Professional Documents
Culture Documents
SOFTWAREREQUIRED:
MATLAB software package.
THEORY:
If the system is connected to numerous loads in a power system, then the system
frequency and speed change with the characteristics of the governor as the load changes.
If it’s not required to maintain the frequency constant in a system then the operator is
not required to change the setting of the generator. But if constant frequency is required the
operator canadjust the velocity of the turbine by changing the characteristics of the
governor when required. If a change in load is taken care by two generating stations running
parallel then the complex nature of the system increases. The ways of sharing the load by two
machines are as follow:
1) Suppose there are two generating stations that are connected to each other by tie line. If the
change in load is either at A or at B and the generation of A is regulated so as to have
constant frequency then this kind of regulation is called as Flat Frequency Regulation.
2) The other way of sharing the load is that both A and B would regulate their generations
to maintain the frequency constant. This is called parallel frequency regulation.
3) The third possibility is that the change in the frequency of a particular area is taken care of
bythe generator of that area thereby maintain the tie-line loading. This method is known as flat
tie-line loading control.
4) In Selective Frequency control each system in a group is taken care of the load changes on
its own system and does not help the other systems, the group for changes outside its own limits.
5) In Tie-line Load-bias control all the power systems in the interconnection aid in
regulating frequency regardless of where the frequency change originates
waterfalls, steam turbine whose energy come from burning of coal, gas and other fuels. The model of
turbine relates the changes in mechanical power output ΔPm and the changes in the steam valve position
ΔPV.
Gt = = (5)
where the turbine constant is in the range of 0.2 -2.0s.
(6)
In s-domain
(7)
The command ΔPg is transformed through amplifier to the steam valve position command
ΔPV. We assume here a linear relationship and considering simple time constant we get this
s-domain relation
Δ Pv = ΔPg(s) (8)
Combining all the above block diagrams, for a isolated area system we get the following:
The closed loop transfer function that relates the load change ΔP L to the frequency deviation
Ω is
ALGORITHM:
STEP: 1 Click the Simulink icon.
STEP: 2 Open the untitled window and create the model for loan frequency control of
single area power system using various library functions available in the Simulink
browser.
STEP: 4 Double click the scope and we can get the waveform as change in frequency with
respect to time.
STEP: 5 simulate the model for uncontrolled case and observe the waveform.
STEP: 6 Simulate the model for controlled case (i.e.), introduce one integral control in the
model and observe the waveform.
STEP: 7 Finally compare the results obtained from simulation and comment the result.
PROBLEM:
Single area system
An isolated power station has the following parameters
Turbine time constant = 0.5 sec
Governor time constant = 0.2 sec
Generator inertia constant = 5 sec
Governor speed regulation = R per unit
The load varies by 0.8 percent for a 1 percent change in frequency i.e., D=0.8. The
governor speed regulation is set to R=0.05 pu. The turbine rated output is 250 MW at
nominal frequency of 60Hz. A sudden load change of 50 MW (ΔPD=0.2 pu) occurs.
i).Find the steady state frequency deviation in Hz.
ii). Draw a MATLAB Simulink model and also verify the output with the manual
calculation results.
EXECUTION:
RESULT:
Thus, the load frequency dynamics of single area power system is analyzed using
MATLAB Simulink and the outputs are verified.
As we have in that the system frequency rises when the load decreases if ΔPref is kept at
zeros . similarly the frequency may drop if the load increases . However it is desirable to
maintain the frequency constant such that Δf =0 . The power flow through different tie-
lines are schedules - for example , area – i may export a pre-specified amount of power to
area – j while importing another pre-specified amount of power to area -K . However it is
expected that to fulfil this obligation , area – i absorbs its own load change , i.e., increase
generation to supply extra load in the area or decrease generation when the load demand
in the area has reduced . while doing this area – i must however maintain its obligation to
areas j and k as far as importing and exporting power is concerned . A conceptual diagram of
the interconnected areas is shown in figure.
1.The speed of the alternating current motors depends on the frequency of the power supply .
There are situations where speed consistency is expected to be of high order.
2.The electric clocks are driven by the synchronous motors . The accuracy of the clocks are not
only dependent on the frequency but also is an integral of the frequency error.
3.If the normal frequency is 50 Hertz and the system frequency falls below 47.5 Hertz or goes up
above 52.5 Hertz then the blades of the turbine are likely to get damaged so as to prevent the
stalling of the generator.
4.The under frequency operation of the power transformer is not desirable . for constant system
voltage if the frequency is below the desired value than the normal flux in the core increases .
This sustained under frequency operation of the power transformer results in low efficiency and
over heating of the transformer windings.
5.The most serious effect of subnormal frequency operation is observed in the case of
thermal power plants . Due to subnormal frequency operation the blast of the ID and FD fans in
the power stations get reduced and there by reduce the generation power in the thermal plants .
This phenomenon has got a cumulative effect and in turn is able to make complete shutdown of
the power plant if proper steps of load shedding technique is not engaged . It is pertinent to
mentioned that , in load shedding technique a sizable chunk of load from the power system is
disconnected from the generating units so as to restore the frequency to the desired value.
We can therefore state that the load frequency control (LFC) has the following two objectives:
* Hold the frequency constant (Δ f=0) against any load change . Each area must contribute
to absorb any load change such that frequency does not deviate .
* Each area must maintain the tie-line power flow to its pre-specified value .
The first step in the LFC is to form the area control error(ACE) that is defined as
ALGORITHM:
STEP: 1 Click the Simulink icon.
STEP: 2 Open the untitled window and create the model for loan frequency control of two
area power system using various library functions available in the Simulink
browser.
STEP: 4 Double click the scope and we can get the waveform as change in frequency with
respect to time.
STEP: 5 simulate the model for uncontrolled case and observe the waveform.
STEP: 6 Simulate the model for controlled case (i.e.), introduce one integral control in the
model and observe the waveform.
STEP: 7 Finally compare the results obtained from simulation and comment the result.
BLOCK DIAGRAM:
MODEL GRAPH:
PROBLEM:
Two area system
A two area system connected by a tie line has the following parameters on a
1000MVA common base
Area 1 2
Speed Regulation R1=0.05 R2=0.0625
Frequency sensitive load coefficient D1=0.6 D2=0.9
Inertia Constant H1=5 H2=4
Base power 1000 MVA 1000 MVA
Governor time constant τ g1=0.2 sec τ g2=0.3 sec
Turbine time constant τ T1=0.5 sec τ T2=0.6 sec
The units are operating in parallel at the nominal frequency of 50Hz. The synchronizing power
coefficient is computed from the initial operating condition and is given to be Ps=2 pu. A load
change of 187.5MW occurs in area1. Determine the new steady state frequency and the change
in tie-line flow.
EXECUTION:
RESULT:
Thus, the load frequency dynamics of two area power system is analyzed using
MATLAB Simulink and the outputs are verified.
AIM:
To develop a program in MATLAB for determining the transmission line parameters and
verify using MATLAB simulation.
SOFTWARE REQUIRED:
MATLAB software package.
THEORY:
A transmission line has three constants R,L and C distributed uniformly along the whole
length of the line. The resistance and inductance form the series impedance. The capacitance
existing between conductor for 1-phase line or form a conductor to neutral for a 3-phase line
forms a shunt path throughout the length of the line. Therefore ,capacitance effects introduce
complications in transmission line calculations. Depending upon the manner in which
capacitance is taken into account ; the overhead transmission line are classified as :
Short transmission lines: When the length of an overhead transmission line is up to about 50km
and the line voltage is comparatively low(<20kv), it is usually considered as a short transmission
line. Due to smaller length and lower voltage , the capacitance effects are small and hence can be
neglected. Therefore while studying the performance of a short transmission line ,only resistance
and inductance of the line are taken into account.
Medium transmission lines: When the length of an overhead transmission line is about 50-
150km and the line voltage is moderately high (>20kv<100kv), it is considered as a medium
transmission line. Due to sufficient length and voltage of the line, the capacitance effects are
taken into account. For purpose of calculations, the distributed capacitance of the line is divided
and lumped in the form of condensers shunted across the line at one or more points.
Long transmission lines: When the length of an overhead transmission line is more than
150km and line voltage is very high (>100kv), it is considered as a long transmission line.
For the treatment of such a line , the line constants are considered uniformly distributed
over the whole length of the line and rigorous methods are employed for solution. It may be
emphasized here that exact solution of any transmission line that must consider the fact that
the constants of the line are not lumped but are distributed uniformly throughout the length of the
line. However, reasonable accuracy can be obtained by considering these constants as lumped
for short and medium transmission lines.
The phasor diagram for the circuit is shown above figure.Taking the receiving end voltage as the
reference phasor ,we have
= VR +j 0
Load current,
=j (C/2) =i∏fc
Line current = +
ABCD PARAMETERS:
voltage(VR)of the line is generally less than the sending end voltage(VS).The voltage drop (VS-
VR) in the line is expressed as a percentage of receiving end voltage and is called regulation.
FORMULAE:
STEP 2: If it is single phase, get the value of distance between the conductors.
unsymmetrical
STEP 6: If symmetrical, get the distance between the conductors and radius of the
conductor.
STEP 8 : If unsymmetrical, get the distance between the conductors and radius of the
conductor. Using the appropriate formula, find inductance and capacitance.
PROBLEM:
Determine the sending end voltage, current, power & power factor for a 160km section of
3phase line delivering 50MW at 132kV and P.F 0.8 lag. Also find the efficiency and regulation of
the line. Resistance per line 0.1557ohm per km, spacing 3.7m, 6.475m, 7.4m transposed.
Evaluate the A, B, C, D parameters also. Diameter is 1.956cm. Write and execute a MATLAB
program and also verify the output with the manual calculation results.
PROGRAM:
EXECUTION:
RESULT:
Thus the computation of line parameters of a given power transmission system
is done by using MATLAB and the output is verified.
APPARATUS:
MATLAB Software
THEORY:
Formation of Y BUS matrix
Bus admittance matrix is often used in power system studies.In most of power system
studies it is necessary to form Y-bus matrix of the system by considering certain power system
parameters depending upon the type of analysis. For example in load flow analysis it is necessary
to form Y-bus matrix without taking into account the generator impedance and load impedance.
In short circuit analysis the generator transient reactance and transformer impedance taken in
account, in addition to line data. Y-bus may be computed by inspection method only if there is no
natural coupling between the lines. Shunt admittance are added to the diagonal elements
corresponding to the buses at which these are connected. The off diagonal elements are
unaffected. The equivalent circuit of tap changing transformer may be considered in forming[y-
bus] matrix.
There are b independent equations (b = no. of buses) relating the bus vectors of currents
and voltages through the bus impedance matrix and bus admittance matrix:
EBUS = ZBUS IBUS
IBUS = YBUS EBUS
The relation of equation can be represented in the form
IBUS = YBUS EBUS
Where, YBUS is the bus admittance matrix, IBUS & EBUS are the bus current and bus
voltage vectors respectively.
Diagonal elements: A diagonal element (Yii) of the bus admittance matrix, YBUS, is equal to
the sum total of the admittance values of all the elements incident at the bus/node i,
Off Diagonal elements: An off-diagonal element (Yij) of the bus admittance matrix, YBUS, is
equal to the negative of the admittance value of the connecting element present between the
buses I and j, if any.
This is the principle of the rule of inspection. Thus the algorithmic equations for the rule of
inspection are obtained as:
Yii = Σ yij (j = 1,2,…….n)
Yij = - yij (j = 1,2,…….n)
For i = 1,2,….n, n = no. of buses of the given system, yij is the admittance of element
connected between buses i and j and yii is the admittance of element
connected between bus i and ground (reference bus).
START
Consider line l = 1
i = sb(1); I= eb(1)
NO YES
Is l =NL?
Stop
MATAB CODE:
EXECUTION:
Exercise No : 5
Date: 06-09-2018.
Aim :-
To find lod flow or power flow analysis using Gauss Seidel method in MATLAB..
APPARATUS:
1) MATLAB Software
2) Sim Power System Toolbox
Theory:-
Load flow analysis is the study conducted to determine the steady state operating
condition of the given system under given conditions. A large number of numerical algorithms
have been developed and Gauss Seidel method is one of such algorithm.
Problem Formulation
The performance equation of the power system may be written of
[I bus] = [Y bus][V bus] (1)
Selecting one of the buses as the reference bus, we get (n-1) simultaneous equations. The bus
loading equations can be written as
Ii = Pi-jQi / Vi* (i=1,2,3,…………..n) (2)
Where,
N
Pi=Re [ Σ Vi*Yik Vk] . (3)
k=1
N
Qi= -Im [ Σ Vi*Yik Vk]. (4)
k=1
The bus voltage can be written in form of
n
Vi=(1.0/Yii)[Ii- Σ Yij Vj] (5)
j=1
j≠i(i=1,2,…………n)& i≠slack bus
Substituting Ii in the expression for Vi, we get
n
Vi new=(1.0/Yii)[Pi-JQi / Vio* - Σ Yij Vio] (6)
J=1
The latest available voltages are used in the above expression, we get
n n
o
Vi new=(1.0/Yii)[Pi-JQi / V i* - Σ YijVjn- Σ Yij Vio] (7)
J=1 j=i+1
voltages in
The above equation is the required formula .this equation can be solved for
interactive manner. During each iteration, we compute all the bus voltage and check
convergence is carried out by comparison with the voltages obtained at the end of previous
iteration. After the solutions is obtained. The stack bus real and reactive powers, the reactive
power generation at other generator buses and line flows can be calculated.
Algorithm:
Step1: Read the data such as line data, specified power, specified voltages, Q limits at the
generator buses and tolerance for convergences
Step2: Compute Y-bus matrix.
Step3: Initialize all the bus voltages.
Step4: Iter=1
Step5: Consider i=2, where i’ is the bus number.
Step6: check whether this is PV bus or PQ bus. If it is PQ bus goto step 8 otherwise go to next
step.
Step7: Compute Qi check for q limit violation. QGi=Qi+QLi.
7).a).If QGi>Qi max ,equate QGi = Qimax. Then convert it into PQ bus.
7).b).If QGi<Qi min, equate QGi = Qi min. Then convert it into PQ bus.
Step8: Calculate the new value of the bus voltage using gauss seidal formula.
i=1 n
Vi=(1.0/Yii) [(Pi-j Qi)/vi0*- Σ Yij Vj- Σ YijVj0]
J=1 J=i+1
Adjust voltage magnitude of the bus to specify magnitude if Q limits are not violated.
Step9: If all buses are considered go to step 10 otherwise increments the bus no. i=i+1 and Go to
step6.
Step10: Check for convergence. If there is no convergence goes to step 11 otherwise go to
step12.
Step11: Update the bus voltage using the formula.
Vinew=Vi old+ α(vinew-Viold) (i=1,2,…..n) i≠ slackbus ,α is the acceleration factor=1.4
Step12: Calculate the slack bus power, Q at P-V buses real and reactive give flows real and
reactance line losses and print all the results including all the bus voltages and all the
bus angles.
Step13: Stop.
START
Read
1. Primitive Y matrix
2. Bus incidence matrix A
3. Slack bus voltages
4. Real and reactive bus powers Pi& Qi
5. Voltage magnitudes and their limits
Form Ybus
Test for
type of bus
Compute Qi(r+1)
Compute Ai
Compute δi(r+1) and
Compute Vi(r+1) Vi(r+1) =|Vis|/δi(r+1)
B Is i<=n
Advance iteration
A Is Vmax<=ε
count, r = r+1
PROBLEM:
Figure shows the one-line diagram of a three-bus power system with generation at bus1. The
magnitude of voltage at bus1 is adjusted to 1.05 per unit. The scheduled loads at buses 2 & 3 are as
marked on the diagram. Line impedances are marked in per unit on a 100MVA base and the line
charging susceptances are neglected.
i). Using Gauss-Seidal method, determine the phasor values of the voltage at the load
buses 2 & 3 (PQ buses) accurate to 4 decimal places.
ii). Write and execute a MATLAB program and also verify the output with the manual
calculation results.
EXECUTION:
RESULT:
Thus the load flow analysis using is performed by Gauss-Seidal method and a program is
developed using MATLAB to find the solution of load flow for given power system and the
output is verified.
STEP 3: Set the iteration count K=0 and assumed voltage profile of the buses are denoted
as V10,V20……Vn0.
STEP 5: Check for slack bus. If it is a slack bus then go to step 13. Otherwise go to next
step.
STEP 6: Calculate the real & reactive power of bus p using the following equation,
Ppk=Σk q=1{epk(eqkGpq+fqkBpq)+fpk(fqkGpq-eqkBpq)}
Qpk=Σkq=1{fpk (eqk+Gpk+fqkBpq)+epk(fqk Gpq-eqkBpq)}
STEP 7: Calculate the change in real power, ΔPk=Pp spec -Ppk Where, Pp spec=specified
real power of bus p.
STEP 8: Check for generator bus. If it is a generator bus gob to next step otherwise go to
step 12. STEP 9: Check for generator bus. If it is a generator reactive power limits
Violation of generator buses. For this compare the calculated reactive power Q
STEP 10: If the calculated reactive power is within the specified limit then consider this bus
as generator bus. Now calculate the voltage residue using the equation
|VPK|2 =|Vp spec|2-|Vpk|2.
Where |Vp spec| = specified voltage magnitude for generation bus. Then go to step
13.
STEP 11: If the reactive power limit violated the treat this bus as a load bus. Now the
specified reactive power for this bus will correspond to Limit violated.
STEP 12: Calculate the change in reactive power for load bus change in reactive power,
ΔQk=|ΔQp spec|-Qpk
STEP 13: Repeat the step 5 to 12 until all residues are calculated for increment the bus
count n. by 1 to 5 steps until the bus count is n.
STEP 14: Determine the largest of the absolute value of the residue (i.e.) Find the largest
value among ΔPpk , ΔQpk or |ΔVpk|2
STEP 15: Compare ΔE and E, if ΔE<E then go to step 20. If ΔE>E go to next Step.
STEP 16: Determine the element, the load flow equation using kth iteration Value.
STEP 17: Calculate the increment in real and reactive part of voltage Δepk and Δfpk
by solving the matrix equation B=JC. STEP 18: Calculate the new bus
voltage.
PROBLEM:
RESULT:
Thus the load flow analysis using is performed by Newton-Raphson method and a
program is developed using MATLAB to find the solution of load flow for given power system
and the output is verified.
SOFTWARE REQUIRED:
MATLAB software package
ALGORITHM:
STEP 1: Get the data for positive and negative sequence impedance materials.
STEP 2: Enter the bus code number, base kV, base MVA number.
STEP 5: Enter the impedance value to be included according to the corresponding choices.
STEP 6: Enter the fault impendence value, fault bus code, and fault bus voltage.
PROBLEM:
Consider the 3bus system as shown in figure. The generators are 100 MVA with transient
reactance 10% each. Both the transformers are 100 MVA with a leakage reactance of 5%. The
reactance of each of the lines to a base of 100 MVA, 110kV is 10%. Obtain the short circuit
calculation for a 3phase solid short circuit on bus 3. Assume pre-fault voltages to be 1pu and pre-
fault currents to be zero.
Write and execute a MATLAB program and also verify the output with the manual calculation
results.