CONSTRUCTION PROGRAMME PRE-CONSTRUCTION

Start
Start: 3/5/10 ID: 1 Start: 3/5/10 ID: 2
Finish: 25/10/11 Dur: 387 days Finish: 3/5/10 Dur: 0 days Milestone Date: Mon 3/5/10
Comp: 0% Comp: 0% ID: 3

SITE SET-UP Mobilization Erection of Protective Work Site investigation Setting out Leveling Construction of Temporary Roads Provision of Temporary Ultilities
Start: 3/5/10 ID: 4 Start: 3/5/10 ID: 5 Start: 3/5/10 ID: 6 Start: 11/5/10 ID: 7 Start: 11/5/10 ID: 8 Start: 14/5/10 ID: 9 Start: 19/5/10 ID: 10 Start: 19/5/10 ID: 13
Finish: 21/5/10 Dur: 15 days Finish: 3/5/10 Dur: 1 day Finish: 10/5/10 Dur: 6 days Finish: 11/5/10 Dur: 1 day Finish: 13/5/10 Dur: 3 days Finish: 18/5/10 Dur: 3 days Finish: 19/5/10 Dur: 1 day Finish: 19/5/10 Dur: 1 day
Comp: 0% Res: Res: Res: Res: Res: Res: Res:

Delivery of Plants and Equipments


Start: 19/5/10 ID: 14
Finish: 19/5/10 Dur: 1 day
Res:

Setting of Plants and Equipments


Start: 19/5/10 ID: 15
Finish: 20/5/10 Dur: 2 days
Res:

Delivery of Construction Materials Erection of Site Office


Start: 20/5/10 ID: 11 Start: 21/5/10 ID: 12
Finish: 20/5/10 Dur: 1 day Finish: 21/5/10 Dur: 1 day
Res: Res:

SUBSTRUCTURE CONSTRUCTION Foundation Construction Sheet Piling Excavation Underground Drainage Piling Blinding Underground Buillding Services Connection
Start: 24/5/10 ID: 16 Start: 24/5/10 ID: 17 Start: 24/5/10 ID: 18 Start: 31/5/10 ID: 19 Start: 9/6/10 ID: 20 Start: 17/6/10 ID: 21 Start: 28/6/10 ID: 22 Start: 29/6/10 ID: 23
Finish: 20/7/10 Dur: 42 days Finish: 5/7/10 Dur: 31 days Finish: 28/5/10 Dur: 5 days Finish: 8/6/10 Dur: 7 days Finish: 16/6/10 Dur: 6 days Finish: 25/6/10 Dur: 7 days Finish: 28/6/10 Dur: 1 day Finish: 5/7/10 Dur: 5 days
Comp: 0% Comp: 0% Res: Res: Res: Res: Res: Res:

Construction of ground slab Back-filling


Start: 6/7/10 ID: 24 Start: 20/7/10 ID: 25
Finish: 19/7/10 Dur: 10 days Finish: 20/7/10 Dur: 1 day
Res: Res:

SUPERSTRUCTURE CONSTRUCTION Structural Frame


Start: 21/7/10 ID: 26 Start: 21/7/10 ID: 27
Finish: 22/8/11 Dur: 284 days Finish: 11/1/11 Dur: 125 days
Comp: 0% Comp: 0%

Roofing
Start: 10/1/11 ID: 40
Finish: 21/2/11 Dur: 31 days
Comp: 0%

External finishing
Start: 10/1/11 ID: 49
Finish: 1/2/11 Dur: 17 days
Comp: 0%

Internal finishing
Start: 10/1/11 ID: 52
Finish: 18/5/11 Dur: 93 days
Comp: 0%

Open Corridor, Lift Lobby & Staircase


Start: 10/1/11 ID: 56
Finish: 6/5/11 Dur: 85 days
Comp: 0%

Special Education Room


Start: 10/1/11 ID: 62
Finish: 18/5/11 Dur: 93 days
Comp: 0%

Conversion of a Conference Room on 2nd Floor


Start: 10/1/11 ID: 73
Finish: 13/1/11 Dur: 4 days
Comp: 0%

Water tank
Start: 10/1/11 ID: 75
Finish: 21/1/11 Dur: 10 days
Comp: 0%

INSPECTION AND HANDOVER Removal of Scaffolding Dismantling material hoist Removal of temp.work Cleaning Inspection of Fire Services Lift Inspection Inspection by EMSD Inspection by Building Department Inspection by HO T&C Making good defective Handover
Completion
Start: 23/8/11 ID: 94 Start: 23/8/11 ID: 95 Start: 29/8/11 ID: 96 Start: 1/9/11 ID: 97 Start: 13/9/11 ID: 98 Start: 15/9/11 ID: 99 Start: 20/9/11 ID: 100 Start: 23/9/11 ID: 101 Start: 28/9/11 ID: 102 Start: 3/10/11 ID: 103 Start: 6/10/11 ID: 104 Start: 13/10/11 ID: 105 Start: 25/10/11 ID: 106
Finish: 25/10/11 Dur: 46 days Finish: 26/8/11 Dur: 4 days Finish: 31/8/11 Dur: 3 days Finish: 12/9/11 Dur: 8 days Finish: 14/9/11 Dur: 2 days Finish: 19/9/11 Dur: 3 days Finish: 22/9/11 Dur: 3 days Finish: 27/9/11 Dur: 3 days Finish: 30/9/11 Dur: 3 days Finish: 5/10/11 Dur: 3 days Finish: 12/10/11 Dur: 5 days Finish: 24/10/11 Dur: 8 days Finish: 25/10/11 Dur: 1 day Milestone Date: Tue 25/10/11
Comp: 0% Res: Res: Res: Res: Res: Res: Res: Res: Res: Res: Res: Project: ID: 107

RESURFACING BASKETBALL COURT Resurfacing of basketball court


Start: 14/1/11 ID: 92 Start: 14/1/11 ID: 93
Finish: 28/1/11 Dur: 11 days Finish: 28/1/11 Dur: 11 days
Comp: 0% Res:

Project: Construction Management


Date: Mon 26/4/10
Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Page 1
Construction of Ground Floor Construction of 1/F Construction of 2/F Construction of 3/F Construction of 4/F Construction of 5/F Construction of Roof Floor Water tank Lift Machine Room
Start: 21/7/10 ID: 28 Start: 13/8/10 ID: 29 Start: 7/9/10 ID: 30 Start: 30/9/10 ID: 31 Start: 25/10/10 ID: 32 Start: 17/11/10 ID: 33 Start: 10/12/10 ID: 34 Start: 24/12/10 ID: 35 Start: 28/12/10 ID: 36
Finish: 12/8/10 Dur: 17 days Finish: 6/9/10 Dur: 17 days Finish: 29/9/10 Dur: 17 days Finish: 22/10/10 Dur: 17 days Finish: 16/11/10 Dur: 17 days Finish: 9/12/10 Dur: 17 days Finish: 23/12/10 Dur: 10 days Finish: 27/12/10 Dur: 2 days Finish: 29/12/10 Dur: 2 days
Res: Res: Res: Res: Res: Res: Res: Res: Res:

FS Room
Start: 28/12/10 ID: 37
Finish: 29/12/10 Dur: 2 days
Res:

Stairhood Demolition of Existing Wall


Start: 24/12/10 ID: 38 Start: 10/1/11 ID: 39
Finish: 7/1/11 Dur: 11 days Finish: 11/1/11 Dur: 2 days
Res: Res:

Steel and metal work Protective layer Rendering Waterproofing Water test Painting Floor screeding Floor Tiling
Start: 10/1/11 ID: 41 Start: 17/1/11 ID: 42 Start: 19/1/11 ID: 43 Start: 26/1/11 ID: 44 Start: 31/1/11 ID: 45 Start: 1/2/11 ID: 46 Start: 8/2/11 ID: 47 Start: 15/2/11 ID: 48
Finish: 14/1/11 Dur: 5 days Finish: 18/1/11 Dur: 2 days Finish: 25/1/11 Dur: 5 days Finish: 28/1/11 Dur: 3 days Finish: 31/1/11 Dur: 1 day Finish: 7/2/11 Dur: 5 days Finish: 14/2/11 Dur: 5 days Finish: 21/2/11 Dur: 5 days
Res: Res: Res: Res: Res: Res: Res: Res:

Erection of Scaffolding Wall Cladding


Start: 10/1/11 ID: 50 Start: 12/1/11 ID: 51
Finish: 11/1/11 Dur: 2 days Finish: 1/2/11 Dur: 15 days
Res: Res:

Installation of material hoist Bricklaying for Partition Waterproofing to Toilets


Start: 10/1/11 ID: 53 Start: 12/1/11 ID: 54 Start: 20/1/11 ID: 55
Finish: 11/1/11 Dur: 2 days Finish: 19/1/11 Dur: 6 days Finish: 24/1/11 Dur: 3 days
Res: Res: ff Res:

Ceiling plastering and painting Wall plastering and painting Installation of Sign
Start: 10/1/11 ID: 57 Start: 14/2/11 ID: 58 Start: 21/3/11 ID: 61
Finish: 11/2/11 Dur: 25 days Finish: 18/3/11 Dur: 25 days Finish: 22/3/11 Dur: 2 days
Res: Res: Res:

Floor tiling Installation of Skirt


Start: 21/3/11 ID: 59 Start: 25/4/11 ID: 60
Finish: 22/4/11 Dur: 25 days Finish: 6/5/11 Dur: 10 days
Res: Res:

Door frame Bricklaying of Door Door Installation


Start: 10/1/11 ID: 63 Start: 18/1/11 ID: 64 Start: 26/1/11 ID: 65
Finish: 17/1/11 Dur: 6 days Finish: 25/1/11 Dur: 6 days Finish: 8/2/11 Dur: 10 days
Res: Res: Res:

Window frame Ceiling plastering & painting Wall plastering & painting Installation of Window Floor screeding and tiling Skirting Ironmongery
Start: 2/2/11 ID: 66 Start: 16/2/11 ID: 67 Start: 16/3/11 ID: 68 Start: 20/4/11 ID: 69 Start: 25/4/11 ID: 70 Start: 16/5/11 ID: 71 Start: 16/5/11 ID: 72
Finish: 15/2/11 Dur: 10 days Finish: 15/3/11 Dur: 20 days Finish: 19/4/11 Dur: 25 days Finish: 22/4/11 Dur: 3 days Finish: 13/5/11 Dur: 15 days Finish: 18/5/11 Dur: 3 days Finish: 18/5/11 Dur: 3 days
Res: Res: Res: Res: Res: Res: Res:

Conversion of a Conference Room on 2nd Floor


Start: 10/1/11 ID: 74
Finish: 13/1/11 Dur: 4 days
Res:

Waterproofing and wall and floor tiling


Start: 10/1/11 ID: 76
Finish: 21/1/11 Dur: 10 days
Res:

Building Services Water Supply System Disable Toilets Other Installation


Start: 10/1/11 ID: 77 Start: 24/1/11 ID: 82 Start: 7/3/11 ID: 83 Start: 18/8/11 ID: 84
Finish: 22/8/11 Dur: 161 days Finish: 4/3/11 Dur: 30 days Finish: 18/3/11 Dur: 10 days Finish: 22/8/11 Dur: 3 days
Comp: 0% Res: Res: Res:

Electrical Supply Transformer Room Installation Power Supply


Start: 10/1/11 ID: 85 Start: 10/1/11 ID: 86 Start: 31/1/11 ID: 87 Start: 14/2/11 ID: 88
Finish: 18/3/11 Dur: 50 days Finish: 28/1/11 Dur: 15 days Finish: 11/2/11 Dur: 10 days Finish: 18/3/11 Dur: 25 days
Comp: 0% Res: Res: Res:

Electricity System Fire Services


Start: 19/5/11 ID: 78 Start: 30/6/11 ID: 79
Finish: 29/6/11 Dur: 30 days Finish: 10/8/11 Dur: 30 days
Res: Res:

Security System
Start: 11/8/11 ID: 81
Finish: 17/8/11 Dur: 5 days
Res:

HVAC System
Start: 30/6/11 ID: 80
Finish: 27/7/11 Dur: 20 days
Res:

Lift Installation Handover to Lift Supplier Lift


Start: 21/3/11 ID: 89 Start: 21/3/11 ID: 90 Start: 11/4/11 ID: 91
Finish: 17/6/11 Dur: 65 days Finish: 8/4/11 Dur: 15 days Finish: 17/6/11 Dur: 50 days
Comp: 0% Res: Res:

Project: Construction Management


Date: Mon 26/4/10
Critical Noncritical Critical Milestone Milestone Critical Summary Summary Critical Inserted Inserted Critical Marked Marked Critical External External Project Summary Highlighted Critical Highlighted Noncritical
Page 2