I PEKERJAAN PERSIAPAN
1 Bouwplank 1 ls 200000 Rp200,000
JUMLAH Rp200,000
II PEKERJAAN TANAH
1 Galian Rollag 10.14 m3 31500 Rp319,410
2 Urugan Sirtu Peninggian Lantai 1.521 m3 139220 Rp211,754
3 Urug Tanah Kembali 0.507 m3 10000 Rp5,070
JUMLAH Rp536,234
III PEKERJAAN BETON
1 Sloof 20 X 20 cm 0.048 m3 4543700 Rp218,098
2 Kolom Praktis 15 x 15 0.69 m3 3594000 Rp2,479,860
3 Balok 15/20 cm 0.21 m3 4543700 Rp954,177
4 Ring Balk 15 x 15 cm 0.3825 m3 3594000 Rp1,374,705
5 Beton Kanopy 0.032 m3 2897000 Rp92,704
JUMLAH Rp5,119,544
IV PEKERJAAN PASANGAN, PLESTERAN & BENANGAN
1 Pasangan Pondasi Rollag 3 m3 516200 Rp1,548,600
2 Pasangan Dinding Bata Merah 1 : 4 6.72 m3 704750 Rp4,735,920
3 Pasangan Bata Merah Bak Mandi Dan Peninggian Klosed jongkok 1 : 4 0.624 m3 704750 Rp439,764
4 Plesteran Dinding 1 : 5 21.84 m2 45100 Rp984,984
5 Acian 21.84 m2 19100 Rp417,144
6 Ban - banan 3.45 m2 45000 Rp155,250
7 Kampratan 1 m2 35000 Rp35,000
8 Benangan 78.1 m 9600 Rp749,760
JUMLAH Rp9,066,422
V PEKERJAAN ATAP
1 Kuda - Kuda Canal C 75x45x15x2,3 46.28 Kg 21500 Rp995,020
2 Gording Canal C 75x45x15x2,3 107.9 Kg 21500 Rp2,319,850
NO NAMA BARANG/SPESIFIKASI VOLUME SATUAN HARGA JUMLAH