Electrical Engineering Workflow for Electrical Equipment specification & Purchase

Vendor
Procurement CBT PO
selection
Elec. Elec. Elec.
Elec.
Eqt Eqt Eqt
ECL PB SLD Eqt TBT ECL PB SLD
Electrical MR DS MR
DS
Engineering IFI IFP IFP

Typ.
control

© The Oil & Gas Engineering Guide, Editions Technip


diagrams
Electrical Eqt
Bids
Vendors

Process Eqt
P&IDs
Engineering list
I&C Control
Engineering principles

Plant Layout Plot SS Plot Plan


Engineering Plan locatio IFD
IFR n & size
Process 60% OF MOTORS/CONSUMERS
Equipment
Eqt power CONFIRMED BY VENDORS BEFORE

Vendors consumption PLACING PO FOR ELECTRICAL


EQUIPMENT
ECL = Electrical Consumers List, PB = Power Balance, SLD = Single Line Diagram, Eqt = Equipment, DS = Data Sheet, MR = Material Requisition, SS
= Sub-Station, IFI = Issue for Inquiry, IFP = Issue For Purchase, PO = Purchase Order, TBT/CBT = Technical/Commercial Bid Tabulation