Professional Documents
Culture Documents
Interviewes
Focus Groups
Facilitated Workshop
Brainstorming
Idea/mind mapping
Affinity diagram
Unanimity
Majority
Plurality
Observations
Prototypes
Define Scope
Product Analysis
Alternatives Generation
Create WBS
Decomposition
Work Package
Planning Package
Validate Scope
Inspection
Variance Analysis
Projectized Organization
Composite Organization
Activities
Mandatory Milestone
Optional Milestone
Sequence Activities
Mandatory dependencies
Discretionary dependencies
External dependencies
Internal dependencies
Lead
Lag
Parametric Estimating
Three-Point Estimating
Contingency reserves
Management reserves
Critical Path
Resource Leveling
Resource Smoothing
Schedule Compression
Crashing
Fast tracking
Hammock activity
Trend Analysis
Definitive estimates
Determine Budget
Cost Baseline
Project Budget
Precision
Accuracy
Cost-Benefit Analysis
Cause-and-effect diagrams
Flowcharts
Checksheets
Pareto Diagram
Control Chart
Scatter Diagram
Design of Experiments
Statistical Sampling
Quality Checklists
Quality assurance
Interrelationship digraphs
Tree diagrams
Matrix diagrams
Quality Audits
Process Analysis
Control Quality
Prevention
Inspection
Attribute sampling
variables sampling
OBS
RACI
Networking
Organizational Theory
Pre-assignment
Interpersonal Skills
Virtual Teams
Scheduled training
Unplanned training
Forming
Storming
Performing
Adjourning
Colocation
Sources of conflict
Collaborate/Problem Solve
Formal Communication
Informal Communication
The Seller
Fixed-price contracts
(FP-EPA)
CPFF
T&M Contract
Conduct Procurements
Weighting system
Bidder Conferences
Advertising
Analytical Techniques
Payment Systems
Procurement Audits
Risk appetite
Risk tolerance
Risk Threshold
Delphi technique
Checklist Analysis
Influence diagrams
SWOT Analysis
Risk Register
Avoid Strategy
Transfer Strategy
Mitigate Strategy
Accept Strategy
Exploit Strategy
Enhance Strategy
Share Strategy
Risk Reassessment
Risk Audits
Workaround
Power/interest grid
Power/influence grid
Stakeholder Register
Expert Judgment
Project Charter
Business Case
Facilitation Techniques
Preventive action
Deliverables
win-lose solutions
Prepared By Mahmoud Karem
Keywords
confidential information
More than 50 %
largest block
Technique used for dividing and subdividing the project scope and
deliverables
The WBS represents all product and project work, including the pr
management work
The cause and degree of difference between the baseline and actual pe
PM has Maximum Authority
Special Team
Inside the project team’s control , cannot test a machine until they ass
Estimate the minimum project duration , without regard for any res
limitations
measure of exactness
Assessment of correctness
vital few sources that are responsible for causing most of a problems
Problems
a data pointe exceeds a control limit (2) seven consecutive plot points
above the mean; or (3) seven consecutive plot points are below the
identify a problem, discover the underlying causes that lead to it, and
.preventive actions
can shorten the amount of time, cost, and effort needed to create the Pl
Resource Management , recommend exercising a flexible leadersh
mitigate human resource risks that may occur during or at the end of
learns about the project and their formal roles and responsibilities ,
members tend to be independent and not as open
technical decisions , Disagreements
The team completes the work , staff is released from the projec
can be viewed during the contract life cycle first as a bidder, then as th
source, and then as the contracted supplier or vendor
the Most Risky Contract on Buyer , Buyer can’t Define the Scope , If y
have Team to review the Invoices don't use it
used to ensure that all prospective sellers have a clear and comm
understanding of the procurement requirements , no bidders receive p
treatment
Below that risk threshold, the organization will accept the ris
likelihood
prioritized (High , low) for further Quantitative analysis , Lock-Up
increase the probability and/or the positive impacts , Adding more resou
activity to finish early
response plan that will only be executed under certain predefined con
triggering events , sufficient warning , If the Steel Prices will be 1000 E
purchase a Stock to be in my Warehouse
Used with The risk which has been happened and wasn’t unanticipate
Unforeseen
Assign project manager and give him authority , Link project to orga
strategic plan , May created by project manager but issued by spo
ensures the future performance of the project work is aligned with the
management plan
how project work will be authorized, ensure that the work is done by the
organization, at the right time, and in the proper sequence
Compromise
Collaborate/Problem Solve
Force/Direct
No. of Comm. Channels =
n(n-1)/2
n = No. of SHs
Question
Who does Select and Prioritize the Right Programs and Projects
The Top Management informed the IT Manager to terminate the Project and
the IT Manager informed the Project Manager to terminate the Project
correct sequence for these tools and techniques used in Project Time
Management
If the sponsor knows the Earned Values like SPI , CPI and so on and can’t
understand
Sponsor tells you that the project will be terminated because of Problems
in the credit limit of the bank . What could have done by the project
manager to prevent this
Your Team inspected the Site before formal join Visit with Customer , what
is the Process
You are approximately 50% physically complete with your project. The
project sponsor has just asked you, the project manager, for a listing of
when and how each of your staff is going to be released from the project.
Which of the following documents will you present to the project sponsor
to answer their question
How to Prevent ?
you realize that you will need 6 resources for 6 months. You can get only 2
resources after negotiating with the functional manager and as per the
organizational policy, you can hire 2 more in every 6 months. As a project
manager what will be your next step
your project team leave the site early at 2:00 pm Friday you would like to
establish clear expectations regarding the acceptable behavior of the team
member to avoid such situations
A conflict appeared between two members of your team. The conflict start
to impact the schedule of project tasks. What should you do?
What you need to Move forward with projects that would have been ignored
due to travel expenses
Can vary from a 5-minute agenda item and help individual team members
work together effectively
If there is a Conflict between two Members and one of them said to you , I
know that you will go with him , ok go with it
Emphasizing areas of agreement rather than areas of difference; conceding
one’s position to the needs of others to maintain harmony and
relationships
If the Customer request a Change and you don't have enough Budget for it
The information is provided in the right format, at the right time, to the right
audience, and with the right impact.
You need to get Approval for Scope Change from Virtual Team
You need to test your Product but you haven't the enough Cababilities to
do that < what you will do ?
You are New PM and the Sponsor informed you to refer to the Previous
projects but you didn't found any data , what the Previous PM Forgot to do
You found the Problems in Contract as the Cost was increased in Fixed
Price Contract , To Prevent that
You have Negotiated with the Customer about Specific Problem what will
you do next
You have Identified New Risks and closed outdated ones what will you do
Next ?
In the final stage of the project the sponsor rejected the final product where
he said it didn't met the project objectives. Which document you will review
to convince him
If the Question that you analyzed the Impact of Change and found that the
Schedule will increase by 2 Months
Audit project success or failure, gather lessons learned and archive project
information for future use by the organization
If the Sponsor informed you to terminate the Project , What will you Do
Next ?
Kick-off meeting happened at :
If the Sponsor informed you to terminate the Project and you have agreed
with the Supplier to Deliver Some Materials or Products
Answer
Portfolio Manager
Functional Organization
Precedence is Incomplete
Milestone chart
Performance report
Control Quality
Plan Human Resource MGMT Plan (OPA & EEF & Activity
Resource Requirements )
Ground Rules
Virtual Team
Team-Building Activities
Withdraw/Avoid
Smooth/Accommodate
Comporomise
Effective communication
Efficient communication
Sender Responsibility
Receiver Responsibility
.Meditation/arbitration
Negotiation then Meditation/arbitration then litigation
Secondary risk
Create SH Register
Sponsor
Project Manager
Project Charter
PM
scope baseline (If it will not be found in choices so choose
Project MGMT Plan)
Administrative Closure
Change Request