You are on page 1of 1

ANALISA HARGA SATUAN KEGIATAN KONSTRUKSI

PAKET : RENOVASI GEDUNG PEMADAM KEBAKARAN DURIANGKANG BATAM


LOKASI : BATAM

JENIS PEKERJAAN : Pemasangan dan Fabrikasi Aluminium Composite Panel


SATUAN PEKERJAAN : m2
HARGA SATUAN : Rp 717,790.00
SUMBER : SNI DT 91-0010-2007

PERKIRAAN HARGA JUMLAH


NO. KOMPONEN SATUAN KUANTITAS SATUAN HARGA
(Rp.) (Rp.)

A. TENAGA
1 pekerja OH 0.6500 100,000.00 65,000.00
2 Tukang OH 0.6500 130,000.00 84,500.00
3 Kepala Tukang OH 0.0650 125,000.00 8,125.00
4 Mandor OH 0.0320 135,000.00 4,320.00

JUMLAH HARGA TENAGA 161,945.00

B. BAHAN

1 ACP m2 1.1000 350,000.00 385,000.00


2 Hollow 1 x 2" m 6.6000 16,000.00 105,600.00

JUMLAH HARGA BAHAN 490,600.00

C. ALAT

JUMLAH HARGA ALAT -

D. JUMLAH HARGA TENAGA, BAHAN DAN ALAT ( A + B + C ) 652,545.00


E. Profit 10 % 65,254.50
F. Jumlah 717,799.50
G. Dibulatkan 717,790.00