Professional Documents
Culture Documents
Presented by :
Ir Wilson W. S. Mok
FICE CEng FHKIE RPE(Civil and Geotechnical)
1
Wilson W.S. Mok
Kowloon Bay
Location Plan
Wilson W. S. Mok 2
Wilson W.S. Mok
Scope of Works
Wilson W. S. Mok 3
Wilson W.S. Mok
2 nos. of DN 2800
Kai Tak Approach Channel Pipejacked Tunnel, each
350m Long
Open Trench
1 x 2800mm dia. TBM
(~140m long)
1 x 1200mm dia. TBM
2 x 1500mm dia. TBM
(~32m long each)
Open
Trench
Wilson W. S. Mok 7
Wilson W.S. Mok
Choose Slurry Pressure Balance Method in the Project due to Highly Variable
Ground Conditions
Wilson W. S. Mok 8
Wilson W.S. Mok
Wilson W. S. Mok 9
Wilson AW.S. Mok B C
Section A-A
A B C
Side Elevation
Section B-B
9 5
10
3
2 6
7 1
4
11 8
Pipejacking Operation –
Disc Cutters Cutting Analysis
Wilson W. S. Mok 13
Wilson W.S. Mok
Wilson W. S. Mok 16
Wilson W.S. Mok 5. Backfilling and
reinstatement
1. Construction of 1. Construction of
Receiving Pit Jacking Pit
25m
-20.5mPD -20.5mPD
3. Laying of 1xDN1000 and 1xDN900
DCS pipes in each DN2800 tunnel
Sheet Piles Sheet Piles
350m long
Construction Sequence
Wilson W. S. Mok 17
Wilson W.S. Mok
RECEIVING
PIT
N
= 28 ALLUVIUM
N
= 28 N
= 22 N
= 25 N N
= 31 = 16
PROPOSED CROSSING
SUB-SURFACE SETTLEMENT
MARKERS
TILT PLATE
PIEZOMETER
EXTENSOMETER
Vertical
seawall made
Of concrete
blocks
THICKNESS VARIES
ROAD SLAB
∅
PVC TUBE
SAND FILL
600mm (MAX.)
∅ REBAR WELDED
VERTICALLY AND
CONCENTRIC WITH A
75 x 75 x 5mm THK. STEEL
PLATE
ELEVATION
PLAN
Settlement Marker
Wilson W. S. Mok 23
Wilson W.S. Mok
Ground Level
Wmax
C
Zn
r
2r = D TBM
Tunnel Axis
Tunnel Lining
D
r
Wilson W. S. Mok 26
Wilson W.S. Mok
S
S = Maximum settlement at Centre Line of Tunnel
JACKING PIT
Wilson W. S. Mok 28
GL
Treated Soil
Block for TBM
Hydraulic Pushing Launching
Cylinders
Thrust
Wall
3000
10000
TBM
FL
3000
5000
Grout Zone
14600
Jacking Pit
Sheetpile
1st2800mm 2nd2800mm
diameter jacked
pipeline
3000 diameter jacked
Grout Hole
pipeline
2nd 2800mm
diameter jacked
pipeline
3000
Edge of Sheetpile
Spacing of Grout
+ +
+ Hole 600mm c/c
Overlapping
Zone
+ + + +
+ + +
Grout Hole
Positioning of TBM
Machine Cans
in Jacking Pit
Wilson W. S. Mok 33
Wilson W.S. Mok
Jacking Pipe
• Precast Concrete Pipe with a Strength of 50MPa
• 18mm Thick Soft Wood Packer Provided for Each Pipe
• Grout Holes Provided at Crown Level, and at Axis Level (for Every Fifth
Pipe), for Lubrication and Grouting
Wilson W. S. Mok 34
Wilson W.S. Mok
Wilson W. S. Mok 37
Wilson W.S. Mok
Wilson W. S. Mok 42
Wilson W.S. Mok
EXISTING TREE TO BE
RETAINED
SHEETPILES FOR WORKING PIT
B-2
B-3
1 x 1200mm dia. pipeline by
TBM
Giant Tree 2 x 1500mm dia. pipelines
by TBM
Giant Tree
B-1
Wilson W. S. Mok 45
Wilson W.S. Mok
Original Working Pit
B-1
Relocated Working
Hand-Dug Tunnel
Hand-dug Tunnel Excavation
Pit B-1 (Receiving
Pit) from Working Pit
A School
Carriageway Planter
Planter Footpath Site
A Telecoms Cables
with Conc. Surround Ground Level
N
N
= 17
N
=7 FILL N
= 30 =9
N N
N = 45 ALLUVIUM = 45 N
= 32
= 22
N
= 32
N
= 48 CDG N
= 48
N
= 25
Wilson W. S. Mok 50
Note: 2 nos. of 1500 mm dia. TBM advanced
Wilson W.S. Mok simultaneously at a distance of 40m apart.
GL = 6.00 mPD
Sheetpiles
1.2ɸ
Working Pit B-2
1x 1200mm dia. Hand-
shield Pipejacking
1.5ɸ 1.5ɸ
1x 1200mm dia. Man-shield
Pipejacking X SECTION X-X
1000
2x 1500mm dia. Hand-
shield Pipejacking
2x 1500mm dia. TBM
FL = - 5.59 mPD
X
SIDE ELEVATION
Wilson W. S. Mok 56
2800mm dia. Pipeline by
Wilson W.S.Caving
Hand-dug Mok TBM from Working Pit B-5
Pipepile
Plan
Construction of Hand-dug Caving in Working Pit B-4
5800
3400
DN2800 TBM
Wilson W. S. Mok 59
Wilson W.S. Mok
Wilson W. S. Mok 62
Wilson W.S. Mok Tailored made steel trolley for
Concrete platform for transportation of DCS pipes in
placing guide rails Pipejacked Tunnel
Railing
Railing
Wilson W. S. Mok 65
Wilson W.S. Mok
Wilson W. S. Mok 66