SUMINISTRO E INSTALACION DE CERCOS PERIMETRALES_Rev_2_23062018 Informe Semanal tuto 24/7/18 11:51

Activity ID Activity Name Original Start Finish BL Project BL Project Performance Schedule % Budgeted Planned Value Earned Value Actual RemainingM J J A S O
Duration Start Finish % Complete Complete Labor Units Labor Units Labor Units Labor Units Labor Units1 2 0 2 0 2 0 1 3 1 20
1 0 1 2 1 2 1 2 0 2

SUMINISTRO E INSTALACION DE CERCOS PERIMETRALES_Rev_2_23


SUMINIST 146 16/5/18 A 7/10/18 15/5/18 29/8/18 20,12% 58,06% 19210 11154 3866 3865 15345

HITOS CONTRACTUALES
CO 46 16/5/18 A 20/5/18 A 15/5/18 18/5/18 0% 0% 0 0 0 0 0 20/5/18 A, HITOS CONTRACTUALES

CERCOS PE
PERIMETRALES 46 16/5/18 A 20/5/18 A 15/5/18 18/5/18 0% 0% 0 0 0 0 0 20/5/18 A, CERCOS PERIMETRALES
A1220 Carta de adjudicacion 0 16/5/18 A 15/5/18 100% 100% 0 0 0 0 0 Carta de adjudicacion, 16/5/18 A
A1230 Orden de servicio 0 16/5/18 A 17/5/18 100% 100% 0 0 0 0 0 Orden de servicio, 16/5/18 A
A1290 Entrega de planos 0 20/5/18 A 18/5/18 100% 100% 0 0 0 0 0 Entrega de planos, 20/5/18 A

HITOS DE CONSTRUCCION 139 5/6/18 A 7/10/18 22/5/18 29/8/18 0% 0% 0 0 0 0 0

HITOS BHP 139 5/6/18 A 7/10/18 22/5/18 29/8/18 0% 0% 0 0 0 0 0


A1240 Entrega de area refino-oxidos-sulfuros 0 5/6/18 A 22/5/18 100% 100% 0 0 0 0 0 Entrega de area refino-oxidos-sulfu

A1250 inicio de los trabajos refino-oxidos-sulfuros 0 6/6/18 A 28/5/18 100% 100% 0 0 0 0 0 inicio de los trabajos refino-oxidos-
A1260 Entrega de area piscina de ILS-PLS de sulfuro 0 4/8/18 27/6/18 0% 100% 0 0 0 0 0 Entrega de area
A1310 Inicio de los trabajos de ILS-PLS de sulfuro 0 7/8/18 30/6/18 0% 100% 0 0 0 0 0 Inicio de los trab
A1320 Entrega de area piscina recolectora 0 7/9/18 31/7/18 0% 0% 0 0 0 0 0 Entrega
A1330 Inicio de los trabajos piscina recolectora 0 10/9/18 3/8/18 0% 0% 0 0 0 0 0 Inicio d
A1400 Termino de los trabajos refino-oxidos-sulfuros 0 14/8/18 4/7/18 0% 100% 0 0 0 0 0 Termino de los
A1510 Termino de los trabajos de ILS-PLS de sulfuro 0 18/9/18 10/8/18 0% 0% 0 0 0 0 0 Term
A1520 Termino de los trabajos piscina recolectora 0 7/10/18 29/8/18 0% 0% 0 0 0 0 0
HITOS MPM 106 5/6/18 A 7/9/18 25/5/18 31/7/18 0% 0% 0 0 0 0 0 7/9/18,
A1300 Suministro Cercos perimetrales piscina refino-oxido-sulfuro 0 5/6/18 A 25/5/18 100% 100% 0 0 0 0 0 Suministro Cercos perimetrales pis
A1340 Suministro Cercos perimetrales piscina de ILS-PLS de sulfuro 0 4/8/18 27/6/18 0% 100% 0 0 0 0 0 Suministro Cerco
A1350 Suministro Cercos perimetrales piscina recolectora 0 7/9/18 31/7/18 0% 0% 0 0 0 0 0 Sumini

ACTIVIDADES PREVIAS
ACTIVIDA 137 5/6/18 A 7/10/18 24/5/18 29/8/18 0% 0% 0 0 0 0 0

MOVILIZACION
MOVILIZACI 110 5/6/18 A 10/9/18 24/5/18 2/8/18 0% 0% 0 0 0 0 0 10/9/1
A1270 Movilizacion de instalacion de faena refino-oxidos-sulfuros 3 5/6/18 A 7/6/18 A 24/5/18 26/5/18 100% 100% 0 0 0 0 0 Movilizacion de instalacion de faen
A1280 Movilizacion de instalacon de faenas PLS-ILS sulfuro 3 4/8/18 7/8/18 27/6/18 29/6/18 0% 100% 0 0 0 0 0 Movilizacion de
A1360 Movilizacion instalacion de faenas piscina recolectora 3 7/9/18 10/9/18 31/7/18 2/8/18 0% 0% 0 0 0 0 0 Moviliz
DESMOVILIZACION
DESMOVILI 58 10/8/18 7/10/18 1/7/18 29/8/18 0% 0% 0 0 0 0 0
A1370 Desmovilizacion de instalacion de faenas refino-oxidos-sulfuros 4 10/8/18 14/8/18 1/7/18 4/7/18 0% 100% 0 0 0 0 0 Desmovilizacio
A1380 Desmovilizacion de instalacon de faenas PLS-ILS sulfuro 4 14/9/18 18/9/18 7/8/18 10/8/18 0% 0% 0 0 0 0 0 Des
A1390 Desmovilizacion de instalacion de faenas piscina recolectora 4 3/10/18 7/10/18 26/8/18 29/8/18 0% 0% 0 0 0 0 0

CONSTRUCCION CERCO PISCINAS


CONSTRU 129 6/6/18 A 3/10/18 28/5/18 25/8/18 20,12% 58,06% 19210 11154 3866 3865 15345

PISCINA DE RESPALDO REFINO-OXIDOS-SULFURO 68 6/6/18 A 10/8/18 28/5/18 30/6/18 56,15% 100% 6885 6885 3866 3865 3020 10/8/18, PISCIN
TRAMO N°1 (NORTE) 382 mts 11 6/6/18 A 26/7/18 28/5/18 7/6/18 78,21% 100% 1950 1950 1525 1525 425 26/7/18, TRAMO N°
A1410 Normalizacion del area 2 6/6/18 A 7/6/18 A 28/5/18 29/5/18 100% 100% 149 149 149 149 0 Normalizacion del area
A1420 Excavacion 3 8/6/18 A 7/7/18 A 30/5/18 1/6/18 100% 100% 200 200 200 200 0 Excavacion
A1430 Instalacion de postes y poyos de hormigon 3 10/6/18 A 7/7/18 A 1/6/18 3/6/18 100% 100% 495 495 495 495 0 Instalacion de postes y p
A1440 Instalacion de mallas 3 12/6/18 A 8/7/18 A 3/6/18 5/6/18 100% 100% 520 520 520 520 0 Instalacion de mallas
A1450 Dimensionado, preparacion e instalacion puesta a tierra 4 11/6/18 A 24/7/18 2/6/18 5/6/18 25% 100% 293 293 73 73 220 Dimensionado, prep
A1460 Instalacion de alambre puas 2 15/6/18 A 26/7/18 6/6/18 7/6/18 30% 100% 293 293 88 88 205 Instalacion de alam
TRAMO N°2 (SUR) 469.4 mts 53 16/6/18 A 2/8/18 4/6/18 20/6/18 48,14% 100% 2365 2365 1139 1138 1227 2/8/18, TRAMO N
A1470 Normalizacion del area 2 16/6/18 A 22/7/18 4/6/18 5/6/18 90% 100% 66 66 59 59 7 Normalizacion del are
A1480 Excavacion 4 16/6/18 A 24/7/18 6/6/18 9/6/18 69,15% 100% 495 495 342 342 153 Excavacion
A1490 Instalacion de postes y poyos de hormigon 4 7/7/18 A 28/7/18 10/6/18 13/6/18 51,06% 100% 495 495 253 253 242 Instalacion de pos
A1500 Instalacion de mallas 4 7/7/18 A 30/7/18 14/6/18 17/6/18 65,95% 100% 511 511 337 337 174 Instalacion de mal
A1570 Dimensionado, preparacion e instalacion puesta a tierra 6 14/7/18 A 30/7/18 10/6/18 15/6/18 25% 100% 449 449 112 112 337 Dimensionado, pre

Actual Level of Effort Remaining Work Milestone Page 1 of 3 TASK filter: All Activities

Actual Work Critical Remaining Work summary © Oracle Corporation


SUMINISTRO E INSTALACION DE CERCOS PERIMETRALES_Rev_2_23062018 Informe Semanal tuto 24/7/18 11:51

Activity ID Activity Name Original Start Finish BL Project BL Project Performance Schedule % Budgeted Planned Value Earned Value Actual RemainingM J J A S O
Duration Start Finish % Complete Complete Labor Units Labor Units Labor Units Labor Units Labor Units1 2 0 2 0 2 0 1 3 1 20
1 0 1 2 1 2 1 2 0 2
A1590 Instalacion de alambre puas 3 14/7/18 A 2/8/18 18/6/18 20/6/18 10% 100% 349 349 35 35 314 Instalacion de ala
TRAMO N°3 (PONIENTE) 468.6 mts 54 24/6/18 A 10/8/18 14/6/18 30/6/18 46,78% 100% 2570 2570 1202 1202 1368 10/8/18, TRAM
A1530 Normalizacion del area 2 24/6/18 A 30/7/18 14/6/18 15/6/18 90% 100% 110 110 99 99 11 Normalizacion del
A1540 Excavacion 4 25/6/18 A 1/8/18 16/6/18 19/6/18 56,68% 100% 420 420 238 238 182 Excavacion
A1550 Instalacion de postes y poyos de hormigon 4 26/6/18 A 4/8/18 20/6/18 23/6/18 52,88% 100% 600 600 317 317 283 Instalacion de po
A1560 Instalacion de mallas 4 27/6/18 A 7/8/18 24/6/18 27/6/18 52,81% 100% 600 600 317 317 283 Instalacion de m
A1580 Dimensionado, preparacion e instalacion puesta a tierra 6 14/7/18 A 7/8/18 20/6/18 25/6/18 25% 100% 420 420 105 105 315 Dimensionado, p
A1600 Instalacion de alambre puas 3 16/7/18 A 10/8/18 28/6/18 30/6/18 30% 100% 420 420 126 126 294 Instalacion de a
PISCINA PLS-ILS
PL DE SULFURO 38 7/8/18 14/9/18 30/6/18 6/8/18 0% 54,74% 7798 4269 0 0 7798 14/9/
TRAMO N°1 (LADO SUR) 205 mts 13 7/8/18 20/8/18 30/6/18 12/7/18 0% 100% 2278 2278 0 0 2278 20/8/18, TRA
A1620 Normalizacion del area 2 7/8/18 9/8/18 30/6/18 1/7/18 0% 100% 400 400 0 0 400 Normalizacion d
A1630 Excavacion 3 9/8/18 12/8/18 2/7/18 4/7/18 0% 100% 420 420 0 0 420 Excavacion
A1640 Instalacion de postes y poyos de hormigon 3 12/8/18 15/8/18 5/7/18 7/7/18 0% 100% 420 420 0 0 420 Instalacion de
A1650 Instalacion de mallas 3 15/8/18 18/8/18 8/7/18 10/7/18 0% 100% 420 420 0 0 420 Instalacion d
A1660 Dimensionado, preparacion e instalacion puesta a tierra 5 12/8/18 17/8/18 5/7/18 9/7/18 0% 100% 309 309 0 0 309 Dimensionad
A1670 Instalacion de alambre puas 2 18/8/18 20/8/18 11/7/18 12/7/18 0% 100% 309 309 0 0 309 Instalacion d
TRAMO N°2 (LADO ORIENTE) 455 mts 17 15/8/18 1/9/18 8/7/18 24/7/18 0% 85,38% 2121 1811 0 0 2121 1/9/18, T
A1680 Normalizacion del area 2 15/8/18 17/8/18 8/7/18 9/7/18 0% 100% 143 143 0 0 143 Normalizacion
A1690 Excavacion 4 17/8/18 21/8/18 10/7/18 13/7/18 0% 100% 384 384 0 0 384 Excavacion
A1700 Instalacion de postes y poyos de hormigon 4 21/8/18 25/8/18 14/7/18 17/7/18 0% 100% 660 660 0 0 660 Instalacion
A1710 Instalacion de mallas 4 25/8/18 29/8/18 18/7/18 21/7/18 0% 75% 420 315 0 0 420 Instalacio
A1720 Dimensionado, preparacion e instalacion puesta a tierra 6 21/8/18 27/8/18 14/7/18 19/7/18 0% 100% 309 309 0 0 309 Dimension
A1730 Instalacion de alambre puas 3 29/8/18 1/9/18 22/7/18 24/7/18 0% 0% 205 0 0 0 205 Instalacio
TRAMO N°3 (LADO NORTE)198 mts 9 25/8/18 3/9/18 18/7/18 26/7/18 0% 25,1% 717 180 0 0 717 3/9/18, T
A1740 Normalizacion del area 1 25/8/18 26/8/18 18/7/18 18/7/18 0% 100% 90 90 0 0 90 Normalizac
A1750 Excavacion 2 26/8/18 28/8/18 19/7/18 20/7/18 0% 100% 90 90 0 0 90 Excavacio
A1760 Instalacion de postes y poyos de hormigon 2 28/8/18 30/8/18 21/7/18 22/7/18 0% 0% 110 0 0 0 110 Instalacio
A1770 Instalacion de mallas 2 30/8/18 1/9/18 23/7/18 24/7/18 0% 0% 110 0 0 0 110 Instalacio
A1780 Dimensionado, preparacion e instalacion puesta a tierra 4 28/8/18 1/9/18 21/7/18 24/7/18 0% 0% 97 0 0 0 97 Dimensio
A1790 Instalacion de alambre puas 2 1/9/18 3/9/18 25/7/18 26/7/18 0% 0% 220 0 0 0 220 Instalaci
TRAMO N°4 (LADO PONIENTE 488 MTS 17 28/8/18 14/9/18 21/7/18 6/8/18 0% 0% 2682 0 0 0 2682 14/9/
A1800 Normalizacion del area 2 28/8/18 30/8/18 21/7/18 22/7/18 0% 0% 142 0 0 0 142 Normaliza
A1810 Excavacion 4 30/8/18 3/9/18 23/7/18 26/7/18 0% 0% 520 0 0 0 520 Excavac
A1820 Instalacion de postes y poyos de hormigon 4 3/9/18 7/9/18 27/7/18 30/7/18 0% 0% 550 0 0 0 550 Instalac
A1830 Instalacion de mallas 4 7/9/18 11/9/18 31/7/18 3/8/18 0% 0% 550 0 0 0 550 Instala
A1840 Dimensionado, preparacion e instalacion puesta a tierra 6 3/9/18 9/9/18 27/7/18 1/8/18 0% 0% 533 0 0 0 533 Dimen
A2050 Instalacion de alambre puas 3 11/9/18 14/9/18 4/8/18 6/8/18 0% 0% 387 0 0 0 387 Insta
PISCINA RECOLECTORA
RE 23 10/9/18 3/10/18 3/8/18 25/8/18 0% 0% 4527 0 0 0 4527
TRAMO N°1 (LADO SUR) 94 mts 10 10/9/18 20/9/18 3/8/18 12/8/18 0% 0% 1136 0 0 0 1136 20/
A1850 Normalizacion del area 1 10/9/18 11/9/18 3/8/18 3/8/18 0% 0% 108 0 0 0 108 Norma
A1860 Excavacion 2 11/9/18 13/9/18 4/8/18 5/8/18 0% 0% 220 0 0 0 220 Excav
A1870 Instalacion de postes y poyos de hormigon 3 13/9/18 16/9/18 6/8/18 8/8/18 0% 0% 262 0 0 0 262 Insta
A1880 Instalacion de mallas 3 16/9/18 19/9/18 9/8/18 11/8/18 0% 0% 262 0 0 0 262 Inst
A1890 Dimensionado, preparacion e instalacion puesta a tierra 4 13/9/18 17/9/18 6/8/18 9/8/18 0% 0% 142 0 0 0 142 Dim
A2060 Instalacion de alambre puas 1 19/9/18 20/9/18 12/8/18 12/8/18 0% 0% 142 0 0 0 142 Ins
TRAMO N°2 (LADO ORIENTE) 139 mts 12 13/9/18 25/9/18 6/8/18 17/8/18 0% 0% 1063 0 0 0 1063 25
A1900 Normalizacion del area 1 13/9/18 14/9/18 6/8/18 6/8/18 0% 0% 108 0 0 0 108 Norm
A1910 Excavacion 3 14/9/18 17/9/18 7/8/18 9/8/18 0% 0% 142 0 0 0 142 Exca

Actual Level of Effort Remaining Work Milestone Page 2 of 3 TASK filter: All Activities

Actual Work Critical Remaining Work summary © Oracle Corporation


SUMINISTRO E INSTALACION DE CERCOS PERIMETRALES_Rev_2_23062018 Informe Semanal tuto 24/7/18 11:51

Activity ID Activity Name Original Start Finish BL Project BL Project Performance Schedule % Budgeted Planned Value Earned Value Actual RemainingM J J A S O
Duration Start Finish % Complete Complete Labor Units Labor Units Labor Units Labor Units Labor Units1 2 0 2 0 2 0 1 3 1 20
1 0 1 2 1 2 1 2 0 2
A1920 Instalacion de postes y poyos de hormigon 3 17/9/18 20/9/18 10/8/18 12/8/18 0% 0% 264 0 0 0 264 Ins
A1930 Instalacion de mallas 3 20/9/18 23/9/18 13/8/18 15/8/18 0% 0% 264 0 0 0 264 Ins
A1940 Dimensionado, preparacion e instalacion puesta a tierra 5 17/9/18 22/9/18 10/8/18 14/8/18 0% 0% 140 0 0 0 140 Dim
A2070 Instalacion de alambre puas 2 23/9/18 25/9/18 16/8/18 17/8/18 0% 0% 145 0 0 0 145 In
TRAMO N°3 (LADO NORTE) 103 mts 11 17/9/18 28/9/18 10/8/18 20/8/18 0% 0% 1141 0 0 0 1141 2
A1950 Normalizacion del area 1 17/9/18 18/9/18 10/8/18 10/8/18 0% 0% 53 0 0 0 53 Norm
A1960 Excavacion 2 18/9/18 20/9/18 11/8/18 12/8/18 0% 0% 144 0 0 0 144 Exc
A1970 Instalacion de postes y poyos de hormigon 3 20/9/18 23/9/18 13/8/18 15/8/18 0% 0% 264 0 0 0 264 Ins
A1980 Instalacion de mallas 3 23/9/18 26/9/18 16/8/18 18/8/18 0% 0% 264 0 0 0 264 In
A1990 Dimensionado, preparacion e instalacion puesta a tierra 5 20/9/18 25/9/18 13/8/18 17/8/18 0% 0% 208 0 0 0 208 D
A2080 Instalacion de alambre puas 2 26/9/18 28/9/18 19/8/18 20/8/18 0% 0% 208 0 0 0 208 I
TRAMO N°4 (LADO PONIENTE) 144 mts 13 20/9/18 3/10/18 13/8/18 25/8/18 0% 0% 1187 0 0 0 1187
A2000 Normalizacion del area 1 20/9/18 21/9/18 13/8/18 13/8/18 0% 0% 86 0 0 0 86 No
A2010 Excavacion 3 21/9/18 24/9/18 14/8/18 16/8/18 0% 0% 141 0 0 0 141 Ex
A2020 Instalacion de postes y poyos de hormigon 3 24/9/18 27/9/18 17/8/18 19/8/18 0% 0% 264 0 0 0 264 In
A2030 Instalacion de mallas 3 28/9/18 1/10/18 21/8/18 23/8/18 0% 0% 264 0 0 0 264
A2040 Dimensionado, preparacion e instalacion puesta a tierra 5 24/9/18 29/9/18 17/8/18 21/8/18 0% 0% 216 0 0 0 216 D
A2090 Instalacion de alambre puas 2 1/10/18 3/10/18 24/8/18 25/8/18 0% 0% 216 0 0 0 216

Actual Level of Effort Remaining Work Milestone Page 3 of 3 TASK filter: All Activities

Actual Work Critical Remaining Work summary © Oracle Corporation