Pictorial Evidence

Facility Name : AZM Style Wear Ltd. (Accord ID: 22968)


Pictorial Evidence for : Corrective Action Plan- Structural

Previous Drawing Corrected Drawing- There is no Roof Bracing


Item-Number as per CAP no-01 Item-Number as per CAP no-01

Previous Drawing Corrected Drawing- There is no Roof Bracing


Item-Number as per CAP no-01 Item-Number as per CAP no-01
Previous drawing- Vertical bracing Corrected drawing- Threre is no Vertical bracing
Item-Number as per CAP no-01 Item-Number as per CAP no-01

Previous drawing- Column Rotation not shown Corrected drawing- Column has been rotated on first floor
Item-Number as per CAP no-01 Item-Number as per CAP no-01
Previous drawing- Rafter size does not match with field value Corrected drawing- Rafter size with haunch dimention has been updated
Item-Number as per CAP-01 Item-Number as per CAP-01

Previous drawing- Column schedule does not match with field value Corrected drawing- Column Schedule with haunch dimention has been updated
Item-Number as per CAP-01 Item-Number as per CAP-01
Provided drawing- Beam has been shown but actually not exist Corrected drawing- No beam has been found in selected location
Item-Number as per CAP-01 Item-Number as per CAP-01

Factory engineer to check the stability of the steel shed


and separated toilet block under lateral and vertical
loading.
Factory engineer has prepared corrected as built drawing and
already started their analysis

Item-Number as per CAP-02 Item-Number as per CAP-02


Produce and actively manage a loading plan for all floor
plates considering floor and column capacity.

Floor load plan has been produced and started to maintain


Item-Number as per CAP-03 Item-Number as per CAP-03

Carry out remedial


assessment works resulting from engineering
where necessary.
Factory engineer has prepared corrected as built drawing and
already started their analysis

Item-Number as per CAP-04 Item-Number as per CAP-04


Continue to implement load plan

Floor load plan has been produced and started to maintain on the floor
Item-Number as per CAP-05 Item-Number as per CAP-05

Corrosion was found in steel column Painting work has been done on corroted steel column
Item-Number as per CAP 06 Item-Number as per CAP 06
Threre were no drawing south & emergency stair Drawing has been prepared for south & emergency stair
Item-Number as per CAP 07 Item-Number as per CAP 07

Mismatch was found between as built drawing and site condition Drawing has been corrected as per site condition
Item-Number as per CAP 08 Item-Number as per CAP 08
There were no as built drawing for boiler room New as built drawing for boiler room has been prepared
Item-Number as per CAP 09 Item-Number as per CAP 09

Mismatch was found between as built drawing and site condition Drawing has been corrected as per site condition for brick column
Item-Number as per CAP 10 Item-Number as per CAP 10
Mismatch was found between as built drawing and site condition Drawing has been corrected as per site condition for brick column
Item-Number as per CAP 11 Item-Number as per CAP 11

Mismatch was found between as built drawing and site condition Drawing has been corrected as per site condition for brick column
Item-Number as per CAP 12 Item-Number as per CAP 12
Factory engineer has started their job to solve this issue.

Mismatch was found between as built drawing and site condition


Item-Number as per CAP 13 & 14 Item-Number as per CAPCAP 13 & 14