanianLuxembourgishM acedoni anMal agas yM alayM ala yal amMaltes eMaoriMar athiMongolianN epaliNor wegianN yanjaPashtoPersi anPolishPortugues ePunjabiRomani anRus sianSamoanSc ottish Gaelic Ser bi anShonaSindhi SinhalaSlovakSlovenianSomali Southern SothoSpanishSundaneseSwahiliSwedishT aji kT amilTelug uThai Tur kishU kr aini anUrduUzbekVietnameseWelshWestern FrisianXhosaYiddis hYorubaZul uIndonesi an

how to install iron for pipes

You might also like