Subject: Monthly performance review of transmission works for the month of August-

2017 in respect of TS Zone Hisar.

(A) Ongoing works completed up to 31.08.2017:

The details of the transmission works which have been completed upto August-2017
are as under:
Sr. No Name of Transmission work Capacity in MVA/ Project Date of
Line length in Ckt Cost commissioning
Km (Rs. In
lacs)
I. New Substation
1 66 KV S/Stn Sec 4 Gurgaon (District- New Sub Station 1300.00 25.11.2015
Gurgaon) 2x25/31.5 MVA,
66/11 KV
2 220kV S/Stn GIS A-4, Faridabad. 2 x 100 MVA 2500 30.12.2015
(District Faridabad) 220/66kV
3 220 KV S/Stn HSIIDC Bawal (District New S/Station, 100 HSIIDC 31.12.2015
Rewari) MVA, 220/33 KV
4 132KV Bhattu Sotter 2 x 20/25 MVA, 690 26.03.2016
(District Fatehabad) 132/33 KV
( 50 MVA)
5 220kV substation Hukmawali 1 x 220/132KV, 100 2500 23.04.2016
(District Fatehabad) MVA + 1 x 220/33KV,
100 MVA
(200 MVA)
6 132KV Makrani 2 x 20/25 MVA, 1700 29.07.2016
(District Bhiwani) 132/33 KV 30.09.2016
( 25 MVA)
7 66 KV S/Stn. Sector-35, HSIIDC, New Sub Station HSIIDC 21.09.2016
Gurgaon. 1x25/31.5 MVA,
66/11 KV
8. 220 kV S/Stn. Sec-20 Gurgaon  New M/s CGL 10.11.2016
S/Station,
2x25/31.5 15.11.2016
MVA, 66/11 kV 03.05.2017
T-2 & T-1 T/F.
 2x100MVA, 29.05.2017
220/66KV T/F.
9 220kV S/Stn Meerpur Kurali 1st 100 MVA 220/66kV 29.04.2017
(Commissioned)
2nd 100 MVA 220/66kV
(Not Commissioned)
1 x 12.5/16 MVA 02.05.2017
66/11kV
(Commissioned)
10 220KV S/Stn. Sec-33, Gurugram 1x160MVA, 220/66KV 447 04.06.2017
T-2 447 20.07.2017
1x160MVA, 220/66KV
T-1
220KV S/Stn. Panchgaon 100MVA, 220/33KV 706.18 18.07.2017
T/F
II. Augmentation
1 66kV substation Sector-2 Gurgaon Additional 25/31.5 160 03.04.2015
(District Gurgaon) MVA, 66/11 KV
2 66kV substation Sector-9 Additional 12.5/16 80 11.04.2015
Gurgaon(District Gurgaon) MVA, 66/11 KV
3 220kV substation Daultabad (District Additional 100 MVA, 400 14.04.2015
Gurgaon) 220/66kV
4 66kV substation A-2 Faridabad 25/31.5 MVA, 66/11 165 14.04.2015
(District Faridabad) KV in place of
12.5/16 MVA
5 66kV substation Sector-38 Gurgaon Additional 16/20 MVA, 200 06.05.2015
(District Gurgaon) 66/11 KV
6 66kV substation Chhainsa 25/31.5 MVA, 66/11 165 21.05.2015
(District Faridabad) KV in place of 12.5/16
MVA
7 66kV substation Sector-15 Gurgaon Additional 12.5/16 100 23.05.2015
(District Gurgaon) MVA, 66/11kV
8 132kV substation Fatehabad 40/50 MVA, 132/33 kV 307 03.06.2015
(District Fatehabad) in place of 20/25 MVA
9 220kV substation Palwal 25/31.5 MVA, 66/11 kV 210 12.06.2015
(District Palwal) T/F in place of 12.5/16
MVA.
10 66kV substation Hyderabad Additional 12.5/16 60 14.06.2015
(District Faridabad) MVA, 66/11 kV T/F.
11 132kV substation Teliwara 40/50 MVA, 132/33 kV 350 11.06.2015
(District Fatehabad) in place of 16/20 MVA
12 132kV substation Dharsul 40/50 MVA, 132/33 kV 287 17.06.2015
(District Fatehabad) in place of 20/25 MVA
13 220kV substation Bhuna Additional 20/25 MVA, 272 30.07.2015
(District Fatehabad) 132/33 KV
14 132kV substation Nagura Additional 20/25 MVA, 311 31.07.2015
(District Jind) 132/33 KV
15 220kV substation Isherwal 40/50 MVA, 132/33 kV 288 12.08.2015
(District Bhiwani) in place of
10/16 MVA, 132/33 kV
16 66kV substation Bhopani Additional 12.5/16 60 14.08.2015
(District Faridabad) MVA, 66/11 kV T/F.
17 66kV substation Punhana Additional 12.5/16 60 28.08.2015
(District Nuh) MVA, 66/11 kV T/F.
18 66kV substation Bhagola 25/31.5 MVA, 66/11 kV 210 31.08.2015
(District Palwal) in place of 12.5/16
MVA, 66/11 T/F.
19 132kV substation Dadri-II 40/50 MVA, 132/33 kV 293 31.08.2015
(District Bhiwani) in place of 20/25 MVA,
132/33 kV
20 132 KV Substation Bhiwani 40/50 MVA, 132/33 kV 294 20.09.2015
(District Bhiwani) in place of 20/25 MVA,
132/33 kV
21 66 kV S/Stn Sohna Aug. of existing 210 11.10.2015
(District Gurgaon) 12.5/16 MVA 66/11 kV
T/F by 25/31.5 MVA
66/11 kV T/F
22 66 kV S/Stn Allawalpur Add. 12.5/16 MVA 60 18.10.2015
(District Palwal) 66/11 kV T/F
23 132 KV substation Khedar Additional 20/25MVA, 289 02.11.2015
(District Hisar) 132/33KV T/F
24 66kV S/Stn Ford,Faridabad Aug. of existing 210 12.01.2016
(District Faridabad) 12.5/16 MVA 66/11 kV
T/F by 25/31.5 MVA
66/11 kV T/F
25 132KV S/Stn. I.A. Bhiwani Additional 20/25MVA, - 09.02.2016
(District Bhiwani) 132/33KV T/F
26 66kV S/Stn Nuh Providing additional 10 Deposit 03.03.2016
(District Nuh) MVA 66/33kV T/F for work of
33kV independent M/s Varun
feeder of M/s Varun Bevrages
Beverage as a deposit
work.
27 220 kV S/Stn. Sec-52A Gurgaon Augmentation of T/F 250 04.05.2016
(District Gurgaon) from 16/20 MVA to
25/31.5 MVA 66/11 kV
T-1
28 66 kV S/Stn. Sec-34 Gurgaon Augmentation of T/F 250 22.05.2016
(District Gurgaon) from 12.5/16 MVA to
25/31.5 MVA 66/11 kV
T-3
29 66 kV S/Stn. Sec-51 Gurgaon Augmentation of T/F 250 25.05.2016
(District Gurgaon) from 12.5/16 MVA to
25/31.5 MVA 66/11 kV
T-1
30 132kV substation Fatehabad 16/20 MVA, 132/11 kV - 27.05.2016
(District Fatehabad) in place of 10/16 MVA
(Damaged)
31 66kV S/Stn Idgah, Faridabad Augmentation of 66KV 210 31.05.2016
(District Faridabad) S/Stn Idgah from
(1x12.5/16+1x10/12.5
) MVA 66/11KV to
(1x12.5/16) +
(1X25/31.5 MVA)
66/11KV T/F

32 66 kV S/Stn. Sec-10 Gurgaon Augmentation of T/F 250 06.06.2016


(District Gurgaon) from 12.5/16 MVA to
25/31.5 MVA 66/11 kV
T-2
33 132KV substation Jind New 40/50 MVA, 132/33 kV 240 09.06.2016
(District Jind) in place of 20/25 MVA,
132/33 kV
34 220 kV S/Stn. Sec-52 A Gurgaon Augmentation of T/F 250 23.06.2016
(District Gurgaon) from 16/20 MVA to
25/31.5 MVA 66/11 kV
T-2
35 132 KV S/Stn, Kosli Augmentation of T/F 300 24.06.2016
(District Rewari) from 20/31.5 MVA to
40/50 MVA 132/33 kV
T-2
36 132KV S/Stn. Atela 16/20 MVA, 132/33kV - 01.07.2016
District Bhiwani) in place of 10/16 MVA,
132/33 kV against
damaged
37 66 KV Sub Station Sec 8 IMT Additional 25/31.5 250 26.07.2016
Manesar MVA, 66/11 kV T/F
(District Gurgaon)
38 132KV S/Stn. Uchana Additional 20/25MVA, - 02.08.2016
(District Jind) 132/33KV T/F
39 66kV S/Stn Nimoth Additional 12.5/16 60 26.08.2016
(District Gurgaon) MVA 66/11kV T/F
40 66kV S/Stn FCI Faridabad Augmentation of 66kV 138.40 30.08.2016
(District Faridabad) S/Stn FCI from 12.5/16
MVA 66/11kV T/F to
25/31.5 MVA 66/11kV
T/F T-1.
41 132KV S/Stn. Julana (District Jind) Additional 132/33 KV 272.91 07.09.2016
20/25 MVA T/F

42 220KV S/Stn. Safidon(District Jind) Additional 220/132 KV 573.45 20.09.2016


100 MVA T/F
43 220 kV S/Stn. Rewari Additional 100 MVA, 343.00 26.11.2016
220/132 kV T-7 T/F
44 66 KV S/Stn. Sector- 2 IMT Manesar Augmentation of T/F 250.00 02.12.2016
from 12.5/16 MVA to
(Distric Gurgaon) 25/31.5 MVA 66/11
kV T-1
45 66 KV S/Stn. Sector- 44 Gurgaon Additional 25/31.5 300.00 29.12.2016
(Distric Gurgaon) MVA, 66/11 kV T/F
46 132 KV substation Arya Nagar Additional 40/50MVA, 285.52 29.12.2016
(District Hisar) 132/33KV T/F
47 132 KV S/Stn. HSIIDC Bawal 40/50 MVA, 328 15.01.2017
(District Rewari)
48 132 KV S/Stn. Satnali 20/25 MVA, 132/33 kV 260 25.01.2017
T/F
49 132KV Haluwas Additional 10/16MVA, 299.09 09.03.2017
(District Bhiwani) 132/33KV T/F
50 66 kV S/Stn. Hodal Add. 12.5/16 MVA 60 14.04.2017
(District Palwal) 66/11 kV T/F T-3
51 220 kV S/Stn. Sec-1 IMT Manesar 220/66 kV, 160 MVA 582 25.04.2017
52 132KV Behal Additional 132/33KV, - 07.06.2017
(District Bhiwani) 16/20 MVA
53 66 KV S/Stn. Sector-2, Palwal ( Add. 12.5/16 MVA 60 12.06.2017
Distt. Palwal) 66/11 kV T/F T-2
54 220KV Rania 132/11KV, 16/20 MVA 165.00 21.06.2017
(District Sirsa) T/F in place of
132/11KV, 10/16 MVA
T/F
55 66KV S/Stn. Harsaru From 12.5/16MVA 219 22.07.2017
66/11KV to 25/31.5
MVA 66/11 KV T-1 T/F
Transmission lines:
Sr. No Name of Transmission work Line length in Ckt Project Date of
Km Cost commissioning
(Rs. In
lacs)
1 220kV line from Sector-72 PGCIL- 0.46 KM 150 29.04.2015
Sector-72 HVPNL Ckt.-3 & 4
(District Gurgaon)
2 220kV & 66 kV D/C line from Sector- 13.6 KM 1200 30.04.2015
72 PGCIL-Sector-33 HVPNL Ckt.-1 &
2 on Multi Ckt Tower (District
Gurgaon)
3 220kV D/C line from Masudpur to 91.264 KM 2834 10.05.2015
Samain (District Hisar)
4 132kV line from Masudpur to Barsi 21.744 KM 400 23.05.2015
(District Hisar)
5 220kv D/C Sector-72, Gurgaon to 146 KM 3200 10.09.2015
220kv Rangala Rajpur Mewat
Transmission Line. (District Gurgaon)
6 LILO of 66 KV Daultabad-Sec 9 line 3.8 KM 400 24.11.2015
at 66 KV S/Stn Sec 4 Gurgaon (XLPE
Power Cable) (District Gurgaon)
7 2nd circuit of 220kV Rewari – 23.76 KM 86 18.01.2016
Bhiwadi line with 0.4 Sq inch
conductor (District Rewari)
8 LILO of 1 Ckt. of 66 KV D/C Sector- 3.8 KM 1029 22.03.2016
23 -Dundahera line at 220kV GIS
Sector-20, Gurgaon (District
Gurgaon)
9 132 kV D/C line from 220 kV S/Stn. 5.52 km 136.82 30.04.2016
HSIIDC Bawal to 132 kV kV S/Stn. (both (1st Circuit)
HSIIDC Bawal with 0.4 sq” ACSR Ckt.) 10.05.2016
conductor. (Rewari) (2nd Circuit)
10 Construction of 2 Nos. 132 kV line NA 147.65 30.04.2016
bays at 132 kV S/stn. HSIIDC Bawal
to accommodate 132 kV D/C line
from 220 kV S/stn. HSIIDC Bawal
(District Rewari)
11 66kV BBMB Ballabgarh- 4.040 KM 159 11.06.2015
Jharsetly(Ckt-1)(District Faridabad)
12 132KV Dhudiyanwali – Kariwala line 11.650 KM 200 18.06.2015
(District Sirsa)
13 LILO of existing circuit of 132kV 12.496 KM 381 26.02.2016
Ratia-Aherwan S/C line on D/C
towers at 220kV substation
Hukmawali (District Fatehabad)
14 Stringing of 2ndCircuit of 132 KV Ratia 10.946 KM 171 26.02.2016
- Aherwan Line (District Fatehabad)
15 132 KV S/C Hukmawali- Bhattu 16.230 KM 454 13.03.2016
Sotter line on D/C towers
(District Fatehabad)
16 66kV S/C on D/C Tower from 220kV 16.807 KM 441 19.05.2016
substation Meerpur Kurali to 66kV
substation Hodal (District Palwal)
17 66kV S/C line on D/C towers 19 KM 340 06.06.2016
Mandkola - Nuh (District Palwal)
18 LOOP out of 220 KV Fatehabad- 20.50 KM 985 24.06.2016
Chormar line at 220 KV Hukumawali
(District Fatehabad)
19 220kV D/C line from A-5 to A-4 7.61 KM 679.66 30.12.2015
(Faridabad) (District Faridabad) (Ckt-II)
08.06.2016
(Ckt-I)
20 66kV D/C line from 220kV S/Stn. 3.6 KM 246 29.08.2016
Palwal to 66 KV S/Stn. Sector-2,
Palwal District: Palwal
21 220 KV Bhiwadi-HSIIDC Bawal S/C 25 KM 300.00 16.09.2016
line. (District Rewari)
22 66kV BBMB Ballabgarh-Jharsetly 4.04 KM 250.00 14.10.2016
Ckt-II
23 Line 66kV D/C from Sector-2, IMT 1.50 Km 375.00 02.12.2016
Manesar to Sector-3, IMT Manesar,
Gurgaon.
24. Line 66kV D/C from Sector-1, IMT 2.00 Km 250.00 22.12.2016
Manesar to Sector-2, IMT Manesar,
Gurgaon.
25 400kV D/C line from 400kV 50.5 KM 5353.00 10.03.2017
substation Kirori to 400 kV PGCIL
Jind ckt-II
26 220kV D/C Line from 220kV 53.704 1440.20 14.04.2017
substation Palwal to 220kV
substation Meerpur Kurali- 26.852
Km, Loc.- 106 Funding : WB-G-19A
District : Palwal Contractor : M/s
Shyam Indus Cost(In Rs. 1440.2
Lacs) :
27 132KV D/C Dhadhibana – Jhojhu 8.96 KM 278.40 05.06.2017
Kalan line
28 LILO of 66kV S/C Aurangabad – 1.463 523 05.06.2017
Hassanpur Line at 220kV substation
Meerpur-Kurali- 1.463 Km Loc.-9
Funding: WB-G-19B
District: Palwal
Contractor :Ms Cobra JV with M/s
M/s Shyam Indus Power Solutions
Cost(In Rs. Lacs) : 523
29 66kV S/C line on D/C Tower from 25.969 621 14.06.2017
220kV Meerpur Kurali to 66kV
Allawalpur with LILO at 66kV
substation Chandhut- 25.969 Km
Loc.-111 Funding: WB-G-19B
District: Palwal
Contractor : Ms Cobra JV with M/s
M/s Shyam Indus Power Solutions
Cost(In Rs. Lacs) :621
30 400kV D/C line from 400kV 50.5 KM 5353 10.08.2017
substation Kirori to 400 kV PGCIL
Jind ckt-I (Test charge)
Annexure-‘A’
Ongoing works related to Sub-Stations:
Sr Name of Substation Date of Likely Status
No award/ date of
Contractua completio
l n
completion
date
1. 220kV Substation 14.02.14/ 31.10.2017 Progress Civil:
Panchgaon 9.05.15 1st T/F Switch house building:
2x160MVA, 220/66kV commission  Tile tracing work is complete.
1x100MVA, 220/33kV ed on dated  Floor tiling except toilets & pantry
Funding : WB-G-23A 18.07.2017 is complete (95%).
District: Gurgaon  Chequer plates are left.
Contractor : M/s  Door/window are in progress.
Emirates Tech.  IDCT work is complete
Associate JV M/s ETA  Internal wiring work is in progress.
Star International LLC  ODCT work in 66kV yard has been
Abudhabi completed.
Cost (In Rs. 3800 Lacs)  Civil works is held up at site.
:
Tower Foundations:
 Completed-96 Nos.
 Balance-01 No ( Not required
though mentioned in BOQ)

Equipment foundations:
 Completed-290 Nos,

T/F Plinth:
 03 Nos T/F plinth are completed.
 Radiator foundation of 160MVA
T/Fs is completed (1 No.).

Boundary wall:
 Plaster and painting work
completed.
Cable trenches:
 33 KV side complete
 66 KV side complete
 220KV side completed 90%,
Balance- 10% (Only 400 mtr. out of
450 mtr, done) Raft & PCC work in
progress.

Progress Electrical:
Tower Erection-
 33 KV side complete.
 66 KV side complete.
 220 KV side – Completed.
 Equip Str. Erection- Completed-290
Nos
 All 3 Nos transformers received at
site.
 Earthing in respect of 220kV is
complete except raisers on 2nd bus.
 Stringing of 01 no. main bus of 220
KV side has been completed 2nd is
in progress.
 Equipment testing & relay testing
are under progress.
Impediments:
 Man power mobilization further to
be strengthened.
 Electrical gang – 1 No with 12+6
nos.
 Wiring work is in progress.

Pending:
Supply:
 Battery set (DOE-Sept, 2017.
Under manufacturing)- Rs. 5. 15
lacs.
 48 V battery- Rs. 3 Lacs.
 C Wedge connector (Under
manufacturing)- 6 Lacs.

Erection- Balance- Rs. 40 lacs

Civil Works: Amount- Total- 686.5


Lac, Balance- 70 Lacs
 Earth filling- Rs. 11.3 Lacs
 ODCT- 13.4 Lacs
 Site surfacing- 22 Lacs
 Switch house building- Rs. 13 Lacs
 Water harvesting – Rs. 10.23 Lacs.
Target of commissioning:
 1st T/F 100MVA, 220/33kV
energized (Test Charge) on dt.
18.07.2017 at 11:00 PM.
 Recharging of above T/F likely to
be done before 6th September,
2017.
 2nd T/F 160MVA, 220/66kV by last
week of Sept 2017.
 3rd 160MVA, 220/66kV T/F by 1st
week of Oct 2017.
 01 No. 220 KV Line bay energized
on dated 18.07.2017.

Status of Progress:
 Civil Activity completed- 92%
 Total Material received-95%
2. 66kV substation 28.03.14/ 31.10.20 Progress Civil:
Jamalpur 27.03.15 17 Switch house building-
2x25/31.5 MVA, 66/11  Only final finishing / paint coat is left.
KV  Foundations-Complete.
Funding : WB-G-23B  T/F Plinth- Complete.
District: Gurgaon  Boundary wall- Complete & gates are
Contractor: M/s Shreem pending.
Electric Limited  Cable trenches- ODCT complete.
Jaisinghpur  Site surfacing – PCC complete only
Cost(In Rs. 1000 Lacs) gravel is left.
 Drainage – Work started
 Rain harvesting – Yet to be started.

Civil Works Balance- Rs. 38.60 Lacs (


Drainage, rain harvesting – 9.5 Lacs, Site
surfacing- 7 Lacs, Earth filling- 4 Lacs,
Covers- 3.5 Lacs, Boundary wall- 4 lacs)

Progress Electrical:
 Power T/F- Both T/F erected and testing
will be started by Sept, 2017.
Erection of tower & eqp str- Completed
-72 Nos, Balance-NIL
 Laying of control cable almost completed
and termination is in progress.
 Indoor equipment’s have been erected.
 AC Kisoks & control panels erected.
Impediments:
 The associated feeding line awarded to
M/s Isolux ltd. is yet to be started.
Supply- Nil
Erection – 8 Lacs.
Status of Progress:
 Civil Activity completed- 90 %
 Total Material receive
3. 220kV GIS substation 07.10.13/ 31.10.20 Progress (Civil):
Sec-57, Gurgaon 30.12.14 17 Switch House Building- Pending
1x100MVA, 220/66KV  Final paint.
1x100MVA, 220/33kV 220 KV GIS Hall:
Funding : WB-G-18A  Complete & Final coat is left.
District: Gurgaon 66 KV GIS Hall:
Contractor:  Complete & Final coat is left.
M/s Isolux Ingenieria ODCT:
Spain  Work completed. Except Trench Cover.
Cost(In Rs. Lacs) :4184 Rain harvesting:
 Work in progress.
Boundary wall:
 Completed-81%, Balance-19% due to
court case. Several meeting taken up
with Administrator HUDA.
Road:
 100% complete.
Plinth:
 220/66KV T/F plinth completed,
Radiator Foundations completed.
 220/33KV T/F plinth completed.
 Site surfacing to be started after laying
of cables.
 Work held up at site due to financial
constraints.

Pending. Total- 4.63 Cr, Done-3.67


Cr, Balance- 0.96 Cr)

 Earth filling- 3.90 Lac


 ODCT- 7 Lac
 Road- 20 Lac
 Road Culvert- 1.25 Lac
 PCC/ Site surfacing – 4.61 Lac
 Drainage & water harvesting- 14.72
Lac.
 Boundary wall- 11.0 Lacs
 Misc Activities- 10 lacs.
 Final Finishing Control- 2 Lac
 Final Finishing 220kV GIS- 4 lac
 Final Finishing 66kV GIS- 4 lac
 Boundary wall Final Finish-1.5 Lac
 DG Set- 0.26 Lac

Electrical Funds: 98 Lacs


 Labour (Power Electors)- 20 Lacs.
 Testing commissioning (Elite Powers)
10 Lacs
 Material (SVL, cable supporting
structure)- 38 Lacs.
 Termination (Raycam)-10 Lacs
 Siemens (Relay, 33kV)-10 Lac
 Schenider (Relay)- 10 Lacs

Liability:
 Labour (Power Electors)- 60 Lacs.
 Civil ( Neeven) – 1 Cr.
 Raycam- 16 Lacs.
Progress Electrical:
 Installation of both transformers
including oil filtration is completed
except installation of 4 Nos NCTs
(Structure erected only)
 HV Test for 66 KV GIS & 220kV GIS is
complete.
 Termination of 66kV is complete
except 3 Nos pending of indoor & 1
No outdoor due to short material.
For 220kV, Outdoor – 9 Nos complete
& 3 Nos pending (Half Done) (T/F -
220/33kV). Indoor- 9 Nos is complete
& 3 Nos ready but plug in is pending
due to degassing.
 33kV GIS has been tested, however,
relays ( M/s Siemens Ltd) &
termination are pending.
 DCDB, ACDB, battery charger, set are
installed.
 SCADA arrived at site.
Pending Electrical works:
 220kV Termination- 3 Nos Outdoor &
3 Nos indoor.
 Testing of relays installed on
220kV/66kV C&R Panel is pending by
M/s Schnider Electric Limited. The
service engineer is awaited.
 33kV GIS - Relays ( M/s Siemens Ltd)
& termination are pending.
 Partial jumpering of conductor at
various points.
 Risers & water level earthing of NCTs
are balance.
 Testing & commissioning of
transformer.
Impediments:
 Inadequacy of funds, material man
power.
 SVL has not been arranged by the firm.
 Funds required:
Civil works- Rs. 1.15 Cr., Electrical
supply- 0.315 lacs & erection – 0.70 Cr.
 The firm is facing the severe financial
crisis & nearly bankrupt and has
expressed their inability to complete
other transmission projects.
 Status of Progress:
 Civil Activity completed-93%
 Total Material received-95%

4. 220kV substation GIS 04.02.13/ 1st T/F- Progress (Civil):


Sector-20 Gurgaon 31.07.14 03.05.2017.
3x100MVA, 220/66kV, 2nd T/F- Switch House Building-
2x25/31.5MVA,66/11kV 29.05.2017  Complete except final paint.
Funding : JICA-11 ODCT: -
District: Gurgaon  Complete.
Contractor: M/s 66kV GIS Hall:-
Crompton Greaves Ltd.  Complete.
Gurgaon 220kV GIS Hall:-
Cost(In Rs. Lacs)  Complete.
:6458.81 Rain water Harvesting:
 100% complete.
Foundations-
 Complete
T/F Plinth-
 Complete.
Boundary wall-
 Completed-96%, Balance- 4%.
Only painting is left.
Cable trenches-
 Complete.
Site Surfacing-
 80% done.

Progress (Electrical):
 66kV GIS, 2 Nos. 25/31.5 MVA T/F
commissioned on 06.11.2016, 1st
10.11.2016 & 2nd 15.11.2016.
 220 KV line bay & bus bar energized on
1st of May 2017
 2 No. T/Fs T-1 & T-3 energized on 3rd
May, 2017 & 29th May, 2017.
 1 no. T/f T-2 is pending to charge,
because of pendency in testing of HV
Duct. Relay testing done.
 Overall Progress:

 Civil Activity completed-97.3%


 Total Material received-100%
5. 220kV substation GIS 07.03.14/ 30.09.201 Switch House Building-
Sector-33 Gurgaon 06.06.15 7  Complete except final paint.
2x160MVA, 220/66KV ODCT: -
160MVA,  Complete.
Funding :JICA-013 220/ 66KV 66kV GIS Hall:-
T-2 & T-1  Complete.
District: Gurgaon T/F 220kV GIS Hall:-
Contractor: M/s Skipper energized  Complete.
Electrical (India) Ltd. on Site Surfacing:
Gurgaon 04.06.2017  Under progress. Only 10% is
Cost(In Rs. Lacs) & balance.
:4357 20.07.2017 Rain water Harvesting:
respectively  Under progress. Only 20% is
balance.
Foundations-
 Complete.
T/F Plinth-
 Complete.
Boundary wall-
 Completed-92%, Balance- 8%.
Progress Electrical:
 220kV GIS tested and energized on
25.05.2017.
 2 No 160MVA, 220/66kV T/F is
erected / complete in all respect. 1st
T/F commissioned on 04.06.2017.
 160MVA T-1 T/F is also charged on
20-07-2017
Impediments-
 Inadequacy of funds, man power &
resources.
 Issue of custom duty delayed the
project.

Status of Progress:
 Civil Activity completed-96%
 Material received 100%

6. 400KV Sub-Station, 09.02.16 08.05.17/ Progress:


Daultabad 31.10.17 Civil Works:
Construction of - Clear site handed over to the firm on
Additional Bays 09.02.2016.
- Site mobilized.
Turnkey Contractor: - Raft 2 no. isolator foundation (220 kV
M/s TBEA Shenyang site has been casted)
Transformer Group Co., - Raft 2 no. isolator foundation (400 kV
site has been casted)
Shenyang Liaoning - Work of T/F plinth is complete.
Province, PR, CHINA - Equipment foundations are in progress.
- Work of Anti Fire wall completed.
Contract awarded - Drawing of SF-6 breakers not approved
on: 25.01.2016 so far. ODCT drawing not approved so
Funding : REC-137 far.
- Work is held up at site since last 3
months.
Electrical Works:
 ICT received at site, placed on the
plinth.
 Some ICT Accessories received at site,
more to come.

Civil Activity completed-57.53 %

7. 66KV Sub-Station 28.03.2014 31.10.20 Progress:


Farukhnagar 27.03.2015 17  Foundation –Completed except
Construction of 66KV hybrid.
Additional Bays  Cable trenches-Balance- 100%.
 Erection- Completed except
 Turnkey hybrid.
contractor: Civil Works:
M/s Shreem Electric  Total- 15 Lacs
Ltd, Jaysingpur,  Done- 11.72 Lacs
District-Kolhapur.  Balance- 3.38 Lacs
 Date of Award:
12.02.2014 Electrical Part:
 Funding agency:  Total supply plus labour- 3.35 Cr.
World Bank-G-  Done- 3.25 Cr
23/Pkg-A  Balance- 0.10 Cr
 Amount- Rs.3.50
Cr. Impediments:
 The hybrid system has reached at
site, however, however, its
foundation is yet to be cast.
 The associated feeding line is yet to
be commenced by M/s Isolux Ltd.
Status of Progress:
 Civil activity completed- 77%
 Total material received-50%
8. 220KV GIS Sub- 04.03.2017 03.09.20 Progress: -
Station Sector-65, 18  Clear site handed over to the firm.
Gurgaon  FGL of sub-station has been fixed
2 x 100MVA except GIS halls.
220/33KV T/F  Work of boundary wall is in
progress.
 Layout of switch house building in
progress.
 Shifting of malba completed.
 Level taken and checked by Design
Wing.

9. Construction of 04.03.2017 03.09.20 Progress: -


220KV GIS Sub- 18  Clear site handed over to the firm.
Station Sector-95,  FGL of S/Stn. has been fixed.
Gurugram 2x100  Switch house building and ODSG is
MVA, 220/33KV in progress.
 Work of boundary wall is in
progress.
10. 66kV substation 08.03.14/ 30.09.20 Civil Activity Completed : - 95%
Mohamadpur Ahir 22.03.2015 17 Total Material Received : - 100%
2x25/31.5 MVA, 66/11  Work is lagging behind schedule
KV  Firm has been requested to ensure
Funding : WB-G-23B commissioning by 30.09.2017 in
District: Gurgaon any case.
Contractor: M/s Shreem  Commissioning of S/Stn is also
Electric Ltd. linked with commissioning of 220
Cost(In Rs. Lacs) :1213 KV S/Stn Panchgaon.

11. 220kV substation 07.02.14/ 30.09.20  Civil Activity Completed : -


Meerpur Kurali 04.05.15 17 72%
2x100MVA, 220/66kV,  Total Material Received : -
1x12.5/16MVA, 90%
66/11kV  The progress of work is highly
Funding : WB-G-18B dismal and lagging behind
District: Palwal schedule.
Contractor: M/S TBEA  Following
Shenyang Transformer equipment’s/arrangements
group company Limited have been charged
Cost(In Rs. Lacs) :2491  100 MVA, 220/66 kV T/F T-1
has been commissioned on
dated 29.04.2017 at 19:00 Hrs.
 12.5/16MVA 66/11kV T/F
commissioned on 02.05.2017.
 66 KV Bays for Hodal line,
Hassanpur-Aurangabad line
and 66 KV Alwalpur line has
been charged.
 Balance work to be completed.
o Commissioning of 2nd 100 MVA
220/66kV T/F T-2.
o Providing CTs on power
transformers.
o Providing line CTs on 2nd Ckt.
o Providing CTs for Bus Coupler.
o Providing L&E Switch for 2nd Ckt
of 220 KV line.
o Providing isolator on 2nd ckt of
220 KV line.
o Complete Commissioning of
SCADA.
o Providing Air Conditioning to
Kiosks.
o Commissioning of 2nd 220 KV
Bus.
o Levelling & dressing of switch
yard.
o To ensure adequacy of
firefighting arrangements.
o Providing light fixtures,
furniture and other logistics as
per contract.

12. 220kV GIS substation 28.03.14/ 31.12.20  Civil Activity Completed : -


Roj-Ka-Meo 21.06.15 17 25%
2x160MVA, 220/66kV  Total Material Received : -
1x100MVA, 220/33kV 15%
Funding : WB-G-23C  The Project progress is highly
District: Mewat dismal. The contractor M/s Isolux
Contractor: M/S Isolux has practically not done any
Ingenieria activity in the last four months at
Cost (In Rs. Lacs):5677 site.
 M/s Isolux has supplied three T/Fs
which are lying on loose soil since
last six months.
 The firm is being served notices
on dismal progress.

 S/H Bldg.
 1st lift of columns completed.
 Main tower F/D
 3 nos. PCC (0/24).
 Equipment F/D (0/78)
 Boundary wall has been
completed.
 Earth filling
 approx.35000cum
 Since last week of March-2017,
there is no activity with regard to
work at site by firm and progress
with regard to work is Nil since
then.
 Notices for dismal progress of of
works are being issued to firm from
time to time. Further, a detailed
reference has been mooted vide
Ch-81/S-56/Vol-V dated
06.06.2017 to apprise status
position to all concerned in the
matter.
 CE/MM, HVPNL Panchkula vide
memo no. Ch-85/WB-85/WB-85/G-
23/Pkg-C/Vol-IA/XEN/WB dated
18.08.2017 has terminated the
contract under clause 42.2. of GCC
and has blacklisted the firm.
13. Providing 3rd 09.02.16/ 31.10.17 Civil Activity Completed : - 90 %
400/220kV 315 MVA 08.05.17 Total Material Received : - 45%
ICT at 400kV S/Stn.
Nawada  Only plinth of ICT has been
Funding : REC-137 completed by firm. 315 MVA, 400/220
District: Faridabad kV ICT received at site.
Contractor: M/S TBEA  Work is held up by firm since
Shenyang Transformer one month.
group company Limited
Cost (In Rs. Lacs) : 1650
14. Creation of 2 No. 66 KV 07.02.2014 15.09.20 Civil Activity Completed : - 100 %
Bay at 66 KV 17 Total Material Received : - 100 %
substation Allawalpur
for 66 KV S/C line on  The work has been completed & got
D/C tower Meerpur- tested by the firm & same is to
Kurali to Allawalpur line witness by the M & P wing of HVPNL.
(6B 1147*) & will be commissioned with in next
Funding - REC-114 week.
Contractor: M/s TBEA
15. Creation of 2 No. 66 KV 07.02.2014 15.09.20 Civil Activity Completed : - 95 %
Bay at 66 KV 17 Total Material Received : - 100 %
substation Chandhut
for LILO of 66 KV S/C  Civil works completed except site
line Meerpur-Kurali to surfacing.
Allawalpur line ( 6B  Erection of towers/beams & equipment
1147*) structures, bus bar completed except
Funding - REC-114 erection of 3 nos. CT & 1 No. SF-6
Contractor – M/s TBEA breaker at existing Ckt Palwal-
Chandhut line.
 The work of bays for LILO has been
completed, tested & commissioned on
dated 28.08.2017, but in the C&R
panel DPS Relay showing Mal function
& DC Ckt is not healthy.
 Matter has been conveyed to the firm
& firm representative Sh. Dhirender
has committed that testing Engineer
will be arranged next week and will sort
out the problem.
16. Const. of 02 Nos. 66kV 05.02.2014 31.10.20 Civil Activity Completed : - 90 %
line bays at 66kV /04.05.201 17 Total Material Received : - 90 %
S/Stn. Chhainsa for 5  Civil works completed except site
take in of LILO of 66kV surfacing.
Nawada-Fatehpur  Material except Control cables, Earth
Biloch line wire received at site.
Funding : WB, G-18(B)  Erection of towers/beams &
District: Faridabad equipment structures, equipments,
Contractor: M/S TBEA bus bar completed. Earthing work
Shenyang Transformer completed.
group company Limited
Cost (In Rs. Lacs) : 261
17. 220kV substation 28.02.2017 30.09.20 Civil Activity Completed : - 9 %
Sector-46 / 18 Total Material Received : - 0 %
2x160MVA, 220/66kV, 30.09.2018
Funding : REC-160  Land has been handed over to firm
District: Faridabad and contouring etc. has been
Contractor: M/S SPML completed.
Infra Limited, 22,  Construction of boundary wall is in
Camac Street, Block-A, progress and earth filling is in
3rd Floor, Kolkata - progress.
700016  Tower Foundations are also in
Cost (in lacs) 4888 progress.
 GELO finalized.
18. 66kV substation 20.02.2017 22.06.20 Civil Activity Completed : - 20 %
Hassapur Khadar / 18 Total Material Received : - 0 %
1x12.5/16MVA, 22.06.2018
66/11kV,  Land has been handed over to firm.
Funding : REC-168 The work of site survey contouring
District: Faridabad etc. has been carried out and FGL
Contractor: M/s Kanti has been fixed.
Prasad Mittal, E-48B,  Site office constructed by firm.
New Ashok Nagar,  Earth Mat Design is in process.
Delhi-110096 JV with  Construction of boundary wall,
M/s A.K.Engineers, R- Switch house building and tower
13/40, Rajnagar, foundations are under progress.
Ghaiabad .
Cost (in lacs) 930
19. Construction of 2 No. 25.01.2016 30.09.17 Civil work is in progress.
400 KV line bays and The work is delayed, matter taken up
1 No. TIE bay at 400 with M/s TBEA
KV substation Kirori

Mode: Turn Key


Contractor: TBEA
Shenyang Transformer
Group Co China
Contract no.
PO No. HDP-2119/REC-
137/XEN/Tr(P)dated
25.01.2016
&
HDP-2120/REC-
137/XEN/Tr(P)dated
25.01.2016
Annexure-B
Status of on-going transmission works-Transmission Lines:

Sr. Name of Date of Likely Status


No Transmission Line award/ date of
Contractu completio
al n
completio
n date
1. 220kV line connecting 26.2.14/ 12/2017  Route plan of 220 kV line from
400kV substation 02.05.15 400 kV S/Stn. PGCIL Panchgaon
Panchgaon with 220kV to 220 kV S/Stn. HVPNL
substation Panchgaon- Panchgaon has already been
0.5 Km approved.
Funding-World bank  In spite of innumerable meetings
District: Gurgaon at various level, no response is
M/s Inabensa Spain coming from the firm.
in JV with inabensa
Bharat Progress:
Contractor :  Foundation- Not yet started.
Cost(In Rs. Lacs) :40  Erection-Not yet started.
Lacs  Stringing-Not yet Started.
2. 66kV D/C Panchgaon – 26.02.14/ 12/2017  Approx. 13.5 KM part route of 66 KV
Farukh Nagar line- 02.05.15 D/C Panchgaon - Farukhnagar line
23.2 Km has been approved on 02.12.16.
Funding-World Bank  Inspite of innumerable meetings at
Mode-Turnkey District: various level, no response is coming
Gurgaon from the firm.
Contractor : M/s
Inabensa Spain in Progress:
JV with inabensa  Foundation- Not yet started.
Bharat  Erection-Not yet started.
Cost(In Rs. Lacs):  Stringing-Not yet Started.
2297
Impediment-
Activity completed- Nil
Total Material received-Nil
3. LILO of 1 Ckt. of 66 KV 26.02.14/ 12/2017  Partial route 50% of total route
D/C Harsaru – Pataudi 02.05.15 length approved on 02.12.2016.
line at 66 KV  Inspite of innumerable meetings
substation Panchgaon- at various level, no response is
12 KM Funding-World coming from the firm.
Bank
Mode-Turnkey District:  Inspite of innumerable meetings
Gurgaon at various level, no response is
M/s Inabensa Spain coming from the firm.
in JV with inabensa Progress:
Bharat  Foundation- Not yet started.
Cost(In Rs. Lacs)  Erection-Not yet started.
:2297  Stringing-Not yet Started.

4. LILO of 1 Ckt. of 66 KV 26.02.14/ 12/2017  Approx. 13.5 KM part route of 66


D/C Panchgaon – 02/05/15 KV D/C Panchgaon -
Farukh Nagar line at Farukhnagar line has been
66kV substation approved on 02.12.16.
Jamalpur-0.8 Km  In a meeting on 2.02.2017, Ld
Funding-World Bank ACS Power desired to
Mode-Turnkey District: commission 66kV Jamalpur by
Gurgaon 31.03.2017.
M/s Inabensa Spain  Inspite of innumerable meetings
in JV with inabensa at various level, no response is
Bharat coming from the firm.
Cost(In Rs. Lacs) : Progress:
 Foundation- Not yet started.
 Erection-Not yet started.
 Stringing-Not yet Started.
5. 132 KV D/C line from 19.08.14/ 30.09.17 Progress:
132 KV S/Stn. Nangal 18.08.15  Foundation- Completed-92 Nos,
Mohanpur to 132 KV Balance-0 Nos.
S/Stn. DFCCIL Ateli  Erection-Completed- 92 Nos,
with 0.4” ACSR Balance- 0 Nos.
conductor.  Stringing- Completed- 23.473 KM,
 Turnkey contractor: Balance- 0 KM.
M/S Fedders Lloyd Impediment:
Corporation Ltd.  Inadequate manpower & resources
 Contract awarded with the firm.
on: 19.08.14.
 Funding agency: Note:- only gantry side jumper
REC-125 work pending.
 Length of line-
22.588 Km
 No of location- 92
Nos.
 Cost (In
Lacs):396.00
6. 132 kV S/c line from 17.06.16 16.07.2017 Progress:
220 kV S/Stn. Lula Ahir /  Foundation- Completed-24 Nos,
to 132 kV TSS on D/C 31.10.2017 Balance-23 Nos.
towers at Jatusana  Erection-Completed- 10 Nos,
 Turnkey contractor: Balance- 37Nos.
M/s Arcon Engicon  Stringing- Completed- 0 KM,
Ltd. Balance- 10.67 KM.
 Contract awarded
on: 17.06.2016 Impediment:
 Funding agency:  Inadequate manpower & resources
REC-150 with the firm.
 Length of line:  Total Material received-50%(Tower
10.625 Km. material only)
 No of location: 47
Nos. Civil Activity completed-51 %
 Cost (In Lacs): Total Material received-50 %
520.00
7. Supply, Laying 04.06.15/ 31.10.2017 Progress:
erection Civil Works, 03.06.16  Cables have been laid &
Testing & termination completed.
Commissioning of  After testing, “Loop In” ckt has
LILO of one Ckt. Of been energized on no load from
66 KV Badshahpur – sec-47 for soak test. “Loop Out”
Sec 15 line at 66 KV Ckt. is pending for charging.
S/Station Sector 47
Gurgaon through HDPE Pipe:
Underground 66 KV
1200 Sq mm PO- 920 Mtr
Aluminum Conductor Site- 3200 Mtr
XLPE power cable
with
trench/Trenchless
method.
 Turnkey
contractor: M/s
Cable Corporation of
India, Mumbai
 Contract No-HDP-
2061/REC 132
 Date of Award-
05.05.2015
 Funding agency-
Rec-132.
 Length of Line-
0.68 Km
 Cost( In
Lacs):140.58
8. Supply, Laying 04.06.15/ 31.12.16 Progress:
erection Civil Works, 03.06.16  Route plan approved.
Testing & 31.10.17  HDPE Pipe, Power cable (partial) and
Commissioning of termination kit have been received.
LILO of one Ckt. Of  Laying of HDPE pipes under progress.
66 KV Sec 44 –Sec 38 Except a road crossing, the balance
line at 66 KV HDPE pipe has been laid.
S/Station Sector 45
Gurgaon through HDPE Pipe:
Underground 66 KV
1200 Sq mm PO- 1360 Mtr
Aluminum Conductor  Site- 5500 Mtr
XLPE power cable
with
trench/Trenchless Constraints:
method.  In recent meeting held on 23.11.2016
 Turnkey under the chairmanship of Director
contractor: M/s Projects at Gurgaon, the firm gave the
Cable Corporation of commitment to complete the line by
India, Mumbai 31.03.2017.
 Contract No-HDP-  AVP CCI Mumbai again gave
2061/REC 132 assurance for completion of project by
 Date of Award- committed date on 06.12.2016 to
05.05.2015 Director/Technical.
 Funding agency-
Rec-132. Meeting held:
 Length of Line-  6 Nos ( 25.04.2016 (CE/TS),
1.09 Km 07.05.2016 (CE/TS), 21.09.2016,
 Cost(In 19.11.2016 (CE/TS) 23.11.2016 &
Lacs):216.10 16.01.2017 (Director/Projects),
9. Supply, Laying 04.06.15/ 31.05.17 Progress:
erection Civil Works, 03.06.16  No physical work done till today.
Testing & 31.10. 17  Route plan approved.
Commissioning of 66  HDPE Pipe has been received at site.
KV D/C line from
220kV Sector 57 to HDPE Pipe:
proposed 66 KV Sec
45,Gurgaon through PO- 800 Mtr
Underground 66 KV Site- 1568Mtr
1200 Sq mm
Aluminum Conductor
XLPE power cable
with
trench/Trenchless
method.

 Turnkey
contractor: M/s
Cable Corporation of
India, Mumbai
 Contract No-HDP-
2061/REC 132
 Date of Award-
05.05.2015
 Funding agency-
Rec-132.
 Length of Line-
4.68 Km
 Cost( In
Lacs):803.26
10. Supply, Laying 04.06.15/ 31.12.16 Progress:
erection Civil Works, 03.06.16  No physical progress till date.
Testing & 31.10. 17  Route plan approved.
Commissioning of 66  Cable inspection completed but not
KV S/C line from received at site.
220kV Sector 52 to
66 KV Sec HDPE Pipe:
44,Gurgaon with 4
Nos 66 KV 1200 Sq PO- 2400 Mtr
mm Aluminum Site- 5544 Mtr
Conductor XLPE
power cable with
trench/Trenchless
method.

 Turnkey
contractor: M/s
Cable Corporation of
India, Mumbai
 Contract No-HDP-
2061/REC 132
 Date of Award-
05.05.2015
 Funding agency-
Rec-132.
 Length of Line-
1.34 Km
11. 220kV D/C line from 10.10.16 02.01.2018 i. The work was initially allotted to M/s
765kV substation / Inabensa who does not carry out the
PGCIL Bhiwani to 02.01.18 work and hence contract was
220kV substation terminated on 29.06.2015.
Bhiwani.
Funding : WB-G-24A ii. Work re-allocated to M/s ISOLUX
Mode: Turnkey vide contract No – WB-98&99 / G-
District: Bhiwani 24A (Re-bid) / XEN / WB dated
Contractor - M/s 26.08.2016
Isolux
Line length – 20 KM
Cost (In Rs. Lacs): iii. The check survey work partially
1993 completed & some crossing profile
12. 220kV D/C line from 10.10.16 has been submitted for further
765kV substation / approval.
PGCIL Bhiwani to 02.01.18
220kV substation iv. M/s ISOLUX is not carrying out
Isherwal further activity for the last 4 months.
Funding : WB-G-24A Letters have been sent to M/s
Mode: Turnkey ISOLUX by CE/TS, HVPNL, Hisar,
District: Bhiwani SE/TS, HVPNL, Hisar and Xen/TS,
Contractor -M/s Isolux HVPNL, Jind & Bhiwani.
Line length – 65 KM
Cost (In Rs. Lacs) The contract has been terminated by
:4115 CE/MM, HVPNL, Panchkula vide office
13. LILO of Both circuit 10.10.16 memo No- Ch- 104/WB-99/G-24A (Re-
220KV Narwana-Mund / bid) / Xen / WB dated 18.08.2017.
Line at 400KV 02.01.18
substation Khatkar
(PGCIL) Funding: WB-
G-24A
Mode: Turnkey
District: Jind
Contractor - M/s
Isolux Line length -
Cost(In Rs. Lacs) :
1802
14. 400kV D/C line from 31.10.13/ 10.08.2017 Stub setting:- 149/149 No,
400kV substation Kirori 29.01.15 Tower erection:- 149/149 No
to 400 kV PGCIL Jind - Stringing: 50.5/50.5 KM
Loc-149 Funding : Earth wire : 50.5/50.5 KM
WB-G-17C OPGW – 50.5 KM / 50.5 KM
District: Hisar Work completed. 400 KV Kirori-Jind ckt
Contractor : M/s 2 has been test charged on dated
Cobra JV with M/s M/s 10.03.2017.
Shyam Indus Power Ckt 1 test charged on 10.08.2017.
Solutions Line could not be commissioned due to
Line length – 50.5 KM non-availability of 400kV bays at 400kV
Cost(In Rs. Lacs) : Substation Kirori.
5353
15. LILO of both circuits 26.04.12/ 31.12.2017 Loop-In
of 220kV Chormar- 20.07.13 Stub setting:- 84 / 84 No,
Fatehabad D/C line Tower erection:- 74 / 84 No
at 220kV substation Stringing: 14.5 / 21 KM
Hukmawali - 42 Km Loop out commissioned on 24.06.2016
Loc.-170 Erection & stringing work of Loop-in line
Funding : WB-G-10A is held up for the last 7-8 months as M/s
District : Fatehabad ISOLUX is not carrying out any work in
Contractor : M/s spite of repeated requests/reminders
Isolux Line length – made by O/o SE/TS, HVPNL, Hisar &
21 KM Xen/TS Division, HVPNL, Hisar.
Cost (In Rs. Lacs) :
1970
16. 132kV line from 220kV 17.06.10/ 05.06.2017 Stub setting:- 53/53 No,
substation Dadhi Bana 17.06.11 Tower erection:- 53/53 No
to 132kV substation Stringing: 8.96/8.96 KM
Jhojhu Kalan line–
8.960 Km, Loc. –53 Line charged on 05.06.2017
Funding : REC-103
District: Bhiwani
Contractor : Arcon
Cost(In Rs. Lacs)
:278.40
17. Construction of 2 07.09.16 31.12.2017 Stub setting:- 34/118
phase 132 kV S/C line Tower erection:- 10/118
on D/C towers with Stringing: Nil
0.4 Sq ACSR Work allocated to M/s Fedders Lioyd
conductor from 132 Ltd. vide contract No – HDP-2145 &
kV S/Stn., Kalanaur to 2146/ REC-159 / XEN / Project (TL)
132 kV TSS Manheru. dated 26.08.2016.
Funding : REC-159
District: Bhiwani Work held up for the last 2 weeks due
Contractor: M/S to non-availability of material and
Fedders Lloyd Ltd. erection gang. Matter taken up with M/S
Line length – 30 Km Fedders Lloyd.
Total Location – 126
Cost (In Rs. Lacs):
329
18. Construction of new 10.01.17 09.04.2018 Foundations:- 22/35 No,
132 KV D/C line with Tower erection:- 4/35 No
ACSR conductor size Stringing:- 0/8.7 KM
of 0.4 sq. inch from
220 KV S/Stn. Jind to Foundation casting & erection work is in
new 132 KV S/Stn. progress.
Sector-9 Jind
Funding : REC-162
Contractor: M/S RS
Infra
Line Length: 8.7 km
Total Locations:35
Nos. Cost : 479 Lacs
19. 132KV S/C line on D/C 10.01.17 09.04.2018 Stub setting:- 108/111
tower from 400KV Tower erection:- 102/111
S/Stn Nuhiyanwali to Stringing: 24/30
132KV S/Stn. Work allocated to M/S R.S. Infra
Assakhera. Projects Pvt. Ltd.
Funding : REC-162 vide contract No – HDP-2189 / REC-
District: Sirsa 162 / XEN / Project(TL) dated
Contractor:M/S R.S. 10.01.2017.
Infra Projects Pvt. Ltd. Work of stubbing, tower erection &
Line length – 33 Km stringing is in progress.
Mode:- Trunkey basis
Cost(In Rs. Lacs) :
10969
20. Stringing of 2nd circuit 10.01.17 09.04.2018
of existing 220Kv Stringing: 61.07 / 61.07
Fatehabad-Rania line Work allocated to M/S R.S. Infra
on D/C tower. Projects Pvt. Ltd.
Funding : REC-162 vide contract No – HDP-2189 / REC-
District: Sirsa 162 / XEN / Project(TL) dated
Contractor:M/S R.S. 10.01.2017.
Infra Projects Pvt. Ltd. Stringing work completed.
Line length – 61.07
Km
Mode:- Trunkey basis
Cost(In Rs. Lacs) :
6406
21. Creation of LILO of 03.01.17 02.07.2018 Stub setting:- 44/81
both circuit of 220KV Tower erection:- 5/81
Fatehabad-Rania line Stringing: Nil
at proposed 220KV Work allocated to M/S R.S. Infra
S/Stn Mehna Khera Projects Pvt. Ltd.
with 0.4 Sq” ACSR vide contract No – HDP-2187 / REC-
Zebra. 158 / XEN / Project(TL) dated
Funding : REC-158 3.01.2017.
District: Sirsa Work of stubbing & tower erection
Contractor:M/S R.S. is in progress
Infra Projects Pvt. Ltd.
Line length – 26.6 Km
Mode:- Trunkey basis
Cost(In Rs. Lacs) :
13550
22. Construction of 132KV 03.01.17 02.07.2018 Stub setting:- 37/47
S/C line on D/C tower Tower erection:- 36 / 47
with 0.4 Sq” ACSR Stringing: Nil / 13 Km
from 220KV S/Stn. Work allocated to M/S R.S. Infra
Mehna Khera to Projects Pvt. Ltd.
132KV S/Stn. vide contract No – HDP-2187 / REC-
Ellenabad. 158 / XEN / Project(TL) dated
Funding : REC-158 3.01.2017.
District: Sirsa Work of stubbing & tower erection
Contractor:M/S R.S. is in progress.
Infra Projects Pvt. Ltd.
Line length – 13 Km
Mode:- Trunkey basis
Cost(In Rs. Lacs) :
4768

23. Construction of 132KV 03.01.17 02.07.2018 Stub setting:- 20/86


D/C line with 0.4 Sq” Tower erection:- 02/86
ACSR conductor from Stringing: Nil
220KV S/Stn. Mehna Work allocated to M/S R.S. Infra
Khera- Projects Pvt. Ltd.
Madhosinghana- vide contract No – HDP-2187 / REC-
Ramnagaria on D/C 158 / XEN / Project(TL) dated
3.01.2017.
towers. Out of 2 Work of stubbing & tower erection
circuit one will be is in progress
terminated at 132Kv
S/Stn Madhosinghana
and other will be
extended to 132KV
S/Stn. Ramnagria to
bifurcation point (on
132KV S/C lines on
S/C towers.
Funding : REC-158
District: Sirsa
Contractor:M/S R.S.
Infra Projects Pvt. Ltd.
Line length – 20.5 Km
Mode:- Trunkey basis
Cost(In Rs. Lacs) :
13921
24. LILO of 66kV D/C 9.7.13/ Work Stub setting:- 34/34 No,
Nawada - Fatehpur line 08.07.14 completed Tower erection:- 34/34 No
at 66kV substation (Line yet to Stringing: 8.3/8.4 KM
Chhainsa- 8.4 Km be charged Work of LILO has been completed on
Loc.-34, on 66 KV dated 07.07.2014 but, commissioning is
Funding: WB-G-19B Voltage) pending due to non-availability of bay at
District: Palwal Chhainsa for LILO and pending
Contractor : M/s construction work on new 66kV D/C
Cobra JV with M/S Nawada - Fatehpur line which has been
Shyam Industries re-awarded to M/s Shyam Indus under
Power the package REC-127 and the same is
Cost(In Rs. Lacs) in progress.
:293
25. 66 kV D/C Panchgaon 04.03.14/ Work  Line Stands Completed.
- Mohamadpur-Ahir 03.03.15 completed
(Taoru) line- 8.458 (Line Yet to
Km, Loc.- 45 be charged
Funding : WB-G-24B on 66 KV
Mode : Turnkey Voltage)
District: Mewat
Contractor: M/S R.S.
Infra Projects Pvt. Ltd.
Cost (In Rs. Lacs)430
26. 66kV D/C line from 04.03.14/ Work  Line stands completed and charged
220kV substation Roz 03.03.15 completed with 66 kV Sohna –Nimoth line on
Ka Meo to 66kv dated 21.12.2016 to avoid theft due
substation Sohna- to non- completion of construction of
11.532km Loc.-58 220 KV S/Stn Roj-Ka-Meo.
Funding : WB-G-24B
Mode : Turnkey
District: Gurgaon
Contractor: M/S R.S.
Infra Projects Pvt. Ltd.
Cost(In Rs. Lacs)
:685
27. LILO of 66kV S/C 09.07.13/ Work Stub setting:- 9/9 No,
Aurangabad – 08.07.14 completed Tower erection:- 9/9 No
Hassanpur Line at (Line from Stringing: 1.463/1.463 KM
220kV substation 220 KV  The LILO portion has been utilized
Meerpur-Kurali- 1.463 S/Stn for stop gap arrangement to feed 66
Km Loc.-9 Meerpur kV S/Stn. Punhana through 66 kV
Funding: WB-G-19B Kurali is S/Stn. Aurangabad by providing
District: Palwal yet to be jumpers between LILO portion to 66
Contractor :Ms Cobra charged) kV newly erected Meerpur Kurali to
JV with M/s M/s Hodal line and then Meerpur Kurali –
Shyam Indus Power Hodal to Punhana line on dated
Solutions 20.05.2016 at 19:25 Hrs.
Cost(In Rs. Lacs) :  Work completed
523
28. 66kV S/C line on D/C 09.07.13/ Work Stub setting:- 111/111 No,
Tower from 220kV 08.07.14 completed Tower erection:- 111/111 No
Meerpur Kurali to 66kV (Line is yet Stringing: 25.924/25.969 KM
Allawalpur with LILO at to be
66kV substation charged) Progress: - The line has been
Chandhut- 25.969 Km completed except sag between terminal
Loc.-111 towers to gantries as the work of 66 KV
Funding: WB-G-19B bays at 66 KV S/Stns Chandhut and
District: Palwal Alawalpur is still under progress by M/S
Contractor : Ms Cobra TBEA.
JV with M/s M/s
Shyam Indus Power
Solutions
Cost(In Rs. Lacs)
:621
29. 220kV D/C Line from Jun-13/ Work Stub setting:- 106/106 No,
220kV substation 09.07.13 completed Tower erection:- 106/106 No
Palwal to 220kV (Line from Stringing: 26.852/26.8 KM
substation Meerpur 220 KV  The line has been test charged on
Kurali- 26.852 Km, S/Stn 27.04.2016 from 220 kV Voltage but,
Loc.- 106 Meerpur load has not been drawn due to
Funding : WB-G-19A Kurali is incomplete work of 220 kV S/Stn
District : Palwal yet to be Meerpur Kurali.
Contractor : M/s charged)
Shyam Indus
Cost(In Rs. 1440.2
Lacs)
30. 66kV D/C line from 18.4.15/ 30.11.17 Stub setting:- 27/39 No,
220kV substation Pali 28.01.16 Tower erection:- 27/39 No
to 66kV substation Stringing:- 1.99/7.454 km
Dhouj- 7.444 Km Progress-
Loc.-39  The revised route has been
Funding : REC-127 approved by WTD on dated
District: Faridabad 08.07.2016.
Contractor : M/s  At 12 Nos. locations (TL No. 9 to 17
Shyam Indus at the including TL No. 12 A & Gantry at 12
risk & cost of M/s GET B & 12 C) the approval of mining is
Cost(In Rs. 450 Lacs) required for which matter is being
: pursued with Mining Deptt. The
case for approval of Forest for 12
Nos. locations which was earlier
submitted on 04.12.15 in o/o DFO,
Faridabad has been resubmitted to
DFO on 22.09.2016 after
compliance of observations raised.
The case of forest clearance is
pending with DFO due to certain
observations raised by GOI as per
status shown online. The complete
case after attending the observation
raised by RO Govt. of India has been
re-submitted in the O/o DFO
Faridabad on dated 16.05.2017 for
consideration. Some observations
have been raised by RO, Govt. of
India and same have been
attended. The case been re-
submitted to O/o DFO Faridabad on
18.08.2017.
 Stringing work is in progress.
31. 66kV S/C on D/C 05.01.11/ 30.011.17 Stub setting:- 108/117 No,
tower Rangala Rajpur- 04.02.12/ Tower erection:- 79/117 No
Punhana line – 27 Km 28.01.16 Stringing: 1/27 KM
Loc.-117 Progress-
Funding : REC-127  Revised route has been approved by
District: Mewat WTD on dated 08.07.2016.
Contractor : M/s  Stubbing civil work (for 20 no.
Shyam Indus at the locations) has been awarded to
risk & cost of M/s GET Umesh Brother Bombay.
Cost(In Rs. 1015.25  Stubs have been provided to the
Lacs) : firm to execute the work & the firm
has started the work and work in
progress.
 Extra tower material procured by
CE/MM through M/s Salasar has been
received till 07.04.2017 and the
material has been handed over to the
firm on dated 15.04.2017 for
erection.
 The stub setting work is held up at
TL No. 102, 103 103A 103B, 103C &
104 due to ROW problem. Matter
being consistently pursued with
District Administration and SP, Nuh.
District administration has conveyed
that the issue will be resolved
amicably.
32. 66kV line from 400kV 2011-12/ 30.10.17 Stub setting:- 38/38 No,
substation Nawada to 07.02.12/ Tower erection:- 38/38 No
66kV substation 28.01.16 Stringing: 4.6/8.733 km
Fatehpur Biloch- 8.815  Revised route plan between TL No. 3
Km Loc.-38 to 7 has been approved by WTDs of
Funding : REC-127 HVPNL recently on dated 17.03.2017.
District: Faridabad  Stringing is under progress on the left
Contractor : M/s out locations.
Shyam Indus at the  E- NIT for laying of 500 meter 66kV
risk & cost of M/s GET cable from gantry of 400kV S/Stn
Cost (In Rs. 500 Lacs) Nawada to TL No. 1 in under const.
line which had opened on dated
22.02.2017 has been approved by
competent authority on dated
16.08.2017. Work order has been
placed to the firm M/s Adeco Energy
Pvt. Ltd.
 Cable & jointing kits available in
Ballabgarh store has been allocated
by CE/MM wing.
 HDPE Pipe and SVL are being
procured as envisaged by the
contractor in final survey.
33. LILO of both circuit of 05.05.15 30.11.2017  Work at site is yet to be started and
66kV D/C Palla – NH-3 / no physical progress at site till date.
line at 66kV S/Stn 21.05.16  Firm has been noticed for causing
Sector-46 through U/G inordinate delay.
XLPE 1200 sqmm  Route plan has been approved.
Cable – 2.389 Km 19KM Cable and 16 no. straight
Funding : REC-132 joints have been received. Work of
District: Faridabad laying of cables is yet to be started
Contractor : M/s CCIL by firm. Work is lagging far behind
Cost (In Rs.706 Lacs) the schedule and Firm has been
: requested to gear up and complete
the work by 30.11.2017
34. LILO of one Ckt of 66 10.01.201 12.08.2017 Stub setting:- 64/64 No,
kV D/C line Panchgaon 7 Tower erection:- 64/64 No
to Mohamad Pur Ahir Stringing: 10.612/10.612 KM
at 66 kV S/Stn Taoru
Funding :- REC -162 Line stands completed except sag
Contractor: - M/s RS between gantry to terminal tower at 66
Project Pvt. Ltd. kV S/Stn. Taoru & charged with 66 kV
Voltage.