You are on page 1of 66

Trenchless Construction of Phase IIIA

District Cooling System (DCS)


By TBM Pipejacking
on Kai Tak Development
26 October 2016

Presented by :
Ir Wilson W. S. Mok
FICE CEng FHKIE RPE(Civil and Geotechnical)

1
Wilson W.S. Mok

Kowloon Bay

Kwun Tong Typhoon Shelter

Kai Tak Approach Channel

Location Plan
Wilson W. S. Mok 2
Wilson W.S. Mok

Scope of Works

• 2.5 km of Alignment Length of District Cooling System

 1.6 km by Open Trench


 0.8 km by TBM Pipejacking Method
 0.1 km by Hand-Dug Tunnelling Method

Wilson W. S. Mok 3
Wilson W.S. Mok

SHING CHEONG ROAD


Jacking Pit (-20.5 mPD) at
Shing Cheong Road and
HOSPITAL CEP Cheung Yip Street

2 nos. of DN 2800
Kai Tak Approach Channel Pipejacked Tunnel, each
350m Long

SHING FUNG ROAD Receiving Pit


(-20.5 mPD) at Kai Tak
Runway

Layout Plan Showing Locations of Working Pits


and TBM Pipeline Alignments of Sub-sea Tunnel
Wilson W. S. Mok 4
Wilson W.S. Mok Open Trench

Open Trench
1 x 2800mm dia. TBM
(~140m long)
1 x 1200mm dia. TBM
2 x 1500mm dia. TBM
(~32m long each)

1 x 1200mm dia. Manshield


Pipejacking Method
2 x 1500mm dia. Manshield
Pipejacking Method
Open (~21m long each)
Trench

1 x 2800mm dia. TBM 1 x 1200mm dia. TBM


Hand-Dug (~142m long) 2 x 1500mm dia. TBM
Tunnel (~165m long each)

Open
Trench

Layout Plan Showing Locations of Working Pits


and TBM Pipeline Alignments
Wilson W. S. Mok 5
Wilson W.S. Mok

Tunnel Boring Machine


Jacking Shaft 隧道鑽挖機

Typical Arrangement for


TBM Pipejacking Works
Wilson W. S. Mok 6
Wilson W.S. Mok

Advantages of Adopting Pipejacking Techniques


(in Comparison with Conventional Open-trench Method)

• Less disturbance to traffic


• Faster
• Less ground settlement
• Diversions of utilities limited to only the jacking and receiving shaft
locations
• Less environmental problems
• Earth moving is reduced to a minimum
• Operational almost in all weathers
• Fully automatic operation, thus ensuring the safe and efficient completion
of works on time

Wilson W. S. Mok 7
Wilson W.S. Mok

Method of TBM Pipejacking


• Earth Pressure Balance
• Slurry Pressure Balance

Choose Slurry Pressure Balance Method in the Project due to Highly Variable
Ground Conditions

Wilson W. S. Mok 8
Wilson W.S. Mok

Construction Method – Pipe Jacking

Wilson W. S. Mok 9
Wilson AW.S. Mok B C

Section A-A

A B C

Side Elevation

Section B-B

Front View and Side View Section C-C

Configuration of 2800mm dia. TBM


Wilson W. S. Mok 10
Wilson W.S. Mok

TBM Control Panel


Wilson W. S. Mok 11
Wilson W.S. Mok

Pipejacking by Slurry Pressure Balance Method


Wilson W. S. Mok 12
Wilson W.S. Mok

9 5
10

3
2 6
7 1
4
11 8

Circular Path in Rock Face


Formed by Cutting Discs

Pipejacking Operation –
Disc Cutters Cutting Analysis
Wilson W. S. Mok 13
Wilson W.S. Mok

Mechanism of Rock Cutting by Disc Cutter


Wilson W. S. Mok 14
Wilson W.S. Mok

Circular Kerfs in Rock Face Formed by


Disc Cutters
Wilson W. S. Mok 15
Wilson W.S. Mok

Section A - Sub-sea Tunnel

Wilson W. S. Mok 16
Wilson W.S. Mok 5. Backfilling and
reinstatement

1. Construction of 1. Construction of
Receiving Pit Jacking Pit

Cheung Yip Street


Kai Tak Runway
4. Construction of chamber (+5mPD)
(+5mPD)
and pipes connection

Kai Tak Approach Channel

25m

10m 2. Construction of 2 nos. of DN2800


tunnels by pipejacking using TBM

-20.5mPD -20.5mPD
3. Laying of 1xDN1000 and 1xDN900
DCS pipes in each DN2800 tunnel
Sheet Piles Sheet Piles
350m long

Construction Sequence
Wilson W. S. Mok 17
Wilson W.S. Mok

Site Investigation in Seabed


Wilson W. S. Mok 18
Wilson W.S. Mok
JACKING +5.0 mPD
PIT +3.0 mPD
EXISTING SEAWALL
N
N = 13 FILL
= 46
N
N =4 MARINE DEPOSIT
=4 N
=6

-20.5 mPD ALIGNMENT of 2 x 2800 mm DIAMETER PIPELINES


N
= 31 N ALLUVIUM
N = 28
= 20

+5.0 mPD RECEIVING


EXISTING SEAWALL PIT
+3.0 mPD
FILL N N
= 16 = 15
N
N
= 21 = 13
N N
=6 MARINE DEPOSIT = 10
N
= 18
N
N N
=4 -20.5mPD =7
= 20 -20.5 mPD

RECEIVING
PIT
N
= 28 ALLUVIUM
N
= 28 N
= 22 N
= 25 N N
= 31 = 16

Inferred Geological Profile


Wilson W. S. Mok 19
Wilson W.S. Mok

Typical Arrangement of Jacked Pipeline


with Intermediate Jacking Stations
Wilson W. S. Mok 20
Wilson W.S. Mok KAI TAK APPROACH CHANNEL
Sloping seawall
LEGEND made by rubble

PROPOSED CROSSING

SUB-SURFACE SETTLEMENT
MARKERS

TILT PLATE

PIEZOMETER

EXTENSOMETER

INCLINOMETER CA2 ROAD

Vertical
seawall made
Of concrete
blocks

Geotechnical Instrument Plan


Wilson W. S. Mok 21
STEEL COVER WITH HINGED
OPENING
Wilson W.S. Mok ROAD SURFACE

THICKNESS VARIES
ROAD SLAB

∅
PVC TUBE

SAND FILL

600mm (MAX.)
∅ REBAR WELDED
VERTICALLY AND
CONCENTRIC WITH A
75 x 75 x 5mm THK. STEEL
PLATE

ELEVATION

75 x 75 x 5mm THK. STEEL PLATE


∅ 
PLACED CONCENTRIC WITH THE
PVC TUBE ON UNDISTURBED GROUND

PLAN

Typical Details of Sub-surface Settlement Markers


Wilson W. S. Mok 22
Wilson W.S. Mok

Settlement Marker
Wilson W. S. Mok 23
Wilson W.S. Mok

Installation of Settlement Marker


Wilson W. S. Mok 24
Wilson W.S. Mok

Completed Settlement Marker


Wilson W. S. Mok 25
Wilson W.S. Mok
Settlement Trough
Settlement Profile

Ground Level
Wmax
C
Zn

r
2r = D TBM
Tunnel Axis

Tunnel Lining

Longitudinal Settlement Profile From O’Reilly and News (1982)



 
2
Settlement Trough Width where i = 0.43Zn + 1.1 (cohesive soil)
CL
Ground Level -2i -i i 2i I = 0.28Zn – 0.12 (granular soil)
Assume overcut = x mm
0.61Wmax Wmax  
   2    2  
C
4
Zn i = Point of inflexion or maximum gradient
VS = Volume of Settlement Trough

D
r

Transverse Settlement Profile

Wilson W. S. Mok 26
Wilson W.S. Mok
S
S = Maximum settlement at Centre Line of Tunnel

Settlement Trough for One Tunnel

Settlement Trough for Two Tunnels

Settlement Trough for Three Tunnels

Typical Shape of Settlement Trough


Wilson W. S. Mok 27
Wilson W.S. Mok

JACKING PIT

HOSPITAL CEP SITE

General View of Jacking Pit at Excavation with Lateral Support


Cheung Yip Street and Shing for Jacking Pit
Cheong Road

Wilson W. S. Mok 28
GL

Wilson W.S. Mok


Sheetpiles
GWL

2.8m Dia. TBM

Treated Soil
Block for TBM
Hydraulic Pushing Launching
Cylinders

Thrust
Wall
3000

10000
TBM
FL

3000

5000

Grout Zone

Typical Arrangement of Jacking Pit


Wilson W. S. Mok 29
5000
Treated Soil Block
Wilson W.S.Treated
Note: Mok soil block formed by BC
grout followed by chemical grout
1st 2800mm
diameter jacked
Treated Soil Block pipeline

3000 3000 3000 Treated Soil


Block

14600
Jacking Pit
Sheetpile
1st2800mm 2nd2800mm
diameter jacked
pipeline
3000 diameter jacked
Grout Hole
pipeline

2nd 2800mm
diameter jacked
pipeline

Formation of Working Pit

3000
Edge of Sheetpile

Grout Pattern for Treated Soil Block outside


Launching Eye in Jacking Pit
Wilson W. S. Mok 30
Influence Zone of
Grout Spread
Wilson W.S. Mok

Spacing of Grout
+ +
+ Hole 600mm c/c

Overlapping
Zone

+ + + +

+ + +
Grout Hole

Typical Details of Treated Soil Block


Wilson W. S. Mok 31
Wilson W.S. Mok
Rubber Seal Entrance Ring Hydraulic Jack Slurry Pipeline
System

Installation of Entrance Ring Pushing First Can of TBM to


Entrance Ring

Operation in Jacking Pit


Wilson W. S. Mok 32
Wilson W.S. Mok

Positioning of TBM
Machine Cans
in Jacking Pit
Wilson W. S. Mok 33
Wilson W.S. Mok

Jacking Pipe
• Precast Concrete Pipe with a Strength of 50MPa
• 18mm Thick Soft Wood Packer Provided for Each Pipe
• Grout Holes Provided at Crown Level, and at Axis Level (for Every Fifth
Pipe), for Lubrication and Grouting

Wilson W. S. Mok 34
Wilson W.S. Mok

Appearance of Intermediate Jacking Station


Wilson W. S. Mok 35
Wilson W.S. Mok

Spoil Handling System


Wilson W. S. Mok 36
Wilson W.S. Mok

Sodium-based Bentonite After


Bentonite Mixing

Bentonite Being Pumped


to Jacked Pipeline for
Lubrication

Wilson W. S. Mok 37
Wilson W.S. Mok

Automatic Lubrication Station


Wilson W. S. Mok 38
Wilson W.S. Mok

Separation of Excavated Materials in Desander


Wilson W. S. Mok 39
Wilson W.S. Mok

Appearance of TBM after


being pushed into Receiving Pit
Wilson W. S. Mok 40
Wilson W.S. Mok
Intermediate Slurry Pipes and Electric Lifting eye /
Jack Cables Grout Hole

Tunnel Formed by Precast Condition of Completed Tunnel


Concrete Pipes

Tunnel Formed by TBM Pipejacking


Wilson W. S. Mok 41
Wilson W.S. Mok

TBM Pipejacking in Triangular Configuration

Wilson W. S. Mok 42
Wilson W.S. Mok
EXISTING TREE TO BE
RETAINED
SHEETPILES FOR WORKING PIT

132kV CLP CABLES


RELOCATED WORKING PIT B-3

11kV CLP CABLES


11kV / 132kV 2 x 1500mm dia. pipeline by 2 x 1500mm
CLP CABLES HandShield Pipejacking from dia. TBM
Working Pit B-3 Pipejacking
1 x 1200mm dia. pipeline
to Working
by HandShield Pipejacking
Pit B-1
from Working Pit B-3
400 mm. DIAMETER GAS MAIN WORKING PIT B-2

1200mm dia. TBM


Pipejacking to Working Pit B-1

Jacked Pipeline Arrangement in Working Pit B-2


Wilson W. S. Mok 43
Wilson W.S. Mok
1 x 1200mm dia. pipeline by Handshield
Pipejacking
2 x 1500mm dia. pipelines by Handshield
Pipejacking

B-2

B-3
1 x 1200mm dia. pipeline by
TBM
Giant Tree 2 x 1500mm dia. pipelines
by TBM

Giant Tree
B-1

Plan Showing Locations of Working Pits B-1, B-2,


B-3 and the Pipeline Alignment in Between
Wilson W. S. Mok 44
Wilson W.S. Mok

Construction of Hand-dug Tunnel from


Receiving Pit

Wilson W. S. Mok 45
Wilson W.S. Mok
Original Working Pit
B-1

3 nos. of DN200 DCS


Chilled Water Pipes
with Conc. Surround

Relocated Working
Hand-Dug Tunnel
Hand-dug Tunnel Excavation
Pit B-1 (Receiving
Pit) from Working Pit

A School
Carriageway Planter
Planter Footpath Site
A Telecoms Cables
with Conc. Surround Ground Level

CLP Cables (400kV) Telecoms Cables


With Conc. Surround with Conc. Surround 3 nos. of
DN200
DCS Chilled
CLP Cables (132kV) CLP Cables With Water Pipes
With Conc. Surround Conc. Surround with Conc.
Surround
CLP Cables (11kV)
With Conc. Surround Original
Working Pit
Planter B-1 location

Hand Dug Tunnel

Jacked Pipeline Section A-A


from Working Pit Revised Working Pit B-1 to
Utilities Congested at Original B-2 suit site constraints
Working Pit Location

Location of Working Pit B-1 and Hand-dug Tunnel


Wilson W. S. Mok 46
Wilson W.S. Mok

WORKING PIT WORKING PIT


B-1 (RECEIVING PIT) +6.00 mPD +6.00 mPD B-2 (JACKING PIT)

N
N
= 17
N
=7 FILL N
= 30 =9

1 No. TBM PIPEJACKING DN1200


-4.6 mPD -5.59mPD
2 Nos. TBM PIPEJACKING DN1500

N N
N = 45 ALLUVIUM = 45 N
= 32
= 22

N
= 32
N
= 48 CDG N
= 48
N
= 25

Inferred Geological Profile


Wilson W. S. Mok 47
Wilson W.S. Mok

Manual Excavation in Upper Bench Lower Bench Excavation in Hand-


of Hand-dug Tunnel dug Tunnel by Mini-excavator

Hand-dug Tunnel Excavation from Receiving Pit


Wilson W. S. Mok 48
Wilson W.S. Mok

Hand-dug Tunnel Excavation from Receiving Pit


Wilson W. S. Mok 49
Wilson W.S. Mok

Parallel Running of 2 Nos. of 1.5m Diameter TBM

Wilson W. S. Mok 50
Note: 2 nos. of 1500 mm dia. TBM advanced
Wilson W.S. Mok simultaneously at a distance of 40m apart.

GL = 6.00 mPD

Sheetpiles
1.2ɸ
Working Pit B-2
1x 1200mm dia. Hand-
shield Pipejacking
1.5ɸ 1.5ɸ
1x 1200mm dia. Man-shield
Pipejacking X SECTION X-X

1x 1200mm dia. TBM

1000
2x 1500mm dia. Hand-
shield Pipejacking
2x 1500mm dia. TBM
FL = - 5.59 mPD

X
SIDE ELEVATION

Pipejacking in Working Pit B-2


Wilson W. S. Mok 51
Wilson W.S. Mok

Parallel Running of 2 nos. of 1.5m Dia. TBM


Pipejacking in Jacking Pit
Wilson W. S. Mok 52
Wilson W.S. Mok

TBM Breakthrough in Hand-dug Tunnel


from Receiving Pit
Wilson W. S. Mok 53
Wilson W.S. Mok

Lifting Up of TBM from Receiving Pit


to Ground Surface
Wilson W. S. Mok 54
Wilson W.S. Mok

Preparation of Receiving Eye for TBM Entry


Wilson W. S. Mok 55
Wilson W.S. Mok

Caving Construction in the Lower Portion of


Receiving Pit for Receiving 2.8m Diameter TBM

Wilson W. S. Mok 56
2800mm dia. Pipeline by
Wilson W.S.Caving
Hand-dug Mok TBM from Working Pit B-5

Working Pit B-4

Pipepile
Plan
Construction of Hand-dug Caving in Working Pit B-4
5800

PIPE PILE ROOF


(PIPES AT 0.6m c/c) 254 x 254 x 89kg/m UC
(COLUMN OF PORTAL FRAME)

PIPES AT 0.7m c/c


4500

3400

DN2800 TBM

305 x 305 x 97kg/m UC


GUIDE RAIL BLINDING CONCRETE

Front Elevation of the Caving As-Constructed Caving in Working Pit B-4

Working Pit B-4 - Change of Construction Methodology for


Receiving Tunnel Boring Machine due to Constraints by Existing Utilities
Wilson W. S. Mok 57
Wilson W.S. Mok

TBM Entry in Caving of Working Pit B-4


Wilson W. S. Mok 58
Wilson W.S. Mok

Skin-off of 2.8m Diameter TBM


for Lifting up to Ground Surface

Wilson W. S. Mok 59
Wilson W.S. Mok

TBM Entry in Caving and Skin-off of TBM


at Working Pitp for Lifting up to Ground Surface
Wilson W. S. Mok 60
Wilson W.S. Mok

Skin-off of TBM at Working Pit for


Lifting up to Ground Surface
Wilson W. S. Mok 61
Wilson W.S. Mok

Installation of DCS Pipelines


in the Completed Jacked Pipelines

Wilson W. S. Mok 62
Wilson W.S. Mok Tailored made steel trolley for
Concrete platform for transportation of DCS pipes in
placing guide rails Pipejacked Tunnel
Railing
Railing

Installation of guide rails in Installation of DCS Pipes


Concrete Platform

DCS Pipes Installation in Jacked Pipeline


Wilson W. S. Mok 63
Wilson W.S. Mok

DCS Pipelines Installation in Jacked Pipeline


Wilson W. S. Mok 64
Wilson W.S. Mok

Problems Commonly Encountered by TBM


Pipejacking
• Alignment Control
• Ground Settlement
• Obstruction
• Damage of Jacking Pipes

Wilson W. S. Mok 65
Wilson W.S. Mok

Wilson W. S. Mok 66

You might also like