You are on page 1of 21

BEST PRACTICE GUIDE

CONSTRUCTION RAILWAYS
OPERATIONS

MOVING LONDON FORWARD


Best Practice Guide – Construction Railway Train Movements Page 1 of 38
A best practice guide produced in collaboration between Index
INTRODUCTION Preface and Purpose Page 3

Part A – Tunnel Vehicle Movements


SECTION A1 Train Duties Page 5

SECTION A2 Roles and Competencies Page 6

SECTION A3 Pre-use Checks Page 10

SECTION A4 Vehicle Movement Safety Page 12


Joint Venture
Part B – Tunnel Vehicle Maintenance
SECTION B1 General Page 23

SECTION B2 Maintenance Plans – General Page 25

SECTION B3 Maintenance Plans – Specific Page 26

Part C – Tunnel Track Maintenance


SECTION C1 General Page 31

SECTION C2 Tunnel Works Tracks Permit Page 33

SECTION C3 Tunnel Track Maintenance Works Page 34

Part D – Additional Information


SECTION D1 Additional Information Page 38

Best Practice Guide – Construction Railway Train Movements Page 1 of 38 Best Practice Guide – Construction Railway Train Movements Page 2 of 38
Introduction
Preface The Railway and Other Guided Transport
Systems (Safety) Regulations (ROGS)
A fundamental element of the Crossrail do not apply to a construction railway,
project is the construction of a number although relevant sections should be
of tunnels under London; eight of these considered as a ‘best practice’ guide.
tunnels are being created using tunnel However, PUWER and CDM Part 4 both
boring machines (TBMs) which are used to apply to construction railways.
bore the tunnels and place concrete lining
segments. Each of these tunnels is served This Best Practice Guide details best
by a construction railway which is used practice standards specific to the
to transport personnel, equipment and movement of vehicles on a construction
materials into and out of the tunnel. railway. This guide will help to optimise
safe operation whilst at the same time
Each of the construction railways is maintaining efficiency and productivity.
operated differently with the result that
identified best practice tends to be limited This Best Practice Guide suggests
to single sites. This Guide has brought minimum requirements for the safe
together these best practices to ensure operation of the construction railway; local
that construction railways are operated arrangements should meet (or exceed)
equally safely across all Crossrail sites. these requirements.

This Best Practice Guide was produced This Best Practice Guide applies to all
as a result of collaboration between personnel with an involvement in the
Preface and Purpose

representatives from Crossrail and the movement of trains on the construction


three main tunnelling contractors engaged railway.
in TBM activities – BFK (C300), DSJV
(C305) and HMJV (C310). Thanks are due This Best Practice Guide should be used
to all those involved in the preparation, alongside:
review and issue of this Guide.
BS EN 1889-2:2003 – Machines for
Purpose underground mines – Mobile machines
working underground – Safety (Part 2:
A construction railway is defined as Rail Locomotives)
a temporary railway that is used on
tunnelling worksites and is exclusively BS 6164:2011 – Code of practice for
for the purposes of moving construction health and safety in tunnelling in the
related personnel, equipment and construction industry (in particular
materials only. A construction railway Section 23)
is not considered to be an ‘operational’
railway because it is not a part of the UK Local rules, procedures and processes Part A – Tunnel Vehicle Movements
railway network. governing safe operation of the
construction railway

Best Practice Guide – Construction Railway Train Movements Page 3 of 38 Best Practice Guide – Construction Railway Train Movements Page 4 of 38
Section A1 Section A2
Train Duties Roles and Competencies
Train duties (inbye) Haul out empty cars The Locomotive Driver shall: Check points are fully (and correctly)
engaged before entering any
Inbye trains will supply the tunnel and Typical train configuration - tunnel Be responsible for ensuring that all crossings
TBM with a number of items including working loads are properly secured before a
(but not limited to): loco movement is commenced (both Ensure that when propelling
A typical train configuration might inbye and outbye) (breasting) the train into the tunnel,
Operatives - transported on the man include: this is carried out in accordance with
rider only Be responsible for ensuring that BS 6164: 2011 (Section 23.1.3) – the
Segment cars/bogies identified defects are entered in the driver must have sufficient visibility
Emergency Response teams (when Daily Loco Checklist of the track ahead to be able to stop
required) Grout / concrete car within his field of view
Hold appropriate certification such
Grout / concrete – which is carried in Standard flat car for transporting as CPCS Certification (A67 Tunnel Be trained in the use of derailers,
purpose built vehicles temporary materials Locomotive, Diesel, Category D, all wheel blockers, Manchester gates
sizes) or equivalent etc
Temporary materials – pipes, Manrider
brackets, walkway, oils, greases, soil Have received a minimum of 30 Be trained in the use of
conditioning agents Locomotive hours familiarisation training in communications systems and all
accordance with local arrangements relevant procedures and protocols
Electrical equipment and Variations in the train composition may and have been assessed as
miscellaneous items of small plant - be required during service periods (e.g. competent Be trained in the use of fire
Duties and typical configurations

Duties and competence requirements


transported on a flat car in a purpose cherry-picker, HIAB crane etc.). extinguishers and relevant fire
built stillage Successfully complete Crossrail fighting equipment
Each locomotive will be known as (and Tunnel Safety Card (TSC) training
Tunnel lining segments - carried by controlled by) a specific individual Be trained in the application of this
purpose designed segment cars designation (which will be marked Attend local Tunnel Induction Best Practice Guide. This training will
on each locomotive) in the following training and be trained in the be supported by refresher training
Train duties (outbye) format: requirements of this Best Practice and any other briefings as deemed
Guide appropriate by local management
Outbye trains will: Locomotive + “Number” i.e.
“Locomotive 1” Be appointed as a Locomotive Driver
Provide egress for operatives by way in writing by site management;
of the man rider Should a locomotive be required to records of this are to be held on
service either tunnel or switch from site in accordance with BS6164:2011
Carry maintenance equipment, westbound to eastbound, a locomotive (23.1.1)
rubbish, empty drums and other designation shall be assigned to avoid
waste materials out in purpose built any confusion between the Operations Be fully briefed and conversant with
stillages on flat cars Board Controller (OBC) and driver. all relevant local procedures

When transporting compressed gas A driver will be assigned to each Be aware of track walking
bottles (e.g. propane, fuel gas) use a locomotive on a shift by shift basis. procedures, persons walking on the
protective steel enclosure, mounted track, persons working on the track,
on a flat car and under a Permit to track possessions etc
Work (PTW)

Best Practice Guide – Construction Railway Train Movements Page 5 of 38 Best Practice Guide – Construction Railway Train Movements Page 6 of 38
Operations Board Controller (OBC) The contractor will ensure that there are Flagman
local instructions in place which cover
The Operations Board Controller shall: key issues including: Where a flagman is engaged (e.g. at a
California crossing) they shall:
Be responsible for the management Use of the Operations Board
of all railway movements Hold CSCS Certification RED
What information is recorded (Experienced Worker)
Have been assessed as competent
to carry out all activities associated How and where information is Receive a minimum of 12 hours
with the role recorded familiarisation training

Be responsible for maintaining a How train locations are known by Have been assessed as competent
record of all hazardous materials the OBC to carry out all activities associated
contained in each load so that with the role
appropriate information is available Priority assignment on California
should an emergency arise crossings Successfully complete Crossrail
Tunnel Safety Card (TSC) training
Hold PTS (Personnel Track Safety) Note: Where there is a permanent single
certification only if there will be a line running arrangement (i.e. only one train Attend local Tunnel Induction
requirement for them to go on or on the track at any given time), it will not training
about the operational railway (i.e. be necessary to engage an OBC, but ONLY
Network Rail) if the contractor has put in place adequate Be fully briefed and conversant with
arrangements to protect the train and those all relevant local procedures Back-up operator / slinger
Have experience of a similar role working in the tunnel.
Be trained in the application of this The Back-Up Operator shall:
Successfully complete Crossrail Best Practice Guide. This training will
Tunnel Safety Card (TSC) training be supported by refresher training Hold CSCS Certification RED
and any other briefings as deemed (Experienced Worker)
Attend local Tunnel Induction appropriate by local management
training and be trained in the Have experience of working within
requirements of this Best Practice and on a TBM
Guide
Have receive a minimum of 12 hours
Be fully briefed and conversant with familiarisation training
all relevant local procedures
Have been assessed as competent
Be trained in the application of this to carry out all activities associated
Best Practice Guide. This training will with the role
be supported by refresher training
and any other briefings as deemed Have successfully complete Crossrail
appropriate by local management Tunnel Safety Card (TSC) training

The contractor will ensure that there is Attend local Tunnel Induction
adequate cover for this post at all times. training

Best Practice Guide – Construction Railway Train Movements Page 7 of 38 Best Practice Guide – Construction Railway Train Movements Page 8 of 38
Be fully briefed and conversant with Section A3
Pre-use Checks
all relevant local procedures

Carry out all duties as defined in


local working instructions Locomotives and rolling stock receiving instructions at the start of
each shift.
Operate the Manchester gate as and Locomotives and rolling stock scheduled
when required for use will be inspected by the driver at Train-borne plant
the start of each day to ensure that it is
Supervise the ingress / egress of fit for service and capable of delivering The following items are to be checked
personnel movements into and from safe operation. This inspection will by fitters at predetermined periods:
the stationary man rider include a brake functionality test (as
required by BS 6164:2011). The engine compartment fire
Be trained in the application of this
Best Practice Guide. This training will suppression system
be supported by refresher training The Daily Loco Checklist (DLC) remains
and any other briefings as deemed on the locomotive; any defects or issues The hydrostatic transmission and
appropriate by local management identified by the driver are to be logged retarder
at the first available opportunity prior
to use. Pneumatic wheel brakes

Unserviceable safety critical equipment In addition, couplers and chains (for


must be removed from use as soon as a the rolling stock) are to be checked by
defect is identified. drivers before each movement.

Actions to be taken prior to use


The DLC is to be checked daily by the Should any of the above items be found
locomotive fitters who will: to be defective during checking, the
loco fitter should be consulted and
Review entries appropriate remedial action taken.

Carry out and record any necessary Training and briefing


repairs
The following are to be applied:
Schedule or carry out routine
maintenance as appropriate Locomotive drivers must have
received familiarisation training on
Report recorded defects to the OBC the locomotive they are driving and
have been assessed as competent
Complete a record of all work carried to drive
out on the locomotive
All personnel on site are to be
The driver will test on board briefed in the communication
communications and confirm both procedure so that they are aware of
the locomotive and communications actions to take in the event of an
are operational with the OBC prior to emergency

Best Practice Guide – Construction Railway Train Movements Page 9 of 38 Best Practice Guide – Construction Railway Train Movements Page 10 of 38
Locomotive driver aids Communications and signalling Section A4
Vehicle Movement Safety
equipment
The following checks are to be carried
out by the loco driver at the beginning The following will be applied for
of each shift: communications and signalling General Apart from walking along approved
equipment: safe walking routes, personnel
CCTV system is functionally tested The OBC will be located within transport into the tunnel will be by
and camera lens wiped clean The tunnel radio system is to be a clearly defined area and will man rider only. Travelling on any
functionally tested by the OBC at be in overall charge of all train other part of the train is prohibited
Functional brake test the start of each shift movements between the yard / loco
stabling area and TBM Carrying work equipment or
Test that lights are operational and The CCTV system (where installed) is materials in the man rider is
showing correct direction of travel to be functionally tested by the OBC The Pit Boss (or designated prohibited EXCEPT for surveying
at the start of each shift operative where there is no Pit equipment
Communication system is Boss) will be in charge of all train
functionally tested Signs are to be installed establishing movements up to the TBM Pedestrians are not allowed into
the maximum speed at relevant tunnels unless carrying out surveys,
Locomotive Electronic Control is sections (e.g. California crossings) The Back-Up operator will be in track inspections, maintenance
tested control of all train movements etc. In such cases, access is only
“Trains have priority” signs are to be within the TBM for segment permitted under the control of the
Horns tested installed at all level crossings movements, train unloading OBC and with an appropriate Permit
movements and personnel to Work in place
Note: The locomotive should not Cameras are to be installed, tested, movements
be used if any of these systems are certified and working at both ends Pedestrians are only permitted
defective. of all crossings Where flagmen are used they will to cross the track on marked safe

Carrying out safe vehicle movements


direct all trains as required and walking routes
Rail Movement Control Centres The following horn blasts are to be always under the control of the OBC
(RMCCs) used in the tunnels to designate the and yard staff to ensure safety All tools and materials are to be
imminent action of a loco: kept clear of the track at all times
Where RMCCs are in use, the following In addition to being appropriately UNLESS work is being carried out
will apply: 3 blasts Moving outbye trained and certificated, locomotive on the track. All such work will be
drivers will have read the operations carried out under (and in accordance
Where the RMCC is equipped 2 blasts Moving inbye manual for the locomotive they are with the requirements of) a Permit
with CCTV cameras they are to operating, and will have been briefed to Work issued by the OBC
be tested and confirmed to be 1 long blast Stopped on this Best Practice Guide
working correctly by the OBC at the The tunnel will be equipped with
beginning of each shift A continuous blast is to be given when Passengers are not permitted in the a communication system allowing
the driver identifies personnel ahead in locomotive cab at any time EXCEPT radio communication between
The communication system in the the tunnel who have not acknowledged the loco operator and other tunnel
RMCC is tested and confirmed to be and moved out of the way of the train. • when the driver is under training personnel
working correctly by the OBC at the and the passenger is the
instructor
beginning of each shift
• if the passenger is someone
authorised to inspect track,
signals etc. (but only if there is
a seat in the loco cab)

Best Practice Guide – Construction Railway Train Movements Page 11 of 38 Best Practice Guide – Construction Railway Train Movements Page 12 of 38
Inbye and outbye trains will The loco driver will be responsible
signal their intention to move in for carrying out checks to ensure
accordance with local instructions. that there is adequate clearance
Appropriate coloured lights at along the route for the train to travel
the front and rear of the train will safely without risk of colliding with
indicate direction of travel obstructions; adherence to gauge
limits must be ensured
Where local noise restrictions exist,
alternative arrangements will be put Tampering with couplings is
in place for noise restricted times forbidden

Train movements in working areas Prior to inbye movements, both the


of the TBM will be controlled by loco driver and the yardman will
the local TBM traffic light; the loco check train loads to ensure they are
driver will comply with the traffic secure
lights which are controlled by the
appointed Back-Up Operator Engines should be switched off
when not required to reduce
Parked trains or trailers will be unnecessary fuel consumption and
individually air braked and wheel emissions
scotches placed under wheels of
uncoupled rolling stock. Scotches Tunnel movements When passing personnel in the
may be of wooden or metal tunnel the train driver will sound the
construction. Dog chains (or similar) The following are to be applied for all horn to advise of his approach; the
are not permitted tunnel movements: personnel concerned are to wave a
hand to acknowledge that they are
Brakes and scotches / rail clamps The maximum train speed within aware of the approaching train
are to be applied on static uncoupled the tunnels is to be displayed on
trailers to prevent them running signposts at appropriate locations; Walking in the tunnels is not
away this speed limit is an absolute and is encouraged. However it is
not to be exceeded at any time acknowledged that teams are
The loco driver will be responsible required to work in the tunnels at
for carrying out checks of the loco The maximum speed for traversing certain times. When doing so they
to ensure that it is fit for service. a California crossing will be 5km/h; will protect their working area with
Checks are to be carried out in warning notices are to be placed advanced warning lights which may
accordance with the mechanical 60m either side of the crossing be obtained from the OBC; these
and operational manual checklists instructing loco drivers to slow down warning lights are to be placed 60m
provided by the loco manufacturer either side of the work area. Such
Movement direction lamps at the works may only be carried out under
front and rear of the train are to be a controlled Permit to Work (PTW) in
illuminated at all times to indicate accordance with local arrangements
the direction of travel. The lights
should show white at the front of
the train in the direction of travel
and red at the rear when a travel
direction is selected

Best Practice Guide – Construction Railway Train Movements Page 13 of 38 Best Practice Guide – Construction Railway Train Movements Page 14 of 38
PTWs will be held by the OBC who is Uncoupling trailers Coupling trailers Trains entering the TBM backup
responsible for briefing all relevant
personnel on the content of the The following actions are to be taken The following actions are to be taken The following rules are to be applied for
PTW including the nature of the when uncoupling wagons and trailers: when coupling / uncoupling wagons and all trains entering the TBM backup:
work and number of personnel in the trailers:
work group Apply parking brakes and put The train must signal its arrival by
scotches / chocks in place before Where Manchester gates have been sounding the horn in accordance
Loco drivers are to be continuously uncoupling; no unbraked vehicles installed, they must be kept closed with local procedures and stop in
advised of all PTWs that are should be allowed in the tunnels until the fully coupled train is ready front of the Manchester gate
introduced / signed off during a to move into the tunnel
shift Install the scotch / chock on the No train movements are to take
downhill side of the trailer; if Ensure scotches / chocks are in place place at the rear of the TBM until
PTWs are only signed off when the ‘downhill’ is not clear (or if the before commencing coupling the Back-Up operator on the TBM
work is complete, the site has been vehicle is on level ground), clamps has confirmed to the loco driver
made safe and all members of the should be applied at both back and Connect vehicles using couplers that:
working group are accounted for. A front and secure the safety chain. Safety
PTW may be passed to a subsequent chains must be loose enough to • All personnel are clear of the
working group, but the names of all Verify that brakes are still on allow the trailers to travel round track
outgoing and incoming personnel bends in the tunnel but not so long • No personnel are attempting to
must be recorded in accordance with Disconnect lighting, CCTV and that they are able to touch the track board or disembark from the man
the local PTW procedure telephone cables rider
Connect the hydraulic brake lines.
There will be intermediate stop Disconnect hydraulic brake lines Care must be taken to ensure that The appointed Back-Up Operator
points (crossings and booster ensuring that all supplies are connections are clean and seated will co-ordinate with the Pit Boss
locations) where workers will be isolated as per the operational properly with no leaks. Visual / via two-way radio to sequence the
able to alight, but always within the instructions for the vehicle audible checks are to be carried out. unloading of the train at the various
confines of the PTW and under the Hydraulic pipes must not touch the gantries where the traffic light
control of the OBC Check again that the brake is applied track controls are placed
and that scotches / chocks are firmly
Personnel may only board / in place Connect lighting, CCTV and When the Manchester gate is open
disembark from a Manrider in telephone cables the free access will be indicated with
the tunnels when the Manrider Disconnect the safety chain and a green light indicating permission
is stationary in an appropriately then uncouple the vehicle Once all the above connections to move inbye. The Manchester gate
designated area have been completed the scotches opens only through hand operation
The vehicle may now be left / chocks may be removed and the controlled by the appointed Back-Up
All derailments must be reported vehicle can then be moved Operator
for appropriate investigation,
identification of trends and NOTE: Vehicles should not be moved until
implementation of corrective the driver has confirmed that the train is
actions. Should a derailment occur, fully functional.
local procedures for re-railing are to
be followed

No work is permitted to start in the


tunnels until a Permit to Work is in
place.

Best Practice Guide – Construction Railway Train Movements Page 15 of 38 Best Practice Guide – Construction Railway Train Movements Page 16 of 38
The locations for stopping the train Track inspections and maintenance In the event of a derailment,
will be marked on the gantries and any affected track must be fully
indicated by a switch of the traffic Track inspection and maintenance inspected and appropriate remedial
light to red. Entry to the rear of the activities will be completed by a action taken where necessary
TBM must be at creeping speed dedicated track maintenance team on
a scheduled basis (additional works will Spillage of materials that may
One long blast on the loco horn will be carried out as necessary). This work affect safe train operation will be
be used to indicate that the loco has will be compliant with the following: reported to the OBC who will make
stopped moving and brakes have arrangements with the Pit Boss
been applied. Personnel entering or Local processes will be in place to / Tunnel Superintendents for the
leaving the man rider will only do detail routine maintenance, planned spillage to be cleared as soon as
so when given the all clear by the preventive maintenance, breakdown practical
appointed Back-Up Operator repair protocols and re-railing
procedures Track geometry will be checked
Once the train is unloaded it will (gauge and rail inclination). Special
leave outbye the TBM backup at Local processes should include attention is to be paid to track at the
creeping speed once a blue light is information on when train portals and sections with very small
displayed movements are to be stopped radius (<40-50m) in order to avoid
for emergency maintenance (e.g. derailments
The Appointed Back-Up Operator will submerged track, build up of grease
check before permitting movement in points etc.) Checks are to be carried out on the
of the man rider that no personnel different geometrical parameters of
are attempting to board the train The Designated Person / Persons the California crossings in order to
before it departs undertaking track maintenance avoid derailments
must be known / communicated to
Once the operation is complete, drivers and other tunnel personnel Following any change to the
the loco will not be permitted to track, gauge is to be checked and
move off until the appointed Back- All track maintenance and inspection movements only permitted when
Up Operator has indicated to the activities must be carried out under confirmation is given that gauge is
loco driver that no personnel are a Permit to Work issued by the OBC correct
attempting to board or disembark
from the man rider Any track defects are to be reported Personnel working on the railway
to the OBC as soon as they are will wear the appropriate PPE and
Immediately prior to moving off the identified, by whoever identifies will operate under a Permit to
loco driver will sound three blasts them Work in accordance with the local
of the loco horn to indicate that the procedure
loco is moving outbye In order to avoid derailments, the
track will be inspected visually The invert is to be kept clear
during the routine maintenance of hazards as far as reasonably
shift. Bolts will be retightened as practicable; the underside of the
necessary rails must be visible above any muck
in the invert
Visual inspections are carried out
following any change to the track;
fishplate bolts as well as any other
clips and fixings are to be physically
checked

Best Practice Guide – Construction Railway Train Movements Page 17 of 38 Best Practice Guide – Construction Railway Train Movements Page 18 of 38
Loading and unloading (yard) Loco and train maintenance Refuelling

The following are to be applied for The locomotives and trailers are Refuelling will be at a dedicated
loading and unloading activities: to be checked and maintained and segregated area as far from the
according to the manufacturer’s works area as practicable
The yardman is responsible for operation manual
supervising the loading/unloading of The refuelling point will be in open
all plant, equipment and materials Maintenance is only to be carried out air; fuel will be obtained using a
onto / off of trains by competent personnel appointed hose and trigger nozzle from a tank
in accordance with the requirements located on the surface
On each trip to and from the of BS 6164 : 2011
yard and TBM a record is to be The trigger is to be locked off when
maintained of what has been A record is to be maintained of all not in use
loaded / unloaded onto each loco; maintenance and repairs carried out
the departure time is also to be on the loco and trailers Bulk spill containment, fire
recorded extinguisher and oil binder will be in
Where a defect has been identified place as close to the fuelling point as
When loading / unloading in the yard that makes the loco / train unfit for practicable
the yardman and the loco driver must safe use, it is not to be used until
make sure materials are: appropriate remedial action has Leaving the nozzle unattended while
been taken refuelling is underway is prohibited
Correctly loaded Loading and unloading (TBM) in all circumstances; if it is necessary
Maintenance and repairs are only to leave the refuelling point the
Secured to prevent them from The Pit Boss (or in his absence the to be carried out in designated nozzle must be removed and
moving lead miner) and the loco driver must areas. It is forbidden to carry out replaced in its’ retainer on the pump
make sure that a competent person any maintenance / repair activities
Not in excess of the maximum load supervises the loading/unloading of outside the designated areas Communications protocols
for the loco the loco. This includes ensuring that the EXCEPT when the train has failed
load is: in the tunnel and must be repaired OBCs are to have overall responsibility
before it can be moved for management of communications. In
Correctly loaded all cases:
Use of new plant
Secured to prevent movement Instructions issued by the OBC are
The Tunnel Manager must approve to be followed UNLESS it is believed
Within the maximum load limit for any new plant that is to be used in that the instruction may present a
the vehicle the tunnel risk

Within the maximum gauge limit for All plant must be recorded on the
the track asset register and regularly checked
and maintained in accordance with
The Pit Boss (or in his absence the lead manufacturers recommendations
miner) and the loco driver must sign
the loading note and train log book to Maintenance records are to be kept
certify the load as being correct and for the new piece of plant, along
safe to travel. with records for all other plant
currently in use

Best Practice Guide – Construction Railway Train Movements Page 19 of 38 Best Practice Guide – Construction Railway Train Movements Page 20 of 38
Instructions issued by the OBC take precedence over all other instructions relating
to the railway UNLESS it is believed that the instruction may present a risk

All communications relating to incidents (including near misses) are to be


recorded by the OBC

When communicating alphanumerics, the phonetic alphabet is to be used at all


times (see Section D)

Emergencies

Local emergency response procedures are to be followed.

Part B – Tunnel Vehicle Maintenance

Best Practice Guide – Construction Railway Train Movements Page 21 of 38 Best Practice Guide – Construction Railway Train Movements Page 22 of 38
Section B1 The maintenance plan.

General This is the structured set of tasks that include the activities, procedures, means
and the working time required to carry out the maintenance task
All rail vehicles are required to be The limit values for components
maintained in accordance with a which must not be exceeded It contains a description of the maintenance activities which include the following:
maintenance plan. in service shall be stated. The
possibility to specify running • Disassembly / assembly drawings & instructions necessary for correct assembly /
The organisation responsible for restrictions in degraded mode (limit disassembly of replaceable parts
management of the construction value reached) can be considered
railway must obtain the maintenance • Maintenance criteria
documentation which details vehicle Records of maintenance work
maintenance activities from the vehicle carried out • Checks and tests
manufacturer. Maintenance activities • Tools and materials required to undertake the task
include all activities necessary such
as inspections, monitoring, tests, • Consumables required to undertake the task
measurements, repairs, replacements
• Personal protective safety provision and equipment
and adjustments.
• Necessary tests and procedures to be undertaken after each maintenance operation
Maintenance activities are split into: before re-entry in to service of rolling stock

Preventive maintenance; scheduled • Checks on lifting / jacking point


and controlled
Troubleshooting (fault diagnosis) manuals or facilities for all reasonably
General requirements for maintenance documentation

Corrective maintenance (repair) foreseeable situations. This includes functional and schematic diagrams of the
systems or IT-based fault finding systems
Maintenance documentation should
include the following:

Component hierarchy and functional


description. The hierarchy should list
all the items belonging to the vehicle
and use an appropriate number of
discrete levels; the lowest level shall
be a replaceable unit

Schematic circuit diagrams,


connection diagrams, wiring
diagrams, pneumatic schematics
and lubrication diagrams

Best Practice Guide – Construction Railway Train Movements Page 23 of 38 Best


Best Practice
Practice Guide
Guide –– Construction
Construction Railway
Railway Train
Train Movements
Movements Page
Page 24
24 of
of 38
38
Section B2 Section B3
Maintenance plans - General Maintenance Plans - Specific
Relevant to all vehicles • Technical instructions that define Relevant to all vehicles Functional tests of the brake
actions required to ensure that systems should be carried out to
Vehicle maintenance activities are a vehicle can be hauled safely Wheelsets ensure that they are operating
only to be carried out by appropriately when inoperative (e.g. the correctly. This should take into
adjustment, isolation, removal The maintenance plan shall, as a account the environment in which
qualified personnel.
or addition of some components
or the imposition of a restrictive
minimum, set out the requirements for the vehicle is being used
The maintenance plan shall detail maximum speed to travel the following items of the wheelset and
all maintenance activities to be constituent parts: The functional brake tests should
undertaken on the applicable type of • The minimum engineering show that the systems respond
rail vehicle maintenance facilities that are Relative movement of wheels, axles, to graduated brake application
necessary for the maintenance tyres and axle mounted equipment demands, up to and including an
to be carried out (e.g. pits, major emergency stop
The maintenance plan should
equipment, covered work areas)
include all maintenance activities Cracks and fractures
that must be carried out to ensure • The minimum level of Brake cylinder pressures should be
that the rail vehicle(s) continue to competencies required for the Dimensions affecting running checked to confirm that pressure
conform to the safe limits defined staff carrying out the specified safety: increases in proportion to the
by the vehicle manufacturer maintenance tasks controller movement
• Minimum wheel diameter
The maintenance plan shall, as a Each rail vehicle shall be maintained Appropriate functional brake tests
• Tolerance between diameters of
minimum, include the following: so that the prescribed tolerances for should be undertaken whenever
wheels on the same axle
all components and assemblies are components of the brake system
General requirements for a maintenance plan

Specific requirements for a maintenance plan


• Maintenance requirements not exceeded throughout the life of • Tolerance between diameters of are replaced and reconnected or
including the safety conditions the vehicle wheels on the same bogie or rail following component repair, renewal
to ensure the rail vehicle can be vehicle or disconnection
safely worked on for each task
• Back to back dimensions
• A maintenance schedule which If a fault in a brake system or
defines the periodicity at which • Flange and tread profile component is revealed by either
each item shall be actioned • Wheel tread surface damage the maintenance or functional
brake tests, details of appropriate
• An inspection programme for • Wheel flat limits remedial action should be available
regular inspection of the vehicle
to confirm that it is safe to
in the maintenance plan
continue in service Brakes

• Definitions of the appropriate The maintenance plan should detail


actions to be taken to ensure that the components of rail vehicle
that all systems and equipment brake systems are maintained at
continue to operate safely over appropriate periods
the full range of environmental
conditions, particularly in snow,
flood, freezing or abnormal heat Maintenance activities and periods
must be designed to ensure that
the brake systems function correctly
and safely between maintenance
activities

Best Practice Guide – Construction Railway Train Movements Page 25 of 38 Best Practice Guide – Construction Railway Train Movements Page 26 of 38
The maintenance plan shall, as a The speedometer test shall cover Trainborne signalling and
minimum, set out the requirements the whole range of the speed communications equipment
for (where fitted): indicating equipment. The test, shall
cover: All signalling and communications
• Brake disc integrity, condition and equipment shall be managed
dimensions • The accuracy of readings to ensure that its integrity and
• Brake pad and brake block performance remains compliant with
• Intermittent or jerky operations
integrity and dimensions its specification
• Clarity and cleanliness of
• Brake rigging (pins, bushes and indicators and correct operation The maintenance requirements for
associated equipment) of associated lighting each item of trainborne signalling
• Integrity of operating devices, • The integrity of connections and communication equipment shall
reservoirs, hoses, cocks, and components that cannot be be developed to control the risks
pipework, safety loops and included in the equipment test which would arise from failure of any
associated equipment part the system
As a minimum, speedometer and
Rail vehicle structure speed control system testing shall The maintenance requirements Other equipment
be undertaken in the following for trainborne signalling and
Vehicles shall be maintained so that circumstances: communication equipment shall be Consideration shall be given to the
the body and running gear remain documented following during the production of
structurally sound and safe • When a wheelset has been the maintenance plan. The list is not
replaced Maintenance requirements shall exhaustive or necessarily representative
Vehicles shall be maintained so that form part of the rail vehicle of all types of vehicles used on
• When a wheelset has been construction railways.
the connections between the body re-profiled
maintenance plan for the vehicle
and running gear remain structurally
sound and safe • When the speed indicating The procedures to ensure Buffers:
equipment, speed control system configuration control of any
Prescribed tolerances must be or their components have been software and hardware shall also • Heights
checked and maintained – this disturbed, adjusted, repaired or be documented in the maintenance
replaced • Integrity and condition
includes all components, assemblies plan
and systems • When there has been a report • Greasing
of a malfunction of the speed Headlights
Speed indicating equipment indicating equipment or speed Drawgear:
control system The maintenance plan shall set out a
The maintenance plan must • When there has been a report
method for testing the functionality • Dimensions
include a method for testing speed questioning the accuracy of the and alignment of the headlights
• Rubber condition
indicating equipment – this must speed indicating equipment or
include acceptable tolerances. If speed control system Testing of the headlights shall be • Integrity and condition
readings are outside this tolerance, carried out at a periodicity to reflect
• Following an allegation of • Operation
the speed indicating equipment the use and working environment of
exceeding the speed limit the vehicle
must be corrected before the vehicle
re-enters service

Best Practice Guide – Construction Railway Train Movements Page 27 of 38 Best


Best Practice
Practice Guide
Guide –– Construction
Construction Railway
Railway Train
Train Movements
Movements Page
Page 28
28 of
of 38
38
Primary and secondary suspension: Internal combustion engines:

• Spring integrity, rules for • Security and condition of


changing mountings
• Linkage wear, dimensional limits • Checks for leakage of fluids
• Suspension settlement • Integrity of shaft couplings

• Damper integrity • Engine safety systems (for


example, overspeed, crankcase
Suspension tube bearings: explosion)
• Emissions (compliant with
• Condition, integrity and security specification)
of components and installation

• Bearing float Power systems (including associated


protection systems):
Traction and auxiliary generators,
alternators, other electrical • Integrity and security
machines and electrical equipment • Earthing condition and integrity
cases:
• Presence, condition and cleaning
• Integrity and security of all safety labelling

• Earthing condition and integrity


• Presence, condition and cleaning Hydraulic and pneumatic systems:
of all safety labelling
• Condition and integrity of hoses,
Cleaning: pipework, valves, etc

• Ventilation ducts Fire protection systems:


• Bogies and underframe • Integrity and condition
equipment
• Currency of certification
• Front end and windscreens
Lighting Systems
Final drives / transmissions:
Emergency Facilities:
• Security to body or bogie frame
• Condition checks of safety critical • Emergency lighting capacity
items • Other emergency and safety
equipment provided
• Lubrication
Part C – Tunnel Track Maintenance
• Safety loops
• Presence and security of balance
weights, where fitted

Best Practice Guide – Construction Railway Train Movements Page 29 of 38 Best


Best Practice
Practice Guide
Guide –– Construction
Construction Railway
Railway Train
Train Movements
Movements Page
Page 30
30 of
of 38
38
Section C1 Track Inspector Operations Board Controller (OBC)

Roles and Competencies The Track Inspector shall: The Operations Board Controller (OBC)
shall:
General Mechanical Superintendent Be responsible for carrying out
inspection and maintenance Provide protection for track
This Section defines the general duties The Mechanical Superintendent (or of track, California crossings, inspectors whilst undertaking
and competence requirements of equivalent) shall: sleepers, fishplates and associated track maintenance and inspection
personnel with a role in maintaining components to the standards activities
track, crossovers and associated Be responsible for ensuring that prescribed in the contractors’ track
equipment on the construction a track maintenance programme maintenance procedures Communicate with all locomotive
railway. It should be referred to when is in place covering all tunnel drivers when track inspectors are
clarification is required on specific railways track, California crossings, Have received training and hold working in the tunnel
responsibilities. sleepers, fishplates and associated the necessary competence in the
components inspection and maintenance of track Arrange the safe system of work
The role titles used below may not so the location of track inspectors
necessarily correspond with job titles in Ensure that all track and associated Report any track defects to the working in the tunnel is known
the Contractors’ organisation, however equipment is inspected on a regular Operations Board Controller (OBC)
the Contractor will be expected to basis and to a pre-determined and Mechanical Superintendent Note: The Contractor shall ensure that
demonstrate that the responsibilities frequency (see section C3 of this there is continuous cover for this post at all
listed below have been discharged by Best Practice Guide) Be responsible for maintaining a times.
a competent person with sufficient record of all track inspections Where there is a permanent single line
knowledge and experience. Ensure that a forward-looking running arrangement (i.e. only one train
programme is in place covering the Hold CPCS Certification on the track at a given time), it will not be
inspection and maintenance of track necessary to engage an OBC, but only if
and associated components
General duties and competence requirements

Successfully complete Crossrail the contractor has put in place adequate


Tunnel Safety Card (TSC) training arrangements to protect the train and those
Hold CPCS Certification working in the tunnel through a permit to
Attend local Tunnel Induction work system.
Successfully complete Crossrail training and be trained in the
Tunnel Safety Card (TSC) training requirements of this Best Practice
Guide and the Contractor’s Track
Attend local Tunnel Induction Maintenance Procedures
training and be trained in the
requirements of this Best Practice Note: Tracks laid in the TBM are to be
Guide and the Contractor’s Track inspected immediately after installation. This
Maintenance Procedures can be carried out by an inspector or by any
suitably qualified member of the track gang.

Best Practice Guide – Construction Railway Train Movements Page 31 of 38 Best Practice Guide – Construction Railway Train Movements Page 32 of 38
Section C2 Section C3
Tunnel Tracks Work Permit Tunnel Track Maintenance Works
Arranging the Track Works Permit Issuing the Tunnel Track Works Permit Track Inspection Programme Track Inspections
Before any track inspection or The OBC will sign the The Mechanical Superintendent The Track Inspection Programme
maintenance work is carried out, Tunnel Track Works will develop a forward-looking shall ensure that every section of
the Track Inspector (or other person Permit and the permit programme of track inspections track is inspected at least once every
undertaking work on or about the track) will then be approved covering a 12 month period 2 weeks
shall report to the OBC to arrange for by the Mechanical
a Permit to Work – the Tunnel Track Superintendent, Tunnel The Tunnel Track Inspection The track inspection will be
Works Permit - to be issued. The OBC Superintendent, Pit Programme will detail the sections undertaken on foot under adequate
will raise the Tunnel Track Works Permit Boss or other nominated of track to be inspected on a lighting conditions. Where 2 or more
which will specify, as a minimum: person named in the contractor’s local particular track patrol, identified by lines exist on a stretch of track, each
procedure. segment ring number line shall be walked separately
The location of the works to be
carried out A permit to work must be issued when The Tunnel Track Inspection The track inspection will include a
entry to the tunnel is required to carry Programme will also define any visual examination of the condition
The names and details of persons out track inspection or maintenance components, for example California of the track and identification of any
undertaking the track inspection and duties, irrespective of whether train Crossings, which require specialised rail defects, pitting, track spread or
maintenance works movements are taking place or not. inspections other than a normal rail buckles
Arrangements for issuing the Tunnel Track Works Permit

visual check
The means of communication Cancelling the Tunnel Track Works At regular intervals defined in the
between the Track Inspector and the Permit Additional visual track inspections contractor’s track maintenance
OBC during the works

Inspection and maintenance requirements


shall be undertaken following any procedure, the track gauge will be
Upon completion of the works, the Track reported rough ride, derailment or measured and recorded using a
The duration of the work to be Inspector will notify the OBC that: track defect observed by the loco calibrated track gauge. Where the
carried out drivers gauge is outside the prescribed
All personnel are clear of the track tolerance of 900mm +/- 25mm, the
The nature of the work and any and are in a position of safety OBC shall be notified immediately
requirements for train movements
to be suspended or restricted All tools and equipment have been Any significant defects in the
(for example a temporary speed removed from the track track, for example broken rail,
restriction during or after the works) track spread, buckled rail shall
The track is safe for normal be reported to the OBC and train
The time at which the permit will be operations to be resumed, unless movements suspended until repairs
closed operating restrictions (for example a have taken place or the Mechanical
speed limit) need to remain in place Superintendent has confirmed that
it is safe for passage of trains

Track inspections shall be recorded


on a proforma defined in the
contractor’s track maintenance
procedure

Best Practice Guide – Construction Railway Train Movements Page 33 of 38 Best Practice Guide – Construction Railway Train Movements Page 34 of 38
Track Bed Inspections of the California Crossing The section of track patrolled –
shall include: identified by segment ring numbers
The track inspection shall include a
visual examination of the sleepers & A visual check of the crossing, The line patrolled, where more than
track bed, which will take place as part including the switch blades, for signs one exists
of the track inspection, including: of damage, corrosion, wear and
obstructions in the switch blades Nature of any defects identified
Loose or missing Pandrol clips, or
other rail to sleeper fixture A check of the movement of the Any work that was identified from
switch blades from normal to the inspection that could not be
Broken or damaged sleepers reverse positions and back completed at the time

Loose or damaged “anchors” which Application of mineral or bearing Overall remarks on the condition of
connect the sleepers to the concrete California Crossings grease to the moving parts of the the track and any potential defects
segments switch blades which could arise before the next
California Crossings represent a higher scheduled inspection
Build up of oil, waste material, or risk of derailment than plain line track A visual check of the mechanical
excessive water on or around the and therefore an enhanced inspection parts of the California Crossing,
track bed regime shall be adopted. to include the tie rods, stabilisers,
section connections, point levers and
Fishplates and bolts The frequency of inspections of spring mechanisms
California Crossings and associated
The track inspection shall include a switches shall be at least twice weekly. In the case of a post-derailment
visual examination of the fishplates and Inspections shall be undertaken by the inspection, the Track Inspector shall
fishplate bolts, which will take place as Track Inspector and recorded on the observe train movements in both
part of the track inspection, for: contractor’s record of track inspection. directions over the crossing to check
the operation
Loose or missing fishplate bolts Inspections of California Crossings shall
additionally be undertaken following Records of Track Inspections
Broken or cracked fishplates any report of rough ride, derailment or
other malfunction reported to the OBC. A bespoke record of track inspections
Condition of the grease between the and maintenance shall be kept for
fishplate, the fishplate bolts and every track inspection. The completion
rails of the record of track inspection shall
be defined in the contractor’s track
Where “dry joints” are detected, the inspection procedures.
fishplate bolts will be loosened, grease
will be applied to the rail edges of the The record of track inspection shall
fishplate and bolts, then the bolts include the following information, as a
shall be re-tightened using a torque minimum:
spanner to the setting prescribed in
the contractor’s track maintenance The date and time of the track
procedure. inspection

The name and signature of the Track


Inspector

Best Practice Guide – Construction Railway Train Movements Page 35 of 38 Best Practice Guide – Construction Railway Train Movements Page 36 of 38
Section D1
Additional Information
Glossary of terms used in this Guide

CCTV Closed Circuit Television

DLC Daily Loco Checklist

MC Movement Controller

OBC Operations Board Controller (Note – on sites where there is no OBC, a


designated Authorised Person may be installed)

PTW Permit to Work

RMCC Rail Movement Control Centre

TSC Tunnel Safety Card

External standards that support the use of this Guide

BS 6164:2011
Code of practice for health and safety in tunnelling in the construction industry

BS EN 1889-2:2003
Machines for underground mines – Mobile Machines working underground - Safety

Phonetic alphabet

A Alpha J Juliet S Sierra


B Bravo K Kilo T Tango
C Charlie L Lima U Uniform
D Delta M Mike V Victor
E Echo N November W Whisky
F Foxtrot O Oscar X X-ray
G Golf P Papa Y Yankee

Part D – Additional Information H


I
Hotel
India
Q
R
Quebec
Romeo
Z Zulu

Numerals should be spelled out, not given as whole numbers:


121 is ‘one-two-one’, NOT ‘one hundred and twenty one’

Best
Best Practice
Practice Guide
Guide –– Construction
Construction Railway
Railway Train
Train Movements
Movements Page
Page 37
37 of
of 38
38 Best PracticeGuide
Best Practice Guide – Construction
– Construction Railway
Railway Train Train Movements
Movements Page 38ofof38
Page 38 38
MOVING LONDON FORWARD
Best Practice Guide – Construction Railway Train Movements Page 39 of 38

You might also like