Professional Documents
Culture Documents
TABLE OF CONTENTS
DESCRIPTION PAGES
1.
Acknowledgement 2
2.
Certificate 3
3.
Executive Summary 4-14
4. Introduction (History of the Plant) 15-16
ACKNOWLEDGEMENT
Energo Engineering Projects Limited, New Delhi carried out Residual Life
Assessment of HRSG # 1 (Regn. No. UP- 5318) at Kribhco Shyam Fertilizers
as per IBR 391 A (table 1) & Scope of work of Kribhco Shyam Fertilizers.
CERTIFICATE
Certified that the NDT on HRSG # 1 (Reg.no. UP- 5318) at Kribhco Shyam
Fertilizers has been conducted meeting the requirement of IBR 391(A) table
-1 and the requirements of Kribhco Shyam FertilizersWork Order
No.:KSFL/SPN/M-O/S/6000201/PD/85000736 Dated 01/08/15.
All remarkable findings on Visual Inspection, Cold walk through survey and
NDT were recorded jointly with Kribhco Shyam Fertilizersin the form of Daily
reports copy of which were furnished for immediate action if any, these are
now furnished in duly typed form in the Final Report No.
F136/RLA/KSFL/BLR1/07/2017 show the boiler is fit for steaming at design
parameter. Further final recommendations have been furnished after chemical
analysis of Drum, metallurgical analysis, destructive test of tube samples in
laboratory.
EXECUTIVE SUMMARY
The intent for the Residual Life Assessment Study of Boiler Pressure Parts is
to Inspect and test the various Pressure Parts of the Boiler as per IBR 391(A)
Table-1 and as per scope of study desired by Kribhco Shyam Fertilizersin
their order and agreed by EEPL.
Following Non-Destructive Tests were carried out during site RLA Study.
1. Visual Examination
2. Dye-Penetrant Test
3. Magnetic particle inspection
4. Ultrasonic test
5. Ultrasonic Thickness Measurement
6. Dimensional Measurement
7. In-Situ Metallography and Replication for lab study
8. In-Situ Oxide Scale Thickness Measurement
9. Hardness measurement
This final report includes major findings of the RLA study carried out on Boiler
(100MTPH) of KSFL, Shahjahnpur . Photographs and micrographs along
with expert comments and recommendations have been included in this final
report.
The Boiler was commissioned on 1992 & has already clocked 1, 00,000
working hours.
INTENT OF STUDY
& WILCOX LTD PUNE make HRSG # 1 Pressure Parts (Reg. No.UP-5318) of
The RLA Study was carried out as per the guidelines of Indian Boilers
Regulation Clause 391 (A), (a) table 1 and also the detailed specific
requirements of Kribhco Shyam Fertilizers Vide their Work Order No.:
KSFL/SPN/M-O/S/6000201/PD/85000736 Dated 01/08/15
Although tubes and pipes have some unique problems of their own, two
fundamental and common factors that dictate material selection are creep
strength and resistance to oxidation at high temperatures.
Failure of boiler tubes is the foremost cause of the forced boiler outages. The
major failure categories in boiler tubes are listed as below.
Stress – Rupture.
Short-term overheating.
High-temperature creep.
Dissimilar-metal welds.
Water-Side Corrosion.
Caustic corrosion.
Hydrogen damage.
Pitting (localized corrosion).
Stress-corrosion cracking.
Fatigue.
Vibration.
Thermal.
Corrosion.
Short-Term Overheating: -
A short-term-overheating failure is one in which a single incident or a
small number of incidents exposes the tube steel to an excessively
high temperature (hundreds of degree above normal) to the points
where deformation or yielding occurs. These abnormal conditions are
created by following circumstances:
The finned attachment also can transfer more heat to the tube and result in
higher metal temperature .
Prevention of high temperature creep failure involves keeping tube metal
stress and temperature within the capabilities of tube material.
C. Fatigue
Fatigue is the result of cyclical stresses in the component. Mechanical
fatigue associated with external applied stresses, may be associated with
vibration due to flue gas & uneven expansion of component.
D. Lack of quality control
Lack of quality control comprises of feed water chemistry, mechanical
damage of tube during installation & overhauling , poor welding of joints,
alignment of drums & headers to ensure proper assembly of tubes. Tubes
should be free to expand during operation to avoid any buckling.
given below:
A brief outline of the procedure that is adopted at each one of these steps
is furnished in the following sections.
II. Stress Computations: - This task is essential for the creep fatigue
and crack growth analysis of critical components.
a. Stress Computation for Creep.
a. Stress Computation for Fatigue.
V. Crack-Growth Analysis-Procedure
Stepwise procedure for remaining life estimates using crack growth
analysis is furnished below:
a.Collect data on crack size (length-a), location and orientation from
NDE (if available) or data may be assumed as indicative above. The
corresponding stress (Л) evaluated is the principal (maximum) tensile
stress normal to direction of crack opening.
b.Find shape factor Q for the crack geometry and fracture toughness
Klc for component material.
Q Klc
c. Find critical crack length using ac = [----- + ------]2
1.21Л σ
d. Set a factor of safety (fs) on ac and obtain a working limit a r: ar =
ac /fs.
Knowing da/dN and da/dt and (a1-a), the no. of cycle / duration through
which the particular location in the component undergoes a certain cyclic /
steady stress can be determined for the crack to propagate from a to (a 1 –
a), the no of cycles / duration through which the particular location in the
component undergoes a certain cyclic / steady stress can be determined
for the subsequent stages, say from a 1 to a2 to a3 and so on. These
computations are repeated until the crack length – a attains the terminal
value i.e., af. The corresponding no. of cycles/time duration is determined
for each such step and summed up until value a f is attained. The total life
left is decided by the sum of total hours (cycles are converted to hours
from cycle duration and no. of cycles) obtained from calculations.
This is the most common and first inspection technique done by trained
personnel. The inspection is sometimes aided by magnifying glass. Records
consist of description of visual observations often aided by sketches,
photographs, vital measurements.
During the health assessment of Boiler components, components should be
first visually inspected to look for the damage, Disholoration, scaling, erosion,
corrosion, dust deposit etc. These factors give clue to the internal material
and stress status of the components.
The components liable for deformation / bulging due to wear creep namely
Headers & tubes etc. were thoroughly cleaned and dimensions measured to
observe the extent of deformation.
5.5 - Ultrasonic Thickness Measurement (UT-T):-
UT thickness measurements are made on tubes and headers etc. to know the
remaining thickness after erosion and corrosion.
6.1 Tube samples from critical zones are removed for detailed examination
and analysis in laboratory. Tube samples cut on each boiler for
Examination at Laboratory
(a) Eco tube from low temperature zone
(b) Eco tube from high temperature zone
Requirements of scope of work as given in have been duly covered.
Formula:
WP = 2F (t-C) / (D-t + C)
WP = Design working pressure in kg/cm2
Ts = Minimum tensile strength at room temperature.
Et = Yield point strength at room temp.
Sr = Average stress at working temperature & working metal to produce
rupture in 1,00,000 hours and in no case more than 1.33 times the
lowest stress produced in 1,00,000 hours.
Sc = Average stress at working temperature of metal to produce elongation
of 1% creep in 1,00,000 hours.( Sc values are not available in
material standard and such material are known to have been used in
boilers)
F = Permissible stress at working temperature
F is minimum of following
Ts/2.7 or Sr/1.5 or Sc or Et/1.5 for temperature less than 454⁰c
Sr/1.5 or Sc whichever is lower for temperature above 454⁰c
t = Nominal wall thickness after negative thickness tolerance
adjustment.
C = 0.75 mm for WP upto and including 70kg/cm2.
= 0 for WP upto exceeding 70kg/cm2.
D = Outer Diameter of tube.
Formula:
T min = [(WP) (D+C) + 2FC] / (2F+WP)
T min = minimum wall thickness required.
1.0 Scope:
2.0 Purpose:
5.0 Lighting:
6.0 Examination:
1.0 Scope:
2.0 Purpose:
3.0 Technique:
7.0 PT Materials:
Penetrant : SKL-SP
Cleaner : SKC-1
Developer : SKD-S2
11.0 Examination:
11.5 Developing:
12.0 Inspection:
13.0 Interpretation:
13.1 Final interpretation shall be made after 10 to 60 minutes.
14.0 Evaluation:
14.1 The size of the indication is the basis for
acceptance
evaluation. Only indications, which have any dimension
greater than 1.6 mm, shall be considered as relevant.
14.2 A linear indication is one having a length greater
than 3
times the width.
14.3 A rounded indication is one of circular or
elliptical shape
with a length equal to or less than three times its width.
1.0 Scope:
2.0 Purpose:
3.0 Technique:
Reference Documents:
Surface Preparation:
The location for thickness measurement shall be free from dust, scale or
any other matter that could interfere with the effective coupling and the
thickness reading.The thickness measurement shall be performed at
ambient surface temperature.
6.0 Calibration:
1.0 SCOPE:
1.1.1 This procedure is applicable for in-situ metallography of Tubes, piping
& weld surface.
2.0 PURPOSE:
2.1.1 Metallography is performed to obtain Metallurgical structure of material
to study the degradation level.
3.0 PRINCIPLE:
3.1.1 Sampled location is cleaned, grind and polished to the extent that
micro structure is visible. Quality of polish and microstructure is
observed through portable microscope. Image is stored as soft copy
and transferred to PC for study and interpretation.
6.0 PROCEDURE:
6.1 Select the locations for metallography
6.2 Perform preliminary cleaning for removal of scale, rust oil etc.
6.3 Grind the surface to make it smooth, if pitting is present.
6.4 Perform buffing of the spot using different grades of buffing wheels.
6.5 Perform polishing with polish paper and polishing liquid.
6.6 Clean and wash the surface.
6.7 Chemical etching after cleaning the surface.
6.8 Inspect the surface for grain structure and record the image.
6.9 Take Replication on gold plated & / or Replication strip.
6.10 Replica will be studied through an optical microstructure in the
laboratory.
7.0 STUDY:
7.1 Study the microstructure recorded and the image with reference
structures for study of degradation.
Based on the analysis and the studies presented in various chapters of the
forgoing text and out of the NDTs / DTs carried out on the components for
Boiler & Auxiliaries of HRSG # 1 (Regn. No. UP- 5318) of Kribhco Shyam
Fertilizers. The following are component wise recommendations.
CONCLUSION
Based on the results of tests carried out during the course of RLA study, It
suitable for continuous operation for another ten to twelve years provided
recommended that RLA study be carried out after five years. This is to
assess the effect of any abnormal stresses arising out of any mal-
parameters.
Dimensional measurement:
Recommendation:
Residual Life:
200X
Observation Microstructure show predominent structure of pearlite & farrite.
No microstructural degradation is observed.
Life Fraction As per Wedel–Neubauer classification the component is in
between level I & level II, i.e expended life fraction is 0.38.
Recommendation This microstructure does not show any metal degradation. As per
general internationally accepted classification of creep cavitation,
this microstructure matches nearly damage class ‘1’ which
corresponds to no creep cavitation.
200X
Observation Microstructure show predominent structure of pearlite & farrite.
No microstructural degradation is observed.
Life Fraction As per Wedel–Neubauer classification the component is in
between level I & level II, i.e expended life fraction is 0.38.
Recommendation This microstructure does not show any metal degradation. As per
general internationally accepted classification of creep cavitation,
this microstructure matches nearly damage class ‘1’ which
corresponds to no creep cavitation.
Dimensional measurement:
PM : 142,138
WM: 157,162
Recommendation:
Residual Life:
TEST REPORT
200X
Observation Microstructure shows columnar ferrite & pearlite/ bainite
structure. No microstructural degradation is observed.
Life Fraction As per Wedel–Neubauer classification the component is in
between level I & level II, i.e expended life fraction is 0.38.
Recommendation This microstructure does not show any metal degradation. As
per general internationally accepted classification of creep
cavitation, this microstructure matches nearly damage class ‘1’
which corresponds to no creep cavitation.
200X
Observation Microstructure shows columnar ferrite & pearlite/ bainite
structure. No microstructural degradation is observed.
Life Fraction As per Wedel–Neubauer classification the component is in
between level I & level II, i.e expended life fraction is 0.38.
Recommendation This microstructure does not show any metal degradation. As
per general internationally accepted classification of creep
cavitation, this microstructure matches nearly damage class ‘1’
which corresponds to no creep cavitation.
Dimensional measurement:
EVAPORATOR HEADER
THICK OD
1 34.6 N.A
2 35.0 N.A
3 34.0 N.A
4 35.9 N.A
Hardness: 132,137
Recommendation:
Residual Life:
TEST REPORT
Recommendation:
Residual Life:
TEST REPORT
EVAPORATER-1 COILS
SR NO. THICK OD
1. 4.9 51.1
2. 5.0 51.2
3. 4.8 51.0
4. 4.9 51.0
5. 4.8 51.3
6. 4.8 51.2
7. 4.9 51.1
8. 4.8 51.2
9. 5.0 51.3
10. 5.0 51.1
11. 5.0 51.2
12. 4.9 51.1
13. 5.2 51.0
14. 4.8 51.2
15. 4.9 51.1
16. 5.0 51.0
17. 5.0 51.3
18. 4.7 51.2
19. 4.9 51.1
20. 5.1 51.3
21. 5.0 51.2
22. 4.8 51.1
23. 4.7 51.3
24. 4.9 51.0
25. 4.9 51.0
26. 5.1 51.2
27. 5.0 51.1
28. 5.0 51.1
29. 4.9 51.2
30. 4.8 51.0
EVAPORATER-2 COILS
SR NO. THICK OD
1. 4.6 51.0
2. 4.8 51.1
3. 4.7 51.2
4. 4.9 51.1
5. 4.9 51.1
6. 4.7 51.0
7. 4.6 51.2
8. 4.7 51.0
9. 4.9 51.1
10. 5.0 51.2
11. 4.7 51.1
12. 4.9 51.1
13. 4.8 51.2
14. 4.6 51.1
15. 4.9 51.1
16. 5.1 51.2
17. 5.0 51.1
18. 5.0 51.2
19. 4.7 51.1
20. 4.8 51.1
21. 5.0 51.0
22. 4.9 51.0
23. 4.9 51.2
24. 4.8 51.1
25. 5.0 51.2
26. 4.9 51.1
27. 5.0 51.0
28. 5.2 51.1
29. 4.9 51.2
30. 4.8 51.0
Dimensional measurement:
PM: 143,148,132
WM: 157,164,162
Recommendation:
Residual Life:
TEST REPORT
200X
Observation Microstructure shows columnar ferrite & pearlite/ bainite
structure. No microstructural degradation is observed.
Life Fraction As per Wedel–Neubauer classification the component is in
between level I & level II, i.e expended life fraction is 0.38.
Recommendation This microstructure does not show any metal degradation. As
per general internationally accepted classification of creep
cavitation, this microstructure matches nearly damage class ‘1’
which corresponds to no creep cavitation.
200X
Observation Microstructure shows columnar ferrite & pearlite/ bainite
structure. No microstructural degradation is observed.
Life Fraction As per Wedel–Neubauer classification the component is in
between level I & level II, i.e expended life fraction is 0.38.
Recommendation This microstructure does not show any metal degradation. As
per general internationally accepted classification of creep
cavitation, this microstructure matches nearly damage class ‘1’
which corresponds to no creep cavitation.
Dimensional measurement:
Recommendation:
Residual Life:
If further operating condition continues as in the past, it is expected that the Feed
Water line will remain fit for further service for more than 6 years as it is observed
during testing that there is less variation in thickness & dimension measurement &
microstructure is nearly matching damage class ‘1’ .
.
Cleaner Used
Brand Name Orion
Developer Used
Brand Name Orion
Developing Time 05 minutes
Method of Inspection Using magnifying glass
Observation
Component Feed Water line
S.NO. Component Quantit Interpretation Remarks
y
1 Circumferential joints 02 Nos. No surface defect Acceptable
Result Accepted All Defects Noticed Nil
200X
Observation Microstructure shows dendrite form of ferrite & pearlite structure.
No microstructural degradation is observed.
Life Fraction As per Wedel–Neubauer classification the component is in between
level I & level II, i.e expended life fraction is 0.46 to 0.48.
Recommendation This microstructure does not show any metal degradation. As per
general internationally accepted classification of creep cavitation, this
microstructure matches nearly damage class ‘1’ which corresponds to
no creep cavitation.
200X
Observation Microstructure shows ferrite & pearlite structure. No microstructural
degradation is observed.
Life Fraction As per Wedel–Neubauer classification the component is in between
level I & level II, i.e expended life fraction is 0.46 to 0.48.
Recommendation This microstructure does not show any metal degradation. As per
general internationally accepted classification of creep cavitation, this
microstructure matches nearly damage class ‘1’ which corresponds to
no creep cavitation.
Dimensional measurement:
DOWN COMER-1
THICK OD
1 24.7 275.0
2 24.5 275.0
3 25.3 275.3
4 24.9 275.1
DOWN COMAR-2
THICK OD
1 25.6 275.1
2 24.3 275.0
3 24.6 275.2
4 25.0 275.0
RISER TUBE
SR NO. THICK OD
1. 14.6 170.0
2. 14.3 170.2
3. 13.6 170.1
4. 13.9 170.1
5. 14.0 170.3
6. 14.3 170.0
7. 13.4 170.0
8. 14.5 170.1
9. 13.3 170.1
10. 13.7 170.0
11. 14.1 170.2
12. 13.9 170.1
13. 13.7 170.0
SATURATED TUBE
SR NO. THICK OD
1 9.7 100.3
2 10.0 100.2
3 9.6 100.0
4 9.9 100.1
Recommendation:
Residual Life:
If further operating condition continues as in the past, it is expected that the Down
Comer , Riser Tube , Saturated Tube will remain fit for further service for more than
6 years as it is observed during testing that there is less variation in thickness &
dimension measurement & microstructure is nearly matching damage class ‘1’ .
.
Cleaner Used
Brand Name Orion
Developer Used
Brand Name Orion
Developing Time 05 minutes
Method of Inspection Using magnifying glass
Observation
Component Down Comer , Riser Tube , Saturated Tube
S.NO. Component Quantit Interpretation Remarks
y
1 Stub l joints ALL No surface defect Acceptable
Result Accepted All Defects Noticed Nil
OBSERVATION
Result: Acceptable
OBSERVATION
Sl.
Area of examination Interpretation Remarks
No.
RESULT : Acceptable
OBSERVATION
Sl.
Area of examination Interpretation Remarks
No.
RESULT : Acceptable
OBSERVATION
Sl.
Area of Examination Interpretation Remarks
No.
RESULT : Acceptable
ECONOMISER-2 COILS
SR NO. THICK OD
1. 4.9 51.1
2. 5.1 51.2
3. 5.0 51.1
4. 5.2 51.0
5. 4.9 51.0
6. 4.9 51.0
7. 5.0 51.0
8. 5.1 51.2
9. 4.9 51.1
10. 4.9 51.0
11. 4.7 51.0
12. 5.2 51.1
13. 5.0 51.1
14. 5.0 51.1
15. 4.8 51.0
16. 4.8 51.2
17. 5.0 51.1
18. 4.9 51.1
19. 4.8 51.0
20. 4.8 51.0
21. 4.7 51.2
22. 4.9 51.1
23. 5.0 51.2
24. 5.2 51.1
25. 5.0 51.1
26. 4.9 51.0
27. 4.8 51.2
28. 4.7 51.0
29. 4.9 51.2
30. 4.9 51.1
ECONOMISER-1 COILS
SR NO. THICK OD
1. 4.9 51.0
2. 4.8 51.1
3. 5.0 51.2
4. 5.2 51.1
5. 5.0 51.1
6. 4.9 51.2
7. 4.8 51.1
8. 4.8 51.1
9. 4.9 51.0
10. 4.9 51.2
11. 4.8 51.1
Residual Life Assessment study of HRSG Page No. 82
Report No. F136/RLA/KRIBHCO/BLR1/07/2017
ENERGO ENGINEERING PROJECTS LIMITED KRIBHCO SHYAM FERTILIZERS
12. 4.9 51.1
13. 5.0 51.2
14. 5.1 51.0
15. 5.0 51.0
16. 5.3 51.1
17. 4.9 51.2
18. 4.7 51.0
19. 4.6 51.1
20. 5.0 51.0
21. 4.9 51.0
22. 4.7 51.2
23. 4.8 51.0
24. 4.9 51.2
25. 4.9 51.1
26. 4.7 51.2
27. 4.7 51.2
28. 4.9 51.0
29. 5.0 51.1
30. 5.0 51.2
SH O/L HEADER
THICK OD
1 34.6 N.A
2 35.0 N.A
3 34.4 N.A
4 35.6 N.A
OBSERVATION
Result: Acceptable
OBSERVATION
Sl.
Area of examination Interpretation Remarks
No.
RESULT : Acceptable
OBSERVATION
Sl.
Area of examination Interpretation Remarks
No.
RESULT : Acceptable
OBSERVATION
Sl. Area of Examination Interpretation Remarks
Residual Life Assessment study of HRSG Page No. 88
Report No. F136/RLA/KRIBHCO/BLR1/07/2017
ENERGO ENGINEERING PROJECTS LIMITED KRIBHCO SHYAM FERTILIZERS
No.
RESULT : Acceptable
FSH-2(LOC-1)
Sr no. THICK UT-O THICK UT-O OD
1. 6.50 <150 6.51 <150 51.0
2. 6.76 <150 6.60 <150 51.2
3. 6.96 <150 6.84 <150 51.0
4. 6.33 <150 6.43 <150 51.1
5. 6.70 <150 6.80 <150 51.2
6. 6.77 <150 6.65 <150 51.5
7. 6.33 <150 6.46 <150 51.0
8. 6.54 <150 6.64 <150 51.0
9. 6.62 <150 6.71 <150 51.2
10. 6.52 <150 6.60 <150 51.1
11. 6.76 <150 6.53 <150 51.3
12. 6.78 <150 6.61 <150 51.2
13. 6.43 <150 6.63 <150 51.1
14. 6.49 <150 6.64 <150 51.0
15. 6.79 <150 6.53 <150 51.2
16. 6.67 <150 6.54 <150 51.3
17. 6.92 <150 6.43 <150 51.2
18. 6.51 <150 6.52 <150 51.1
19. 6.67 <150 6.68 <150 51.1
20. 6.48 <150 6.67 <150 51.3
21. 6.68 <150 6.69 <150 51.1
22. 6.52 <150 6.64 <150 51.0
23. 6.84 <150 6.45 <150 51.0
24. 6.52 <150 6.81 <150 51.3
25. 6.98 <150 6.43 <150 51.2
26. 6.63 <150 6.53 <150 51.1
27. 6.45 <150 6.61 <150 51.0
28. 6.46 <150 6.47 <150 51.1
29. 6.42 <150 6.63 <150 51.2
30. 6.46 <150 6.59 <150 51.0
FSH-2(LOC-2)
Sr no. THICK UT-O THICK UT-O OD
SH-1 COILS
SR NO. THICK UT-O OD
1. 5.3 <150 51.2
2. 5.4 <150 51.1
3. 5.0 <150 51.1
4. 5.1 <150 51.2
5. 5.0 <150 51.0
6. 5.2 <150 51.0
7. 5.1 <150 51.1
8. 5.3 <150 51.2
9. 5.4 <150 51.0
10. 5.2 <150 51.4
11. 5.3 <150 51.1
12. 5.4 <150 51.0
13. 5.3 <150 51.2
14. 5.4 <150 51.1
Residual Life Assessment study of HRSG Page No. 90
Report No. F136/RLA/KRIBHCO/BLR1/07/2017
ENERGO ENGINEERING PROJECTS LIMITED KRIBHCO SHYAM FERTILIZERS
15. 5.4 <150 51.1
16. 5.6 <150 51.0
17. 5.4 <150 51.0
18. 5.2 <150 51.1
19. 5.3 <150 51.3
20. 5.0 <150 51.1
21. 5.6 <150 51.1
22. 5.5 <150 51.0
23. 5.4 <150 51.2
24. 5.2 <150 51.0
25. 5.4 <150 51.0
26. 5.0 <150 51.0
27. 5.2 <150 51.1
28. 5.6 <150 51.0
29. 5.3 <150 51.1
30. 5.4 <150 51.0