DAFTAR HARGA SATUAN UPAH DAN BAHAN

SATUAN KERJA : DINAS PENDIDIKAN PROVINSI NUSA TENGGARA TIMUR


PEKERJAAN : REHABILITASI RUANG LABORATORIUM IPA
LOKASI : SMA KRISTEN TARUS TENGAH KAB. KUPANG
TAHUN ANGGARAN : 2018
BAGIAN I : DAFTAR HARGA SATUAN UPAH
No Jenis Tenaga Kerja Satuan Harga
1 Mandor Org/Hari
2 Kepala tukang Org/Hari 75,000.00
3 Kepala tukang Besi Profil Org/Hari 75,000.00
4 Tukang batu Org/Hari 70,000.00
5 Tukang besi Org/Hari 70,000.00
6 Tukang cat Org/Hari 70,000.00
7 Tukang Kayu Org/Hari 70,000.00
8 Tukang Besi Profil Org/Hari 70,000.00
9 Pekerja Org/Hari 65,000.00

BAGIAN II : DAFTAR HARGA SATUAN BAHAN

No Jenis Material Satuan Harga


1 Amplas lbr 8,000.00
2 Baja Siku kg 25,000.00
3 Baja Profil kg 25,000.00
4 Balok Kayu Klas I Lokal Terbaik m3 4,000,000.00
5 Kayu Klas I (Setara Jati) m3 4,500,000.00
6 Balok Kayu Klas II Lokal m3 3,500,000.00
7 Bataco bh 3,000.00
8 Batu pecah m3 300,000.00
9 Batu karang m3 125,000.00
10 Besi beton kg 15,000.00
11 Cat kayu dasar (altex) kg 24,000.00
12 Cat kayu/besi kilap (Altex) kg 45,000.00
13 Cat menie kayu (altex) kg 24,000.00
14 Cat tembok (Altex) kg 16,000.00
15 Engsel Jendela set 24,000.00
16 Engsel pintu set 40,000.00
17 Gerendel Jendela bh 10,000.00
18 Gerendel pintu bh 15,000.00
19 Kaca Polos (5 mm) m2 110,000.00
20 Kait angin psg 28,000.00
21 Kawat beton kg 20,000.00
22 Kayu dolken btg 10,000.00
23 Kuas cat bh 15,000.00
24 Kuas Rol bh 20,000.00
25 Kunci Pintu 2 double slag bh 160,000.00
26 Lem Aica Aibon kg 48,000.00
No Jenis Material Satuan Harga
27 List Plafond lebar 5 cm m 1
12,000.00
28 List kaca m1 8,000.00
29 Minyak cat kg 24,000.00
30 Multipleks 9 mm lbr 160,000.00
31 Paku 5-12 cm kg 20,000.00
32 Paku List kg 20,000.00
33 Paku seng kg 22,000.00
34 Papan Begisting/Kayu klas III m3 1,750,000.00
35 Papan kayu klas I Lokal ( Setara Jati ) m3 4,500,000.00
No Jenis Material Satuan Harga

36 Papan kayu klas II m3 3,500,000.00


37 Pasir pasang m3 275,000.00
38 Pasir Beton m 3
300,000.00
39 Pasir urug m3 200,000.00
40 Plamur kayu/dempul kg 22,000.00
41 Plamur tembok kg 14,000.00
42 Politur kg 45,000.00
43 Screw taping bh 130,000.00
44 Saklar tunggal bh 20,000.00
45 Saklar ganda bh 28,000.00
46 Saklar triple bh 33,000.00
47 Sement Portland (S.Kupang/Bosowa/Tiga Roda) zak 58,000.00
48 Semen warna kg 10,000.00
49 Seng Gelombang 0.30 Lbr 73,500.00
50 Seng Bubungan 0.20 Lbr 35,000.00
51 Stop kontak bh 30,000.00
52 Pipa Listrik PVC Ø 3/4 " btg 16,000.00
53 Fitting Lampu Tempel bh 15,000.00
54 Kabel NYM 2,5 mm M' 12,000.00
55 Isolasi Bh 8,000.00
56 Lampu Hemat Energi SL 11 W ( philip ) bh 46,000.00
57 Lampu Hemat Energi SL 18 W ( philip ) bh 75,000.00
58 Tanah urug m 3
85,000.00
59 Semen Putih zak 95,000.00
60 Teak wood lbr 60,000.00
61 Teak wood lapis aluminium lbr 85,000.00
62 Tegel keramik 30/30 m 2
60,000.00
63 Tegel wafel keramik 20/20 m2 60,000.00
64 Tegel keramik dinding 20/25 m 2
60,000.00
65 Triplek lapis aluminum lbr 95,000.00
66 Triplek 3 mm lbr 54,000.00
67 Triplek 4 mm lbr 74,500.00
68 Usuk 5/7 kayu klas II m 3
3,500,000.00
69 Kran air + Pasang bh 45,000.00
AR HARGA SATUAN UPAH DAN BAHAN
PENDIDIKAN PROVINSI NUSA TENGGARA TIMUR

BAGIAN I : DAFTAR HARGA SATUAN UPAH


Keterangan

AGIAN II : DAFTAR HARGA SATUAN BAHAN

Keterangan
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
Keterangan
On site
On site
On site
On site
On site
On site
On site
On site
On site
Keterangan

On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
On site
ANALISA HARGA SATUAN PEKERJAAN
SATUAN KERJA : DINAS PENDIDIKAN PROVINSI NUSA TENG
PEKERJAAN : REHABILITASI RUANG LABORATORIUM IPA
LOKASI : SMA KRISTEN TARUS TENGAH KAB. KUPAN
TAHUN ANGGARAN : 2018
Harga Jumlah Harga
N0 Jenis Pekerjaan Koefisien Satuan Satuan Bahan
( Rp ) ( Rp )
1 2 3 4 5 6
An. 01 1 M 3 Pasangan batu bataco camp, 1 pc : 4 psr
Pasir pasang 0.5040 m3 275,000.00 138,600.00
Semen 1.9000 zak 58,000.00 110,200.00
Batu bataco 125.0000 bh 3,000.00 375,000.00
Pekerja 3.2000 org 65,000.00
Mandor 0.0500 org 0.00
Tukang batu 1.2000 org 70,000.00
Kepala tukang batu 0.1500 org 75,000.00
Jumlah 623,800.00
An. 02 1 M 2 Plesteran trasram camp, 1 pc : 2 psr, tebal 15 mm
Pasir pasang 0.0170 m3 275,000.00 4,675.00
Semen 0.2130 zak 58,000.00 12,354.00
Pekerja 0.1000 org 65,000.00
Mandor 0.0100 org 0.00
Tukang batu 0.1500 org 70,000.00
Kepala tukang batu 0.0150 org 75,000.00
Jumlah 17,029.00
An. 03 1 M 2 Plesteran biasa camp, 1 pc : 5 psr, tebal 15 mm
Pasir pasang 0.0220 m3 275,000.00 6,050.00
Semen 0.1350 zak 58,000.00 7,830.00
Pekerja 0.1000 org 65,000.00
Mandor 0.0100 org 0.00
Tukang batu 0.1000 org 70,000.00
Kepala tukang batu 0.0105 org 75,000.00
Jumlah 13,880.00
An. 04 1 M Acian PC
2

Semen 0.1500 zak 58,000.00 8,700.00


Pekerja 0.2000 org 65,000.00
Mandor 0.0030 org 0.00
Tukang batu 0.0600 org 70,000.00
Kepala tukang batu 0.0400 org 75,000.00
Jumlah 8,700.00
An. 05 1 M Pekerjaan kosen kayu Klas I
3

Balok kayu klas I 1.1000 m3 4,500,000.00 4,950,000.00


Pekerja 4.0000 org 65,000.00
Mandor 0.3000 org 0.00
Tukang kayu 10.0000 org 70,000.00
Kepala tukang kayu 1.0000 org 75,000.00
Jumlah 4,950,000.00
An. 06 1 M 2 Pas. Jelusi/krepyak Kayu Klas II
Papan kayu klas II 0.020 M3 3,500,000.00 69,300.00
Paku 0.030 Kg 20,000.00 600.00
Tukang kayu 1.500 org 70,000.00
Kepala Tukang kayu 0.150 org 75,000.00
Pekerja 0.500 org 65,000.00
Mandor 0.025 org 0.00
Jumlah 69,900.00
An. 07 1 M Pasangan listplank
1

Papan klas II 0.0216 m3 3,500,000.00 75,600.00


Paku 0.0500 kg 20,000.00 1,000.00
Tukang kayu 0.2000 org 70,000.00
Kepala Tukang kayu 0.0200 org 75,000.00
Pekerja 0.1000 org 65,000.00
Mandor 0.0050 ls 0.00
Jumlah 76,600.00
An. 08 1 M 1 Pasangan list plafond
List plafond profil lebar 5 cm 1.0000 m1 12,000.00 12,000.00
Paku tripleks 0.0250 kg 20,000.00 500.00
Upah kerja per m1 1.0000 ls 1,500.00
Jumlah 12,500.00
An. 09 1 M 2 Plafond tripleks 4 mm + rangka
Usuk kayu klas II 0.0110 m3 3,500,000.00 38,500.00
Tripleks tebal 4 mm 0.3500 lbr 74,500.00 26,075.00
Paku tripleks 0.0150 kg 20,000.00 300.00
Paku reng 0.0400 kg 20,000.00 800.00
Pekerja 0.2800 org 65,000.00
Mandor 0.0200 org 0.00
Tukang kayu 0.4000 org 70,000.00
Kepala tukang kayu 0.0800 org 75,000.00
Jumlah 65,675.00
An. 10 1 M 2 Pek. Meni Kayu
Meni 0.1800 kg 24,000.00 4,320.00
Minyak cat 0.3500 kg 24,000.00 8,400.00
Kuas biasa 4" 0.0800 bh 15,000.00 1,200.00
Pekerja 0.2000 org 65,000.00
Mandor 0.0200 org 0.00
Tukang cat 0.0750 org 70,000.00
Kepala tukang cat 0.0075 org 75,000.00
Jumlah 13,920.00
An. 11 1 M 2 Pekerjaan cat kayu
Cat kilap 0.2840 kg 45,000.00 12,780.00
Minyak cat 0.0500 ltr 24,000.00 1,200.00
Plamur/Dempul kayu 0.0800 kg 22,000.00 1,760.00
Kuas biasa 4" 0.0800 bh 15,000.00 1,200.00
Amplas 0.2000 lbr 8,000.00 1,600.00
Pekerja 0.0400 org 65,000.00
Mandor 0.0020 org 0.00
Tukang cat 0.0500 org 70,000.00
Kepala tukang cat 0.0050 org 75,000.00
Jumlah 18,540.00
An. 12 1 M Pekerjaan cat dinding/plafond
2

Cat dinding 0.3500 kg 16,000.00 5,600.00


Plamur dinding 0.1400 kg 14,000.00 1,960.00
Kuas roll 0.0500 bh 20,000.00 1,000.00
Amplas 0.2000 lbr 8,000.00 1,600.00
Pekerja 0.1000 org 65,000.00
Mandor 0.0050 org 0.00
Tukang cat 0.0600 org 70,000.00
Kepala tukang cat 0.0060 org 75,000.00
Jumlah 10,160.00

An. 13 1 M 2 Pekerjaan cat atap


Cat besi 0.2100 kg 45,000.00 9,450.00
Minyak cat 0.1500 kg 24,000.00 3,600.00
Kuas 0.0500 bh 15,000.00 750.00
Pekerja 0.1000 org 65,000.00
Mandor 0.0100 org 0.00
Tukang cat 0.1000 org 70,000.00
Kepala tukang cat 0.0010 org 75,000.00
Jumlah 13,800.00
An. 14 1 M 3 Campuran rabat beton 1 pc : 3 psr : 5 krl
Semen 5.6000 zak 58,000.00 324,800.00
Pasir Beton 0.5200 m3 300,000.00 156,000.00
Batu pecah 0.8700 m3 300,000.00 261,000.00
Pekerja 6.0000 org 65,000.00
Mandor 0.3000 org 0.00
Tukang batu 1.0000 org 70,000.00
Kepala tukang batu 0.1000 org 75,000.00
Jumlah 741,800.00
An. 15 1 M Lantai Tegel Keramik 30/30 cm
2

Tegel keramik 30x30 1.0000 m2 60,000.00 60,000.00


Pasir 0.0300 m 3
275,000.00 8,250.00
Semen 0.1150 zak 58,000.00 6,670.00
Semen warna 0.0100 kg 10,000.00 100.00
Pekerja 0.2000 org 65,000.00
Mandor 0.0500 org 0.00
Tukang batu 0.5000 org 70,000.00
Kepala tukang batu 0.0150 org 75,000.00
Jumlah 75,020.00
An. 16 1 M Pekerjaan kosen pintu / jendela
3

Balok kayu klas I Lokal 1.1000 m3 4,000,000.00 4,400,000.00


Paku > 7 cm 0.8000 kg 20,000.00 16,000.00
Pekerja 4.0000 org 65,000.00
Mandor 0.3000 org 0.00
Tukang kayu 10.0000 org 70,000.00
Kepala tukang kayu 1.0000 org 75,000.00
Jumlah 4,416,000.00

An. 17 1 M 2 Pasangan jendela kaca mati 5 mm


Kaca 5 mm 1.0000 m2 110,000.00 110,000.00
Plamur/Dempul kayu 0.0470 kg 22,000.00 1,034.00
List kaca 4.0000 m' 8,000.00 32,000.00
Paku halus 0.0050 kg 20,000.00 100.00
Pekerja 0.0200 org 65,000.00
Mandor 0.0020 org 0.00
Tukang kayu 0.2000 org 70,000.00
Kepala tukang kayu 0.0600 org 75,000.00
Jumlah 143,134.00

An.18 1 M 2 Pekerjaan daun pintu panil


Papan kayu klas I Kayu Jati 0.0150 M3 4,500,000.00 67,500.00
Bingkai kayu klas I Kayu Jati 0.0220 M3 4,500,000.00 99,000.00
Tukang Kayu 4.0000 org 70,000.00
Kepala Tukang kayu 0.7500 org 75,000.00
Pekerja 3.0000 org 65,000.00
Mandor 0.1000 org 0.00
Jumlah 166,500.00
An. 19 1 M Pasangan daun jendela panil kaca 5 mm
2

Kaca 5 mm 1.0000 m2 110,000.00 110,000.00


Plamur/Dempul kayu 0.0470 kg 22,000.00 1,034.00
List kaca 4.0000 m' 8,000.00 32,000.00
Paku halus 0.0050 kg 20,000.00 100.00
Papan kayu klas I 0.0350 m2 4,500,000.00 157,500.00
Pekerja 0.9000 org 65,000.00
Mandor 0.0450 org 0.00
Tukang kayu 0.6000 org 70,000.00
Kepala tukang kayu 0.0600 org 75,000.00
Jumlah 300,634.00

An. 20 PEKERJAAN ATAP, LISTPLANK


1 M3 PEK. KUDA-KUDA & GORDING KAYU KLS II
Kayu klas II 1.1000 M3 3,500,000.00 3,850,000.00
Paku 0.4000 Kg 20,000.00 8,000.00
Bout,begerl ,plat dll 1.0000 ls ls 200,000.00
Tukang kayu 15.0000 org 70,000.00
Kepala Tukang kayu 1.5000 org 75,000.00
Pekerja 6.0000 org 65,000.00
Mandor 0.5000 org -
Jumlah 4,058,000.00
An. 21 1 M2 Pasang Papan Listplank
Papan klas II 0.0072 m3 3,500,000.00 25,200.00
Paku 0.0500 Kg 20,000.00 1,000.00
Tukang kayu 2.0000 org 70,000.00
Kepala Tukang kayu 0.2000 org 75,000.00
Pekerja 0.2500 org 65,000.00
Mandor 0.0250 org -
Jumlah 26,200.00

An. 22 1 M2 Pasang Atap Seng BJLS 0.30


Seng gelombang 0.8500 Lbr 73,500.000 62,475.000
Paku seng 0.0600 Bh 22,000.00 1,320.00
Tukang kayu 0.0100 org 70,000.00
Kepala Tukang kayu 0.0500 org 75,000.00
Pekerja 0.1000 org 65,000.00
Mandor 0.0010 org -
Jumlah 63,795.000
An. 23 1 M' Pasang Seng Bubungan BJLS 0.20
Seng plat 0.5000 M' 35,000.00 17,500.00
Paku seng 0.0800 Bh 22,000.00 1,760.00
Tukang kayu 0.1000 org 70,000.00
Kepala Tukang kayu 0.0100 org 75,000.00
Pekerja 0.0500 org 65,000.00
Mandor 0.0050 org -
Jumlah 19,260.00
An. 24 1 M2 Pekerjaan Teak Oil
Teak Oil 0.0750 kg 45,000.00 3,375.00
Minyak cat 0.0750 kg 24,000.00 1,800.00
Dempul 0.0800 Kg 22,000.00 1,760.00
Kwas 0.0500 bh 15,000.00 750.00
kertas Pasir 0.5000 lbr 8,000.00
Kepala Tukang kayu 0.0750 org 75,000.00
Tukang kayu 0.0080 org 70,000.00
Pekerja 0.0500 org 65,000.00
Jumlah 7,685.00

*An. 25 1 M 3 Urugan tanah


Batu karang 0.5000 m3 125,000.00 62,500.00
Pasir Uruk (Sirtu) 0.5000 m3 200,000.00 100,000.00
Pekerja 0.3000 org 65,000.00
Mandor 0.0100 org 0.00
Jumlah 162,500.00
An. 26 1 M 2 Plafond tripleks 4 mm Tanpa Rangka
Tripleks tebal 4 mm 0.3500 lbr 74,500.00 26,075.00
Paku tripleks 0.0150 kg 20,000.00 300.00
Paku reng 0.0400 kg 20,000.00 800.00
Pekerja 0.3000 org 65,000.00
mandor 0.1500 org 0.00
Tukang kayu 0.6000 org 70,000.00
Kepala tukang kayu 0.0600 org 75,000.00
Jumlah 27,175.00
SA HARGA SATUAN PEKERJAAN
: DINAS PENDIDIKAN PROVINSI NUSA TENGGARA TIMUR
: REHABILITASI RUANG LABORATORIUM IPA
: SMA KRISTEN TARUS TENGAH KAB. KUPANG

Jumlah Harga Jumlah Harga


Upah Harga Bahan &
( Rp ) Upah ( Rp )
7 8

138,600.00
110,200.00
375,000.00
208,000.00 208,000.00
0.00 0.00
84,000.00 84,000.00
11,250.00 11,250.00
303,250.00 927,050.00

4,675.00
12,354.00
6,500.00 6,500.00
0.00 0.00
10,500.00 10,500.00
1,125.00 1,125.00
18,125.00 35,154.00

6,050.00
7,830.00
6,500.00 6,500.00
0.00 0.00
7,000.00 7,000.00
787.50 787.50
14,287.50 28,167.50

8,700.00
13,000.00 13,000.00
0.00 0.00
4,200.00 4,200.00
3,000.00 3,000.00
20,200.00 28,900.00

4,950,000.00
260,000.00 260,000.00
0.00 0.00
700,000.00 700,000.00
75,000.00 75,000.00
1,035,000.00 5,985,000.00

69,300.00
600.00
105,000.00 105,000.00
11,250.00 11,250.00
32,500.00 32,500.00
0.00 0.00
148,750.00 218,650.00

75,600.00
1,000.00
14,000.00 14,000.00
1,500.00 1,500.00
6,500.00 6,500.00
0.00 0.00
22,000.00 98,600.00

12,000.00
500.00
1,500.00 1,500.00
1,500.00 14,000.00

38,500.00
26,075.00
300.00
800.00
18,200.00 18,200.00
0.00 0.00
28,000.00 28,000.00
6,000.00 6,000.00
52,200.00 117,875.00
4,320.00
8,400.00
1,200.00
13,000.00 13,000.00
0.00 0.00
5,250.00 5,250.00
562.50 562.50
18,812.50 32,732.50

12,780.00
1,200.00
1,760.00
1,200.00
1,600.00
2,600.00 2,600.00
0.00 0.00
3,500.00 3,500.00
375.00 375.00
6,475.00 25,015.00

5,600.00
1,960.00
1,000.00
1,600.00
6,500.00 6,500.00
0.00 0.00
4,200.00 4,200.00
450.00 450.00
11,150.00 21,310.00

9,450.00
3,600.00
750.00
6,500.00 6,500.00
0.00 0.00
7,000.00 7,000.00
75.00 75.00
13,575.00 27,375.00

324,800.00
156,000.00
261,000.00
390,000.00 390,000.00
0.00 0.00
70,000.00 70,000.00
7,500.00 7,500.00
467,500.00 1,209,300.00

60,000.00
8,250.00
6,670.00
100.00
13,000.00 13,000.00
0.00 0.00
35,000.00 35,000.00
1,125.00 1,125.00
49,125.00 124,145.00

4,400,000.00
16,000.00
260,000.00 260,000.00
0.00 0.00
700,000.00 700,000.00
75,000.00 75,000.00
1,035,000.00 5,451,000.00

110,000.00
1,034.00
32,000.00
100.00
1,300.00 1,300.00
0.00 0.00
14,000.00 14,000.00
4,500.00 4,500.00
19,800.00 162,934.00

67,500.00
99,000.00
280,000.00 280,000.00
56,250.00 56,250.00
195,000.00 195,000.00
0.00 0.00
531,250.00 697,750.00

110,000.00
1,034.00
32,000.00
100.00
157,500.00
58,500.00 58,500.00
0.00 0.00
42,000.00 42,000.00
4,500.00 4,500.00
105,000.00 405,634.00
3,850,000.00
8,000.00
200,000.00
1,050,000.00 1,050,000.00
112,500.00 112,500.00
390,000.00 390,000.00
- -
1,552,500.00 5,610,500.00

25,200.00
1,000.00
140,000.00 140,000.00
15,000.00 15,000.00
16,250.00 16,250.00
- -
171,250.00 197,450.00

62,475.00
1,320.00
700.00 700.00
3,750.00 3,750.00
6,500.00 6,500.00
- -
10,950.00 74,745.00

17,500.00
1,760.00
7,000.00 7,000.00
750.00 750.00
3,250.00 3,250.00
- -
11,000.00 30,260.00

3,375.00
1,800.00
1,760.00
750.00
4,000.00 4,000.00
5,625.00 5,625.00
560.00 560.00
3,250.00 3,250.00
13,435.00 21,120.00

62,500.00
100,000.00
19,500.00 19,500.00
0.00 0.00
19,500.00 182,000.00

26,075.00
300.00
800.00
19,500.00 19,500.00
0.00 0.00
42,000.00 42,000.00
4,500.00 4,500.00
66,000.00 93,175.00
RENCANA ANGGARAN BIAYA ( RAB )
SATUAN KERJA : DINAS PENDIDIKAN PROVINSI NUSA TENGGARA TIMUR
PEKERJAAN : REHABILITASI RUANG LABORATORIUM IPA
LOKASI : SMA KRISTEN TARUS TENGAH KAB. KUPANG
TAHUN ANGGARAN : 2018
1. Rehabilitasi Ruang Laboratorium IPA

No Uraian Pekerjaan Satuan Volume

A PEKERJAAN PERSIAPAN/PEMBONGKARAN
1 Pekerjaan Pembongkaran ls 1.00
2 Pengadaan Papan Nama dan Prasasti ls 1.00
3 Penyediaan air kerja ls 1.00
Jumlah Biaya Pekerjaan Persiapan
C PEK. PASANGAN & PLESTERAN
1 Pasangan dinding batako 1PC : 4Psr m3 1.68
2 Plesteran 1 PC : 5 Psr m2 67.31
3 Plesteran Pondasi m2 20.00
4 Acian m 2
87.31
Jumlah Biaya Pekerjaan Pasangan & Plesteran
E PEKERJAAN LANTAI
1 Pasang Lantai keramik 30x30 cm m2 150.00
2 Pasang keramik plint m2 7.88
Jumlah Biaya Pekerjaan Lantai
F PEKERJAAN PINTU, JENDELA DAN PENGGANTUNG
1 Kosen kayu klas I Lokal (setara jati ) lbg 53.00
2 Daun jendela + kaca 5 mm unit 24.00
4 Angker, Dok Besi, besi plat U, mur bout ls 1.00
5 Daun pintu panil kayu jati lbr 3.00
6 Kunci tanam 2 putar bh 2.00
7 Engsel pintu set 4.00
8 Grendel Pintu bh 3.00
9 Engsel Jendela set 24.00
10 Grendel Jendela bh 48.00
11 Kait Angin set 24.00
Jumlah Biaya Pekerjaan Pintu, Jendela & Penggantung
G PEKERJAAN KUDA-KUDA, ATAP DAN PLAFOND
1 Pek. Kuda-kuda Kayu Klas II Lokal m3 0.58
2 Pek. Gording Kayu Klas II Lokal m3 1.29
3 Atap Seng Gelombang 0.30 m2 255.00
4 Atap Seng Bubungan 0.20 m' 17.00
5 List Plank kayu klas II m' 64.00
6 Plafond triplek 4 mm + rangka m2 86.40
6 Plafond triplek 4 mm tanpa rangka m 2
129.60
7 List Plafon Lebar 5 cm m' 248.00
Jumlah Biaya Pekerjaan Kuda-kuda, Atap dan Plaf
H PEKERJAAN FINISHING
1 Cat Kusen + list Plank m2 44.57
2 Cat Tembok m2 87.31
3 Cat Plafond m 2
86.40
4 Cat Seng dan bubungan m2 255.00
Jumlah Biaya Pekerjaan Finishing
I PEKERJAAN LISTRIK
1 Pemasangan Kotak MCB bh 1.00
2 Stop Kontak bh 4.00
3 Instalasi Dalam Gedung ttk 12.00
4 Lampu SL 18 Watt ( Philip ) bh 8.00
5 Lampu SL 11 Watt ( Philip ) bh 3.00
6 Fitting Tempel bh 11.00
7 Saklar Tunggal bh 1.00
8 Saklar Ganda bh 2.00
Jumlah Biaya Pekerjaan Listrik
J PEKERJAAN REHABILITASI SANITASI
1 Pek. Plesteran m2 1.36
2 Pek. Acian m2 1.97
6 Pek.Pasang Kran Air bh 4.00
7 Pek. Instalasi Air Kotor ls 1.00
8 Pek. Bak Pembuangan/ Penampungan Limbah unit 1.00
Jumlah Biaya Pekerjaan Sanitasi
2 PEKERJAAN PERENCANAAN DAN PENGAWASAN
1 Biaya Pekerjaan Perencanaan ls 1.00
2 Biaya Pekerjaan Pengawasan ls 1.00
Jumlah Biaya Pekerjaan Perencanaan dan Pengawasan
RENCANA ANGGARAN BIAYA
SATUAN KERJA : DINAS PENDIDIKAN PROVINSI NUSA TENGGARA TIMUR
PEKERJAAN : REHABILITASI RUANG LABORATORIUM IPA
LOKASI : SMA KRISTEN TARUS TENGAH KAB. KUPANG
TAHUN ANGGARAN : 2018
1. Rehabilitasi Ruang Laboratorium IPA

No Uraian Pekerjaan

A PEKERJAAN PERSIAPAN/PEMBONGKARAN
C PEK. PASANGAN & PLESTERAN
E PEKERJAAN LANTAI
F PEKERJAAN PINTU, JENDELA DAN PENGGANTUNG
G PEKERJAAN KUDA-KUDA, ATAP DAN PLAFOND
H PEKERJAAN FINISHING
I PEKERJAAN LISTRIK
J PEKERJAAN REHABILITASI SANITASI
JUMLAH
TOTAL
DIBULATKAN
Terbilang : Seratus Tiga Puluh Tujuh Juta Enam Ratus Tujuh Puluh Empat Ribu Rupiah
Menyetujui :
Kepala SMA Kristen Tarus Tengah
Kabupaten Kupang

DRA. ESTER LENGGU, M.Si.


NIP. 1960 1202 198111 2005
REKAPITULASI RENCANA ANGGARAN BIAYA
SATUAN KERJA : DINAS PENDIDIKAN PROVINSI NUSA TENGGARA TIMUR
PEKERJAAN : REHABILITASI RUANG LABORATORIUM IPA
LOKASI : SMA KRISTEN TARUS TENGAH KAB. KUPANG
TAHUN ANGGARAN : 2018

No Uraian Pekerjaan

1 PEKERJAAN REHABILITASI LABORATORIUM IPA

2 PEKERJAAN PERENCANAAN DAN PENGAWASAN

JUMLAH
TOTAL
DIBULATKAN
Terbilang : Seratus Empat Puluh Tiga Juta Seratus Delapan Puluh Ribu Rupiah
Menyetujui :
Kepala SMA Kristen Tarus Tengah
Kabupaten Kupang

DRA. ESTER LENGGU, M.Si.


NIP. 1960 1202 198111 2005
RENCANA ANGGARAN BIAYA
SATUAN KERJA : DINAS PENDIDIKAN PROVINSI NUSA TENGGARA TIMUR
PEKERJAAN : PEMBANGUNAN LABORATORIUM IPA
LOKASI : SMA NEGERI 2 AMARASI BARAT KABUPATEN KUPANG
TAHUN ANGGARAN : 2017
2. Pekerjaan Pengadaan Meubelair Laboratorium IPA

No Uraian Pekerjaan Satuan Volume

B PEKERJAAN MEUBELAIR
1 Meja Kerja bh 6.00
2 Kursi Laboratorium bh 36.00
3 Meja Persiapan bh 1.00
4 Meja demonstrasi bh 1.00
5 Meja Guru bh 1.00
6 Kursi Guru bh 1.00
7 Papan Tulis bh 2.00
8 Lemari Penyimpanan Alat bh 2.00
9 Lemari Penyimpanan Bahan bh 1.00

JUMLAH
TOTAL
DIBULATKAN
Terbilang : Dua Puluh Lima Juta Rupiah
Menyetujui :
Kepala SMA Kristen Tarus Tengah
Kabupaten Kupang

DRA. ESTER LENGGU, M.Si.


NIP. 1960 1202 198111 2005
AN BIAYA ( RAB )
USA TENGGARA TIMUR

Harga Satuan NAMA SEKOLA


Jumlah Harga
(Rp.) (Rp.)
1
2,500,000.00 2,500,000.00 2
800,000.00 800,000.00 4
600,000.00 600,000.00 5
3,900,000.00 6
15
927,050.00 1,560,225.15 398.34 18
28,167.50 1,895,841.76 20
35,154.00 703,080.00 22
28,900.00 2,523,143.40 23
6,682,290.31 24
31
124,145.00 18,621,750.00 33
124,145.00 978,262.60 35
19,600,012.60 36
39
300,000.00 15,900,000.00 41
300,000.00 7,200,000.00
500,000.00 500,000.00
750,000.00 2,250,000.00
190,000.00 380,000.00
40,000.00 160,000.00
10,000.00 30,000.00
24,000.00 576,000.00
10,000.00 480,000.00
28,000.00 672,000.00
28,148,000.00
5,610,500.00 3,265,311.00
5,610,500.00 7,209,492.50
74,745.00 19,059,975.00
30,260.00 514,420.00
98,600.00 6,310,400.00
117,875.00 10,184,400.00
90,400.00 11,715,840.00
14,000.00 3,472,000.00
61,731,838.50

25,015.00 1,114,868.52
21,310.00 1,860,490.86
25,200.00 2,177,280.00
27,375.00 6,980,625.00
12,133,264.38

135,000.00 135,000.00
30,000.00 120,000.00
180,000.00 2,160,000.00
75,000.00 600,000.00
46,000.00 138,000.00
15,000.00 165,000.00
20,000.00 20,000.00
28,000.00 56,000.00
3,394,000.00

35,154.00 47,809.44
28,900.00 56,875.20
45,000.00 180,000.00
1,000,000.00 1,000,000.00
800,000.00 800,000.00
2,084,684.64

3,441,000.00 3,441,000.00
2,065,000.00 2,065,000.00
5,506,000.00
GARAN BIAYA
USA TENGGARA TIMUR

Jumlah Harga
(Rp.)

3,900,000.00
6,682,290.31
19,600,012.60
28,148,000.00
61,731,838.50
12,133,264.38
3,394,000.00
2,084,684.64
137,674,090.43 ###
137,674,090.43
137,674,000.00
#REF!
Kupang, 20 April 2018
Tim Perencana #REF!

###
MUHAMMAD TEY
Estimator
NA ANGGARAN BIAYA
USA TENGGARA TIMUR

Jumlah Harga
(Rp.)

137,674,000

5,506,000

143,180,000
143,180,000
143,180,000

Kupang, 20 April 2018


Tim Teknis,

MUHAMMAD TEY
Estimator
GARAN BIAYA
USA TENGGARA TIMUR

KABUPATEN KUPANG

Harga Satuan
Jumlah Harga
(Rp.) (Rp.)

800,000.00 4,800,000.00
150,000.00 5,400,000.00
900,000.00 900,000.00
1,250,000.00 1,250,000.00
1,250,000.00 1,250,000.00
400,000.00 400,000.00
1,000,000.00 2,000,000.00
3,000,000.00 6,000,000.00
3,000,000.00 3,000,000.00

25,000,000.00
25,000,000.00
25,000,000.00

Kupang, 17 Juli 2017


Tim Teknis,

BAMBANG W. WIBOWO
Ketua
#REF!

NAMA SEKOLAH
FISIK

SMA NEGERI KABOLA KABUPATEN ALOR 327,065,000


SMA NEGERI 4 ATAMBUA KABUPATEN BELU 271,040,000
SMA KATOLIK FRATRERAN NDAO KAB. ENDE 288,185,000
SMAS SEMINARI SAN DOMINGGO KAB. FLORES TIMUR 299,837,000
SMA NEGERI 1 AMFOANG TENGAH KAB. KUPANG 259,448,000
SMA NEGERI 1 RUTENG ANAM KAB. MANGGARAI 295,581,000
SMA ST. KLAUS WERANG KAB. MANGGARAI BARAT 289,242,000
SMAS SEMINARI PIUS XII KISOL KAB. MANGGARAI TIMUR 295,641,000
SMA SWASTA KATOLIK REGINA PACIS BAJAWA KAB. NGADA 293,619,000
SMA NEGERI 1 ROTE TENGAH KAB. ROTE NDAO 309,376,000
SMA NEGERI MAGEPANDA KAB. SIKKA 279,250,000
SMA NEGERI 1 WEWEWA SELATAN KAB. SUMBA BARAT DAYA 296,698,000
SMA NEGERI 1 MAMBORO KAB. SUMBA TENGAH 298,207,000
SMA NEGERI 1 AMANUBAN TIMUR KAB. TTS 288,819,000
SMA NEGERI BININO KAB. TTU 269,591,000
SMA DHARMA AYU KAB. TTU 269,591,000
SMA KRISTEN 2 KOTA KUPANG KOTA KUPANG 262,346,000

#REF!
5,506,960.00
259,448,000 25,000,000
121,774,000.00
SMA NEGERI 2 AMARASI BARAT KAB. KUPANG 259,448,000

SMA NEGERI 2 AMARASI BARAT


Aprianus S. Mamun, S.Pd 19650424 199903 1 006
MEUBELAIR

25,000,000 352,065,000 OK
25,000,000 296,040,000 OK
25,000,000 313,185,000
25,000,000 324,837,000
25,000,000 284,448,000
25,000,000 320,581,000
25,000,000 314,242,000
25,000,000 320,641,000
25,000,000 318,619,000
25,000,000 334,376,000 OK
25,000,000 304,250,000
25,000,000 321,698,000
25,000,000 323,207,000
25,000,000 313,819,000
25,000,000 294,591,000 ok
25,000,000 294,591,000 OK
25,000,000 287,346,000
284,448,000
25,000,000 284,448,000
Mengetahui :
9650424 199903 1 006 Kota Kupang

DRS. JERHANS A. LEDOH


Pembina Utama Muda
JADWAL PELAKSANAAN PEMBANGUNAN DAN KURVA S
SATUAN KERJA : DINAS PENDIDIKAN PROVINSI NUSA TENGGARA TIMUR
PEKERJAAN : REHABILITASI RUANG LABORATORIUM IPA
LOKASI : SMA KRISTEN TARUS TENGAH KAB. KUPANG
TAHUN ANGGARAN : 2018
NILAI BOBOT Bulan Ke 1 Minggu …. Bulan Ke 2 Minggu …. Bulan Ke 3 Minggu ….
N0 URAIAN PEKERJAAN
( Rp ) % 1 2 3 4 1 2 3 4 1 2 3

1 REHABILITASI RUANG LABORATORIUM IPA

A PEKERJAAN PERSIAPAN/PEMBONG 3,900,000 2.72 1.36 1.36

B PEKERJAAN PASANGAN & PLESTER 6,682,290 4.67 1.56 1.56 1.56

C PEKERJAAN LANTAI 19,600,013 13.69 2.74 2.74 2.74 2.74

D PEKERJAAN PINTU , JEND & PEN 28,148,000.00 19.66 2.81 2.81 2.81 2.81 2.81 2.81 2.81

E PEKERJAAN KUDA-KUDA, ATAP DA 61,731,838.50 43.11 6.16 6.16 6.16 6.16 6.16

F PEKERJAAN FINISHING 12,133,264.38 8.47

G PEKERJAAN LISTRIK 3,394,000.00 2.37

H PEKERJAAN REHABILITASI SANITAS 2,084,684.64 1.46

2 PEKERJAAN PERENCANAAN DAN 5,506,000.00 3.85 0.24 0.24 0.24 0.24 0.24 0.24 0.24 0.24 0.24 0.24 0.24

Jumlah 143,180,090.43 100.00 1.60 1.60 1.80 1.80 4.60 3.05 9.21 11.95 11.95 11.95 11.95

Akumulasi % Progress 1.60 3.20 5.00 6.80 11.40 14.45 23.66 35.60 47.55 59.50 71.44
`
Menyetujui : Kupang, 20 April 2018
Kepala SMA Kristen Tarus Tengah Tim Teknis,
Kabupaten Kupang
DRA. ESTER LENGGU, M.Si. MUHAMMAD TEY
NIP. 1960 1202 198111 2005 Estimator

120.00

100.00

80.00

60.00

40.00

20.00

0.00
1 2 3 4 5 6 7 8 9 10 11 12 13
KURVA S

e3 Minggu …. Bulan Ke 4 Minggu ….

4 1 2 3 4

#REF!
###
2.74

6.16 6.16

2.12 2.12 2.12 2.12

1.19 1.19

0.49 0.49 0.49

0.24 0.24 0.24 0.24 0.24

9.14 8.52 2.84 4.03 4.03

80.58 89.10 91.94 95.97 100.00

ang, 20 April 2018


HAMMAD TEY
Estimator