You are on page 1of 16

Doc No.

: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

METHOD OF STATEMENT OF
TRACK ATO-SYSTEM
EQUIPMENT

SIEMENS ATO TRACK SYSTEM


NAME DEPARTMENT POSITION DATE SIGNATURE

PREPARED
BY:

REVIEWED
BY:

REVIEWED
BY:

APPROVED
BY
Note: No part of this publication may be reproduced, stored
LRT LINE 2 EAST
in a retrieval system, or transmitted, in any form or by any
(MASINAG) EXTENSION
means, electronic, mechanical, photocopying, recording, or
PROJECT
otherwise, without the written permission of REC.

Sheet No. : 1 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

TABLE OF CONTENTS
1 INTRODUCTION

1.1 Objective 3

1.2 Scope of Work 3

1.3 Document Validity 3

1.4 Abbreviation 4

2 TOOLS and MATERIALS REQUIRED 5

2.1 Loops and Loop Feed Unit 5

2.2 Cabinet Equipment 6

3 INSTALLATION OF TRACK FIELD EQUIPMENT 7

3.1 Site Preparation 7

3.1.1 Pre- Installation Site Survey 7

3.1.2 Preparatory Work 7

3.2 Installation of ATO Marker 8

3.3 Installation of Cabinet 12

4 SAFETY AND HEALTH INFORMATION 13

4.1 Railway of Safety 13

4.2 General Safety 13

4.3 Representation of Information 14

4.4 Contingency Plan 14

Sheet No. : 2 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

1. INTRODUCTION

1.1. OBJECTIVE
This Installation Procedure Siemens Track ATO System Equipment provides, as a regulation, a
summary description of the activities for installation of the track ATO Loop for or this reason,
the installation instructions are accompanied by a drawing which provides a fast, efficient
means of establishing the final installation which is required in each case.

1.2. Scope of Work


This method statement covers supply of required Consumables, Tools and Equipment and
Safety Instructions. This document will also be used for instruction of the personnel, who are
installing the ATO Cabin. The Installation Procedure Siemens ATO Marker installation contains
the following information about the ATO Loop Feed Unit :

 Storage and transport


 Health and Safety
 Determination of mounting location
 Instructions for installation activity

1.3. Document Validity


The document is valid for the installation of the Siemens Track ATO System on the LRTA- Line
2 East Extension project and will be updated if needed.

Sheet No. : 3 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

1.4. Abbreviation

ABBREVIATION MEANING
ATO Automatic Train Operation
ATP Automatic Train Protection
N/A Not Applicable
TC Track Circuits
EMT1 Entry Marker, Track 1.
XMT1 Exit Marker, Track 1.
EMT2 Entry Marker, Track 2.
XMT2 Exit marker, Track 2.
COM. Quad Core cable for communications
LCU Line Connection Unit
LFU Loop Feed Unit
EVCE Enhance Vital Communication Equipment
EVSE Enhance Vital Slave Equipment
CON1 Connector 1
CTC Control Traffic Center
DIP Digital Input
DOP Digital Output

2. TOOLS and MATERIALS REQUIRED

In order to correctly carry out the installation work, the site personnel must have all necessary
tools available.

Sheet No. : 4 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

2.1. Installation of loops and loop feed units

Tools Required Quantity bring in Quantity bring out


Head Torch
Non-conductive measuring tape
Marking Pen
Red Flashing Lights (Engineering Works)
First Aid Kit
Walkie Talkie
Track Trolley
Screwdriver set.
Spanner set.
Wire stripper.
Side cutters.
Round terminal crimping tool. (Ref.:
WEIDMULLER CTI 6 )
Drill for drilling the plinth. f 6mm and f 8mm.
Hammer
Round Nose Shovel
Track Trolley
Torque Wrench
Others:
Inspected by: Date: Location:
Please ensure the below tools are properly remove from the working site.

Sheet No. : 5 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

Materials Supplied Quantity Remarks


ATO cabinet.
Quad (one for each marker and communications)
Loop cable.
L.F.U. (Loop Feed Unit).
Staples for fixing the loop to the rail.
Clamps (f 14mm) for fixing the loop to the plinths
and ground.
Materials Consumables
Heat shrinks for end of stripped cable.
Plugs and screws M8 for fixing the loop feed unit
bases in place.
Drill bitf 6mm .
Drill bitf 8mm.
Others:
Inspected by: Date: Location:
Please ensure the below tools are properly remove from the working site.

2.2. Installation cabinet equipment.


Tools Required Quantity bring in Quantity bring out
Head Torch
Non-conductive measuring tape
Marking Pen
First Aid Kit
Two way radio
Track Trolley
Torque Wrench
Screwdriver set.
Spanner set.
Wire stripper.
Side cutters.
Others:
Inspected by: Date: Location:
Please ensure the below tools are properly remove from the working site.

Sheet No. : 6 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

Materials Supplied Quantity Remarks


ATO cabinet.
Quad (one for each marker and communications)
Loop cable.
L.F.U. (Loop Feed Unit).
Staples for fixing the loop to the rail.
Clamps ( f 14mm) for fixing the loop to the plinths
and ground.
Materials Consumables
Heatshrink for end of sripped cable.
Plugs and screws M8 for fixing the loop feed unit
bases in place.
Drill bitf 6mm .
Drill bitf 8mm.
Others:
Inspected by: Date: Location:
Please ensure the below tools are properly remove from the working site.

3. INSTALLATION OF TRACK FIELD EQUIPMENT

3.1. Site preparation

3.1.1 Pre-installation site survey Prior to any installation work on site, the equipment
installation position will be marked on the dedicated location using a yellow or white
marking pen according to the chainages given by the approved Design Plan drawing. The
ATO markers installation positions (chainages) on the Design Plan will be used as guidance
only as the exact installation position is subjected to actual site conditions.

3.1.2 Preparatory work


 Installation positions for the. The ATO markers location are provided by Siemens. The
positions are mentioned in the respective Design plan.
 A site survey must be performed beforehand to be sure that the. The ATO markers
counter can be installed at the given mounting location.
 The mounting location of the . The ATO markers must be clearly identified.
The mounting location must fulfil the preconditions which are given at
Section 3.1.1.

Sheet No. : 7 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

 The installation can only be done under a possession. Therefore a possession


must be booked for the installation.
 All necessary tools for installation must be available, please refer to chapter 2
No moisture must be allowed to enter the trackside Loop[ Feed Unit box.
Check that necessary cable pipes and troughing is present and ready.
Do not unpack the . The ATO markers wheel until you reach the mounting location.
Before each installation or reinstallation, grease the threads of the fastening
screws with Molykote G-N Plus or G-Rapid Plus to make them easier to undo
the next time.
 Check the code number on the ATO markers housing to ensure you
have the correct variant for the relevant application

3.2. Installation of ATO Marker


The ATO markers are installed referenced to the train stopping point on the platform and
therefore, an essential prior condition is that the train stopping be fixed in order to establish the
marker locations. An ATO marker consist of a loop and a power supply unit (loop feed unit).
Depending on the marker geometry in function of the train’s direction, a distinction is made
between entry and exit markers.

Two markers are located on each track. The entry marker is positioned 70 metres before the
stopping point. The exit marker is positioned 90 metres after the stopping point. The reference
for the marker distance is taken with respect to the route cross made in the loop.

Sheet No. : 8 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

NOTE: S.P. = Stopping Point.

The thick arrows indicate the direction of train movement on each of the tracks.
The installation will be the same for all stations. Only in a situation where the marker position
interferes with the installation of tuning units, short-circuit loops, points, points machines or
other components which are installed on the track will it be necessary to move it so that it is free
of these obstacles. It might also occur, that due to points operation and layout requirements
along the track that the exit markers for certain stations have to be located at a distance greater
than 90 metres from the stopping point in order not to interfere with the points positioned at the
station exit and so that the train is able to capture the marker from any of the platforms. Under
these circumstances, the marker is to be located within the track circuit after the points, as close
as possible to the stopping point, but maintaining a minimum five metres separation from the
tuning unit to the end of the loop
The loop is to be installed between the rails and fixed to the interior face of the outer rail and to
the track, as shown in the following diagram. Special staples are used to fix the loop to the rail.
Clamps are used to fix it to each of the plinths. Double clamps may be used for the route cross
zone. The start, end and loop route cross must coincide with a plinth in order to correctly fix the
loop in place.
The markers are not to be positioned in the termination zones, in other words, between the
tuning unit and the short-circuit loops.
The loop ends of a marker must be separated by at least five metres from the tuning units. The
stopping points should not be established within the parking track circuit body, this means not
within the space between the tuning unit and the short-circuit loop. The construction of the loop
to the L.F.U. is always to be made from one end, just as shown in the diagram. Loop dimensions
are as follows:

Sheet No. : 9 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

Short loop from 1.5 to 1.8 meters.


Long loop From 5.5 to 6 metres.
Width 0.5 metres.

Over a smooth bed, the loop should be constructed with the maximum dimensions. If this is not
possible because of track obstacles, loop must be constructed between the indicated tolerances.
The route cross is to be made as shown in the diagram. A single cross should be made at one
end, and the wires are then taken parallel until they separate in order to continue with each of
the loops.

Loop Feed Unit (L.F.U.)

The L.F.U. will be mounted onto the face closest to the marker, at a distance of 0.5 to 1 metre
from them to the ground. In those cases in which this set-up is not possible, it will be attached
to the ground, next to the track, at a distance of always less than 3 metres from the place where
the loop exits.

The quad from the LFU to the cabinet will be connected directly to the ATO equipment in the
interlocking room without passing through any trackside disconnection box. For this design
will be used the same canalization between the two tracks than for the rest of the cables. The
quad cable must be fixed to the viaduct in the same way that the loop cable. The quad is an
armoured cable (already protected) and the tracks are ballast-less (therefore no tamping

Sheet No. : 10 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

machines to worry about damaging "invisible" cables), so it is not necessary additional


protection for this cable. The power supply wire to the LFU that comes from the On-track Unit
will be connected as in next figure. It is a quad wire measuring 4 x 1 x 1.3 mm², leaving two of
the wires as a reserve. The earth connection will not be connected to the LFU. The external
dimensions of the LFU are:
Width: 248 mm
Length: 270 mm
Height: 140 mm

Round yellow terminals To loop


4 mm section

2 1
Whitout terminal, rigid
4 3
cable. A a round shape
6 5
must be done.
8 7

10 9
12 11

Earth connection
From
cabinet Spare

heatshrink

As a general rule, 4 markers will be installed at each of the stations on the line (2 entrance
markers and 2 exit markers; the markers on each track display the same message). Special care
must be taken when passing the cable through the LFU connectors. The interior minimum rings
should be removed from the compression glands so that after tightening the nuts the
compartment is leak-tight and will not allow water or dust to enter. In the case of MMRLT2, the
LFU is to be mounted on the plinth, taking train clearance into account. For the same reason, the
cover screws have to be correctly adjusted.

Sheet No. : 11 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

The loop cable may be stripped in concentric layers so that a smaller diameter sheath passes
through the compression gland. The following diagram shows the assembly sequence for these
components: In the case of connecting the four-wire cable from the cabinet to the LFU, where
the cable sheath cannot be stripped in several layers, further layers are to be removed from the
compression gland until the cable fits and can be inserted into the box.
3.2 Installation of ATO Cabinet
The ATO rack is installed in a cabinet, which, in addition to the actual ATO equipment itself,
also holds the LCU (Line Connection Unit) and the power supply (50 Vdc) if the equipment is
an EVS. The rack is supplied already wired and on site it is only necessary to connect the 220
Vac and 50 Vdc power supplies (in the case of an EVCE), the marker connections and those for
communications with the other equipment. These connections are made via a block with
terminals grouped five by five, together with a marker that identifies each block. In addition,
when dealing with an EVCE, it will be necessary to connect a communications cable with the
Westrace. This cable is used to receive variable information from the CTC. Connecting this cable
is very easy. The ATO equipment end is connected by means of a 75-pin female connector
(CON 1) and the Westrace end is connected via two connectors identified as DIP and DOP in
the slots specified on the station wiring drawings.

EMT1 = Entry Marker, Track 1.


XMT1 = Exit Marker, Track 1.
EMT2 = Entry Marker, Track 2.
XMT2 = Exit marker, Track 2.
COM. = quad cable for communications with neighbouring equipment.
The second quad communications cable is only connected when dealing with an intermediate
unit within a communications node.
To connect the screen, a cable must be solded to the quad screen cable and a terminal must be
crimped in this cable.

Sheet No. : 12 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

4. SAFETY AND HEALTH INFORMATION

This section contains general safety information which is of fundamental importance. Specific
safety information is given in context in the relevant sections.

4.1 Railway safety

Before, during and after working on the track, site safety is a main priority. The installation of
Siemens Track ATO System shall be in accordance with the approved railway safety plan or
railway safety instruction.

4.2 General Safety

The personnel shall be wearing safety clothing, safety shoes and also a safety helmet if working
close to machinery. Access to the site shall be in accordance to the valid railway safety plan
and the safety instructions. During installation work, there will be situations where work has
to be performed in surface level, during this work working positions should be carefully
considered, use of kneepads or a low stool to this part of the work is recommended.

Sheet No. : 13 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

4.3 Representation of safety information

Where hazards to personnel and equipment cannot be excluded, these are indicated by means
of pictograms, which are explained below. Meaning of the symbols and pictograms used in this
manual:

DANGER
Death or serious injury will occur if you do not take the precautions described.

WARNING
Death or serious injury may occur if you do not take the precautions described

4.4 Contingency Plan / Emergency Procedure

This section of the Method Statement outlines the contingency plan and emergency procedure
for the installation works described in this document.
In case an incident occurred, the on-site person in charge shall follow the step as below:

Sheet No. : 14 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

STEPS PROCEDURE
1 Stop the installation work.
2 Make sure the current installing work is with no potential risk on falling.
3 Make sure all workers are safe and with no potential risks to others.
In case the incident seems major or human life involved, on-site person in charge shall
4 report to station controller / yard master / OCC and Duty Engineer (when
appropriate) immediately.
Investigate the situation of problem and report to Siemens according to the priority of
5
SIEMENS – Site Emergency Response Team Contact List immediately.
Installation Engineer and Deputy Emergency Coordinator shall report to Siemens
6
Project Manager or Safety Manager for further instructions.
Siemens Project Manager and Safety Manager shall responsible for first screening of
7 the incident and follow the procedures of crisis management which stated in the latest
revision of “Crisis Management Plan”.
Siemens Installation Engineer shall discuss with LRTA Line 2 representative to
8 propose the remedial or contingency actions. With the consent is granted, take the
remedial or contingency actions.
After take the remedial or contingency actions, the Safety Manager should assess the
9
environment again.

Sheet No. : 15 of 16
Doc No.: BEC-QMS-OP- SIG-1000
DATE: 24/07/2018
REVISION: 0

Contact List –Site Emergency Response Team


Mobile Office
Priority Position Name
Phone Telephone
Night (TBD) TBD TBD
1 Safety Supervisor
Day (TBD) TBD TBD
Site Engineer (Indoor Night (TBD) TBD TBD
1
Team) Day (TBD) TBD TBD
Site Engineer (Outdoor Night (TBD) TBD TBD
1 Equipment Installation
Team) Day (TBD) TBD TBD
Site Engineer (Cable Night (TBD) TBD TBD
1
Laying Team) Day (TBD) TBD TBD
2 Project Manager Night /Day (TBD) TBD TBD
2 Emergency Coordinator Night /Day (TBD) TBD TBD
2 Project Director Night /Day (TBD) TBD TBD
For Site Engineer / emergency response person, please refer to individual team

Sheet No. : 16 of 16

You might also like