No MS- 2350-04
METHOD STATEMENT FOR Rev. No 0
SURFACE PREPARATION Rev. Date JULY08, 2018
AND PAINTING
Page 1 of 9
STORAGE TANK
JUBAIL
SAUDI ARABIA
CONTENTS
1. PURPOSE
2. SCOPE
3. DEFINITIONS
4. REFERENCES
5. RESPONSIBILITIES
6. PROCEDURE
7. SAFETY
Doc. No MS- 2350-04
METHOD STATEMENT FOR Rev. No 0
SURFACE PREPARATION Rev. Date JULY08, 2018
AND PAINTING
Page 3 of 9
1. PURPOSE
The following Procedure briefly outlines the proposed method statement for Surface
preparation and Painting of Tanks at Saudi Polymers Company/Saudi Chevron(S-Chem).
2. SCOPE
Surface preparation and painting (External & Internal)
3. DEFINITIONS
CL Client-Saudi Polymers Company/Saudi Chevron(S-Chem)
OD Olayan Descon
PM Project Manager
SM Site Manager
SS Site Supervisor
FE Fabrication/Field Engineer
QCE QA/QC Engineer
ITP Inspection and Test Plan
QCI Quality Control Inspector
PQP Project Quality Plan
PPE Personal Protective Equipment
HSEP Health Safety Environment Plan
Doc. No MS- 2350-04
METHOD STATEMENT FOR Rev. No 0
SURFACE PREPARATION Rev. Date JULY08, 2018
AND PAINTING
Page 4 of 9
4. REFERENCES
PROJECT DRAWINGS
Approved issued for Construction Drawings (IFC)
Approved QA / QC documents
REFERENCE DOCUMENTS CODES AND STANDARDS
API-650 : Atmospheric Steel Storage Tank & CES-TAM-SU-967
PVM-DW-GF-C1431: Tanks & Vessels Program.
COM-SU-4743 : External Coating.
COM-SU-5191 : Coating System.
COM-PU-4738-E : Internal Coating.
CES-CIV-SU-398 : Fabrication Steel Structure & Miscellaneous Steel.
COM-EF-844 : Coating Inspection report forms.
QCP-2350 : Paint Surface Preparation & Painting procedure.
5. RESPONSIBILTY
5.1 Project Manager / Manager Projects(s)
It is the responsibility of Project Manager to support the entire project site, provide
all the resources which required at the site and execution of the project in
compliance to project specification in particular and engineering practices in
general with quality, safety and schedule commitments.
5.2 SM (Site Manager)
It is the responsibility of Site Manager that construction activities are executed as
per project specifications, in compliance with quality, schedule & safety
requirements.
It is the responsibility of QC Engineer and /QC Inspector to ensure all the work to
be done as per project specification plan.
5.5 Safety·
Construction activities to be carried out with safe working environment and in
accordance with approved project specific HSE plan.
6. PROCEDURE
Surface Preparation, Painting.
Prior to sand blasting and painting operations protective devices such as clothes,
screens, movable walls / partition shall be provided according to work
requirements to cover the surfaces & parts not requiring painting. Particular
attention shall be given to protect the flange gaskets seating faces for eventual
damage during blasting.
The air compressor used for blasting shall be provided with adequate separators to
ensure that it is free of oil, moisture & other contaminants. Garnets used for
blasting shall be clean and free from contaminants.
All surfaces required to be painted shall be cleaned as free of grease, oil, mill
scale, rust, weld spatters and all other contaminants which will cause for premature
coating failure.
Prior to and during blasting, weather conditions shall be monitored and recorded.
Blasting operation shall not be performed when metal surface temperature is less
than 3°C above the dew point or when the relative humidity of the air is over 90%
painting shall not be applied.
The degree of cleaning shall be accordance with the applicable paint specification.
All dust and abrasive particles shall be thoroughly removed from surfaces by
blowing with clean dry air before application of paint coating. All blast clean
surfaces shall be coated with the specified primer within six (6) hours after blasting
before the surface starts deterioration.
The coating system used for each tank shall be as per applicable General Drawing
requirement. Each coat shall be applied uniformly over the entire surface. Skips,
runs, etc. shall be avoided. When these occur, they shall be brushed out and
surface shall be recoated.
Dry film thickness of each coat shall be measured and recorded using Micro test
Magnetic Gauge. At least five spots readings shall be taken for every 10 sq. meter
of painted surface area. On each spot an average of 3 readings shall be taken
according to specification.
All the gauges used for measurements and meteorological data shall be duly
calibrated.
All damage areas due to handling etc. shall be repaired as per the paint
manufacturer’s recommendations provided in paint data sheets.
After completion of blasting and painting, final report shall be prepared and signed
by OD QA/QC Engineer and presented to the client Inspector for review.
Doc. No MS- 2350-04
METHOD STATEMENT FOR Rev. No 0
SURFACE PREPARATION Rev. Date JULY08, 2018
AND PAINTING
Page 7 of 9
7. SAFETY
7.1 PPE’S