1. In your report you are to submit a description of each on of the system listed
below. You are to number them and arrange them in order that they are shown
above. After the each description you are to include the sketch of that system.
The description in each system must include the purpose of each major
component. You shall include as much detail as you can obtain about the
system, such as line size, pump capacity and head, motor horse power, heat
exchanger duty, etc. this information can be obtain from equipment name
plate, valves or fitting. O&M manuals
b. Auxiliary Steam
Answer : to distribution feed water from cascade tank to boiler from
boiler steam will circulation using boiler circulation pump,
d. Main Condensate
Answer : to make use cascade tank ,water filling from cascade to boiler
an return to cascade again and purpose to distribution fuel oil from service
tank to the boiler as F.O water boiler tube
NAME : MUHAMAD SENDY NUGROHO
Continoue answer no 1
e. Feed Water
Answer : distributing feed water within the drum using fuel water pump,
fuel oil piping brain as part of the package burner assembly purpose to
distribution F.O burner unit in order can happen ignition burner
b. Boiler water level – include in your discussion how the feed water
regulator operates and the interrationship of the feedwater regulator to
the feed pump discharge pressure. How is the feed pump discharge
pressure setting selected ?
Answer : the level gauge important to check for propeller water level
in the boiler unit switch is provided on the delivery side of the feed
water pump and is a protect the feed water pump. This pressure switch
is provided to prevent bobble and it is set a 13,5 kg/cm2 if the pressure
is exceeded the circulated stop the boiler electrically
full ahead because at port boiler use fuel and burning in the
heater tube only 350oc at sea (full ahead) boiler running use exhaust
gas M/E temperature exhaust gas M/E is 470oc automatically
temperature in the boiler water tube increase ,pressure will increase.
NAME : MUHAMAD SENDY NUGROHO
clean burner
-take out pilot main body
-open insulation holder
-take out all nozzle clean with cerosin
-take out swizler and clean with cerosin
NAME : MUHAMAD SENDY NUGROHO
d. Manually control the boiler firing rate using the combustion control
system ,i.e., changing the system from automatic to manual and back
to automatic, as well as how to make proper adjustments to the
systems while it is in manual mode.
Answer : -set the burner select switch
-turn on the combustion switch
-perform pre purge for about 35 second
-start the combustion after several second and combustion lamp light
-steam pressure rises the pressure s/w set valve incase of 3 position
control -high combustion = low combustion- stop
manual run
-auto/manual select with position manual
-fan switch on before start 50 second
-FO p/p switch on
-pilot and ignition switch on
-check firing low combustion switch on
-pilot and ignition switch off
a. Calculated the slip on the ship explain why the slip is either positive or
negative
Answer :total number of revolutions the propeller made over 24
hours
(1 today) Slip of the ship
Slip : distance by propeller-distance over ground
.
𝐷𝐼𝑆𝑇𝐴𝑁𝐶𝐸 𝑃𝑅𝑂𝑃𝐸𝐿𝐿𝐸𝑅 − 𝐷𝐼𝑆𝑇𝐴𝑁𝐶𝐸 𝐵𝑌 𝑂𝑉𝐸𝑅 𝐺𝑅𝑂𝑈𝑁𝐷
SLIP % = 𝑥100
𝐷𝐼𝑆𝑇𝐴𝑁𝐶𝐸 𝑃𝑅𝑂𝑃𝐸𝐿𝐿𝐸𝑅
275 − 220
𝑥100 = 20 %
275
Slip postive : speed of ship more fast, cause wind come from
behind ship and ship follow ttides
Slip negative : speed of ship became slow, cause wind come from
in front of ship and ship in to the tides
book symbols and give their meanings. Describe your bell book entry
if an unusual jarring motion is felt during maneuvering.
c. Explain the reason for the bell book list the bell book symbols and
give their meanings. Describe your bell book entry if an unusual
jarring motion is felt during maneuvering
Answer : ball book it the maneuvering book, we fill with code ,if we
want to maneuver, or departure or arrival.
d. Calculate the total even usage for the day while steaming. Provide
your calculated answer in units of gallons, barrels. Pounds, long tons,
and metric tons. Calculate the fuel usage in barrels for one day in port.
If you are in port for less than one day extrapolate the in. Port to the
as-sea fuel usage calculate the ship’s operating fuel rate (
1BF1E/SHP.HP)
e. Record the total on board distilled and portable water from one day to
the next. Calculate the tons of water produced by the distiller during
for the day. Calculate the water consumption for the day in long tons
and gallons.
NAME : MUHAMAD SENDY NUGROHO
i. High water level in the boiler (include procedures to follow when you can
observe the level in the gauges glass, and when the level is out of sight)
Answer: -check and reduce firing rol
-operated how down system
-check feed valves
-if bad water hummer due to carry over expensed close steam outlet valve
j. Low water level in the boiler (include procedures to follow when you can
observe the level in the gage glass, and when the level out of sight)
Answer: shut off burner (if not cut-of automatically) take the boiler out off
load , ensure no internal damage due to overheating.
NAME : MUHAMAD SENDY NUGROHO
6. Inspect the boilers aboard your vessel and read the manufacturers’ manual.
Provide a detailed description of the boilers completely classifying the boiler
and describing the construction features incorporated in the boilers. Include
capacity, rating, and other design data.
Answer:
The boiler a board your vessel and read the manufactures manual. Provide a
detailed description of the boilers by completely classifying the boilers and
describing the construction features incorporated in the boilers include
capacity rating and other design data.
7. Describe the process and equipment involved in the following functions of the
boiler systems of your ship :
d. Delivery of air for combustion from its source through its entry into
the furnace
Answer:
-to control flow air necessary for combustion oil the boiler forced dist
fan
-the forced draft fan which s and s air to the boiler uses motor to rotate
the impeller to secure pressure and volume
Type : S1627
NAME : MUHAMAD SENDY NUGROHO
8. Describe the boiler water-chemistry test. Explain what the test are performed,
what is being tasted for, the chemicals that are used in the testing, the limits of
acceptable tests reading, and the corrective actions to be taken when the level
are high and low. Summarize the test result for one day of testing and any
adjustment made to the water chemistry
Answer:
- use condensate
- use oxygen control
- use liquid treat
* p. Alkanity test
PH. Test :
7,5 – 14.0 for boiler water
6,5 – 10.0 for condensate water
* chloride test
1. for boiler under 30 bar (kg/cm2) take a 50 ml sample water in the stoppered .
bottle provided
2. add one chloride tablet and shake to disintegrate , sample should be turn . .
. yellow if chlorides are present
3. repeat tablet addition until yellow color change to orange or brown
#Normal rangers
- P Alkanity 100-300 bar/ppm
- chloride 200 ppm max
- ph Boiler 9.5-11
- ph condensate 8.5-9.0
Sketch is attached…
NAME : MUHAMAD SENDY NUGROHO
10. What is boiler design efficiency, the design stack temperature and the design
excess air percentage for the boilers on your ship? What instrumentation is
available to measure these parameters during boiler operation? Record data
for one-week period of steady steaming. Compare your readings with the
design performance and explain any deviation. If stack gas analysis
instrumentation is not available, explain how the boilers are operated at
optimum efficiency without it.
Answer: boiler can operation for combustion using fuel oil can using heavy
fuel oil and diesel oil(HSFO and D.O), the boiler design aft boer the design
start temperature 18kg and design excess air percentage for the boiler per day
2 ton
NAME : MUHAMAD SENDY NUGROHO
11. Inspect the main propulsion reduction gear unit aboard your vassel and study
the manual. Provide a description of the main propulsion turbine and
reduction gear unit. Include classification, rating, performance, and weights of
major parts. Provide narrative description where appropriate.
12. Inspect the main propulsion reduction gear aboard your vessel and study the
manufacturer’s manual. Provide a description of the main propulsion turbines.
Include classifications, ratings, performance, and weights of major parts.
Provide narrative description where appropriate and summarize equipment
data in table from where appropriate.
13. Prepare a detailed sectional drawing of the following using the manufacture’s
manual. Be sure to show the arrangement of all the nozzles, diaphragms,
stationary blades, rotating blades, seals, and bearings on the turbine, and the
arrangement of all of the gears and bearings on the reductions gear assembly
14. Describe each of the following components and systems as they pertain to the
turbo generator on board your ship. If the ship isn’t equiped with a turbo
generator or if the information is unavailable, use the typical main population
turbine and reduction gear unit as found in your references. Provide a detailed
drawing where indicated.
15. Describe the equipment installed on your ship’s main propulsion turbine and
gear unit that perform the following functions provide a detailed drawing
where indicated
16. Describe the redundancy built into the steam ship plant for the following
system and how to operate the plant under emergency condition :
1. In your report you are to submit a description of each on of the system listed
below. You are to number them and arrange them in order that they are shown
above. After the each description you are to include the sketch of that system.
The description in each system must include the purpose of each major
component. You shall include as much detail as you can obtain about the
system, such as line size, pump capacity and head, motor horse power, heat
exchanger duty, etc. this information can be obtain from equipment name
plate, valves or fitting.
a. Aux. steam system ( must include the entire steam system that originates
from both the waste heat and aux. boiler
b. Condensate and feed water system
c. Make up water system
d. Ship fuel oil service up to the aux. boiler
e. Fuel oil piping as part of the package burner assembly
Answer No. 1
d) Fuel oil piping drain as part of the package burner assemay purpose to
distribution.
NAME : MUHAMAD SENDY NUGROHO
2. Describe the functions of the waste head and auxiliary boiler on your ship
include a description as to how to bring the auxiliary and the waste heat
boilers up to pressure and place them in service.
Auto run
- Auto /man select switch position “auto”
- Turn on the combustion switch
- Perforin pre purge for about 35 second
- Start combustion after several second the combustion switch
- If use D.O heater “off”
- If use F.O heater ON “auto”
NAME : MUHAMAD SENDY NUGROHO
c. Manually control the firing rate of the auxiliary boiler, i.e., changing the
system from automatic to manual and back to automatic, as well as how to
make adjustments to the system while it is in manual mode
Answer: if we start boiler with manual mode we just change panel boiler
control box in manual mode
d. Manually operate the burner management system, i.e., manually lighting off
and securing burners when the automatic system is not functioning
Answer: turning of the F.D fan more 30 sec and also turning off ignition
operating switch on after that turning of the heavy oil solenoid valve turning
of the high/low control operating in the manual , turn on heater switch
adjustment of oil temperature by means of the temperature
Answer: total number of revolution the propeller made over a 24 hour today : ..
TOTAL RC 24 hours : 142197
Distance by OG : 275
Average speed : distance OG= 275 =11.45 knots
24 24
Rc total = Rc today-Rc yesterday =
RPM = TOTAL RC / 24 / 60 = 142197 / 24/ 60 = 98.7
Distance engine= Total RC x pitch propeller
=142197 x 3.667 / 1852 = 281
a. Calculate the slip of the ship. Explain why the slip is either positive or
negative
Answer: slip of the ship= distance engine.distance OBS
Distance engine
Slip postive : speed of ship more fast, cause wind come from
behind ship and ship follow ttides
Slip negative : speed of ship became slow, cause wind come from
in front of ship and ship in to the tides
c. Explain the reason for the bell book. List the bel book symbols and give their
meanings. Describe your bell book entry if an unusual jarring motion is felt
during maneuvering
Answer: when accident accured the bell book is very important because
record matters in the bell book, concerning engine operation during arrival or
departure and also during the change Rpm bell log book symbols : full ahead,
half head, slow head, dead slow head, stop, dead slow astern, slow astern, half
astern, full astern.
d. Calculate the total fuel usage for the day while steaming. Provide your
calculated answer in unit of gallons, barrels, pounds, long tons, and metric
ton. Calculate the barrels per nautical mile for the hull-steaming day.
Calculate the fuel usage in barrels for one day in port. If you are in port for
less the one day extrapolate , the in-port fuel usage for 24 hours. By
percentage, compare the in-port to the as-sea fuel usage. Calculate the ship’s
operating fuel rate (lbf1e1/SHIP-hr)
Answer: flow mater today 16673689
flow mater yesterday 16645752
calculate :today-yesterday =16673689-16645752=27937m3
1000
=27937 X 0,95 = 26540,15=26,5 metric ton
1000
e. Record the total on-board distilled and potable water from one day to the next.
Calculate the tons of water produced by the distiller during for the day.
Calculate the water consumption for the day ion long tons and gallons.
Answer: water produce by distiller 13.5 ton per day
water consumption about 8-9 ton per day
NAME : MUHAMAD SENDY NUGROHO
f. Boiler smoking +
Answer: -low oil temperature causes improper combustion if this accur
increase the temperature
-look the atomizer number to check
g. Water in the settler during changeover +
Answer: blow down, check leak in the settes
NAME : MUHAMAD SENDY NUGROHO
i. High boiler water level * (include procedures to follow when you can observe
the level in the gage glass, and when the level is out of sight)
Answer: high water level check and reduce firing rate and operate blow
down, and check return line from boiler to feed water pump and check
regulator valve automatically , if you find trouble stop feed water pump
j. Low boiler water level * (include procedures to follow when you can observe
the level in the gage glass , and when the levels is out of sight)
Answer: shut off burner/out off take boiler out of load ensure no internal
damage due to overheating, and check line from boiler feed water pump to
boiler if you fire trouble in the feed water pump please change to feed water
pump no 2
NAME : MUHAMAD SENDY NUGROHO
7. Inspect the Auxiliary and waste heat boiler installation aboard your vessel and
read the manufacture manual
Describe in detail the constrution of the Auxiliary and waste heat boiler,
aboard your vessel completely classify the boilers ac to the type of boiler and
the type ao water circulation, etc include the manufacture name, capacity and
pressure rating of the boiler, the physical location of the boiler on the ship.
Total heating surface, over all dimensions, number and size of tube, etc
include description of any safety shutdown device on the boiler
Prepare a detailed sectional drawing of both the Auxiliary boiler and the waste
heat boiler showing the arraggemeny of the heat transfer surface and the path
of combustion gas flow where appropriate, label the names of the heat transfer
surface, e.g, economizer, super heater, etc.
Answer :
Type of the fuel atomizer is pressure jet straight type variable burner combustion
rate is available by varying the fuel injection pressure
The burner nozzle atomized bad spray the supplied fuel effectively perform
ignition adn flame maintenance and burn fuel it is important part which affect
burning condition.
Fuel from the fuel pump is regraded and atomized through the nozzle hp after
passing the fuel heater, solenoid valve and burner nozzle pipe contact area with
air is widened and ignition combustion are done by a spark at the end of the
ignition rod the spark goes out in several second after ignition but the flame is
kept by plate.
NAME : MUHAMAD SENDY NUGROHO
9. Describe the equipment associated with the Auxiliary boiler that are involved
in the following function :
10. Prepare drawing of the following equipment, as they exsist on the Auxiliary
boiler on your ship. Use standard symbols and drawing procedures, label
completely.
Sketch is attached…
NAME : MUHAMAD SENDY NUGROHO
11. Explain the objectives of the boiler water chemical treatment program of you
vessel. Describe the tests that are made on the water an your ship’s Auxiliary
boiler. Include readings taken over a two week period. Describe how
decissons are made regarding blow down or chemical addition.
Answer No. 11
Aux test :
1. Take 200ml for sample
2. Add p. Alkalinity and shake for disintegerate. If p. Alkalinity is prevent
the sample with blow
3. Repeat addition until colour change in penetration yellow.
NAME : MUHAMAD SENDY NUGROHO
12. Describe the procedure you would follow for the following maintenance
activities on your ship’s boiler. If a particular section does not pertan to your
ship, use your references and describe the operation for a steam ship.
13. Inspect the turbogenerator turbing and reduction gear unit aboard your vassel
and study the manual. Provide a description of the main propulsion turbine
and reduction gear unit. Include classification, rating, performance, and
weights of major parts. Provide narrative description where appropriate and
summarizw equipment data in table form where appropriate (hunt subchapter
“steam turbine construction”)
Answer No. 13
In my ship no have reduction gear
NAME : MUHAMAD SENDY NUGROHO
Answer No. 14
In my ship no have reduction gear
NAME : MUHAMAD SENDY NUGROHO
15. Describe each of the following components and systems as they pertain to the
turbo generator on board your ship. If the ship isn’t equiped with a turbo
generator or if the information is unavailable, use the typical main population
turbine and reduction gear unit as found in your references. Provide a detailed
drawing where indicated.
Answer No. 15
In my ship not have reduction gear
NAME : MUHAMAD SENDY NUGROHO
16. Describe the equipment installed on your ship’s main propulsion turbine and
gear unit that perform the following functions provide a detailed drawing
where indicated
Answer No. 16
In my ship no have reduction gear
NAME : MUHAMAD SENDY NUGROHO
17. Describe the redundancy built into the steam ship plant for the following
system and how to operate the plant under emergency condition :
b. Failure of the starboard forced draft fan due to a short-circuited motor and
continued operation of the starboard boiler
Answer: fan tube of the start board force and draft fan so we have the
economizer and turbine for produce steam so can monitoring the operation
NAME : MUHAMAD SENDY NUGROHO
1. In your report you are to submit a description of each one of the systems listed
below. You are to number them and arrange them in the order thet they are
show above. After each description you are to include the two sketches of that
system (one finished and one rough-done in the engine room while tracing the
system). The description of each system must include the purpose of the
system and the purpose of the each major component. You shall include as
much detail as you can obtain about the system, such as line sizes, pump
capacity and head, motor horse power, heat exchanger duty, ect. This
information can be obtained from equipment nameplate, valves or fittings.
e. Auxiliary steam system (must include the entire steam system that originates
from both the waste heat and auxiliary boilers)
Answer:
2. Investigate the engine room operating console and turbine control device
4. Describe the ships service diesel generator engine in some detail, including
the following :
a. Classification
model :6EY18ALW
rated output/ revolution :500kW (680ps)/ 900 min-1 (rpm)
rated/voltage :AC450V/722A
cyl bore / stroke :180mm/280mm
effective press. :1.5560Mpa
mean speed speed :8.40m/s
max comb : 19.0 Mpa
cooling sys : fresh water and sea water
b. Governor control
consumption/day : 1.50 MT (HSFO)
c. rated output
AC450V/722A
d. collect operating data over an hour steady operation. Determine the
specific fuel consumption and compare your figure with the
manufacture figure
NAME : MUHAMAD SENDY NUGROHO
5. write description of the equipment that console both the waste heat boiler
steam pressure and aux. boiler water level
c. Calculate the total usage for the day and calculate the barrels per nautical
mile.
Answer:
d. Calculate the tons of water produced by the distiller during for the day.
Calculate the water consumption for the day in both long ton and gallons.
Answer:
NAME : MUHAMAD SENDY NUGROHO
f. Boiler smoking
Answer: -check fuel oil consumption
- Check forced draft fan
- Adjust forced draft fan
NAME : MUHAMAD SENDY NUGROHO
i. The procedures to follow in the event of high water level and low water level
in in the boiler.(competency 20.1.6.3)
Answer:
NAME : MUHAMAD SENDY NUGROHO
a. Change a burner
Answer:
-switch off boiler from panel (stop boiler)
-close inlet and outlet FO valve
-take out flame eye
-take out all fuel oil pipe
-take out burner upper plate
-change burner / take out the old burner and change to the new
-close all bolt burner upper plate
-connect all fuel oil pipe
-connect flame eye ( before must be clean) connect
-switch on boiler from panel
10. Inspect the gas turbine installation aboard your vessel and read the
manufacture manual. Provide. A detailed description of the gas turbine by
completely classifying the combustion chamber and describe the construction
feature incorporated into the gas turbine . include the horsepower, rpm rating,
fuel consumption and other design data
11. Describe the process and equipment involved in the following function of the
gas turbine system of your ship. Provide schematic drawing of each system
a. ignition of the fuel air mixture through the ignition system
b. fire direction and alarm
c. fire extinguishing systems
d. water washdown system
e. cooling air systems
f. ice detecting systems
g. fuel heating system
h. enclosure lighting system
12. Prepare drawing for the following system and or equipment as they exist in
the vessel to which you are assigned. Use standard symbols and drawing
procedures. Label completely
a. Propulsion fuel oil service system to each gas turbine including all
regulating valves and all automatic valves, heaters, filters,
filter/separators, back pressure regulator, emergency fuel trip valves,
and fuel maters
b. Air intake system including all ducting, filters, and cooling
c. Exhaust system including the exhaust collector, exhaust ducting, and
stack.
d. Hydraulic starting system including the hydraulic starting module,
hydraulic oil used, and clutch cooling system.
e. Lube oil system including all pumps, sumps and air jackets
f. Gas turbine hydraulic system including system attached pumps and
components served.
13. What design gas turbine efficiency, the design stack temperature and the
design excess air percentage for the unit on your ship? What instrumentation
is available to measure these parameters during the operation of the operation
of the gas turbine. Record the data for a one week period of steady operation.
Compare with the design performance and explain any deviations.
14. Prepare a discussion and drawing foe each of the following component of the
gas generator
a. compressor
b. combustor
c. high pressure turbine
d, accessory
15. Describe the procedure schedule maintenance program for the gas turbine a
board your ship.
16. Describe the function of each bleed air manifold welded on the turbine
17. List and explain each gas turbine prestart check manual start and automatic
start procedure
18. List and explain each of the automatic, manual and emergency shutdown
procedure
19. Control :
a. describe the control system for the engine. Include:
1. Types of input and output signals
2. Sensors
3. Redundancy of sensors and controls
4. Safety device and settings
5. Biasing of signals
20. For a multi engine application, discuss all operating combinations, nothing
advantages and disadvantages of each.
1. inspect the main propulsion turbine and reduction gear unit aboard your vessel
and study the manufactures manual. Prepare a detailed sectional view of the
gas turbine and the reduction gear. If your vessel is equipped with two sets of
gas turbine/reduction gear assemblies, prepare and explanation of the
rotational changer and place it in the drawing
2. provide a description of the main propulsion gas turbine and reduction gear
unit. Refer to the sectional drawings
3. describe each of the components and system listed below as they pertain to the
main gas turbine propulsion turbines and reduction gear units. Where
indicated, prepare a detailed drawing of the part of the system.
a. turbine radial and thrust bearing
b. High speed coupling shaft coupling to compressor
c. Reduction gear radial bearings
d. Main thrust bearing (drawing)
e. synchro-self shifting clutch
f. Power turbine break assembly
5. describe the startup and shut down procedures for the reduction gear and
reduction gear lube oil.
7. If any gas turbine gear failure accoured during your period aboard ship,
describe the nature of the failure, the cause and the correction. If not failure
occurred, then describe from your text of the ship technical manual two
possible failures, their causes and the correction.
1. In your notebook you are to submit a description of each one of the systems
listed below. You are to number them and arrange them in the order thet they
are show above. After each description you are to include the two sketches of
that system (one finished and one rough-done in the engine room while
tracing the system). The description of each system must include the purpose
of the system and the purpose of the each major component. You shall include
as much detail as you can obtain about the system, such as line sizes, pump
capacity and head, motor horse power, heat exchanger duty, ect. This
information can be obtained from equipment nameplate, valves or fittings.
changing air on the main engine and fresh water cooler through the
thermostatic valve the returning water is party reciculated through the pipe.
To maintenance constant temperature at inlet to coolers and partly sent
overboard.
Sketch is attached..
NAME : MUHAMAD SENDY NUGROHO
Answer No. 2
3. Write a descriptiom of the steps required to perform each of the operation below
Answer: -close the fuel oil inlet and outlet unscrew the union nut by means of
the hook spanner
-take out the injector if the injector is sticking use the special tool
-clean the injector bore in cylinder cover and check the seating in the bore for
marks which if any must be dominated
-fit the spring housing & tighten
-check the fuel oil high pressure
-check the adjustment of the high pressure pipe
Build : 2012
NAME : MUHAMAD SENDY NUGROHO
3. Prepare a detailed description of the steps required to start up the M/a F.O
system. Be sure to address the following in the description
a) Correct position of the valves
b) Method of fuel recirculation and heating
c) Swiching to H.F operation
Answer
4. Describe the maintenance program of the fuel injection system of the M/E.
Include what inspections and overhouls are made and the time schedule for
doing them. Discuss the procedure for testing and over houling the fuel
injection.
Answer No. 4
Fuel injection system
1) Replace with spare
2) Cleaning of nozzle, checking, automizing and adjusting of
nozzle/injection pressure
3) Cheking pressure regulating springs and filters one a year an board
procedure for tested and overhouling the fuel injector.
Put injector in injector tester and test the presure nd make sure injector be 450
kg/cm2 for pressure lower is 200kg/cm2 for mnimun pressure before renew the
injector we should be tested.
NAME : MUHAMAD SENDY NUGROHO
5. Describe the equipment and the procedures used in taking firing pressure and
or pressure indicator diagrams on the M/E provide a sample of the reading and
explain why they are taken.
Answer :
1) Plain meter
2) Mid ordinate methode
3) Counting the number of square if the diagrams is taken on aspecial square
type graph shut.
Procedure :
First blow through by opening the indicator cock partially to cleare soot and oil
accumulate in the indicator bore and protect cock against burning.
Before use the indicator should be hold warm by placking it on cylinder cover for
5 minute
With the indicator shold be closed trace the atmosphere line by pressing the
stylus against the paper while the drum is turn one or two timesmanually
Conneted the card line to indicator drive and open the indicator cock value and
press the styws against the paper to the drum at moment it moves up wards and
get pressure volume working diagram.
After replace the card from the indicator drive make a timming in take both
compression and maximum pressure on draw diagram by suitable pull the card
just quickly enough to draw on each cylinder.
NAME : MUHAMAD SENDY NUGROHO
6. Describe the chemical water treatment used on the fresh water cooling system.
What is the objective of the treatment plan and what do the chemical actually
do inside the system?
Answer No. 6
Cooling water treatment
The cooling water used for engine cooling should be prappely treated with an
approved cooling water inreberator alkaline against to avoid corotion attack
sludge scale deposite the following treatment are used
- Adjunct B (drew marine product)
NAME : MUHAMAD SENDY NUGROHO
7. Comment on the adequacy of the starting air system to supply air to the M/e
during manauvering operation, if both starting air compressors fail during
manauvering waht would be the proper procedure to follow. What would you
estimate be of how many starts you had left?
Answer :
Air recevoir must be at least 20 bar, but started to manuvering 25-26 bar of
course we used emergency compresser and we have only 3 times
NAME : MUHAMAD SENDY NUGROHO
8. Describe how the revesal of propeller thrust is obtained. If the engine direct
reversing, describe the engine mechanisme that allow it to start up and run in
the reverse diretion if a controllde pitch propeller is installed describe its
systems and mechanisms.
Answer :
Moucd C/R manouvering handle from stop to ahead position in one stroke
Respem acting
Reversing handle to the may ahead position the transfer to ahead indicator
lamp at E/C/R indicator lamp panel W/H manuvering starel lamp on when
the transfer complete the camsheet stopper is engaged.
NAME : MUHAMAD SENDY NUGROHO
9. Describe the L.O purification equipment used for the M/E L.O (filter,
centrifugal separators, or combination) include both operation and
maintenance.
Answer :
We used F.O purification for M/E L.o centrifugal separator type the operation of
purification M/E L.O
10. What are the crank web deflection reading and why are they important?
How and when are they taken aboard your ship?
Answer :
l.e webs open and close as the engine in the vertical as will as horizontal
direction we meansure also web betwen we got checked top bottom part bottom
STBD port and STBD cause the result after that we can calculation for checked
performance of engine we can find crank shaft alignment
deflection procedure
place a dial gauge opposite the crank pin on the part side and set the pioner /
pointer to zero looking in the forward direction and readed the dial gauge reading
every six months we have taken.
NAME : MUHAMAD SENDY NUGROHO
11. List and briefly desrible all afthe safety devices used to protect the N/E shall
be stopped or slow down under safety device automatic to protect any of
accident caused on the abnormally listed on the table there for the safety
device also has to be inspected the realiable funtion.
Answer :
Auto slow down slow down emoy/stop
Over speed - 130 Rpm
Low inlet press of L.O system - 1,2 kg km2
Low inlet press of piston cooling oil 15 kg / cm2 -
Low inlet press of T/C L.O - 0,7 kg/cm2
Low inlet press of C.S.W 0,5 kg/cm2 -
Fire in scavenging chamber fire -
Failur electric source - -
NAME : MUHAMAD SENDY NUGROHO
a. How does the governor react to steady increase in load placed on the
engine?
Answer: increasing the load on the prime mover at given speed have an
identical affection either case, the flyweights move in ward. (under speed) due
to either the increase in speeder spring force or to the increase in centrifugal
force caused by the decrease in primer mover speed as load. Is added the
movement of the fly weights is translate into a down ward movement of the
pilot plunger this directs pressure oil into the buffer system causing the buffer
piston. Forces the power piston to move toward the power cylinder. The oil
displaced by the move ment upwards in the increase direction.
b. What happens inside the fuel injections pumps are the governor reacts
to the increase in load?
Answer: Inside fuel injection pump will decrease amount fuel oil because the
governor cut off additional fuel needed for acceleration by stoping the power
piston when it reached a point corresponding to that amount of fuel reovired
for steady state operation at the new load.
c. Explain how draft, sea state, and rudder angle affect the load and the
fluctuation of the load on the main engine.
Answer: when draft increase load to increase at sea state rough load increases
a rudder angle increases load increases
13. Describe the bridge, control room and local control stations for the M/E
14. Explain in detail the procedures that should be followed in the following olant
emcy :
a. Low F.O pressure to the M/E
b. Serious fuel leak on the M/E fuel system
c. Excessive use of make up water to various expansion tanks
d. High exhoust temp from one cylinder
e. High exhaust temp from all cylinder
f. Block smoke from stack
g. High engine cooling water outlet temp
h. High engine bearing L.O temp
i. Crank case explosion
j. During manevvering the engine will not start in reverse direction
Answer :
F. AUXILIARY MACHINERY
1. In your notebook you are to submit a descriotion of one of the system listed
below. your are to number them and arrange them and arrange them in the
order that they are shawn above after each desciption.
Your are incluide the two scetches of the system (one finished andone rough –
done in the E/R while tracing the system). The description of each system
must incluide the purpose of the system and the purpose of each mayor
component. You shall incluide as much detail as you can abtain about the
ystems, such as liner izes, pump capacity and head motor horse power, heat
exchangers duty, etc This information can be obtained from equipmant name
plate, V/V of fittings.
2. Describe the our diesel engine unit on your vessel function of the unit ( Ship
service generator, emcy generator, cargo p/p engine, blow thruster engine, of
other ) name plate data location of the unit , and type of fuel burned.
Answer.:
Major of specification of generator
No 1, 2, and 3 generator
Engine model : Yanmar Diesel engine 6EY18ALW
Type : 6 Cylinder, 4 Stroke
Rated output/rev : 500kw (680 PS) / 900 min-1 (rpm)
Cylinder bore/stroke : 180 mm / 280 mm
Mean piston speed : 8.40m/s
Max combustion press : 19.0 Mpa
Firing order : 1-4-2-6-3-5-1
NAME : MUHAMAD SENDY NUGROHO
b. Engine speed
Answer: first remove the governor dial plate and turn synchronizer (speed
setting) if friction drive slip before reaching the required high speed setting
mark the intermediate and the synchronizer, for control room use handle
pneumatic system to move governor with hydraulic pump system, can control
speed engine
NAME : MUHAMAD SENDY NUGROHO
Answer:
- dissemble the nozzle
-check the outside of the nozzle for sulfuric acid corrosion. If you find lot of
corrosion replace the nozzle with a new one
-check if the nozzle valve moves easily.
-adjust the nozzle with the adjusting nut
-quickly operate the hand lever of the tester ( at rate of 2 or 3 strkes per second)
and examine the spray
-to check the leaks, apply a pressure of 2.0 Mpa lower than the specified opening
pressure. If only a little bit of fuel comes out of the nozzle tip. The nozzle can be
used again. After finish the adjusting you can tighten the lock nut.
-do the injection test again and check if the injection pressure is correct
-renew all O-ring of the fuel injection valve
6. Describe the chemical water treatment used on the auxiliary diesel cooling
water system. Describe the test, chemicals used and intervals between test.
Answer:
- fill the sample cup to the 25 ml mark with simple
- slide the open and of the valve assembly over the tapered tip of the titrest so . .
that it fist sugly to the reference line
- snap the tip of the titret at the score mark into the body of the tetrehor
- with the tip of the valve assembly immersed in the sample press the controlll
. bar firmly , but briefly to pull in a small amount , the contents will tive . . . . . .
abreen colour
- press the control bar again briefly to allow another small amount of sample to be
drawn in the ampule
- after each addition rock the entire assembly to mix the contenst of the . . . . .
ampule watch for color change from green to bright orange
- repeat step 6-7 until a permanent color change
- when the color of the liquid in the ampoule change to bright orange . . . . . .
remove the ampoule from the tit sector hold the ampule in a vertical position .
and check fully read the test result on the cycle opposite the liquid level
- satisfactory ranges NC 3,5-5,0 300 x 200
Chemical water treatment used for protection against corrosion in fresh water
cooling system the quality of cooling water is to be checked regular possible one
week. Normal ph valve should be 7-10, measure at 200C, and chloride
concertation which normally not to exceed 50 ppm (50 mg/liter) and every three
should be shore
NAME : MUHAMAD SENDY NUGROHO
8. Describe the lubricating oil analysis program used for the auxiliary diesel.
Include in your description the type of oil that is used in the engine, the
sampling procedures, and the test that are made onboard the ship. If oil
samples are sent out for analysis, who provides the service and what tests are
made on the oil.
9. Describe the lubricating oil purication equipment used for the auxiliary diesel
( filters, centrifugal separator, or combination). Include both operation
maintenance
Answer:
lubricating oil purification equipment for the auxiliary machinery on my ship used
filter and centrifugal separator
Operation start up
- start centrifugal separator by pressing push-button of the starter
- operate oil heater
- close the bowl, since bowl valve cyl open at the time of startup, supply water by
turning low pressure of rating water valve to the position of running
- after supplying the prescribed amount of fresh water into measuring water
hopper open globe valve and supply water ti the bowl
- after confirming that oil has been heated to the setting temperature , open feed
valve gravity to feed oil
- the open feed valve fully and set the feed rate by regulating pump by pass valve
Operation stopping
- close feed water valve
- stop the operation oil heater
- supply the fresh water into the measuring Hooper and by opening valve , poor
water on to push out of inside the bowl in order to decrease oil loss
- turn high pressure operating water to the position discharge and keep it for more
than 5 second
-it is very effective method to wash and clean the bowl inside by pouring water
into the bowl after sludge discharge and perform the discharge again
- turn low pressure operating water level to the position
- stop the motor
- apply brake when necessary
Maintained: bowl, vertical shaft part, dear pump, L.O , brake equipment,
operating water supply equipment, detector
the lubricating oil purification used lubricating oil filters is a duplex cartridge of
initial fineness of 0030 mm , maintenance a duplex cartridge type every one week
must be cleaned
NAME : MUHAMAD SENDY NUGROHO
10. Describe the fuel oil purification equipment used for the auxiliary diesel
(filters, centrifugal separator, or combination). Include both operation and
maintenance
Answer:
lubricating oil purification equipment for the auxiliary machinery on my ship used
filter and centrifugal seperator
Operation start up
- start centrifugal seperator by pressing push-button of the starter
- operate oi heater
- close the bowl, since bowl valve cylopen at the time of start up, suply water by
turning low pressure of rating water valve to the position of running
- after suplying the prescribed amount of fresh water into measuring water hopper
open globe valve and supply water ti the bowl
- after confirmins that oil has been heated to the prescrb temperature , open feed
valve gravity to feed oil
- the open feed valve fully and set the feed rate bt regulating pump by pass valve
Operation stoping
- close feed water valve
- stop the operation oil heater
- supply the fresh water into the measuring hooper and by opening valve , poor
water on to oush out oip inside the bowl in order to decrease oil loss
- turn high pressure operating water to te position discharge and keep it for more
than 5 second
-it is very efectife method to wash and clean the bowl inside by pouring water
into the bowl after sludge discharge and perform the discharge again
- turn low pressure operating wate rlodel to the position
- stop the motor
- apply brake when necessary
the fuel oil purification equipment used fuel oil filter is a duplex filter slit, type
filter element operation the filter element operation.
The filter is equiped with three way cock for change of both inlet and outlet side
ints single or double operations of the filters. Maintenance a duplex every 4 days
must cleaned
NAME : MUHAMAD SENDY NUGROHO
11. Describe the pistons on the auxiliary diesel engine. Include the type of piston,
the type of piston cooling, the type and number of compression rings, the type
and number of oil control rings, and the procedure for piston removeal/
reinstallation from the engine.
Answer: type of piston is mono block pistons with hardened ring groves , piston
cooling has a cooling oil space close to the piston crown and piston ring zone.
The type and number of compression is 3 compression ring
12. Describe the exhaust valves of the auxiliary diesel engine and their
maintenance program. Include what is actually done to the valves and the time
schedule between overhaul.
Answer:
Each cylinder head is made of cast iron and water cooled. The cylinder head has 4
valves : 2 intake valves and 2 exhaust valves. The fuel injection is at the centre.
For maintenance : do not use gas burner to remove carbon from the combustion
surface of the exhaust port. If the flame directly touched the exhaust valve seat, it
will be become loose. Check the cylinder head for crack and corrosion, clean the
water jacket with a descaling agent at least on time in 2 years,
NAME : MUHAMAD SENDY NUGROHO
13. Describe how a diesel engine cylinder liner wears during normal engine
operation how is the wear measured?
Answer: the cylinder liner is made of close grained, pearu be ast iron and is at the
tep provide with a collar resting on top of the frame al bottom the liner has a
guide with grove for two sealing ring which provide iontress againt the frame the
cylinder liner wear measured until 24.00 hours after must be overhoul exchanged
The internal gas pressure with the cylinder liner causes a tensile stress refred to as
hoop tensile stress, the cooling water pressure on the outside of the liner caused
by hoop compressure stress which however is so small that it has no anapprecable
effect when the engine is in operation the mean temperature on the inside surface
(gas side) of the liner is much higher than the outside (cooling water side)it is
procedure a temperature across the thicness of the lines is different being hoter
on the gas side the hitter on te side and cooler on the water side the hotter inside
part of liner troes to expand more than the outlet part in contact with the cooling
water this temperature diffenet and expansion restriction causes a thermal stress.
The thermal stress reduce the hoop stress (from gas pressure) on the inside of the
liner (gas side) and increase it an the outside (cooling water side) at the uppart of
cylinder liner in the region of the flange bending moment are set up when the
cylinder 1 s changing so the material of the cylinder liner is subject to cycle stress
patren care has herefore to be taken in the design of the liner to cobat failune due
to fahque.
NAME : MUHAMAD SENDY NUGROHO
14. With what classification society is your ship registered? Describe the
inspection the auxiliary diesel must undergo and the time schedules that must
be followed
Answer:
NAME : MUHAMAD SENDY NUGROHO
1. Describe the ship store refrigerator system aboard your ship, you must include
the capacity of the system, the type of system the refrigerant used (R12, R22,
R14A, or other) and the size normal contens and normal temp of each
refrigerated space of box.
Answer No 1
Refrigerator system in pos dedicator used R-404a for refrigerant
Normal temp for meat room is -16 oC
Normal temp for lobby room is 6 oC
Normal temp for vegetable room is +2 oC
2. Provide the name plate data for each of the following component in the ships
stores refrigerstor system , state the soorce of the name plate information if
it’s hot from the actual name plate
Answer No 2
a) Compresor
Q’ty : 2 sets
Capacity :
b) Compresor motor
Nominal output current insulation = 30 kw 9,0 A B class
No of pole x revolution = 4 P x 1750 mm -1
Manufacturer = Mitsubishi
c) Condensor
Type : Shell and fin tube
Shell size x efective length : 216,3 ᶲ x 1080 mm
Cooling surface : 2.42 m2
Tube material : C 6872 T
Tube plate material : NAVAL BRASS
Shell plate material : Mild steel Pipe
Water cover material : Cast iron
Water Quantity : 3.42 t/h
Head Loss : about 0,023 Mpa (2.3m H2O)
d) Receiver
The conensor is used as receiver
e) Suction to liquid heat exchanger (economizer)
Economizer working process same with evaporator if’s a modine for
choase the liquid in to gas . so far the liquid into gas, evaporator need
head from iron that’s way, we use paint for take air from engine room
NAME : MUHAMAD SENDY NUGROHO
1.(2) Trace the ship stores refrigeration system, draw a detailed schematic draw of
the ship store refrigeration system, shot all major components those refrigerant from
question.
NAME : MUHAMAD SENDY NUGROHO
3. All manual v/v all auto v/v, pressure gauge, thermometers pressure switch and
other show flow arrows and shot the normal operator pressure and temp for each
of the pressure gauge and and every component in the system indicated the time
of day the outside air temp and the sea water temp when the reading taken (if your
drawing each the necesaly data no credit will be given for the drawing)
Answer :
Show flow arrow and shot the normal operator, pressure and temp for each the
pressure gauge and for every component in the system indicated of a time of
day the outside are temp when the reading were taken.
NAME : MUHAMAD SENDY NUGROHO
If your compressor doesn’t have on item listed above, make note of if and
refer to your text in describing the item, doesn’t leave any part of the question
in answered.
a) Compressor
this raise the pressure of the low temperature and low pressure
refrigerant gas evaporated in the evaporator so that it can be easily
liquefied in the condenser
Capacity : 3200 w
Evaporating temp : -29.0 °C
Condensing temp : 40.0 °C
Revolution : approx. 3450 min-1
Motor power : 3.0 kW
b) We dont have mechanical seal, we using glonel packing
c) Lubricating system
Cap LO 2.0 liter DAPHNE FVC46D initial charge only
Oil separator filter to separate oil droplets with large specific gravity
according to the gravitation. The center of the circle further separates
NAME : MUHAMAD SENDY NUGROHO
them from the gas. The oil gathered at the bottom is automatically
returned to the crank case through capillaries
Type : cyclone model : RAC-RHS5BA
e) Method of protection against over pressure
f) Motor Enclosure
We use 3 phase motor with :
Output : 3.0 Kw AC440V, 60 Hz,3Ǿ
Rating Current : 5.7 A
Starting current : 48 A
Over current relay : 7.5 A
NAME : MUHAMAD SENDY NUGROHO
Answer: from compressor produced high pressure for going to condenser and
in condenser high pressure it will charge to find CO2 Hp it was cooled by sea
water that is we called unloading/high pressure how is work when unloading
done by keeping your inlet valve opened by passing high pressure line to
valve via solenoid valve
Answer: when the filled comes from evaporator or comes in compressor and
mixed with L.O for charge become to H, refrigeration system would the
compressor is fully loaded when gas low pressure goig enter compressor
mixed with lube oil only for lube oil (oil vapour with gas and help lubricating
piston) and at the time we called fully loading
c. Describe the method used to audits the under (capacity control system) and
explain how an engineer would know when the unloader is properly adjusted
Answer: we can detested unloaded is done or only keeping inlet vlve open by
passing a Hp to thhe valve using solenoid valve just setting the selenoid valve
and kept opened inlet valve pressure gague and selenoid valve
NAME : MUHAMAD SENDY NUGROHO
6. Describe each of the following control installed in the ship store refeigerstion
system, include an exploration of the purpose of the control, what each control
sense and how the control function during both normal and abnormal system
operation also where availble include the actula setting of each the control.
D. Thermostats
Answer: the power supply for electro magnetic valve can be opened or closed
by truning on or off a thermo swicth couple a with a cappiliary tabe by
allowine the temperature of condensor
7. Describe each of the following heat exchanger installed in the ship stores
referigerstion system include type number of pastes number outside diameter
and wall thickness of tubes material of construction low leaks are prevented
from mixing protecting againt over pressurization and prtection against
corrosion
a. Condensor
Answer: marine condensor are very subtitle to corosion and much research
has teen done to long then their use which halogen hdryocarbon refrigerats the
used of alminus or nickle tubes and sea water side
b. How a lower rate of evaporation in the evaporation coil causes in the valve to
close and reduce the flow rate of refrigerant through the coil
Answer: lower rate of evaporation in the evaporate coil the pending
temperature of from and thermal will give. Signal to control panel give order
to TVX increase of decrease in flow rate.
c. How an increase in the box temperature results in increase in the flow rate of
refrigerant through the evaporator coil
Answer: a started condition in the evaporator will result in a super heat witch
throught expansion of the liquid in the bub and cappilary will causes the valve
to open heater and increase flow of engineer
e. Why the when an engineer would want to adjust the TXV spring
compressionand how engineerwould dtermine whether the valve was properly
adjusted
Answer: the enginer would adjust the TVX spring compression for acheive
the temperatur we had regulated on refrigerant box and for het good cooling
and when the temperature in refrigerant box is too long running and indicate
NAME : MUHAMAD SENDY NUGROHO
9. Describe the proper produce for doing each of the following with the ships
store refrigeration system in your description refer to the schematic that you
prepare for question 3 indicated what v/v are opened, what v/v are closed the
sequence of evants is important to follow.
a. System stamp
Answer:
1. start cooling sea water through the condenser
2. check opening and closing condition of the following
a)valves opened during operation are:
-compressor suction and discharge valve
-strainer inlet and outlet valve
-valve for each gauge
b)valves closed during operation are refrigerant supply :
- refrigerant machine oil supply
- condenser purge air valve
3. switch the crank case heater on ( 2 hours before start)
4.start the fan
5.start the compressor
6. change the liquid the solenoid valve
b. System shutdown
Answer:
1. close the liquid line solenoid valve
2.after while coolant in the piping and cooler is returned
3.close the suction
4.stop the fan
5.switch the crank case heater off
6.stop water cooling to the condenser
c. Replacing a TVX
Answer: replacing a TVX is piping section concerned shall be extraded by
the compressor or when this is not possible by vacum unit after repair is the
parts that has been opened. Shall be vacumed coreful ly and check for leakage
d. Purging noncondensibies from thw system
NAME : MUHAMAD SENDY NUGROHO
Answer:
- stop the compressor , keep cooling water running for 20-30 minutes
- open the purge valve provided in upper eart of the condensor and remove air
and gas until the high pressure gets salvarted equalent to the cooling water
temperature
10. Describe how evoporator coil defrasting in the ship’s refrigerator system
freeze boxes perpormed on your ship include the following
c. The defrost cycle? (refer to the schematic that you prepared for
question 3.)
Answer: heat from refrigerant room
e. How the water (the melted ice) is removed from the freeze boxes?
Answer: close the by pass , pass valve to evaporator
14. Draw a schematic diagram of the air handing system. Include fan rooms and
supply. Exhaust and recirculating ducts.
a. And controls used to describe component a typical air handler unit ( preheat.
Cooling, and rehear coils)
Answer: steam heated coil
this coil heated the bolding supply air having the handling unit , sending
supply air to all of the rooms larging eleminating the need. For reheat coil
this coil uses a tube , in tube arrangement to prevent freezing in case the
system valve is off and fold out sideair is pressing.
-base board radiator
The primary function of the base board radiator it to prevent cold drafs
exterion watt and windows
-reheat coil
In thearly full before the cooling system has been shut down for the seas
b. List rating (air flow rate, motor KW or hp and speed.etc) also list the spaces
supplied with air from each fan. Indicate whether the air is unconditioned
(ventilation) or conditioned.
Answer:
Temp indoor outdoor
0
Cooling air 270 C 320C
Air heating 270C 320C
Summer winter
0
Room temperature 30 C -450C
Engine space woll 180C -120C
Galley 100C -180C
c. Describe the fans and motor used to supply outside airmthise used to
recirculated air. And those used to exhaust air
Answer: my ship used fan with air flow 120m3/main with to HZ motor output
3,7 x 4
d. Describe method regulated method regulated the amount recirculated air
Answer: we have regulated air and use method ventilation close and open
regulator
NAME : MUHAMAD SENDY NUGROHO
16. Describe each the following used for refrigeration system maintenance on your
vessel. Include typical operating procedures:
A. Service manifold
Answer: we must check the manifold for the pass ice and freon every 3
months
17. Describe the containers (tanks) used to store new refrigerant on your vessel
include the following:
a. Size
Answer :store is 12m2
b. Tare weight
Answer :118 kG
c. Color
Answer : silver
d. Markings
Answer :stainless stell
18. Describe the environmental laws and concerns that need to be addressed when
doing the following on a refrigeration system:
a. Charging a system
low pressure
b. Purging a system
d. Inplement
Blow of v/v of condensor
Standby close inlet v/v to condensor
If green light have and stoop condensor inlet v/v quickly
Inlet v/v aper to condensor a for after 2 or 3 minutes
compressor walked isn’t again.
NAME : MUHAMAD SENDY NUGROHO
19. Checking the refrigeration and air-conditioning system should be pan of the
routine of the vessel’s machinery spaces. Construct a table that includes the
following:
a) In column one, prepare a check list of all the readings that should be recorded
during an adequat reefer 6:A C round
Answer:
b) In the second column explain the importance of each of the readings. Listed in
column one
Answer:
c) In the third column, record actual readings that you took while performing a
round.(maske sure that you include units of measurement).
Answer:
d) Consult the manufacturer’s manuals and list in column 4 the rated or design
value for each reading that you recordedin column 3
Answer:
e) In column 5 discuss air differences between the designn condition and the
actual condition
Answer:
f) Explain how the choice of refrigerant for the system affect designsuction and
discharge pressures
Answer:
g) Explain how the desired refrigerated space temperature affects the compressor
suction pressure
Answer:
NAME : MUHAMAD SENDY NUGROHO
20. Describe the effects that each of the following would have on the operation of the
ship’s stores refrigeration or air conditioning system and how the engineer
should troubleshoot to determine the cause of each problem:
21. Describe any major repairs that were performed on the refrigeration or HVAC
equipment aboard our vessel