You are on page 1of 10

HOLLOW CORE BAR MICROPILES – DESIGN PARAMETERS INTERPRETED

FROM 404 LOAD TESTS


Jesús E. Gómez, Ph.D., P.E., C. Javier Rodriguez, P.E., Johanna Mikitka, E.I.T., Helen D. Robinson,
P.E., Schnabel Engineering, West Chester, PA, USA; Larry Keough, PKF Mark III, Newtown, PA, USA

This work is a continuation of a paper presented in the 32nd DFI Annual


Conference, Colorado 2007, titled “Hollow Core Bar Micropiles - Design
parameters interpreted from 260 load tests.” The first paper presented the results
of the verification and proof tests performed for the retrofit of two bridges with
hollow core bars that used 260 micropiles. It included an interpretation of the unit
bond values in the different soils where micropiles were installed. Recently two
additional bridges within the same geological environment were also retrofitted
using 144 hollow core micropiles.

This paper includes the interpretation of the additional data from the proof tests
performed and refines recommended values for design of hollow core bar
micropiles in soils similar to those encountered in these two projects. The authors
believe that the data collected will significantly add to the relatively small existing
database on micropile tests and may also be useful during implementation of the
LRFD design methodology.

INTRODUCTION hollow core bar micropiles may be higher than


traditional micropile reinforcing such as threaded
This paper discusses the use of hollow core bars, faster installation rates often offset these
micropiles to retrofit four existing bridges. additional costs. This is especially true in cases
Underpinning of the foundations was necessary of difficult access and limited headroom.
due to deterioration of the exposed section of
existing concrete precast piles. A total of 180 The micropiles were designed for an allowable
hollow core bar micropiles were installed at capacity of 80 kips (355.9 kN). The micropiles
Bridge 1 through granular soils, while 80 consisted of hollow core bars bonded to the soil,
micropiles were installed through predominantly and had varying bond lengths. In general, the
fine soils at Bridge 2, and 64 micropiles at micropiles installed through granular soil had a
Bridge 3. At Bridge 4, 80 micropiles were bond length of 30 feet, while the micropiles
installed with half of the bond length drilled installed through fine soils had a bond length of
through fine soils and the other half through 40 feet. The upper portion of the micropiles
granular soils. Bridge 1 is a four-lane, four-span included permanent steel casing to provide
structure supported on three piers, each buckling and bending capacity along the
consisting of thirty 18-inch (45.7 cm) precast exposed portion of the micropiles and the
concrete piles. Bridge 2, Bridge 3 and Bridge 4 potential scour zone.
have three spans supported on two piers, each
with twenty 18-inch (45.7 cm) precast concrete The micropiles were connected to the existing
piles. bridge through new cap beams. The cap beams
were constructed in two stages in order to allow
Ongoing deterioration of the precast piles proof testing of all production micropiles.
required full retrofit of the bridge foundations.
Hollow core bar micropiles were chosen for During proof testing, careful measurements of
several reasons. In traditional micropile the micropile deflection, as well as movements
installation, drilling is followed by installation of of the new and existing pile caps were
the reinforcement and grouting. Hollow core bar performed. The proof testing schedule included
micropiles have faster installation rates in many a minimum 12-hour load hold period to verify
soils than traditional micropiles because drilling, creep, and several unload-reload cycles.
grouting, and placement of reinforcement are
done simultaneously. Although material costs for
GEOLOGY respectively. The natural water content ranges
from 32 to 60 percent. The 40-foot (12.2 m)
The project sites are located along the southern bond length of each micropile with a nominal
portion of the New Jersey Turnpike in the grout body diameter of 7-1/2 inches (19.05 cm)
Coastal Plain Province of southwest New was developed entirely within the stiff clay.
Jersey. These unconsolidated sediments
consist of layers of sand, silt and clay deposited Bridge 4
alternately in deltaic and marine environments
as sea level fluctuated during Cretaceous and A layer of very soft organic silt extends to a
Tertiary times (Geologic Map of New Jersey, depth of approximately 10 feet (3.3 m) below the
Geological Survey, 1999). Test borings were river bottom. The silt is underlain by stiff to very
performed at the verification test locations at stiff silty clay to a depth of approximately 61 feet
each bridge. Details on the soils at each bridge with SPT values generally ranging between 8
location are presented below. and 18 blows per foot. The liquid limit and
plasticity index values of the clay range from 48
Bridge 1 to 82 percent and 24 to 58 percent, respectively.
The natural water content ranges from 34 to 38
Subsurface conditions generally consist of very percent. The clay is underlain by dense to very
soft organic silt to a depth of approximately 10 dense silty sand with SPT values generally
feet (3 m) below the bottom of the river, ranging between 28 and 49 blows per foot. The
underlain by medium-dense sand to a depth of natural water content is approximately 29
approximately 57 feet (17.4 m). The sand has a percent. The 40-foot (12.2 m) bond length of
fines content ranging from 10 to 30 percent. The each micropile with a nominal grout body
Standard Penetration Test (SPT) blow count diameter of 7-1/2 inches (19.05 cm) was
ranges from 10 to 16 blows per foot in the sand developed approximately 17 feet within the silty
layer. An interval of stiff clay exists below the clay and 23 ft within the silty sand.
sand layer. The 30-foot (9.1 m) bond length of
the micropiles with a nominal grout body HOLLOW CORE BAR MICROPILES
diameter of 6 inches (15 cm) was developed
within the medium dense sand layer. The design load at each of the four bridges was
80 kips (355.9 kN) per micropile. The
Bridge 2 reinforcement of each micropile for Bridge 1 and
Bridge 2 consisted of one 52/26 IBO-Titan
A layer of very soft organic silt extends to a hollow core bar supplied by Con-Tech Systems,
depth of approximately 14 feet (4.3 m) below the Ltd. (see Figure 1), while the reinforcement of
river bottom. The silt is underlain by stiff to very each micropile for Bridge 3 and Bridge 4
stiff silty clay with SPT values generally ranging consisted of one MAI R51N hollow core bar
between 11 and 16 blows per foot. The liquid supplied by Williams Form Engineering
limit and plasticity index values of the clay range Corporation. The micropiles also included a
from 56 to 78 percent and 38 to 58 percent, 9.625-inch (24.4 cm) external diameter steel
respectively. The natural water content ranges casing with 0.5-inch (1.3 cm) wall thickness,
from 30 to 35 percent. The 40-foot (12.2 m) which extended from the cap beam to the
bond length of each micropile with a nominal anticipated scour depth to prevent buckling of
grout body diameter of 9 inches (22.9 cm) was the micropiles.
developed entirely within the stiff clay.
In the hollow core bar system, the grout is
Bridge 3 injected through the center hole of the bar. Upon
exiting the drill bit at the tip of the bar, the exit
A layer of very soft organic silt extends to a grout velocity undercuts the soils and flushes the
depth of approximately 17 feet (5.2 m) below the drill cuttings to the ground surface along the
river bottom. The silt is underlain by stiff to very annular space around the bar. The completed
stiff silty clay with SPT values generally ranging micropile consists of the hollow core bar as
between 8 and 19 blows per foot. The liquid limit central reinforcement, surrounded by a grout
and plasticity index values of the clay range from body with a diameter larger than the diameter of
44 to 78 percent and 16 to 45 percent, the drill bit.
Figure 2. Installation of Production Micropiles
Figure 1. Hollow Core Bars and Steel Casing. with Limited Headroom.

DRILLING AND QUALITY CONTROL

All work had to take place under limited


headroom with difficult access and within
temporary cofferdams. Figure 2 illustrates
installation of the production micropiles under
low headroom. At each production micropile
location, the 9-5/8 inch (24.45 cm) steel casing
was first installed using the external water flush
method. The hollow core bar was then inserted
until reaching the bottom of the casing. The bars
were fitted with 6-inch (15.2-cm) clay bits at
Bridge 1 and 7.5-inch (19.1-cm) clay bits at
Bridges 2, 3 and 4. J-teeth were welded to each
sacrificial clay bit to obtain the design diameter Figure 3. Drill Bit Fitted to Hollow Core Bar.
and to improve grout flow (see Figure 3). During
drilling, the hollow core bars were fed with a lean Drilling rates were measured during installation
cement grout mix with a water/cement ratio of of each micropile. The time lag during addition of
0.89. each bar segment was not included in the time
measurements and, therefore, did not affect the
The bars were advanced with continuous grout computed drilling rates. Drilling rates typically
flush to the design tip elevation. Upon ranged between 0.5 to 1 ft/min (0.15 to 0.3
completion of drilling, a final grout mix was m/min) in the granular soils of Bridge 1, 0.3 to
prepared for a target water-cement ratio of 0.45. 0.7 ft/min (0.09 to 0.21 m/min) in the fine-
The specific gravity of the grout measured grained soils of Bridge 2, and 0.5 to 0.7
during drilling ranged from 1.4 to 1.6 and ranged ft/min(0.09 to 0.21 m/min) on Bridge 3.
from 1.8 to 1.95 for the final grout, with sporadic
values as high as 2.1.
Load (kip)
0 50 100 150 200 250 300 350
0.0

0.5

1.0

1.5
Deflection (in)

2.0

2.5

3.0

3.5

4.0

Bridge 1

Figure 4 Data from Test Pile at Bridge 1 in Loose to Medium-Dense Sand.

The authors found that measurement of the micropiles is presented in previous work (Gómez
drilling rates was an invaluable tool to confirm et al. 2007).
the materials encountered and to have firm data
for technical discussions with the project team. VERIFICATION TESTS
The drilling rates measured in one site using a
specific set of equipment and tools may be used Two to three verification load tests were
as a measurement of the consistency of performed at each bridge location to a maximum
micropile installation but must not be directly test load of 200 kip (889.6 kN) (250 percent of
correlated with those measured at other sites. the design load). One of the verification tests at
Specific gravity was the primary quality control each bridge site was loaded to geotechnical
of the grout. It was measured using a calibrated failure. For each load increment, micropile
mud balance according to API RP 13B-1, deflections were measured using dial gauges.
“Recommended Practice Standard Procedure Each load increment was held for 10 or 20
for Field Testing Water-Based Drilling Fluids.” minutes. A 12-hour load hold was performed at
The minimum specific gravity value was 133 percent of the design load to verify the
specified at 1.4 for the drilling grout and 1.8 for potential for creep.
final grout.
Figure 4 shows the data obtained from the
Grout cubes were tested following ASTM C109, micropile tested on granular material, Figure 5
“Standard Test Method for Compressive shows the data obtained from the test micropiles
Strength of Hydraulic Cement Mortars.” Grout bonded to fine soils at Bridges 2 and 3, and
cubes were formed in 2-inch (5.1 cm) square Figure 6 shows the data obtained from the
polyethylene or brass molds. Cubes were stratified soil at Bridge 4.
molded from final grout batches at the grout
hopper after mixing and from samples of the Interpretation of the results of the verification
final grout return at the top of the pile. The tests consisted of calculating the average
project specification called for strength of 4000 ultimate bond strength based on the results of
psi (27.6 MPa) at 28 days, which was typically the tests taken to failure, and on the
met throughout the project. Additional approximate interpretation procedure discussed
information on drilling, grouting and quality subsequently in this paper.
control for the installation of hollow core bar
Load (kip)
0 20 40 60 80 100 120 140 160 180 200 220
0.0

0.5

1.0

Displacement (inches)
1.5

2.0

2.5

3.0

3.5

4.0

Bridge 2

Load (kips)

0 20 40 60 80 100 120 140 160 180 200 220


0.0

0.5

1.0
Displacement (inches)

1.5

2.0

2.5

3.0

3.5

4.0

Bridge 3

Figure 5. Data from Test Piles at Bridges 2 and 3 Installed in Stiff Silty Clay.
PROOF LOAD TESTING load hold period. Creep was not significant in
most of the production piles, and did not exceed
All 404 production micropiles were proof-tested the specified maximum of 0.08 inches (0.20 cm)
to a maximum load ranging from 75 to 150 per log cycle of time in any of the production
percent of the 80-kip (355.9 kN) design load. micropiles. Figure 10, Figure 11, and Figure 12
The existing bridges were the reaction for the show the range of load-deflection responses for
proof load tests (Gómez et al., 2007). all the proof-tested micropiles. Micropiles
installed in the granular soils at the Bridge 1
Figure 9 contains typical load-deflection data location were generally stiffer than micropiles
from one of the tests. The deflection values installed in the fine-grained soils at Bridges 2
under the maximum test loads were generally and 3 and the combined soils of Bridge 4. Also,
within 0.1 to 0.4 inches (0.25 to 1.02 cm). The the load-deflection data from micropiles installed
increase in deflection under constant load at 80 in granular soils showed less scatter than those
kip (355.9 kPa) corresponds to creep during the from micropiles in fine-grained soils.
Load (kips)
0 20 40 60 80 100 120 140 160 180 200 220
0.0

0.5

1.0

Displacement (inches)
1.5

2.0

2.5

3.0

3.5

4.0

Bridge 4

Figure 6. Data from Test Pile at Bridge 4 Installed in Stratified Soils


The micropiles installed on fine-grained soils at (258.0 kN). The average load transfer ratio at
Bridge 2 were in general stiffer than the failure was then 10 kip per linear foot (145.9 kN
micropiles installed at Bridge 3. The per linear meter) of bond zone, equivalent to
performance of the micropiles depends on the average ultimate bond strength of 44 psi (303.4
grout exit velocity, differences in the fine-grained kPa) considering the nominal grout body
soils at different sites, the final grout body diameter of 6 inches (15.2 cm).
diameter, drilling rate and other factors.
BOND VALUES IN STIFF SILTY CLAY
INTERPRETATION OF TEST DATA
The average ultimate bond strength along the
The apparent elastic length, Le, of a test pile can clay layer on Bridge 2 was estimated from the
be calculated for each unloading cycle (Gómez results of Verification Load Test 2-3, which
et al., 2003). The value of Le is the apparent reached geotechnical failure under 182 kips
elastic length. It represents the length of a free- (809.6 kN). Considering that the upper casing
standing column with identical axial stiffness that carried approximately 20 kip (89.0 kN) at failure,
undergoes a magnitude of elastic shortening the load carried by the 40-foot (12.2 m) bond
equal to that of the pile under the same load. zone of the pile was 162 kip (720.6 kN). The
The corresponding axial load distribution along corresponding ultimate bond strength was 4.1
the bond zone assumes that the bond strength kip per linear foot (59.8 kN per linear meter) of
is uniform throughout the bond length. For this bond zone, or 18 psi (124.1 kPa) considering a
stick-slip response, the effective bond length is nominal diameter of the grout body of 6 inches
estimated (Gómez et al., 2007). (15.24 cm).

BOND VALUES IN SAND The average ultimate bond strength along the
clay layer on Bridge 3 was estimated from the
Both verification micropiles at Bridge 1 results of Verification Load Test 3-3, which was
satisfactorily carried a load of 250 percent of the loaded close to geotechnical failure under 204
design load. Verification micropile 1-2 at Bridge kips (907.4 kN). Considering that the upper
1 was loaded beyond the maximum specified casing carried approximately 20 kip (89.0 kN) at
test load until the pile reached geotechnical failure, the load carried by the 40-foot (12.2 m)
failure under 318 kip (1414.5 kN). Based on bond zone of the pile was 184 kip (818.5 kN).
interpretation of the load-displacement curve, The corresponding ultimate bond strength was
the load carried by the 26-foot (7.9 m) bond 4.6 kip per linear foot (67.3 kN per linear meter)
length of the pile at failure was approximately of bond zone, or 16 psi (110.3 kPa) considering
260 kip (1156.5 kN), which considered that the a nominal diameter of the grout body of 7.5
upper casing carried approximately 58 kip inches (19.05 cm).
test load until the pile reached geotechnical
failure under 280 kip (1245.5 kN). Considering
that the upper casing carried approximately 20
kip (89.0 kN) at failure, the load carried by the
40-foot (12.2 m) bond zone of the pile was 260
kip (1156.5 kN). The corresponding ultimate
bond strength was 6.5 kip per linear foot (94.8
kN per linear meter) of bond zone, or 23 psi
(158.6 kPa) considering a nominal diameter of
the grout body of 7.5 inches (19.05 cm).

All verification tests satisfactorily complied with


the failure criteria provided in the specifications.

ULTIMATE BOND VALUES INTERPRETED


FROM PROOF TESTS

Figures 13, 14 and 15 summarize the load


transfer ratios estimated from each of the proof
tests. The data obtained during the last
unloading cycle of each test was used for these
calculations.

A simple inspection of the histograms shows


that the load transfer rate of the micropiles
installed in sand ranged from 6 to 12 kip/ft (87.6
to 175.1 kN/m), which is equivalent to 27 to 53
psi (186.1 to 365.4 kPa) considering the nominal
grout body diameter of 6 inches (15.24 cm). For
micropiles installed in stiff silty clay, the load
Figure 7. View of Micropiles and Completed transfer ratio ranged between 2 to 8 kip/ft (29.2
Cap Beam. to 116.8 kN/m), which is equivalent to 7 to 28 psi
(50.6 to 193.1 kPa) considering a nominal grout
body diameter of 7.5 inches (19.1 cm). For
micropiles installed in stratified soils (clay and
sand), the load transfer ratio ranged between 3
to 10 kip/ft (43.8 to 146.0 kN/m), which is
equivalent to 11 to 35 psi (72.4 to 241.3 kPa)
considering a nominal grout body diameter of
7.5 inches (19.1 cm).

The designer must be aware that the nominal


grout body diameter was estimated as the drill
bit diameter. Therefore, the values given in
Figures 14, 15 and 16 may need to be adjusted
if using a different approach to estimate the
grout body diameter.
Figure 8. Typical Proof Load Test Setup
COMPARISON TO PUBLISHED DATA
Performed to a Group of Six Micropiles.
The bond strength values estimated from the
BOND VALUES IN COMBINED MATERIAL
results of verification load tests and proof load
(SAND AND CLAY)
tests are summarized in Table 1, and compared
to ultimate bond strength values for Type-B
Both verification micropiles at Bridge 4
micropiles suggested by the Micropile Design
satisfactorily carried a load of 250 percent of the
and Construction Guidelines, Publication No.
design load. Verification micropile 4-1 at Bridge
FHWA-SA-97-070, 2000.
4 was loaded beyond the maximum specified
Load (kip)
0 10 20 30 40 50 60 70 80 90 100 110 120
0.0

0.1

Deflection (in) 0.2

0.3

0.4

0.5

Figure 9. Typical Load-Deflection Data from One Proof Test on a Hollow Core Bar Micropile.
Load (kip)
0 20 40 60 80 100 120
0.0

0.1
Deflection (in)

0.2

0.3

0.4

0.5

Figure 10. Summary of All Load-deflection Test Data from Proof Tests at Bridge 1.
Load (kip)

0 20 40 60 80 100 120
0.0

0.5
Deflection (inches)

1.0

1.5

2.0
Bridge 2 Bridge 3

Figure 11. Summary of All Load-Deflection Test Data from Proof Tests at Bridges 2 and 3.
Load (kip)

0 20 40 60 80 100 120
0.0

0.5
Deflection (inches)

1.0

1.5

2.0
Bridge 4

Figure 12. Summary of All Load-Deflection Test Data from Proof Tests at Bridge 4.

30 18

16
25

14
Number of Micropiles

20
Number of Micropiles

12

15 10

8
10
6

5
4

0 2
4

10

12

14

16

18

20

More

0
Load Transfer Ratio (kip/ft) - Bridge 1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20More
Load Transfer Ratio (kip/ft) - Bridge 4
Figure 13. Histogram in Sand (Bridge 1).

Figure 15. Histogram in Stratified Soils (clay


45
and sand) (Bridge 4).
40

35
In a Type B micropile, neat cement grout is
placed into the hole under pressure as the
Number of Micropiles

30

25 temporary steel casing is withdrawn. Injection


20 pressures typically range from 70 to 140 psi (0.5
15 to 1 MPa). Table 1 shows that the bond
10 strengths estimated for the hollow core bars in
5
the granular soils at the Bridge 1 site are larger
0
than those values suggested by FHWA. This
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 More
may be due to the beneficial effect of partial
Load Transfer Ratio (kip/ft) - Bridge 2 and Bridge 3
mixing of soil and grout in the periphery of the
grout body, and to the penetration of the grout
Figure 14. Histogram in Stiff Silty Clay (Bridges into the soil mass outside the micropile. The
2 and 3). bond strength values estimated for the
micropiles installed in the fine-grained soils of
Bridge 2 are within the range of values proposed micropile projects where neat cement grout is
by the FHWA manual. used.

CONCLUSIONS Bond Strength


Mobilized
Suggested By
Bond
These projects allowed the opportunity to proof Soil Type FHWA
Strength in
test each of the production micropiles, thus Type B
Proof Tests
providing invaluable information and augmenting micropile
the existing database on hollow core bar Sand
micropiles. Interpretation of the verification and 27 – 53 psi 10 – 28 psi
(some silt)
proof tests showed that the ultimate bond (fine, loose-
strength of the hollow core bar micropiles (186.2 – (68.9 – 193.1
medium
installed in sand was significantly larger than 365.4 kPa) kPa)
dense)
that typically used for design of Type B, Silt & Clay 7-28 psi 10 – 28 psi
pressure-grouted micropiles. It is possible that (some sand)
partial mixing of soil and grout in the periphery of (stiff, dense to (50.6 – 193.1 (68.9 – 193.1
the grout body, and penetration of the grout into very dense) kPa) kPa)
the soil mass outside the micropile contributed Combined Soil
to the excellent performance of the hollow core (approximately
bar micropiles. In stiff silty clay, the ultimate 11 - 35 psi
½ bond length
bond strength values obtained from the tests (72.4 - 241.3 NA
in stiff clay and
were very similar to those typically used for kPa)
½ in medium-
micropile design in these types of soils. The density sand)
range of bond strength values estimated from
the work performed on Bridge 2 was consistent Table 1. Summary of estimated bond strength.
with the range of bond strength estimated by
adding the data obtained from Bridge 3. ACKNOWLEDGEMENTS
However, the micropiles installed on Bridge 2
show a stiffer behavior than the micropiles We thank PKF Mark III and Schnabel
installed at Bridge 3. The data obtained from the Engineering, LLC for providing their support and
micropile tests at Bridge 4 allowed the resources during preparation of this paper.
opportunity to add bond strength values for
combined soils, where approximately half of the REFERENCES
bond length is installed through stiff clays and
the other half is installed in medium-density GEOLOGIC MAP OF NEW JERSEY, Geological
sands. The bond strength values for these soil Survey, 1999.
conditions ranged from the lower limit for clays
to the average between the upper limits for clays GÓMEZ, J.E., CADDEN, A.W., BRUCE, D.A.
and sands. (2003). Micropiles in Rock. Development and
Evolution of Bond Stresses under Repeated
Designers of hollow core bar micropiles may use Loading. 12th Pan-American Conference on Soil
the bond strength values presented in this paper Mechanics and Geotechnical Engineering,
as guidance for preliminary design. Micropile Cambridge, MA.
design loads must always be verified through
suitable load testing in each project. GÓMEZ, J.E., RODRÍGUEZ, C.J., ROBINSON,
H.D., MIKITKA, J., KEOUGH, L. (2007).
Utilization of hollow core bars in this project Installation and Testing of 260 Hollow Core Bar
provided significant schedule savings by Micropiles. 32nd Annual Conference on Deep
allowing simultaneous micropile drilling, grouting Foundations, Colorado Springs, CO.
and placement of reinforcement. Recirculation of
the drilling grout allowed savings in cement and GÓMEZ, J.E., RODRÍGUEZ, C.J.,ROBINSON,
limited the environmental impact to the site. The H.D., KEOUGH, L. (2007). Hollow Core Bar
data collected during quality control testing Micropiles – Design Parameters Interpreted from
confirmed that specific gravity measurement 260 Load Tests. 32nd Annual Conference on
should be the primary control of grout quality in Deep Foundations, Colorado Springs, CO.

You might also like