Professional Documents
Culture Documents
DHI-EHS-HSM-011
LIFTING OPERATIONS
Copyright This document is the property of Doosan Heavy Industries and Construction and all rights are
reserved in respect of it. This document may not be reproduced or disclosed in any manner what so ever, in
whole or in part, without the prior written consent of Doosan.
Doosan expressly disclaims any responsibility for or liability arising from the use
of this document by any third party. Copies printed are UNCONTROLLED.
To outline the minimum requirements for the use, operation and maintenance of cranes. Define the
competencies required and responsibilities for the Safe operation of this type of industrial equipment. Additional
control measures may be required depending on project and country requirements.
DEFINITION
Competent Person: An individual who has immediate knowledge of the subject, either by years
of experience in the specific field, formal education, or specialised training
pertaining to:
Vehicle Mounted Crane mounted on a vehicle / Crane Trucks for the principal purpose of
Cranes/Crane Trucks: loading and unloading such a vehicle.
Rigging: Work involving the use of mechanical load shifting equipment and
associated gear to move, place or secure a load including plant, equipment
or members of a building or structure and to ensure the stability of those
members and for the setting up and dismantling of cranes and hoists. The
definition does not include work performed by operators or drivers of
mechanical load shifting equipment, unless the work is part of the process
of setting up or dismantling cranes and hoists.
Banking/Dogging (Rigging- The application of slinging techniques including the selection and / or
Rigger): inspection of lifting gear, or the directing of a crane / hoist operator in the
movement of a load when the load is out of the operator’s view.
Slinging Techniques: The exercising of judgement in relation to the suitability and condition of
lifting gear, and the method of slinging, but consideration of the nature of
the load, its mass and its centre of gravity.
Certificate of Competency: A certificate issued in accordance with the national standard, and includes
evidence of a satisfactory assessment.
PROCEDURE
1.0 General
No person will use or operate any crane unless they have the required certificates of competency
and have valid authority to operate issued by the Site Manager in accordance with project
requirements.
When the possibility of lifting a load over other personnel working in the direct area exists, the foreman
in charge of the lift shall:
Notify foreman/supervisor in the area of the nature of the lift and the area the load and
boom shall be slewed over;
Prior to commencing the lift, the lifting Erection Contractor’s foreman must have
confirmation from his own and other Erection Contractor’s foremen who have personnel in the lift
area that those personnel have been advised of the lift and are clear of the direct path of the load
and boom travel radius.
A foreman who if notified of a pending lift shall immediately:
Assess the impact of the lift on his crew’s work area;
Notify the crew of the appropriate action;
Advise the lifting foreman / supervisor that a) and b) have been complied with.
Site Manager shall ensure that concrete filled drums are not lifted by reinforcing rod loop cast into the
concrete. Personnel involved in the lifting and moving of these drums must ensure that only approved
lifting gear is used when work of this nature is being carried out.
Drums shall not be used for lifting tools, fittings etc unless fitted into an approved drum lifter.
Site Manager and Contractors shall provide to the EHS Coordinator copies of crane manufacturers
manuals.
All cranes shall be fitted with operational anti free fall devices (auto troll or similar) and air conditioned
operator cabins.
Cranes shall not pick and carry loads on a fly or with a fly in the un-stowed position.
Safe access and egress to operator cabins for drivers and for maintenance personnel to other parts of
the crane shall be provided.
Where cranes are being moved around site the following is mandatory:
The free falling of loads is prohibited on site. All loads are to be lowered by means of power lowering or
positively engaged drive down system.
Cranes shall not lift on two hooks at the same time unless a risk assessment has been undertaken and
there is written confirmation from the manufacturer that the lifting method is within the design criteria of
the crane and does not compromise and Safety or integrity of the crane.
Under no circumstances can independent loads be lifted on two hooks at the same time.
All inspection, maintenance and repair records for cranes working on site shall be available for
inspection upon request.
2.0 Communication
Communication between crane operator and dogman/rigger shall be of such a type that will not interfere
with the operation of other equipment in the immediate or adjacent areas. If radio communication is to be
used, radios must first be approved by the Company and shall be fitted with an effective Safety lock-out
system that will prevent other persons from operating the same channel.
3.0 Training
The Site Manager is responsible for ensuring that the operators who are to operate any crane are
adequately trained and conversant in the following:
The verification of the competency of a person to operate a particular crane shall consist of:
National Certificate of Competency for the size and type of crane to be operated or specific
country competency.
A statement of medical suitability of the person to operate the crane including, eyesight, hearing,
depth perception etc;
An ability to read, write and understand the load charts for the crane(s) to be operated;
Having satisfactorily completed (prior to mobilisation) a competency assessment for the crane(s)
to be operated consisting of a combination of written and verbal test of the load charts, set-up
requirements, operating requirements, pre and post inspection and maintenance requirements
and operators EHS responsibilities;
Having satisfactorily completed an operating test demonstration in the operation of the crane and
set-up and erection of booms, jibs and flys.
Critical Lift More than one crane is utilised Critical Lift Plan
Critical Lift Plans shall be approved by the Site Manager after review by a suitably qualified competent
person (Engineer etc).
The Site Manager shall ensure in all instances that the mats provided under outriggers are of an
appropriate size to ensure the stability of the crane in all lifting operations and are suitable and adequate
for the prevailing ground conditions.
Relevant site information shall be obtained and potential hazards are to be identified, such as:
slings;
ropes;
The job method and sequence is developed to include hazard prevention control measures and safety
procedures.
The job feasibility and schedule are checked with other persons as necessary.
The job plan is developed to include hazard prevention / control measures and to applicable Standards,
codes of practice and equipment manufacturer’s specifications.
Daily pre-operational equipment checks are carried out in accordance with the checklist provided
for the crane and in accordance with the manufacturer’s recommendations;
The service log book for the crane is checked to ensure all service requirements have been met
and action taken as required;
Prior to operations, equipment and site area are visually checked for any evidence of interference,
and any faults reported to a supervisor for corrective action.
The operating and emergency controls and safety devices are located and identified and their correct
operation tested in accordance with prescribed procedures.
All communication equipment, lighting and alarm systems are checked for correct operation.
A Permit approved by the Site Manager is required for the use of crane hoisted work boxes.
The Permit shall only be valid for the specific task and where the task is in excess of one (1) working
day. The Permit shall be revalidated by the rigging supervisor ensuring that the relevant crane checks
are conducted prior to revalidation.
Defective controls, communication equipment, safety devices, lighting, or alarms are reported to
supervision for corrective action and the defects entered into the crane’s service log book.
The operating radii of the crane for planned operations is / are verified and measured taking into account
the estimated increase in radius due to boom deflection. The boom is slewed at the planned radii to
check that there are no unanticipated complications or obstructions.
The lifting gear must be tagged with the corresponding colour tag in accordance with in ‘DHI-EHS-HSM-
032 Inspection and Tagging’.
Supervisors / Superintendents shall provide a comprehensive risk assessment to the EHS Coordinator
for review, a minimum of 1 working day prior to the use of any crane hoisted workbox / man basket and
submit the completed permit application to the Site Manager for approval Appendix B - Crane Inspection
Checklist.
All cranes used to lift workboxes / man basket shall be fitted with a double acting or positively locking
safety catch on the crane hook, drive up and down controls for hoisting and luffing motions, be equipped
with controls that return to the neutral position when released and this action caused the motion to stop.
Personnel in the workbox / man basket shall be issued with, trained and instructed to wear a safety
harness that is attached to an approved anchorage at all times.
Access and egress from a workbox / man basket is prohibited except where approved by the Site
Manager following discussions with the EHS Manager.
A certificated rigger must be in the workbox / man basket at all times when elevated.
Radio communication on a dedicated individual crane channel shall be used at all times when using a
workbox / man basket. A minimum of 2 radios shall be used, in case of battery failure.
Gas cylinders or material other than essential tools etc and objects protruding outside the confines of the
workbox / man basket is not permitted.
The counterweight swing radius of the crane shall be barricaded and clear of obstructions.
Supervisors shall provide a comprehensive risk assessment to the EHS Coordinator for review, a
minimum of 1 working day prior to the use of any crane hoisted workbox / man basket and submit the
completed permit application to the Site Manager for approval.
All cranes used to lift workboxes / man basket shall be fitted with a double acting or positively locking
Safety catch on the crane hook, drive up and down controls for hoisting and slewing motions, be
equipped with controls that return to the neutral position when released and this action caused the
motion to stop.
Personnel in the workbox / man basket shall be issued with, trained and instructed to wear a Safety
harness that is attached to an approved anchorage at all times.
A certificated rigger must be in the workbox / man basket at all times when elevated.
Radio communication on a dedicated individual crane channel shall be used at all times when using a
workbox / man basket. A minimum of 2 radios shall be used, in case of battery failure.
Gas cylinders or material other than essential tools etc and objects protruding outside the confines of
the workbox / man basket is not permitted.
The counterweight swing radius of the crane shall be barricaded and clear of obstructions.
13.0 References
DHI-EHS-HSM-032 Inspection and Tagging
14.0 Appendix
Appendix A - Lifting Operations Risk Checklist
Appendix B - Crane Inspection Checklist
REMA
NO. DESCRIPTION CHECKED BY
RKS