Consider a small project consisting of the following activities and their duration along with

precedence as follows :

Activity Precedence Duration(Days)

A -- 5
B -- 6
C -- 8
D A 9
E B 8
F B,C 7
G D,E,F 8
H A 7
I H,G 7

1) Draw network project scheduling diagram


2) Find Critical path and interpret
3) Calculate slack time and interpret
4) Draw Gantt Chart and interpret

……………………………………………………………………………………….